Contrast Constructions Pty Ltd v Bartlett [2013] QCAT 399
CITATION: Contrast Constructions Pty Ltd v Bartlett [2013]
QCAT 399
PARTIES: Contrast Constructions Pty Ltd
(Applicant)
v
Mr Brett Andrew Bartlett
(Respondent)
APPLICATION NUMBER: BD469-08
MATTER TYPE: Building matters
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Joanne Browne, Member
DELIVERED ON: 5 August 2013
DELIVERED AT: Brisbane
ORDERS MADE: 1. The order made by the Tribunal on 5 July
2013 is amended and the applicant,
Contrast Constructions Pty Ltd is to pay
the respondent, Mr Brett Bartlett the
amount of $218,940.17 plus $130,363.36
in interest by 4:00pm on 5 September
2013.
CATCHWORDS: BUILDING DISPUTE - Application for correction
– where accidental slip or omission
Queensland Civil and Administrative Tribunal
Act 2009, s 135
APPEARANCES and REPRESENTATION (if any):
This matter was heard and determined on the papers pursuant to section 32 of
the Queensland Civil and Administrative Tribunal Act 2009 (QCAT Act).
REASONS FOR DECISION
[1] On 5 July 2013 I ordered that the applicant, Contrast Constructions Pty
Ltd pay the respondent, Mr Brett Bartlett the amount of $219,162.84 plus
$130,547.35 in interest.
-- 1 of 5 --
2
[2] The amount of $219,162.84 awarded to the respondent included an
amount assessed by the Tribunal for alleged incomplete and defective
works that was off-set against money payable to the applicant (by the
respondent) including the balance contract sum and adjustment of time
costs claims also assessed by the Tribunal.
[3] On 15 July 2013 the applicant filed an application seeking an order
pursuant to s 135 of the QCAT Act to correct the amount awarded to the
respondent on 5 July 2013 in relation to the assessed amount for
incomplete and defective works, the amount of $415,429.78;1 and the
amount awarded for interest, the amount of $130,547.35.2
[4] The Tribunal made directions on 16 July 2013 in relation to the filing and
exchange of written submissions in response to the applicant’s application
for correction.
[5] The applicant contends that the Tribunal has ordered an amount in
relation to the alleged value of incomplete and defective works that is in
excess of an amount stated to be the respondent’s position in the agreed
issues for determination handed up at the hearing on 8 February 2013.
[6] The applicant further contends that the Tribunal has calculated interest
payable by the applicant on the total amount assessed for incomplete and
defective work and the respondent should only be entitled to interest on
the net amount.
[7] In relation to the first issue raised by the applicant, the applicant and
respondent agreed on a list of issues to be determined by the Tribunal
during the 5 day hearing. The agreed list of issues included figures
representing “[a] formula after determining the disputed amount” from
which the Tribunal is to determine the “amount due”.
[8] The figures listed on the agreed list of issues document included amounts
being “the value of defective & incomplete work” reflecting each of the
parties’ position in relation to the amounts assessed, by their respective
expert witnesses, for the alleged incomplete and defective works.
[9] The respondent included a figure of $387,357.30 as the value of the
alleged incomplete and defective works. The respondent did not specify,
in the agreed list of issues document, whether the figure of $387,357.30
was inclusive of preliminaries (12%), the builder’s margin (10%) and GST
(10%).
[10] Each party was given an opportunity to file written submissions following
directions made by the Tribunal on 8 February 2013, in relation to the
agreed list of issues to be determined and the evidence before the
Tribunal including issues relevant to determining the value of any
incomplete and defective works; and interest payable.
1 Contrast Constructions Pty Ltd v Bartlett [2013] QCAT 322 at [97].
2 Ibid, at [98].
-- 2 of 5 --
3
[11] The respondent provided “final calculations” in its written submissions filed
on 4 March 2013 and amended written submissions filed on 13 March
2013. The amount of the alleged incomplete and defective works included
in the respondent’s amended written submission filed on 13 March 2013 is
$421,643.37 – this includes an amount for preliminaries (12%), builder’s
margin (10%) and GST (10%).
[12] The applicant also filed written submissions on 6 March 2013 in relation to
the agreed list of issues to be determined and the evidence adduced at
the hearing relating to the assessed amounts for the alleged incomplete
and defective works; and interest payable. The applicant also filed
submissions in reply to the respondent’s amended written submissions
filed on 18 March 2013.
[13] I am not satisfied that the applicant has established any grounds, in its
application and written submissions in support to enliven the Tribunal’s
power under s 135 of the QCAT Act to amend its order made on 5 July
2013, by way of a correction.
