Coral Homes Qld Pty Ltd v Queensland Building Services Authority [2013] QCAT 510
CITATION: Coral Homes Qld Pty Ltd v Queensland Building
Services Authority [2013] QCAT 510
PARTIES: Coral Homes Qld Pty Ltd
(Applicant/Appellant)
v
Queensland Building Services Authority
(Respondent)
APPLICATION NUMBER: GAR076-11, GAR177-11, GAR229-11,
GAR230-11, GAR133-11, GAR341-11,
GAR342-11 and GAR143-11
MATTER TYPE: Building matters
HEARING DATE: 16 September 2013
HEARD AT: Brisbane
DECISION OF: P Roney QC, Member
DELIVERED ON: 26 September 2013
DELIVERED AT: Brisbane
ORDERS MADE: The application for orders that the
Respondent Authority pay the Applicant’s
costs in proceedings numbered GAR076-11,
GAR177-11, GAR229-11, GAR230-11,
GAR133-11, GAR341-11, GAR342-11 and
GAR143-11 is dismissed.
CATCHWORDS: PROCEDURE – COSTS – Queensland Civil
and Administrative Tribunal Act 2009 ss 100,
102(3) and Rule 86 of the Queensland Civil and
Administrative Tribunal Rules – Discretion to
award costs in administrative review matters to
a successful Applicant – whether prima facie
position in s 100 should be displaced and costs
ordered against unsuccessful respondent under
s 102; Building work – direction to rectify,
residential property with defective foundations –
costs of applications to review decisions which
are initially resisted then conceded - absence of
a final hearing on the merits - Calderbank offer;
indemnity costs
-- 1 of 17 --
2
LEGISLATION CITED:
Queensland Civil and Administrative Tribunal
Act 2009 (QCAT Act) ss 19, 20, 21, 100, 102,
102(3)
Queensland Building Services Authority Act
(QBSA Act) ss 72(2), 72(14)
Commercial and Consumer Tribunal Act 2003
(CCT Act) (repealed) ss 70, 71
CASES CITED:
McNab Constructions Australia Pty Ltd v
Queensland Building Services Authority [2013]
QSC 57
Ralacom Pty Ltd v Body Corporate for Paradise
Island Apartments (No 2) [2010] QCAT 412
South East Queensland Electricity Board v
Australian Telecommunications Commission
Qld [1989] FCA 15
Re Minister for Education and Ethnic Affairs, ex
parte Lai Qin (1997) 186 CLR 622
Ustaro v Queensland Building Services
Authority [2005] QCCTB 4
Queensland Building Services Authority v
O’Brien & Ors [2002] QDC 329
Demac Homes (Qld) Pty Ltd v Queensland
Building Services Authority & Others [2011]
QCAT 331
Rix v Queensland Building Services Authority
[2011] QCAT 333
Queensland Building Services Authority v
Johnston [2011] QCATA 265
APPEARANCES and REPRESENTATION (if any):
APPLICANT: Mr T Matthews, Counsel instructed by Holding
Redlich Lawyers
RESPONDENT: Mr B Turnbull, Solicitor HWL Ebsworth Lawyers
REASONS FOR DECISION
Index ......................................................................................................... Page
Introduction/Background 3
The current statutory position – ss 100 and 102 of the QCAT Act 5
The Authority‘s reasons for their decisions 8
The Applicant‘s arguments 9
The approach to be adopted absent findings on the merits 11
The relevant considerations under section 102 14
The relevance of the Applicant‘s Calderbank offers 16
-- 2 of 17 --
3
Introduction/Background
[1] This application involves eight separate review proceedings initiated in the
Tribunal and in respect of each of those, the Applicant in each case, Coral
Homes Qld Pty Ltd, seeks orders that the Queensland Building Services
Authority (the Authority) pay the costs of and incidental to each of the
applications on an indemnity basis.
[2] The relevant applications to which this proceeding relates and the
properties to which they relate are as follows:
a) 13 Bell Street, Greenmount – GAR076-11;
b) 32 Moore Road, Torrington – GAR177-11;
c) 30 Pendoma Drive, Hodgson Vale – GAR229-11;
d) 68 Gowrie Street, Kingsthorpe – GAR230-11;
e) 60 Alawoona Street, Redbank Plains – GAR133-11;
f) 23 Davillea Court, Fernvale – GAR341-11;
g) 118 Tullamore Way, Gleneagle – GAR342-11; and
h) 54 Shoesmith Drive, Westbrook – GAR143-11.
[3] In most cases the Applicant primarily sought a review of a decision by the
Authority to issue a direction to rectify defective works at each of the eight
sites. There was commonality to some significant degree, although not
entirely so, in respect of the relevant defective work at each of the relevant
sites in that each direction was concerned with the rectification of damage
to, and associated with defective footings and slabs associated with the
homes constructed. Each involved the use of what appears to have been
a defective engineering design based upon conduct by an independent
contractor which may have led to those designs being inadequate. There
is dispute as to whether there might have been fault attributable to the
construction methods adopted by the Applicant in each case and as to
whether it was relevant that there might have been contractual
responsibility which lay with the Applicant to the relevant homeowner or
the condition of those slabs, notwithstanding that the slabs themselves
were not designed by the builder, or the builder‘s subcontractor.
