BestLay Pty Ltd v Brisbane Construction Group Pty Ltd [2013] QCAT 597
CITATION: BestLay Pty Ltd v Brisbane Construction Group
Pty Ltd [2013] QCAT 597
PARTIES: BestLay Pty Ltd
(Applicant)
v
Brisbane Construction Group Pty Ltd
(Respondent)
APPLICATION NUMBER: BDL184-13
MATTER TYPE: Building Matters
HEARING DATE: 27 September 2013
HEARD AT: Brisbane
DECISION OF: Member McLean Williams
DELIVERED ON: 6 November 2013
DELIVERED AT: Brisbane
ORDERS MADE: 1. The respondent is to pay to the applicant
the sum of $7,649.48 within 28 days of the
date of these orders.
2. The applicant is to rectify the garage slab
and to fix the slab under the front
bedroom wall at Lot 105 Silverwattle
Drive at Jimboomba at no further cost to
the respondent within 28 days of the date
of these orders, or such further period as
may be agreed between the applicant and
the respondent in writing.
APPEARANCES and REPRESENTATION (if any):
APPLICANT: Mr Mathew Best (director)
RESPONDENT: Mr Carl Graham (director)
REASONS FOR DECISION
[1] The applicant in this matter is Bestlay Pty Ltd, a corporate entity under the
control of Mr Matthew Best. Mr Best is a concreter in the building
construction industry.
-- 1 of 5 --
2
[2] The applicant commences this claim before QCAT seeking the sum of
$13,181.50 from the respondent, Brisbane Construction Group Pty Ltd, a
house construction and general building company operated by Mr Carl
Graham.
[3] On or about 20 April 2013, Bestlay and the Brisbane Construction Group
entered into an agreement for the preparation and pouring of a new house
slab, at Lot 105 Silverwattle Drive, at Jimboomba. The applicant
commenced works at Lot 105 on 22 April 2013, and the job was
essentially complete by 13 May 2013.
[4] On 20 May 2013 Bestlay provided Brisbane Construction Group with an
invoice for an amount of $33,181.50, inclusive of GST. On 28 June 2013
Brisbane Construction Group paid the sum of $20,000.00, yet took issue
with some of the further charges, although it did acknowledge that some
monies were probably still owed to Bestlay.
Factual Background
[5] In about April 2013 a Mr Reoz Cy Taurua, an industry associate who
operates another concreting business under the guise of “Tommy T
Concreting”, contacted Mr Matthew Best, who is the sole director of
Bestlay Pty Ltd.
[6] Mr Taurua told Mr Best that he often performed concreting jobs on behalf
of Mr Carl Graham and the Brisbane Construction Group, yet on this
occasion he was unable to take on the job, such that he wished to refer
the job to Bestlay. Mr Best advised Tommy T that he would have a
discussion with the Brisbane Construction Group, and would be able to
provide concreting services for them at a competitive rate.
[7] Mr Best says that an agreement was then struck between himself and
Mr Graham on about 20 April 2013 to pour the house slab at Lot 105
Silverwattle Drive at Jimboomba, on the basis of the Brisbane
Construction Group paying 110% of the costs incurred by Bestlay for the
supply of materials and plant, and 120% of the costs incurred by Bestlay
for the supply of labour, all exclusive of GST. Other than that, Mr Best
says that there were no discussions in relation to fixed daily rates, or
indeed any discussions in which the Brisbane Construction Group offered
to supply items of plant.
[8] Mr Best says that works commenced on 22 April 2013 and that these were
concluded by 13 May 2013. Mr Best says that the initial site cut was of a
poor standard, such that Bestlay then had to do a lot of further digging and
other preparation works in order to box up the slab. Mr Best also says that
there were difficulties caused by inadequate set-outs, in order that the slab
could be sized and positioned on the site correctly. Then, on 10 May 2013
Mr Best had a discussion with Mr Graham as to when the slab should be
poured. Mr Best recommended against pouring the slab on 11 May
(a Saturday), because rain was forecast for that day and because
overtime rates would be applicable with respect to labour. Despite that,
-- 2 of 5 --
3
Mr Best says that Mr Graham insisted that the slab be poured on Saturday
11 May, as the house frames were already on site, and he wanted to start
erecting these on the following Monday (13 May 2013), such that he was
prepared to accept the risk of rain, and any degradation in the quality of
the slab that may arise as a consequence of that.
