Arcon Constructions Pty Ltd v Queensland Building Services Authority [2013] QCAT 573
CITATION: Arcon Constructions Pty Ltd v Queensland
Building Services Authority [2013] QCAT 573
PARTIES: Arcon Constructions Pty Ltd
(Applicant)
v
Queensland Building Services Authority
(Respondent)
APPLICATION NUMBER: GAR112-13
MATTER TYPE: General administrative review matters
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Jeremy Gordon, Member
DELIVERED ON: 25 October 2013
DELIVERED AT: Brisbane
ORDERS MADE: The Queensland Building Services Authority
shall pay to Arcon Constructions Pty Ltd its
costs in these proceedings incurred after
9 April 2013, fixed at $1,870.80.
CATCHWORDS: COSTS – application to review decision about
scope of works - step leading to that decision
appearing to be void because of Supreme Court
case of McNab – whether scope of works
should have been withdrawn by QBSA soon
after that case
Queensland Civil and Administrative Tribunal
Act 2009 ss 100, 102, 105, 107
Queensland Civil and Administrative Tribunal
Rules 2009 r 89
Queensland Building Services Authority Act
1991 ss 72, 74, 86
McNab Constructions Australia Pty Ltd v
Queensland Building Services Authority [2013]
QSC 057
JM Kelly (Project Builders) Pty Ltd v
Queensland Building Services Authority [2013]
QCAT 216
Ralacom Pty Ltd v Body Corporate for Paradise
-- 1 of 7 --
2
Island Apartments (No 2) [2010] QCAT 412
APPEARANCES and REPRESENTATION (if any):
This matter was heard and determined on the papers pursuant to s 32 of the
Queensland Civil and Administrative Tribunal Act 2009 (QCAT Act).
REASONS FOR DECISION
[1] These proceedings have been withdrawn, and the only outstanding matter
is the question of costs.
[2] In brief, in these proceedings the Applicant Arcon Constructions Pty Ltd
sought a review of a decision made by the Queensland Building Services
Authority about the scope of works to be undertaken under the statutory
insurance scheme in order to rectify certain work which the QBSA said
was defective. The scope of works was issued on 27 February 2013.
[3] The decision to issue the scope of works was made because (according to
the QBSA) Arcon had failed completely to carry out work required in a
direction to rectify issued by the QBSA on 24 September 2012.
[4] While the review proceedings were making their way through the Tribunal,
on 14 March 2013 the decision of the Supreme Court in McNab
Constructions Australia Pty Ltd v Queensland Building Services Authority1
was handed down. That case concerned the statutory requirement that at
least 28 days had to be given to a builder to carry out rectification work in
a direction to rectify.2 Dalton J decided that the 28 days started when the
builder received the direction, rather than when the direction was dated
and posted to the builder. The QBSA was in the practice of posting
directions and only allowing 28 days from the date when this was done.
[5] Because of that decision, the direction to rectify issued by the QBSA on
24 September 2012 and posted on that date to Arcon was known to be
void because it did not give the required 28 days period in which to carry
out the work.
[6] Solicitors on Arcon’s behalf say that the QBSA should have withdrawn the
scope of works sent to Arcon on 27 February 2013 as soon as McNab
was handed down or at least after they suggested this course of action in
a letter of 9 April 2013. They say that because this was not done, further
costs were expended in these proceedings and those costs should be
paid by the QBSA. They also say that their letter was an offer to settle
these proceedings which was not accepted by the QBSA and should have
been.
1 [2013] QSC 057.
2 Queensland Building Services Authority Act 1991 s 72(3).
-- 2 of 7 --
3
[7] The QBSA says that McNab was not fatal to the decision about the scope
of works because a scope of works has validity which is independent of
the direction to rectify. Therefore there was no reason to withdraw it.
In any case it says that it acted reasonably in the proceedings and there is
no reason for QCAT to depart from its usual rule of no order for costs.
[8] However, on 18 June 2013 the QBSA did withdraw the scope of works
and immediately issued a new one. On that basis Arcon sought to
withdraw the review proceedings and now seek costs incurred since the
letter of 9 April 2013 in the sum of $1,870.80.
Considerations
[9] A scope of works is issued by the QBSA when it intends to carry out
rectification or completion of building work under the statutory insurance
scheme it operates.3
[10] The power to carry out such rectification or completion of building work is
in section 74 of the Building Services Authority Act 1991, the relevant part
of which reads:
74 Tenders for rectification work
(1) If rectification work in respect of residential construction work is required
under this Act and the person required to carry out the work does not carry it
out, or have it carried out, within the time allowed by the direction, the
authority must seek tenders for carrying out the work.
(2) The authority must also seek tenders for carrying out building work if the
authority—
(a) is of the opinion that the building work is defective or incomplete; but
(b) has decided not to give a direction under section 72 for the rectification
of the building work.
(3) The authority may accept any tender that it considers appropriate,
irrespective whether the tender was for the lowest cost.