[4] Some minor distinctions can be drawn between the circumstances of the
different review applications. Effectively the proceeding relating to the
property at Hodgson Vale was used by the Applicant as a test case for
determining the critical legal issues which were said to apply broadly to all
eight of them. A number of the relevant applications, namely that at
Redbank Plains and at Westbrook involved the issuance of a scope of
works rather than directions to rectify. In one of the review applications,
that involving the Westbrook property, there was no evidence filed, and no
statement of reasons for the decision in that case to issue a scope of
works. In most other respects the relevant circumstances to be
considered for the purposes of whether to order costs against the
Authority are common to all.
-- 3 of 17 --
4
[5] In McNab Constructions Australia Pty Ltd v Queensland Building Services
Authority [2013] QSC 57, directions to rectify given by the Authority in
respect of defective work were held to be void on the basis that they were
required to give 28 days to rectify the works but did not. The decision in
McNab was delivered on 14 March 2013. On 29 April 2013, the
Authority‘s solicitors wrote to the solicitors for the Applicant advising that
on the basis of the reasoning in McNab, the Authority conceded that six of
the eight directions which were the subject of applications for review were
void. It went on to mention the property at Redbank Plains and suggested
that it was not affected by the decision in McNab, and the Authority
considered the direction there to be valid. It invited comment.
[6] On 1 July the solicitors for the Authority wrote to the solicitors for the
Applicant referring to each of the applications, except for that which
related to the Redbank Plains property, indicating that, without admission,
it was prepared to withdraw the decision, to direct rectification of the
Tribunal work and that it would advise the Tribunal that the Authority had
withdrawn the decision in each of those cases to ―overcome any perceived
(though no admitted) procedural issues‖. It contained a consent order
which sought to deal with that position. Since then the relevant directions
or decisions to issue a scope of works have been set aside, by consent.
[7] When I invited Mr Turnbull, the solicitor for the Authority to explain why
two of the proceedings to which the McNab decision did not apply were
also now the subject of a concession that the relevant directions or
decisions under review ought be set aside, no explanation was
forthcoming. I was therefore left in the position, effectively, of being asked
by the Applicant to infer that the thing which all proceedings had in
common, the defence to them, and indeed the decisions which the
Authority had made in respect of them, were manifestly untenable.
[8] The submission made for the Applicant, not only in support of the
proposition that costs ought be awarded to it, but that they should be
awarded on an indemnity basis, was that ―most if not all‖ of the following
were made out here:
a) good reason was shown than the terms of section 100 of the QCAT
Act as to why an order ought be made. These considerations
included the nature and complexity of the dispute, the relative
strengths of the claims and the fact that it was contended that there
were relevant Calderbank offers which had been made;
b) the proceedings were commenced and continued in wilful disregard
of known facts;
c) allegations were made by the Authority which ought never have been
made;
d) there was undue prolongation of a case by groundless contentions by
the Authority;
e) there was evidence of particular misconduct that caused loss of time
to the Tribunal or other parties;
-- 4 of 17 --
5
f) there were unreasonable refusals of offers to compromise;
g) there was irresponsible conduct by the Authority which exposed the
Applicant to costs which in fairness should be ordered on an
indemnity basis; and
h) the Authority persisted in a practically hopeless case which the
Authority knew was contrary to the facts or despite receiving
evidence that overwhelmingly contradicted that case.
The current statutory position – ss 100 and 102 of the QCAT Act
[9] The statutory position is that set out in ss 100 and 102 of the QCAT Act.
They provide as follows:
100 Each party usually bears own costs
Other than as provided under this Act or an enabling Act, each party to a
proceeding must bear the party's own costs for the proceeding.
102 Costs against party in interests of justice
(1) The Tribunal may make an order requiring a party to a proceeding to pay all or
a stated part of the costs of another party to the proceeding if the Tribunal
considers the interests of justice require it to make the order.
(2) However, the only costs the Tribunal may award under subsection (1) against a
party to a proceeding for a minor civil dispute are the costs stated in the rules as
costs that may be awarded for minor civil disputes under this section.
(3) In deciding whether to award costs under subsection (1) or (2) the Tribunal may
have regard to the following--
(a) whether a party to a proceeding is acting in a way that unnecessarily
disadvantages another party to the proceeding, including as mentioned in
section 48(1)(a) to (g);
(b) the nature and complexity of the dispute the subject of the proceeding;
(c) the relative strengths of the claims made by each of the parties to the
proceeding;
(d) for a proceeding for the review of a reviewable decision--
(i) whether the applicant was afforded natural justice by the decision-
maker for the decision; and
(ii) whether the applicant genuinely attempted to enable and help the
decision-maker to make the decision on the merits;
(e) the financial circumstances of the parties to the proceeding;
(f) anything else the Tribunal considers relevant.
