Bakker & Kramer v Richards Projects Pty Ltd [2013] QCAT 388
CITATION: Bakker & Kramer v Richards Projects Pty Ltd
[2013] QCAT 388
PARTIES: Jan Bakker and Anna Kramer
(Applicants)
v
Richards Projects Pty Ltd
(Respondent)
APPLICATION NUMBERS: BDL048-12; BDL232-12
MATTER TYPE: Building Matters
HEARING DATE: 29 & 30 April 2013
HEARD AT: Brisbane
DECISION OF: Michael Howe, Member
DELIVERED ON: 26 July 2013
DELIVERED AT: Brisbane
ORDERS MADE: 1. Jan Bakker and Anna Kramer pay
Richards Projects Pty Ltd the sum of
$6,601 plus interest of $3135.92 by 9
August 2013.
CATCHWORDS: BUILDING MATTERS - Domestic building
dispute and minor debt claim heard together –
general rule for assessing damages in building
cases – the qualification rule that the rectification
proposed be reasonable – definition of deck –
definition of verandah – efficacy of termite barrier
– loss of amenity - costs – costs of minor civil
dispute minor debt heard in building list
Queensland Civil and Administrative Tribunal Act
2009, ss24(1)(c), 28(3)(b) and (c)
Domestic Building Contracts Act 2000, ss42(1),
(5) and (6), 51(2)
Queensland Building Services Authority Act
1991, ss42(14), 79, 84
Bellgrove v Eldridge (1954) 90 CLR 613
Briginshaw v Briginshaw (1938) 60 CLR 336
Lida Build Pty Ltd v Miller & Anor [2013] QCATA
139
-- 1 of 17 --
2
APPEARANCES and REPRESENTATION (if any):
APPLICANT: The Applicants represented themselves.
RESPONDENT: The Respondent was represented by its director
Robert Richards.
REASONS FOR DECISION
[1] In June 2010 Mr Bakker and Ms Kramer engaged Richards Projects Pty Ltd,
builders, to build them a home on their land at Reedy Creek. They signed a
residential building contract on 4 June, 2010. It was a large home, steel
framed and in brick veneer.
[2] Mr Bakker and Ms Kramer had previously engaged another builder to do the
job, but that builder had done some preparatory work only. Mr Bakker and
Ms Kramer already had the prefabricated steel frame on site and they
supplied existing plans to Richards.
[3] Richards built the home. The owners weren't entirely happy however. They
refused to pay the last amounts claimed by Richards.
[4] The Building Services Authority (BSA) was called in. They made
recommendations and Richards rectified certain items of complaint. The
BSA was called in a second time by the owners who had fresh complaints
but the BSA declined to make further orders1.
[5] Richards applied in the minor civil dispute jurisdiction of QCAT to recover the
balance monies owed to it. Mr Bakker and Ms Kramer commenced
proceedings for a domestic building dispute in the Tribunal. The matters
were ordered to be heard together.
The Claims
[6] Richards seeks payment of $14,794 as the balance monies still owing under
the contract. Mr Bakker and Ms Kramer initially sought $50,000 cost of
rectification in their domestic building application and relief from payment of
$13,525 of the moneys claimed by Richards, but by time of hearing the cost
of rectification claimed had grown to $120,315.
The Garage
[7] The garage is the most significant item in dispute. According to the builder, a
major problem was revealed with the proposed garage before construction.
The Council said the driveway gradient was a problem. To compensate the
garage floor had to be lowered approximately 600 mm. To do that, retaining
walls had to be built at the back and sides of the garage. The scope for
retaining walls was limited because the house was built tight to the
boundaries.
1 Relying on s42(14) Queensland Building Services Authority Act 1991 (unfair to require the
builder to perform rectification work).
-- 2 of 17 --
3
[8] The changes were made but according to the builder those changes required
a further change to the walls of the garage. In end result, the garage walls as
built intrude approximately 30 mm into the planned garage space of 8440
mm by 6230 mm.
[9] The owners’ principal complaint seems to be that the plans were not altered
to reflect the minor reduction in space. Second that they didn’t realize the
garage floor would be lowered by 600 mm. Third the reduction of 30 mm in
each wall makes it inconvenient for Mr Bakker to open his car door. Last the
walls are out of plumb. In consequence they want the garage demolished
and rebuilt at a cost of $92,462.