[9] Mr Best says that he proceeded to pour the slab on Saturday 11 May, yet
as predicted, it rained, and very heavily. Because concrete batching
plants close early on Saturdays, partway through the pour Mr Bests says
he had to order extra concrete in order to avoid the risk that he would run
out of concrete before the batching plant was closed. By the time the slab
was completed there was however as much as 5.8 cubic metres of
concrete left over. Although Mr Graham had previously said that any
excess concrete might be used as the basis for the footing for a block wall
that was to be constructed by him subsequently, this was unable to be
done on the day because there were no starter bars available to
commence the footing. In the result, the excess concrete was not able to
be utilised, and was just wasted. The heavy rain meant that there were
inordinate problems in perfecting the slab, and Bestlay‟s men did not leave
the site until 8pm that evening. Mr Best says that the slab was completed
to the best possible standards, given the weather conditions, yet he does
acknowledge that the slab is not as good as it could have been, had it not
rained during the pour.
[10] Mr Best also concedes that there were some other minor defects, and that
these needed to be rectified, by him. He says that on 16 May 2013 he
and Mr Graham inspected the slab and that Mr Graham noted that the
rebates at the front of the slab required cutting down. Mr Best agreed that
the rebates required cutting down, and these were rectified in accordance
with Mr Graham‟s instructions. After that, Mr Best provided his invoice for
$33,181.50 (on 2 June 2013) yet the full amount of this has still not been
paid by the Brisbane Construction Group, who now dispute that they
should be required to pay as much as that.
[11] At the hearing before the Tribunal Mr Best explained that the additional
costs in the invoices presented by him included the additional labour that
was required and some further costs to hire some machinery including a
plate vibrator and two troweling machines. Mr Graham is unhappy about
that, because Tommy T Concreting has always provided his own
machines, and at no extra cost to him.
[12] On 28 June 2013 the applicant received a cheque for $20,000.00 from the
respondent in payment of the invoice dated 2 June. On 2 July 2013
Mr Graham wrote to Bestlay disputing the amount of the invoice and
pointing out that a number of “unnecessary extra costs” had been passed
onto the Brisbane Construction Group.
[13] Mr Carl Graham is the sole director of the Brisbane Construction Group
Pty Ltd. Although the applicant says that the agreement it had with the
respondent was for the respondent to pay 110% of material and plant
costs and 120% of the costs incurred for the supply of labour, Mr Graham
-- 3 of 5 --
4
refutes this, and says that his standard agreement with his usual concrete
contractor, Tommy T Concreting, was for him to pay 110% of the cost of
materials plus a daily rate of $450 per day for labour. Mr Graham says
that he always presumed that because Tommy T had arranged for Bestlay
to do the job in their stead, that the same arrangements that applied in the
case of work given by him to Tommy T Concreting would also apply, in the
case of work performed by Bestlay.
[14] Although I accept that this may have been the arrangement between the
Brisbane Construction Group and Tommy T Concreting, I am not prepared
to transpose any agreement with that entity to the case of a separate
agreement entered into between Bestlay Pty Ltd and the Brisbane
Construction Group, without clear evidence that Mr Best understood that
he was contracting on exactly the same terms as Tommy T. There is no
evidence of that, and Mr Best rather pointedly denies it. Both parties are
at fault for not having reduced the terms of their arrangement to writing.
Despite that, it is now the case that a slab has been laid by the Applicant
on behalf the Respondent, and the Respondent should be required to pay
the fair and reasonable cost of it, as assessed on a quantum meruit basis.
[15] Mr Graham says that there was a discussion about conducting the
concrete pour on a Saturday, and that it was he who had raised the
concern that it was likely to rain. Mr Graham says that he was then
however assured by Mr Best that the rain would not be a problem, as
Bestlay would use plastic sheeting to protect the slab, in the event of rain.