[10] In Ralacom Pty Ltd v Body Corporate for Paradise Island Apartments
(No 2) [2010] QCAT 412 the President Justice Wilson was considering the
costs question where the proceeding had been commenced when one
statutory costs regime applied, but which concluded under the current
scheme under the QCAT Act. He said:
21. The respondent relies on the decision of the Court of Appeal in Tamawood Ltd
& Anor v Paans [2005] QCA 111, a case decided under the costs provision of the
now repealed Commercial and Consumer Tribunal Act 2003 (CCT Act). Although
those provisions are not analogous to the equivalent provisions under the QCAT
Act, the principles found in Tamawood provide guidance about the circumstances
-- 5 of 17 --
6
in which it may be in the interests of justice for this Tribunal to award costs against
parties.
22. In Tamawood, Ms Paans commenced proceedings in the CCT for damages
against Tamawood Ltd and another party. The two matters were heard together
and Ms Paans was awarded monetary damages. The CCT, however, refused to
order costs in her favour.
23. All parties then sought leave to appeal to the District Court, where the appeals
from the respondents were refused, but Ms Paans was awarded her costs in the
proceedings. The respondents than sought leave to appeal that costs decision to
the Court of Appeal, contending that the decision of the District Court was based on
an erroneous construction of ss 70 and 71 of the CCT Act. Those provisions state:
70 Purposes of div 7
The main purpose of this division is to have parties pay their own costs
unless the interests of justice require otherwise.
71 Costs
…
(4) In deciding whether to award costs, and the amount of the costs, the
Tribunal may have regard to the following—
(a) the outcome of the proceeding;
(b) the conduct of the parties to the proceeding before and during the
proceeding;
(c) the nature and complexity of the proceeding;
(d) the relative strengths of the claims made by each of the parties to
the proceeding;
(e) any contravention of an Act by a party to the proceeding;
(f) for a proceeding to which a State agency is a party, whether the
other party to the proceeding was afforded natural justice by the State
agency;
(g) anything else the Tribunal considers relevant.
Examples of paragraph (g)—
The Tribunal may consider whether a party to a proceeding is acting in
a way that unreasonably disadvantages another party to the
proceeding.
The Tribunal may consider whether the proceeding, or a part of the
proceeding, has been frivolous or vexatious.
(5) A party to a proceeding is not entitled to costs merely because—
(a) the party was the beneficiary of an order of the Tribunal; or
(b) the party was legally represented at the proceeding.
24. The similar QCAT Act provision to s 70 is, it might be said, in terms that more
plainly indicate that the legislature had turned its face against awards of costs in
this Tribunal: s 100 says that ‗Other than as provided under this Act or an enabling
Act, each party to a proceeding must bear the party’s own costs for the
proceeding‘.
25. In considering ss 70 and 71 Keane JA (as his Honour then was) referred,
however, to two matters relevant here. First, his Honour held that the CCT
provisions negated the traditional proposition that costs should prima facie follow
the event (unless of course that the Tribunal considers that another order is more
appropriate) and that the nature and extent of the power to award costs could only
be discerned by close consideration of the terms of the statute which created and
-- 6 of 17 --
7
prescribed the occasions and conditions for its exercise 7. Sections 100 and 102 of
the QCAT Act attract the operation of the same principles.
26. Second, Keane JA was of the view that where the complexity of the matter
justified legal representation, it would not be in the interests of justice to bar the
successful party from recovering costs that were reasonably necessary to achieve
a satisfactory outcome.
27. That conclusion must, here, be considered in the light of the difference between
s 70 of the CCT Act and s 100 of the QCAT Act. Section 70 speaks of a ‗main
purpose‘, but s 100 mandates that parties shall bear their own costs. Section 70
contains, within itself, a reference to the condition or circumstance in which the
main purpose may be subsumed to the interests of justice; s 100 has no such
proviso, although it appears later, in s 102(1).
28. Under that subsection QCAT has a discretion to make a costs order ‘…if the
Tribunal considers the interests of justice require it…’. Section 102(3) says that, in
deciding whether to award costs, the Tribunal may have regard to matters not
dissimilar to those set out in s 71 of the CCT Act including, in particular for present
purposes, the nature and complexity of the dispute and the relative strength of
each party‘s claims.
29. Under the QCAT Act the question that will usually arise in each case in which
costs are sought is whether the circumstances relevant to the discretion inherent in
the phrase ‗the interests of justice‘ point so compellingly to a costs award that they
overcome the strong contra-indication against costs orders in s 100.
30. I am satisfied that is the case here. As the voluminous supporting material
indicated, the application brought in Ralacom‘s name involved a complex history of
disputes between it, and the body corporate. Urgent injunctive relief was sought, as
was relief under the BCCMA, which on any view involved some complexity, and
urgency, and warranted the instruction of solicitors and counsel by the body
corporate. The standing of the company was unclear, and confused by the
applicant‘s failure to inform this Tribunal about the real outcome of the Supreme
Court Proceedings.
[11] Later, in McEwen v Barker Builders Pty Ltd [2010] QCATA 49 the
President, Justice Wilson said in an Appeal heard on the papers:
[13] As to costs, the starting point in this Tribunal is that each party must bear its
own: QCAT Act, s 100. The statutory presumption may be displaced if the Tribunal
considers it in the interests of justice to order a party to pay all or part of the costs
of another party: s 102(1). The phrase ―in the interests of justice‖ is not defined in
the Act but is to be construed according to its ordinary and plain meaning,
conferring a broad discretionary power on the decision-maker 8.