[14] The applicant has had an opportunity, in filing its written submissions
including submissions in reply, to put before the Tribunal any submissions
in relation to the agreed list of issues to be determined and the final
calculation of figures such as the value of any assessed alleged
incomplete and defective works based on the evidence adduced at the
hearing; and interest payable.
[15] The Tribunal has, in paragraphs [83] to [97] of its decision, clearly set out
the relevant evidence before it and the evidence that it accepted or
rejected in assessing the amount to be awarded for the alleged incomplete
and defective items.
[16] In relation to the amount of interest payable to the respondent, the
Tribunal has set out in paragraphs [79] to [82] of its decision relevant
findings and has ordered in paragraph [98] the amount to be allowed in
relation to interest payable by the applicant.
[17] The Tribunal is not satisfied that there has been “a clerical mistake; an
error arising from an accidental slip or omission; or a material
miscalculation of figures”, as required under s 135 of the QCAT Act. The
applicant’s contentions in support of the application for correction
otherwise raises issues which require reconsideration of the evidence
adduced at the hearing and the findings made by the Tribunal. The
Tribunal does not have the power under s 135 of the QCAT Act to
reconsider the evidence having delivered its decision on 5 July 2013.
[18] In considering the application for correction filed by the applicant, the
Tribunal has revisited the calculation of its figures in particular the
assessed amounts for the alleged incomplete and defective works.
[19] The amounts claimed by the applicant and respondent in relation to the
value of the alleged incomplete and defective works were based on
-- 3 of 5 --
4
assessments made by the parties’ expert witnesses. The expert
witnesses’ assessments were set out in the joint experts report and
following amendments made to those assessments, final figures were set
out in the amended schedule of incomplete works.3
[20] The Tribunal made findings in paragraph [96] of its decision made on 5
July 2013 as to the assessed amounts allowed for the incomplete and
defective items in dispute. In relation to item 182, sealer to sandstone, the
Tribunal accepted the evidence of the respondent’s expert witness and
allowed the “assessed amount of $7,425”.
[21] The amount of $7,425 was the amount assessed by the respondent’s
expert witness in the joint expert report which was later amended to be the
amount of $7,260 as it appears in the amended schedule of incomplete
works. The assessed amount for item 182 of $7,260 is also reflected in the
respondent’s amended written submissions filed on 13 March 2013 as the
amount claimed (for item 182).
[22] The Tribunal has the power under s 135 of the QCAT Act to correct a
decision made by it in a proceedings if the decision contains “an error
arising from an accidental slip or omission”. The Tribunal has the power to
act under s 135 of the QCAT Act on the application of a party to the
proceeding or on its own initiative.
[23] The amount of $7,425 awarded by the Tribunal in relation to item 182 in
paragraph [96] of its decision is clearly an error arising from an accidental
slip or omission. The Tribunal has allowed the assessed amount by the
respondent’s expert witness and that amount as it appears in the
amended schedule of incomplete works is $7,260 (not the amount of
$7,425).
[24] The Tribunal will therefore allow the application for correction to amend
the amount previously awarded to the respondent, Mr Bartlett for
incomplete and defective items, by deducting the amount of $165 (the
difference in the assessed amount for item 182) from the total value for
incomplete and defective items. The amount payable by the applicant for
interest will also be corrected.
[25] The amended total cost of the defective and incomplete items plus interest
is:
Agreed items $ 184,750.00
Plus items 85 and 430 $ 15,000.00
Plus assessed items $ 106,630.00
Subtotal $ 306,380.00
Plus preliminaries at a rate of 12% ($36,765.60) $ 343,145.60
Plus builder’s margin at 10% ($34,314.56) $ 377,460.16
3 Ibid, at [84].
-- 4 of 5 --
5
Plus GST ($37,746.02) $ 415,206.17
Total value for incomplete and defective items $ 415,206.17
Plus interest at 10% from 15.12.09 to 04.02.13 $ 130,363.36
Final calculations
[26] The Tribunal has assessed the amounts payable under the contract as
follows:
Adjusted contract sum $ 2,520,097.96
Less amounts paid $ 2,382,974.02
Balance contract sum $ 137,123.94
Plus ATC 18.01.07-16.07.07 $ 30,175.00
Plus ATC 14.03.08-15.08.08 $ 9,052.50
Plus ATC 15.08.08-26.09.08 $ 12,070.00
Plus ATC 02.10.08-20.12.08 $ 7,845.50
$ 59,143.00
Less defective & incomplete items $ 415,206.17
Less liquidated damages $ Nil
Total $ 218,940.17
[27] The Tribunal orders that the amount awarded to the respondent by order
made on 5 July 2013 be amended and that the applicant pay the
respondent the amount of $218,940.17 plus interest in the amount of
$130,363.36 by 4.00pm on 5 September 2013.
-- 5 of 5 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2013/399