Further, Mr Graham says he raised a concern about his needing to pay
penalty rates, yet again Mr Best assured him that this would not be a
problem, as he would „speak to his concrete rep and get the penalties
removed‟. Mr Graham was particularly concerned that so much concrete
(5.8 cubic metres) was left over (effectively an entire truck load), as a
professional concreter ought to be able to calculate how much concrete is
required for a job, to within a couple of wheelbarrow loads.
[16] At the end of it, it would seem that Mr Graham has proceeded on the basis
that he was still contracting with Tommy T Concreting, and that Mr Best
was performing the job as a sub-contractor to Tommy T. I cannot accept
that contention, given that the Brisbane Construction Group has received
invoices from Bestlay and has paid some of these, and negotiations about
arrangements for the job appear to have been with Mr Best rather than
Mr Taurua. In the event that this was a true case of subcontracting with
Tommy T, then one would expect that the invoices received by the
Brisbane Construction Group for this job would have come from Tommy T
and not from Bestlay, yet this is not the case.
[17] It seems clear to me that there has been some confusion in the agreement
between Mr Best on behalf of the applicant and Mr Graham on behalf the
respondent. It now falls to the Tribunal to determine what is a fair and
reasonable outcome in all the circumstances. There are some aspects of
the job performed by Bestlay which are clearly inadequate, and which will
still require rectification. In parts, the slab is too short because Bestlay did
not apparently measure correctly. Even notwithstanding asserted
-- 4 of 5 --
5
problems with the initial set outs for the slab, these are properly matters
that need to be rectified by Bestlay and they should now be rectified at no
expense to the Brisbane Construction Group.
[18] In relation to the extra costs, I determine that because the respondent
agreed to proceed with the pour on a Saturday he thereby agreed - by
necessary implication - to wear any extra costs (such as overtime for
labour, or keeping the batching plant open) that arose as a result of that.
So too, the respondent must ultimately wear the risk of extra costs arising
as a result of rain, as well as for the slab being of a lesser quality than
would have been the case had it not rained. The Applicant should
nonetheless still be required to rectify any difficulties arising as a result of
the slab being too short, and at no further cost to the applicant, as this
problem cannot be attributed to the weather and is a matter that relates to
the competence of the concreter.
[19] In relation to the applicant‟s contention that he was providing plant and
materials at cost plus cost plus 10% and labour at cost plus 20% I find that
to be a generally reasonable market rate, and I allow it, on a quantum
meruit basis.
[20] In my view, the respondent is correct in his contention that any reasonably
diligent concreter should be able to measure and order quantities of
concrete so as to minimise waste, and unnecessary expense. On a job
the size of this one, an acceptable excess of concrete should be no more
than a few wheelbarrows, at most. The Brisbane Construction Group
should therefore not be required to pay for 5.8 cubic metres of excess
concrete, an enormous amount, which is clearly a calculation error on the
day of the pour, by the applicant. Certain remediation costs have also
been incurred by the respondent, for masonry cutting, removal of concrete
edges, the installation of termimesh, etc. Although the respondent
contends that his extra costs are now as much as $8,425.74, I find that the
extra costs to the respondent should be confined to items 1 – 5 (inclusive),
and item 8 in the items claimed by the respondent, in his statement of
response to the applicant‟s claim. This amounts to $5,817.02. That sum
should now be deducted from the applicant‟s claim for $13,446.50 (which
is the sum claimed by the applicant plus the $285 QCAT Filing Fee).
[21] In light of the foregoing I determine that the respondent should pay to the
applicant the sum of $7,649.48 within 28 days of the date of these orders.
In addition, the applicant is ordered to rectify the garage slab (which is
200mm too short) and to fix the slab under the front bedroom wall at no
further cost to the respondent, within 28 days of the date of these orders,
or such further period as may be agreed, in writing, as between the
applicant and the respondent.
-- 5 of 5 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2013/597