[14] In determining whether it is in the interests of justice to award costs against
another party, the Tribunal may have regard to the nature and complexity of the
dispute; the relative strengths of the claims made by each of the parties; and,
whether a party has acted in a way that unnecessarily disadvantages another
party: QCAT Act, s 102(3).
…
[17] The language of s 100 plainly indicates that the legislature has turned its face
against awards of costs in this Tribunal. The question that will usually arise in each
case in which costs are sought is, then, whether circumstances relevant to the
discretion inherent in the phrase ‗the interests of justice‘ have arisen; and, whether
or not they point to a costs award in a sufficiently compelling way to overcome the
statutory hurdle.
[12] I respectfully agree with the approach that the President has taken in
Ralacom and the McEwen decisions. That means that the relevant task is
to proceed on the basis that there is a statutory presumption that parties
-- 7 of 17 --
8
will bear their own costs in a proceeding for the Tribunal, including those in
the review jurisdiction of the Tribunal, but that presumption may be
displaced if the Tribunal considers it in the interests of justice to order a
party to pay some or all of the costs of another.
The Authority’s reasons for their decisions
[13] The reasons for the decisions to issue the directions to rectify in those
matters where directions were issued are not before me. I was however
given one of the sets of reasons, and which the parties were content with
me to proceed with on the basis that similar if not identical reasons were
given in each of the other cases.
[14] Those reasons referenced the fact that the Authority had power to direct
rectification of defective building work and to direct a person who carried
out the work to rectify it. It relied upon the power to take into consideration
―all of the circumstances‖ it considers are reasonably relevant pursuant to
section 72(2) of the QBSA Act in determining the direct rectification. The
factors it was to take into account were:
a) whether the building work was defective under the relevant policy;
and
b) whether it was reasonable in the circumstances to issue the direction
to rectify to the builder.
[15] The Authority objectively determined that the building work undertaken by
the Applicant was defective. In making the decision the Authority made
reference to the fact that the defects were defects about which a direction
would normally be issued under the defects policy and that the Authority‘s
advising engineer had concluded:
a) that the site was a class E site and the site was to be ripped to
800mm deep;
b) that the ripping to be undertaken on the site would consist of certain
specified depths and areas beyond the edge of the proposed slab.
[16] The other matters to which the Authority had regard were that the footing
system of the dwelling was a stable slab footing system which was
effectively a piered slab that was intended to act as a suspended slab and
that soil interaction tended to be prevented by the ripping of the ground
surface prior to the construction of the footing system.
[17] Furthermore, reference was made to the conclusion that the original site
classification did not appear to be correct for the site conditions even given
good conditions of drainage and maintenance.
[18] Further it was contended that the footing system did not comply with the
requirements of the relevant Australian Standard for the original site
classification.
-- 8 of 17 --
9
[19] It was concluded that the major contributing causes to the failure of the
footing system are:
a) ‗possible contribution from poor site drainage conditions that may
have been present shortly after the completion of the construction of
the dwelling‘; and
b) ‗the failure of the ripped soil to prevent soil structure interaction
across the majority of the areas of the buildings (sic) footing system‘ .
[20] On that basis the Authority concluded that it was not unfair nor
unreasonable to issue a direction to the builder.
[21] I pause to mention that these reasons do not expressly reference any
particular fault on the part of the builder other than to do with the way in
which the drainage system and soil conditions were dealt with. Although
mention is made of the site classification and the footing system design,
they do not expressly say that the builder was responsible for that, nor for
that matter does it say that it is not. This issue became important in the
argument before me because essentially the Applicant argued that the
Authority‘s own material showed that from an early stage the Authority‘s
experts who were advising it in relation to the direction, had acknowledged
that the failure of the footings had occurred without any fault on the part of
the builder in the way the building work was carried out.
The Applicant’s arguments
[22] The Applicant sought to demonstrate, both in support of the argument that
costs ought be ordered, and further that they ought be ordered on an
indemnity basis that:
a) the Applicant‘s expert evidence and evidence in compliance with the
rectification of building work policy showed that there was a high level
of commitment to that policy and that its commitment in that regard
was not contested by material from the Authority;
b) the Applicant had procedures in place to ensure compliance with the
subsidence policy, that evidence too not having been contested; and
c) the Applicant had a practice of engaging engineers registered with
the Queensland Board of Professional Engineers to conduct soil
testing and designing of a footing and slab system appropriate to the
soil classification and in the case of each of these homes engaged
Evolution Professional Engineers Pty Ltd which in these cases went
ahead and conducted the relevant design.
[23] The material before me does not include any of the relevant construction
contracts. It is therefore not clear whether the engineer in question was a
nominated contractor or not under those contracts. But having regard to
the fact that the material discloses that the Applicant used the same
engineer for each of these residences, I am prepared to infer that in each
case it was the builder that procured the engineer, and in effect nominated
that engineer‘s design as that to be used under the contract. Therefore, to
the extent that there might be express or implied warranties in the contract
-- 9 of 17 --
10
as to the suitability of any of the work for its intended purpose, there was
always the potential for an argument to the effect that the Applicant might
be held to have been in some way at ―fault‖, or at least responsible for the
resultant work. That is, even if it cannot be suggested that the builder
itself was negligent, or failed to exercise diligence in relation to the quality
of the work for the engineering design in question, there might be a level
of responsibility for the quality of the finished work.