[10] Mr Hillery, the builders construction manager for the job, gave evidence that
before the garage was built he discussed the matter with Mr Bakker and
explained to him the Council requirements which necessitated a lowering of
the garage level and discussed with him moving the garage wall in some 30
mm to allow the wall to sit down on the garage floor and cover the retaining
wall. Mr Bakker disputed the discussion being held and that he agreed with
the end result, though his evidence on the point I found vague and
inconclusive. Mr Hillery was very clear on the matter of discussion and
content. I accept Mr Hillary's evidence that prior to construction of the
garage all necessary aspects of the changes to be made were discussed and
agreed to by Mr Bakker, who throughout acted on behalf of both owners.
[11] It is inappropriate that the owners now fall back on a claim that the changes
agreed to were never reduced to writing and therefore their oral concurrence
in the changes do not bind them.
[12] It is not a matter whereby the builder seeks to recover some additional
amount for a variation to a contract not put into written form2. No additional
costs were claimed by the builder against the owners to effect the necessary
changes. In fact an amount that would otherwise have been payable to the
builder for bored piers which were not needed because of changes to the
garage has been offset and credited to the owners ($178). The credit is
noted in a variation document initialled by Mr Bakker3. It confirms to my mind
that Mr Bakker knew and agreed to the changes with respect to the garage.
Furthermore, in an e-mail dated 3 April, 2011 to the builder4, Mr Bakker
challenges the limited savings credited to him with respect to the bored piers.
[13] Concerning Mr Bakker’s complaint that opening his car door is now more
difficult than originally contemplated, it should be understood that the general
rule for assessing damages for building work not in conformity with contract
is the difference between the contract price of the work and the cost of
making it good in accordance with contract. That rule is qualified however in
that the work proposed to make good must be a reasonable course to adopt
in the circumstances5. Demolition of the existing garage as proposed
because of the loss of 30mm door opening space is not reasonable.
2 Domestic Building Contracts Act 2000 ss79, 84.
3 Exhibit (Ex) 6 item C27.
4 Ex 1.
5 Bellgrove v Eldridge (1954) 90 CLR 613 at 617. And see Lida Build Pty Ltd v Miller & Anor
[2013] QCATA 139 at [22].
-- 3 of 17 --
4
[14] Furthermore I do not accept that the loss of 30 mm has resulted in greater
difficulty to Mr Bakker in opening his car door and thereby utilizing his garage
area. I consider the change involved trivial.
[15] Both parties called expert evidence by way of independent builders. Mr
McCarthy for the owners suggested the left side garage wall was out of
plumb. He said it was difficult to accurately measure the deficiency. Mr
Richards says it is plumb. There was no complaint about this to the BSA
though an inspector attended the premises on two separate occasions -
indeed I note the lack of complaint to the BSA generally about the garage. If
the plumb defect exists, I conclude it is not noticeable to the eye, insignificant
and does not require rectification.
[16] At hearing there was some suggestion that the garage had been built smaller
than provided by the plan dimensions. It became clear however that any
error was a typographical error of the draftsman and his mathematics.
[17] The complaint concerning the garage fails.
Kitchen Cabinet
[18] The owners complained about a moisture stain on the backing board of a
corner kitchen cupboard. The cabinet had been supplied and installed by the
owners but Mr McCarthy suggested water may have entered from a defective
silicone seal at the kitchen window reveal above the benchtop. Mr McCarthy
said the corner cupboard and benchtop should be removed and replaced at a
cost of $1,870.
[19] The window was not directly above the area of stain. Mr McCarthy did not
identify any moisture problems in the cupboard at the time of his inspection.
Mr Corn, a builder who gave evidence for Richards, said there was no actual
water damage to the cabinet and no evidence of any water trail between the
kitchen window and the stain. He suggested there should be one if the stain
was caused by water coming from the window. That makes sense.
[20] Mr Corn suggested it was as likely as not that the stain existed at the time of
manufacture of the cupboard. There is no evidence suggesting structural
problems with the subject backing board. On balance I conclude that the
stain is not likely to have been caused by water ingress at the window seal.
Therefore I cannot conclude the stain is the result of defective work on the
part of the builder. I allow nothing in respect of this head of claim.
Colorbond Roof
[21] The owners claim for the costs of cleaning the colorbond roof from paint
marks and the replacement of a damaged sheet.
[22] Neither expert actually went up onto the roof to look at the damage. The
matter of a damaged sheet above the rear of the garage (which appears to
be the area over the back of the balcony where the present damaged sheet
is said to be) had been a matter of previous complaint to the BSA. The
-- 4 of 17 --
5
builder was directed to rectify the problem and Mr Richards gave evidence
the sheet was replaced.
[23] Mr Corn said it was hard to see any damage to any sheet. Mr Richards said
the only issue that may remain is some minor silicone staining that might
have to be removed.
