Bowen Village Caravan and Tourist Park v Nature Creek Finishes [2013] QCAT 569
CITATION: Bowen Village Caravan and Tourist Park v
Nature Creek Finishes [2013] QCAT 569
PARTIES: Russell Cook T/as Bowen Village Caravan and
Tourist Park
(Applicant)
v
John Grayson Paterson T/as Nature Creek
Finishes
(Respondent)
APPLICATION NUMBER: BDL232-11
MATTER TYPE: Building matters
HEARING DATE: 18 October 2013
HEARD AT: Townsville
DECISION OF: John Carey, Member
DELIVERED ON: 29 October 2013
DELIVERED AT: Townsville
ORDERS MADE: 1. Application is dismissed.
2. No order as to costs.
CATCHWORDS : Building matters - direction to rectify - whether
defects established
APPEARANCES and REPRESENTATION (if any):
APPLICANT : Self
RESPONDENT: Self
REASONS FOR DECISION
[1] The Applicant seeks orders for rectification of numerous alleged defects in
respect of the construction of a swimming pool between December 2009
and February 2010.
[2] A complaint was made to the Queensland Building Services Authority
(“BSA”). The BSA undertook an inspection and issued a report.
That report has been provided to the Tribunal.
[3] BSA distinguishes between category 1 and category 2 defects.
Category 2 defects do not require rectification.
-- 1 of 2 --
-2-
[4] The Respondent says that category 1 defects have been rectified.
The Applicant said he was not sure what they were but seeks rectification
of items listed at attachment 4 to his explanatory document handed up at
the hearing.
[5] The BSA report identifies that the time for ordering rectification of
category 2 defects expired in October or November 2010.
[6] The Applicant gave evidence on his own behalf and asserted that these
matters are defects and should be rectified. The Applicant did not produce
any independent third party evidence to that effect but relied on his own
experience and observations.
[7] The Respondent asserts that items in dispute are not defects and items
installed were installed in accordance with the manufacturer’s
specifications.
[8] The application only sought an order for rectification, however at the
hearing the Applicant verbally claimed monetary compensation.
[9] The Applicant has not satisfied the Tribunal that, on the balance of
probabilities, the items complained of are defects that should be the
subject of a rectification order.
[10] Although the Tribunal has power to direct rectification that is not
appropriate in this instance for the following reasons:
a) an independent third party (the BSA) asserts that the defects are
category 2 defects that do not require rectification. The time for
directing rectifications of category 2 defects has expired;
b) no independent third party evidence has been adduced by the
Applicant to support its case;
c) it would not be reasonable to order rectification and unfair on the
Respondent because:
i) an inspection has been carried out previously by BSA;
ii) the works were completed in 2010;
iii) the absence of independent evidence of defective work.
[11] The Applicant did adduce some evidence of rectification costs. Due to the
findings above, no compensation is payable by the Respondent.
Directions
1) The Application is dismissed.
2) No order as to costs.
-- 2 of 2 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2013/569