[24] In February 2010 an officer with the Applicant received a telephone call
from a Mr Stick from the Authority to discuss a report from the engineer
responsible for the design and the possibility that the Authority would issue
a direction to rectify. In that discussion, Mr Stick, from the Authority,
mentioned that the Applicant would not be found at fault, but that the
engineer would. Further, at the nub of the Applicant‘s argument, it is the
contention that the Authority‘s decision to issue the directions to rectify
were never supported by clear evidence that Coral Homes was actually at
fault.
[25] One of the matters to which the Applicant specifically made reference in
seeking to demonstrate that the Authority did not in fact properly, or bona
fide exercise its discretion under section 72(14) of the QBSA Act because
the directions issued were issued in order to establish what would amount
to be ―test cases‖ which would in some way place these cases before this
Tribunal for a determination, so as to provide the Authority with guidance
as to the correct way in which to treat builders in the position of this one.
In support of that submission reference was made to an email to the
Applicant from Mr Stick of the Authority of 2 March 2011 which was in
these terms:
...
This email is a courtesy to advise of BSA‘s future action on the subsidence related
cases before us particularly in the Toowoomba region.
I have had the opportunity to fully review the Eric Fox report and the subsequent
report from Lindsay Reid and BSA is of the opinion that Coral Homes has a case to
answer in terms of these subsidence cases.
The suggestion I made to get the engineers together to discuss I believe based
upon their reports will not resolve the issues as they are worlds apart.
BSA is desirous of drawing a line under these jobs and as such we have
determined that Direction to Rectify will be issued against Coral Homes regarding
those subsidence cases.
By issuing these directions Coral Homes will have the opportunity to review those
directions should your company feel aggrieved by BSA‘s determination in QCAT.
QCAT will ultimately decide whether BSA‘s position is correct in that building work
performed by Coral Homes is defective.
There will no doubt be much debate regarding the efficacy of the engineering
design etc in any review application that may be lodged and BSA is most
supportive of that debate being had in QCAT.
I have instructed our Toowoomba office to prepare and issue the Directions to
Rectify as a matter of priority as these matters have dragged on to (sic) long
already from the relevant homeowner‘s perspective and no doubt also from Coral
Homes and BSA‘s alike.
-- 10 of 17 --
11
I expect the relevant directions will be issued by the end of the week.
David, whilst I expect Coral Homes will not be happy with our decision a
determination is required in these matters to bring some finality but also any QCAT
ruling will provide guidance to both Coral Homes and BSA on how these matters
should be viewed in the future if similar cases arise.
Please feel free to contact me or alternatively Rod Turkington (BSA‘s Toowoomba
Area Manager) who will be handling these matters on behalf of BSA.
[26] There has of course been no hearing on the issue of whether the Authority
did not bona fide exercise the discretion vested in it. It suffices to note that
in that email, the fact that the Authority had in fact made a decision is
referenced, albeit in the context of recognising that this Tribunal would
decide if its position ―was correct‖.
The approach to be adopted absent findings on the merits
[27] The current proceedings are of course review proceedings in the review
jurisdiction in Division 3 of the QCAT Act. Sections 19 and 20 of the
QCAT Act make clear that this Tribunal has all the functions of the
decision maker for the reviewable decision being reviewed. It also makes
clear that the purpose of a review of the decision is to produce the ‗correct
and preferable decision‘. The Tribunal is to hear and decide a review by
way of a fresh hearing on the merits. Unlike the position that ordinarily
prevails in an adversarial environment, the obligation on the Respondent
in a review application is to ‗use his or her best endeavours to help the
Tribunal so that it can make its decision on the review‘.1
[28] The fact that review applications also invoke different considerations to
those in an ordinary inter parties dispute, may be seen from the fact that
there are special considerations to be considered under section 102 of the
QCAT Act when deciding whether to award costs in such cases. Where
the proceeding is of a kind such as that here, relevant matters include
whether the Applicant was afforded natural justice by the decision maker,
and whether the Applicant genuinely attempted to enable and help the
decision maker to make the decision on the merits. I pause to mention
that I do not regard either of those factors as being relevant to the decision
I am to make here because there is no question that natural justice was
afforded and no question about whether the Applicant attempted or did not
attempt to help the decision maker make the decision on the merits.
[29] The fact that there has been no determination of these issues on the
merits presents difficulties for the Applicant in its arguments either in
support for any kind of costs order, and even more so for an order that the
costs be paid on an indemnity basis.
[30] In the context of administrative review, Pincus J, as he then was in South
East Queensland Electricity Board v Australian Telecommunications
Commission Qld [1989] FCA 15, was dealing with a case where there had
not been a final hearing, but where the parties agreed that the Court
should deal with the whole question of costs.