[24] Mr Richards pointed out that other people had been on the roof since he was
on site, which was not refuted.
[25] There was no mention of paint marks on the roof in the BSA report6. I accept
Mr Richards evidence that he replaced the damaged sheet identified in the
BSA report. I conclude any damage to sheets which now exists occurred
subsequent to the builder's involvement on site. I accept there may be minor
silicone contamination yet to be removed. Mr Corn's estimate of the costs to
do that is $100. The owners are entitled to be paid that under this head of
claim.
Concrete Slab
[26] There is a gap between the concrete pavement at the right front side of the
dwelling and the ground. The concrete pavement is also out of alignment
with the wall. This matter is confusing because during hearing it became
clear that the slab has been replaced once already.
[27] The second BSA report7 estimates the gap at 100 mm. Mr Richards says he
purposely dug away the soil beneath the slab at the direction of Mr Bakker.
Mr Bakker denies that. Mr Richards did not make explain or make clear just
what he was trying to achieve in digging away the soil, at least not to my
satisfaction.
[28] Mr McCarthy suggests the concrete slab may collapse and should be
removed, again at a cost of $1,870. Mr Corn says in his opinion it will not
collapse. The slab has been there for some time now. The gap between the
concrete and the soil can be filled with an expanding grout. His estimate to
do that is $280. Mr Corn's proposal seems appropriate and reasonable in
the circumstances. Generally I might say I found Mr Corn’s evidence showed
a more balanced and reasonable approach to remedial measures necessary
to rectify defective building work than that of Mr McCarthy.
[29] The slab was also out of alignment however. I have no evidence before me
about the additional cost to remedy the alignment defect. In the
circumstances I propose to allow $500 all up in respect of all work necessary
on the slab both as to gap and alignment.
[30] At hearing there was also mention made by Mr Bakker of an additional cost
to the owners for wasted block work. The cost was not quantified and the
claim mentioned in passing in the proceedings. I do not allow any additional
sum for that.
6 Ex 15.
7 Ex 14.
-- 5 of 17 --
6
Silicone Seals
[31] The owners complain that some gaps in tiles at the entries to the upstairs
bathrooms require silicone sealing. It would appear grout had been inserted
but has come away. Mr McCarthy says the gaps need widening to ensure
the silicone is effective. Mr Corn says the silicone will fill the existing gaps.
Mr Smith, a tiler who did tiling work at the house, gave evidence that the
silicone could be applied directly to the existing gaps. He said it was tiler’s
work. His cost estimate for that was $60, the cost of a tiler for one hour and
one tube of silicone. I accept the silicone seal is necessary and the
reasonable cost of rectification is $60.
Verandah Floor
[32] The verandah above the garage is covered but rain sometimes enters
through the open sides. The rain pools on part of the floor. The floor is level.
It has no fall.
[33] The BSA concluded the tiling on the verandah floor was defective work in
that they were not laid flat and true to a tolerance of plus or minus 4 mm in a
length of 2 metres "from the required plane". The builder was identified as
the person responsible for that defective work, but the BSA did not direct
rectification in the circumstances8. The builder maintains the problem lies
with the steel frame beneath the floor supplied by the owners. Mr Richards
says the steel beam beneath the floor has deflected. That has caused the
problem with the tiled floor.
[34] Mr McCarthy does not agree.
[35] Engineers have considered the matter9. Their conclusion is that the pooling
of 8 mm observed by the BSA is consistent with beam deflection and the
pooling is an "inherent result of the way the floor framing is designed". The
solution, the engineers say, is an extra steel support post mid-span or
altering the flooring layout designed to reduce load.
[36] I accept the conclusion of the engineers.
[37] Mr McCarthy for the owners says additionally however that the floor has no
fall, it is a deck, it should have fall, and the compressed sheeting tile base
has therefore been laid incorrectly. Mr McCarthy refers to the document
Technical Specifications James Hardie Compressed Sheeting Decking
Construction10. He suggests those technical specifications call for fall and
manufacturer recommendations must be followed.
[38] The recommendations of manufacturers of materials do form part of the
relevant criteria for use of materials in construction11.
8 Domestic Building Contracts Act 2000 ss 79, 84.
9 Ex 6 item B10 letter Rymark Engineers Pty Ltd 20 March, 2013.
10 Ex 10.
11 Domestic Building Contracts Act 2000 ss 42(1), 42(6).
-- 6 of 17 --
7
[39] Item 2.1 of the James Hardie Decking Technical Specifications states decks
must have a fall of at least one in 100 mm to avoid ponding. Part 10 of the
specifications is a detail showing such recommended fall.