[11] It is clear that in order to reach the position envisaged in s 74(3) of
accepting a tender, either the route provided in subsection (1) or the route
provided in subsection (2) will have been followed. There is no other way
to reach s 74(3). This is because in cases where the QBSA intends to
carry out rectification or completion of building work under the statutory
insurance scheme, inevitably the QBSA will have decided that the building
work is defective or incomplete and that rectification work is required.
Once that decision is made, then the QBSA will decide whether to issue a
direction to rectify. If a direction to rectify is issued and the work is not
carried out then the route in subsection (1) is followed. If a direction to
rectify is not issued then the route under subsection (2) is followed.
[12] These two routes are therefore separate and independent of each other.
In this case it was the route under subsection (1) that was followed.
However the relevant direction to rectify was posted to Arcon and gave it
3 The Queensland Home Warranty Scheme.
-- 3 of 7 --
4
28 days from that date to rectify the work. Under the authority of McNab it
was therefore void. This means in turn that the QBSA could not proceed
under subsection (1) because there had been no direction to rectify under
that subsection. It follows that the decision about the scope of works
which was the subject of this review was also invalid, because that
decision was in pursuit of the intention to seek tenders for the QBSA to
carry out the work.
[13] The decision about the scope of works could not be converted in some
way into one under subsection (2). That subsection only applies where
the QBSA decides not to give a direction to rectify and that had not
happened.
[14] It follows that the proceedings before QCAT for a review of the decision
about the scope of works would inevitably succeed because of McNab.
[15] The QBSA were a party to McNab and would have received that decision
soon after it was handed down on 14 March 2013 or soon after.
[16] By a letter dated 9 April 2013 the Applicant’s solicitors wrote to the
solicitors for the QBSA and suggested that the existing scope of works
should be withdrawn, and that a fresh direction should be issued
complying with section 72 of the Act. They said that if this did not happen
then they would have no alternative but to apply to the Supreme Court for
declarations. They warned the QBSA that if they had to do this they would
seek the costs of the application to the Supreme Court on the indemnity
basis.
[17] To my mind for the reasons given above, the only reasonable course of
action open to the QBSA in the circumstances was to accept that the
original direction was void, and that the decision about the scope of works
could not stand either. Inevitably this would have meant that the QCAT
proceedings would immediately come to an end. I do not agree with the
QBSA that the proceedings could have been converted into a review of
some other decision about another scope of works.
[18] The difficulty with a course of action other than withdrawal of the scope of
works and an immediate end to the proceedings, was that QCAT had set
two timetables for the proceedings in its directions orders of 8 April and
15 April 2013 and these required work to be done by the parties.
The first timetable was to deal with Arcon’s application for a stay of the
decision about the scope of works. Under that timetable Arcon was
obliged by 15 April 2013 to serve its application for a stay, then by
19 April 2013 to serve its submissions for the stay. In the review
proceedings themselves, Arcon had by 29 May 2013 to serve its
statements of evidence. In the order of 15 April 2013 each side had leave
to be legally represented. So unless the proceedings were to come to an
immediate end, Arcon were incurring legal costs in order to deal with
them.
-- 4 of 7 --
5
[19] By 19 April 2013 in accordance with the Tribunal’s order, Arcon’s lawyers
prepared and filed the submissions for the stay of the decision about the
scope of works. On 29 April 2013, the QBSA agreed by letter to the stay
in respect of the scope of works. But that did not address the review
proceedings themselves. Further legal costs were expended by Arcon’s
solicitors discussing with the QBSA’s solicitors what should happen to
those.
[20] Arcon’s solicitors went ahead with the application to the Supreme Court
for a declaration that the direction to rectify of 24 September 2012 was
void, an application which was almost certain to succeed. Despite the
strong merits of that application, the solicitors for QBSA wrote to the
Tribunal at that time stating that in their view the scope of works was valid
despite any problems with the direction to rectify, and requesting that the
proceedings in the Tribunal be ‘not further progressed pending the
determination of any application to be made by Arcon to the Supreme
Court’. The QBSA accompanied this with an application to the Tribunal to
revoke the timetable for directions and to give Arcon a deadline in which to
apply to the Supreme Court.
[21] Although this letter stated that it was written with a view to saving costs, in
fact it may well have had the opposite effect because it encouraged Arcon
to apply to the Supreme Court and incur costs in doing so, whilst also
requiring Arcon’s solicitors to respond to yet another application in the
Tribunal, when in fact the only reasonable reaction to McNab was to
accept that the process was defective and to start again.
[22] At this time there was correspondence between the solicitors for both
sides which did not progress the matter further to its inevitable conclusion.
[23] Finally by letter dated 18 June 2013, the solicitors for the QBSA withdrew
the scope of works of 27 February 2013. The withdrawal of the review
proceedings soon followed.