1 See section 21 of the QCAT Act.
-- 11 of 17 --
12
[31] His Honour was considering how the discretion should be exercised where
there has been no trial. On the issue of the correct approach, His Honour
said as follows:
19 Although the parties have agreed that I should determine it on the
submissions made to me, there is in my view no certain basis on which to
determine the question of liability for costs. One possible solution is simply to
make no order as to costs, on the ground that it is not perfectly clear which
side, if either, should pay them.
20. As a matter of legal policy, however, that appears to be an unsatisfactory
way of disposing of the matter; the Queensland decisions mentioned above,
also, tend against it. The parties' submissions are at one in urging upon me
the view that litigants should not be forced to go on, or discouraged from
settling their differences, by an inability to resolve a dispute as to costs.
I agree; if a piece of litigation has become academic, except as to the issue
of costs, it appears that the Court should co-operate as far as it reasonably
can, in disposing of the question of costs at the parties' request, without
requiring a trial to determine who would have won.
21. Here, although the parties have submitted that I should not attempt to say
who would have won at a trial, the applicant has placed submissions before
me relevant to its claim that it acted reasonably in bringing the proceedings,
and I have taken them into account in assessing its case. Those
submissions, which rely largely upon documents discovered, have persuaded
me that the applicant had, on the face of it, a fairly strong case - one more
promising than that of the respondent. I have also taken into account against
the respondent that the cause of the litigation's not having culminated in a
trial was that the respondent changed its mind, albeit in the circumstances
outlined above. It will be ordered that the applicant's costs of the
proceedings, including reserved costs, be taxed and that 80% of the sum so
fixed be paid by the respondent to the applicant.
[32] The relevant circumstances to which his Honour referred were not that the
decision maker changed his mind, but there was a change in Government
policy; that, as he explained it;
16. While there can be no suggestion that the Minister's statement absolutely
forced a reconsideration of the decision complained of in these proceedings,
I think I should accept that, as a practical matter, the statement and the
change in Government policy it reflected brought about the respondent's
abandonment of its previous stance. This is to be distinguished both from the
case in which a decision-maker just changes his mind, having reconsidered
the facts, and the case where the decision-maker is obliged to reach a new
and opposite conclusion by a change in external circumstances. In the former
case, but not necessarily in the latter, I should think that the decision-maker
would ordinarily pay the costs of incomplete proceedings of this kind; the
present situation falls between the two categories just mentioned.
[33] The discretion to order costs as the Court saw fit in that case was
unimpeded by anything the equivalent of section 100 of the QCAT Act.
[34] In Re Minister for Education and Ethnic Affairs, ex parte Lai Qin (1997)
186 CLR 622 at p624, McHugh J was focused primarily upon the proper
approach to be taken in administrative judicial review cases, where it
appeared that the Defendant had acted unreasonably in exercising or
refusing to exercise the relevant power, and the Plaintiff had no
reasonable alternative but to commence the litigation. In the course of
those reasons, his Honour also made reference to the decision of Pincus J
-- 12 of 17 --
13
to which I have just made reference. McHugh J‘s judgment said as follows
at pp624 to 625 (footnotes omitted):
In an appropriate case, a court will make an order for costs even when there has
been no hearing on the merits and the moving party no longer wishes to proceed
with the action. The court cannot try a hypothetical action between the parties. To
do so would burden the parties with the costs of a litigated action which by
settlement or extra-curial action they had avoided. In some cases, however, the
court may be able to conclude that one of the parties has acted so unreasonably
that the other party should obtain the costs of the action. In administrative law
matters, for example, it may appear that the defendant has acted unreasonably in
exercising or refusing to exercise a power and that the plaintiff had no reasonable
alternative but to commence a litigation. Thus, for example, in R v Gold Coast City
Council; Ex parte Raysun Pty Ltd, the Full Court of the Supreme Court of
Queensland gave a prosecutor seeking mandamus the costs of the proceedings up
to the date when the respondent council notified the prosecutor that it would give
the prosecutor the relief that it sought. The Full Court said that the prosecutor had
reasonable ground for complaint in respect of the attitude taken by the respondent
in failing to consider the application by the prosecutor for approval of road and
drainage plans.
Moreover, in some cases a judge may feel confident that, although both parties
have acted reasonably, one party was almost certain to have succeeded if the
matter had been fully tried. This is perhaps the best explanation of the unreported
decision of Pincus J in South East Queensland Electricity Board v Australian
Telecommunications Commission where his Honour ordered the respondent to pay
80% of the applicant's taxed costs even though his Honour found that both parties
had acted reasonably in respect of the litigation. But such cases are likely to be
rare.
If it appears that both parties have acted reasonably in commencing and defending
the proceedings and the conduct of the parties continued to be reasonable until the
litigation was settled or its further prosecution became futile, the proper exercise of
the cost discretion will usually mean that the court will make no order as to the cost
of the proceedings. This approach has been adopted in a large number of cases.
(citing Australian Securities Commission (1993) 44 FCR 194; 116 ALR 523;
Seventh Mingcourt Pty Ltd v Lawrence (Fed C, 1 August 1996, unreported) per
Branson J; Coleman v City of Melville (SC(WA), 22 September 1994, unreported)
per Scott J; Compadres Australia Pty Ltd v Waterfront Place No 2 Pty Ltd (SC(Qld),
15 August 1995, unreported) per MacKenzie J; Inprint Ltd v K & D Media Pty Ltd
(administrator apptd) (Fed C, 22 December 1995, unreported) per Einfeld J;
Australian Securities Commission v Berona Investments Pty Ltd 18 ACSR 772.