[40] There is nothing however in the technical specifications which talks about
decks under cover. The word deck is variously defined in a number of
dictionaries, not all of which allude to a verandah scenario. In the Collins
Concise English Dictionary the word “deck” is defined as a nautical term
meaning any of various platforms built into a vessel, or a similar platform as
in a bus. The term “verandah” however is defined as a porch or portico,
sometimes partly enclosed, along the outside of a building.
[41] The Oxford Dictionary Online defines deck in similar terms to the Collins but
also adds that it is a timber platform or terrace attached to a house or other
building. It says in respect of a verandah that a verandah is a roofed platform
along the outside of a house, level with the ground floor.
[42] Dictionary.com defines deck as an open unroofed porch or platform
extending from a house or other building. It defines verandah as a large
open porch usually roofed and partly enclosed as by a railing often extending
across the front or sides of a house.
[43] Drawing WD-06 in this matter describes the area concerned as a covered
verandah, not a deck. I do not consider the term deck and verandah is
synonymous. I conclude the draftsman who prepared the drawings here
used the term verandah advisedly.
[44] As such I do not accept that the technical specifications referred to by Mr
McCarthy necessarily apply to the covered verandah the subject of the
present claim. The BSA did not say there was defective work in respect of
the verandah because there was no fall.
[45] Mr Richards, who is a builder, said there was no requirement to have fall
because the area was roofed. Mr Corn, the building expert, agreed that no
fall was required where an area is roofed.
[46] The tiler Mr Smith also drew to my attention the fact that the plans called for
at least a 50 mm drop between the door and the verandah. Indeed I note Mr
McCarthy’s deck specifications also requires a similar 50 mm drop between
any door going out onto a deck. The tiler pointed out it was impossible to
obtain such drop unless the tiles were laid on the verandah as per drawing,
that is, without fall.
[47] Mr McCarthy says that the lack of fall should have been brought to the
attention of the owners. I do not conclude that the verandah required fall. I
therefore do not agree the matter was required to be brought to the attention
of the owners before proceeding with the construction.
[48] Mr Richards points out that in the lower floor a working drawing of an outdoor
entertainment area specifies fall. The upstairs verandah drawing does not. I
cannot see why the builder was obliged to do more than follow the plans.
The plans had been drawn by the owners’ draughtsman and certified by
engineers as complying with the Building Act 1975.
-- 7 of 17 --
8
[49] The lack of expansion joints on the verandah was also raised. On this point I
accept the evidence of Mr Smith the tiler that there was sufficient movement
around the external area of the verandah such as not to warrant an
expansion joint in the centre.
[50] Further concerning the evidence of Mr Smith, he said using a 3.6 metre
straight edge from the front to the rear of the verandah at the time of tiling he
was able to determine that the area was near flat. He found only a 1 to 2 mm
difference in the plane of the floor. I accept his evidence on that point.
[51] I conclude beam deflection occurred after the laying of the tiles on the
verandah and resulted in the 8mm bow in the floor. Accordingly the
respondent builder has no responsibility to rectify the floor. The fault herein,
if any, lies with the draughtsman and the floor design beneath the verandah.
Grout Discolouration
[52] According to the owners, the tiled floor in the bathroom and ensuite show
grout discolouration. Mr Richards says only the bathroom remains in issue,
the ensuite is not affected. Given Mr Smith’s evidence however, that both
areas were affected and he was not able to rectify the problem, I conclude
both areas were affected.
[53] The owners expert maintains the only explanation he can think of to cause
the grout discolouration is that water is leaking under the tiles from the
showers. He suggests there are no water stops under the edges of the
showers.
[54] Mr Richards attributes the problem to a previously leaking toilet, which leak
has been remedied.
[55] Mr Smith the tiler was adamant he put in water stops to each hobless
shower, that is 40 mm aluminium angles isolating each shower base. He
also added one at each doorway.
[56] Mr Smith said tried to fix the discolouration. He regrouted one marked area
using the same coloured bag grout as he used in the original job. On
removing the grout he found excess water inside the tile bed which could
have contributed to the discolouration. He took advice about the
discolouration. He asked grout professionals to regrout the areas at his
expense. They quoted $400 to $800 for the job sight unseen. Those
professionals warranted their work regardless of moisture content.
Unfortunately they weren’t allowed onsite by the owners. That was not
controverted at hearing.
[57] Mr Bakker disputes Mr Smith’s claim he tried rectification. Mr Smith was
adamant about the point. I accept the evidence of Mr Smith in preference to
that of Mr Bakker. I also accept Mr Smith’s evidence that he did add water
stops to both bathrooms.