[24] In resisting this claim for costs, the solicitors for the QBSA argue that the
review proceedings could have proceeded despite the defective direction
to notify, because the Tribunal’s jurisdiction under section 86 of the 1991
Act is not to review a document (in this case the scope of works), but
instead is to review a decision about a document. JM Kelly (Project
Builders) Pty Ltd v Queensland Building Services Authority [2013] QCAT
216 is relied on. Therefore it is argued that even if the scope of works is
defective, the review proceedings could still have proceeded to decide
whether or not the decision about the scope of works was justified.
[25] Technically this argument is correct and in JM Kelly the Tribunal allowed
an application to review a decision to issue a direction to rectify to
proceed, despite the fact that the direction itself was void by reason of
McNab. But the argument ignores the fact that these proceedings involve
a later step. The sequence in these proceedings was:
(a) decision to issue direction to rectify;
-- 5 of 7 --
6
(b) direction to rectify;
(c) decision to issue scope of works;
(d) scope of works.
[26] It is correct that only (a) and (c) can be reviewed in the Tribunal.
When reviewing (a) the validity of (b), and the validity of (c) and (d) if they
are reached, is irrelevant as found in JM Kelly. Equally, when reviewing
(c) the validity of (d) is irrelevant. However, the validity of (c) relies upon
(a) and (b). If (b) did not happen then it must follow that the decision (c)
should not have been made.
[27] Whilst this is a subtle distinction I think it should have been obvious to
QBSA that this was the result of McNab fairly quickly after that decision
was handed down.
[28] The usual rule in QCAT under section 100 of the QCAT Act is that each
party must bear their own costs. Under section 102 costs can be awarded
against a party if the Tribunal considers the interests of justice require it to
make the order. In deciding whether to do so, the Tribunal may have
regard to various matters. The most relevant matters for my consideration
is in paragraph (3)(a) that is, whether a party to a proceeding is acting in a
way that unnecessarily disadvantages another party to the proceeding,
and (3)(c) that is, the relative strengths of the claims made by each of the
parties to the proceeding.
[29] Once McNab was handed down, the merits of resisting the review
proceedings were zero. The QBSA prevaricated in facing the inevitable in
these proceedings. What should have happened is that soon after McNab
was published and certainly by 9 April 2013 when prompted by Arcon’s
solicitors to do so, the decision to issue the scope of works should have
been reversed and the scope of works should have been withdrawn.
Instead, the scope of works was only withdrawn two months later.
As a result Arcon was unnecessarily disadvantaged because it incurred
further legal expense. Arcon had no choice but to incur that further legal
expense since it had to comply with the orders of the Tribunal and to
continue to prosecute the review proceedings. In the circumstances
I regard it as in the interests of justice to make an order for costs in
Arcon’s favour in relation to the costs incurred after 9 April 2013.
This is because I regard the circumstances as pointing so compellingly to
a costs award that they overcome the strong contra-indication against
costs orders in section 100 of the QCAT Act.4
[30] Section 105 authorises the Tribunal to make a costs order in other
circumstances as provided by the rules. One of those circumstances is
under Rule 86 which applies where an offer to settle the dispute was
made but not accepted. In its submissions the QBSA has argued that
Rule 86 does not apply in this case and one of the reasons for that is that
no decision has been made by the Tribunal as required by Rule 86(1)(c).
4 the test applied by Justice Wilson President in Ralacom Pty Ltd v Body Corporate for
Paradise Island Apartments (No 2) [2010] QCAT 412 at [29].
-- 6 of 7 --
7
Here the application for review was simply withdrawn by Arcon and
therefore I agree with this submission by the QBSA. But that is not the
ground on which I make this order.
[31] By section 107 of the QCAT Act, the Tribunal is encouraged to fix costs if
possible and I have the advantage of a costs statement submitted on
Arcon’s behalf. The QBSA contend that the amount claimed is excessive
for two reasons. Firstly it is based on the scale of costs used in the
Supreme Court, and it ought to be based on the scales applicable in the
District Court or Magistrates Court. Secondly it includes the cost of
communicating with the client about what is happening to the Tribunal
proceedings and taking instructions, and therefore the costs claimed
include indemnity costs.
[32] I am satisfied that it is appropriate to fix the costs rather than ordering
them to be assessed. When fixing costs, the Tribunal is not bound by any
particular scale of costs, although the scales used by the mainstream
courts can be a useful guide. Also the Tribunal is also not bound by any
rules of assessment or usual practice as to the basis of assessment
(standard or indemnity). The aim is to make an award which is reasonable
and appropriate in the circumstances of the case.
[33] I regard the hourly rates and the itemised costings for each activity in the
costs statement submitted on Arcon’s behalf as reasonable. I also regard
it as reasonable to include in the costs statement the costs of keeping the
client informed and where necessary taking instructions from the client.
A separate calculation has been made for costs from 9 April 2013 in the
sum of $1,870.80. I accept that as a reasonable approach and order the
QBSA to pay to Arcon its costs in these proceedings incurred after 9 April
2013 fixed at $1,870.80.
-- 7 of 7 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2013/573