The critical question in this case then is whether or not the prosecutrix acted
reasonably in bringing these proceedings and whether the respondents acted so
unreasonably in not informing the prosecutor that an application to review the
decision to refuse a visa was being considered that it would be proper for the
minister to pay the whole or part of the cost of the proceedings.
[35] In making his finding, His Honour was able, by consideration of the
decision under review and the affidavit filed in support of the application
for the grant of an order nisi, to conclude that although the prosecutrix had
an arguable case, she did not have strong prospects of success. He was
able to conclude that if he had been called on to make a prediction about
the outcome of her application, he could see that it would probably have
failed. He then went on:
However, as I have said it is not the function of a court on a costs application — in
most cases at all events — to make a prediction as to the outcome of a
hypothetical case. It is enough that an applicant has acted reasonably. There is
-- 13 of 17 --
14
nothing to suggest that the prosecutrix acted unreasonably in bringing her
application, particularly bearing in mind that she faced imminent deportation unless
the decision of the tribunal or the minister was reversed. If the matter had
proceeded further, it would also have been reasonable for the minister to defend
the decision of the tribunal. If no more appeared in the case, I would think there
were no grounds for making an order for costs in favour of the prosecutrix.
The relevant considerations under section 102
[36] Section 100 presumes that ordinarily each party to a proceeding would
bear that party‘s own costs, irrespective of the result. On that basis there
ought be no order for costs even if the Applicant were able to show that it
would have almost certainly have succeeded on its application. That is,
unless the interests of justice ought lead to a different result.
[37] I have carefully considered all the arguments that have been presented on
behalf of the Applicant. It refers to a body of authority which it submits
establishes that it is unreasonable to issue a direction to rectify to a builder
to rectify defective works in circumstances where the builder has simply
complied with the requirements and specifications of an external
engineering design. Whilst there is some authority in which in particular
cases Courts have been prepared to conclude that it was unreasonable to
issue such a direction having regard to the facts, it does not seem to me
the Respondent would necessarily have failed to show that those cases
were distinguishable from the facts here.
[38] Nor does it necessarily follow that because a builder has adopted an
engineer-prepared design, and the builder had engaged that engineer and
his design in many of its construction contracts, that it would be
unreasonable for the Authority to issue a direction to rectify to the builder,
even if the builder could not be said to have been itself negligent in the
design, or application of that design.
[39] It should not be thought however that I am expressing a concluded view
on the merits of either argument. In Ustaro v Queensland Building
Services Authority [2005] QCCTB 4 the Tribunal specifically held that it
accepted that the Authority was entitled to have regard to the overriding
obligation of a builder to supervise employees and subcontractors, that he
was not satisfied in that case that failing some obvious or apparent error in
a design by an engineer that a reasonable builder should identify a
resolve, that a builder has any obligation to do other than comply with the
requirements and specifications of an engineer-prepared design. The
ratio of that case is that the case law authorities ‗establish that for the
purposes of section 72, the issuing of a direction requires an exercise of a
discretion on the part of the Authority (and of course the Tribunal when
considering a review). The section does not require that there be any fault
on the part of the builder himself prior to the issuing of such a direction.
Clearly, the fault or otherwise of the person to whom the direction is to be
given is a matter which the Authority and Tribunal must have regard in
exercising the discretion. However, it is only one of the matters which
must be considered‘.
-- 14 of 17 --
15
[40] Having said that, Member Moon concluded that having regard to the then
policy of the Authority which specified that ‗to avoid responsibility for
rectification under the subsidence policy, the contractor has only to rely on
the information provided by an engineer, follow the requirements of the
engineer and specify it and have the works certified by a competent
person‖ and the fact that the builder had done precisely that, that it was
―not an appropriate case in which a direction should be given to the
builder’.
[41] There are other examples of decisions in which, having regard to the
particular facts of cases, it is not always unfair to the person to whom a
direction is given that that person is being asked to rectify deficiencies in
the work as a result of some specific fault on the part of that person. In
that regard I refer to the examples discussed by His Honour Judge McGill
SC DCJ in Queensland Building Services Authority v O’Brien & Ors [2002]
QDC 329 at [33]-[34].
[42] Having regard to the policy in section 100 of the QCAT Act, even were I
satisfied that the Respondent ought not in the circumstances have issued
a direction to rectify, or issued scopes of works, that alone would not have
been the basis for the making of a costs order against it.
[43] The issues both of fact and law which arose under the applications were
not complex. Notwithstanding the submission of Mr Matthews to the
contrary, it does not assist in this case in arriving at a conclusion about the
level of complexity of the matter to note that Counsel was briefed for the
Applicant. Indeed, the Respondent‘s advocacy was handled by a solicitor.
[44] I have already dealt with the question of the relative strength of the claims.
Whilst arguably the Applicant may have had better prospects, and
certainly was likely to succeed on the basis of the decision in McNab, once
it became aware of the argument it presented, I do not consider that it can
be said that the decisions of the Respondent under review were
demonstrably unreasonable or misconceived.
[45] There are no relevant considerations that relate to the financial
circumstances of the parties.
[46] I do not consider that the mere fact that one of the persons associated
with the Authority expressed a view on the matter which may suggest
some inconsistency amongst those in the Authority as to whether fault was
a relevant factor in the considerations which led to the directions in this
case, leads me to the view that this was a case brought in circumstances
in which review proceedings were never supported by clear evidence that
the Applicant was actually at fault.
[47] It may be accepted that the principal, even not the sole reason for the
Authority‘s change of position was that the decision in McNab invalidated
the directions. Prior to McNab, there was no reason for the Authority to be
on notice that those directions were clearly invalid on the basis eventually
decided in McNab and the challenge to those decisions did not originally
-- 15 of 17 --
16
invoke the arguments which were successful in McNab.
[48] In those circumstances, it does not seem to me that this case bears any
resemblance to the circumstances identified by the President in Ralacom,
which his Honour found that the Applicant brought an application which
was misconceived, futile and persisted in, in circumstances which were
unreasonable and irresponsible. His Honour concluded that the conduct
in question ‗bordered on the inexplicable‘. This is not the case here.
[49] In my view, the interests of justice, in the sense referenced in section 102
of the QCAT Act, do not require the making of a costs order here.
[50] It follows that subject to the question of whether the making of offers to
resolve the matter ought lead to a different result, I would disinclined to
make an order for costs against the Respondent. It obviously follows that
I would have not made that order on an indemnity basis even had
I otherwise been prepared to make an order for costs.
The relevance of the Applicant’s Calderbank offers
[51] There is a body of authority which recognises that Calderbank offers may
be relevant to the exercise of the discretion to award costs.2 This is
implicit also in what appears in Rule 86 of the QCAT Rules. Rule 86
provides as follows:
86 Additional power to award costs if particular offers to settle rejected
(1) This rule applies if—
(a) a party to a proceeding, other than a proceeding for a minor civil dispute,
makes another party to the proceeding a written offer to settle the dispute the
subject of the proceeding; and
(b) the other party does not accept the offer within the time the offer is open;
and
(c) in the opinion of the tribunal, the decision of the tribunal in the proceeding
is not more favourable to the other party than the offer.
(2) The tribunal may award the party who made the offer all reasonable costs
incurred by that party in conducting the proceeding after the offer was made.
(3) If a proceeding involves more than 2 parties, this rule applies only if the
acceptance of the offer would have resulted in the settlement of the matters in
dispute between all the parties.
(4) In deciding whether a decision is or is not more favourable to a party than an
offer, the tribunal must—
(a) take into account any costs it would have awarded on the date the offer
was given to the other party; and
(b) disregard any interest or costs it awarded relating to any period after the
date the offer was given to the other party.
2 See Demac Homes (Qld) Pty Ltd v Queensland Building Services Authority & Others
[2011] QCAT 331; Rix v Queensland Building Services Authority [2011] QCAT 333;
Queensland Building Services Authority v Johnston [2011] QCATA 265.
-- 16 of 17 --
17
[52] An offer was made here relatively late in the course of the subject
proceedings. An offer was made in a letter dated 27 May 2013. The letter
gave notice that if the Applicant was successful in the review proceedings,
it would be applying for indemnity costs against the Authority, and would
rely upon that letter in support of that application.
[53] After setting out why it regarded the Authority as likely to fail, including the
assertion that it would be demonstrated that the decision maker for the
Authority did not in fact make the decision in dispute at all, an offer was
made to resolve the matter on the basis that:
a) both parties consent to allowing the setting aside of each direction
and review proceeding;
b) the directions to rectify were not reissued to the Applicant i.e. there
would be no new ones issued;
c) the Authority did not pursue the Applicant for any payments made
subsequently under the Home Warranty Insurance Scheme in
relation to the properties the subject of review proceedings;
d) the Applicant would provide a written undertaking that it would not
use the Evolution Professional Engineers Pty Ltd or Heltech
Industries Pty Ltd footing and slab design in the construction of any
future residential homes in Queensland; and
e) the Authority pay to the Applicant 80% of all its costs incurred in the
review proceedings.
[54] On any view of the matter, that offer contained terms which went well
beyond the issues which were raised for determination on the review
applications. It involved terms which sought to settle other potential and
yet to be made claims, such as the right to recover sums paid out under
the homeowner‘s policy. Another was that no further directions be issued
to the Applicant. That is not a matter that would have been determined in
this review application. The offer required that the Authority pay the
Applicant 80% of all its costs, in other words, 80% of its costs on an
indemnity basis.
[55] Obviously, apart from obtaining an order by consent that the directions be
set aside, the Applicant has not succeeded in obtaining orders, or a result
which was equal to or better than the basis upon which it was prepared to
resolve the matter in its Calderbank letter earlier this year.
[56] In the circumstances, I do not regard the making of this offer as a basis to
depart from the usual rule in section 100, or in the application of the
provisions of Rule 86 of the Tribunal‘s Rules.
[57] I therefore dismiss the applications.
-- 17 of 17 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2013/510