-- 8 of 17 --
9
[58] The BSA report12 draws no link between the discoloured grout and leaking
showers. The BSA’s recommendation was to dry out the floor over a long
time until the moisture no longer migrated to the surface.
[59] I conclude that more probably than not the cause of the discolouration is as
suggested by both the tiler and the BSA, water pooling in the tile base from
the leaking toilet that has been repaired. It is unclear how long the owners
must wait for the discolouration to go if they follow the course suggested by
the BSA, to simply wait until it dries. The ongoing discolouration constitutes
ongoing defective work which I accept affects the amenity of the dwelling.
[60] I accept Mr Smith's suggestion as to his proposed solution, namely allow
experts to re-grout the floor to a uniform finish regardless of moisture content.
He said the cost quoted to him by those experts was between $400 and
$800. Mr Corn put the cost of regrouting at $800 in the Scott Schedule. I
allow rectification costs under this head of claim of $800.
Chipped and Broken Tiles
[61] The owners complain there are chipped and broken tiles and uneven grout
lines in the powder and ensuite walls. Mr McCarthy estimates between 30
and 40 tiles are affected. Mr Corn initially said in his evidence only a couple
then settled on perhaps 10. The BSA report13 makes reference to one
chipped tile of approximately 1.5 mm in length below the external corner PVC
trimming to the ensuite windowsill. The BSA report makes no reference to
uneven grout or additional problem tiles.
[62] I conclude the number of affected tiles are few and any resultant visual defect
minimal, certainly not reducing the value of the property. Mr Corn's estimate
of the costs of repair for both bathrooms based on 10 affected tiles is $300.
He does mention a potential problem if new tiles cannot be purchased to
match, however that possibility was taken no further by the owners at hearing
and there was no evidence about that. I allow the estimate of $300 to
remedy all defects with respect to tiling in the ensuite and powder rooms.
Cistern
[63] There is a complaint that the cistern in the powder room was incorrectly
fitted. The evidence concerning this was confusing. It is not clear what the
ongoing problem is. Mr Bakker said in his evidence the toilet hadn't been
used for 2 years and the tiles were cracked. He said the problem was the
internal cistern support brackets were improperly fitted. Mr McCarthy for the
owners states in a report he prepared14 (on about 10 April, 2013) that the
cistern was loose and out of level.
[64] The matter was the subject of complaint to the BSA. The BSA15 observed a
defect with the toilet pan, and that was that the toilet tilted away from the wall,
not that the cistern was loose.
12 Ex 14.
13 Ibid
14 Ex 4.
15 Ibid.
-- 9 of 17 --
10
[65] Prior to the inspection of the BSA however16 the owners engaged their own
plumber to repair the toilet in the powder room. Ashmore Plumbing Service
attended and worked on the cistern on or about 30 December 2011. After
that the owners got in yet another plumber, Charlie the Plumber, on 19
January 2012 who did further work, or repeated the work of Ashmore
Plumbing Service. Again, the matter was not made very clear.
[66] An invoice document from Charlie the Plumber17 mentions the pan not being
secure but makes no mention that this has caused tiles to crack.
[67] The BSA concluded the purported rectification of problems by Ashmore
Plumbing Service compromised the complaint as against the builder.
Accordingly the BSA refused to direct rectification work on the cistern by the
builder.
[68] Mr Bakker still maintains a claim against the builder however for incorrect
installation despite two different plumbers being engaged to work on the
problem after the builder installed the system. Mr McCarthy supports Mr
Bakker’s complaint though he has had no actual access to the cistern
because it is an internal wall cistern. He relies on photographs to reach his
conclusions which photographs show one of the support legs of the cistern is
truncated because the waste pipe is in the way. Mr Richards says that was
the only way the builder could construct the cistern given the whereabouts of
the waste pipe and the structure was however made solid.
[69] Ashmore Plumbing Service make mention in their invoice18 of finding the
toilet on an angle and it being incorrectly installed. They also appear to say
they cracked tiles when removing the toilet and putting the toilet back
correctly. They reset the tiles. It is not clear what part of the charges on their
invoice relates to the work on this cistern. They removed and reinstalled
three toilets at the house that day.
[70] It was also not made clear why the attendance of the second plumber,
Charlie the Plumber, was necessary on 19 January, 2012. He seems to
have redone all the work done by Ashmore Plumbing Service. That plumber
concluded the cavity wall was not plumb and the bracket support system of
the cistern having been cut had left the pan insecure. Charlie the Plumber
tightened and adjusted the pan fixing bolts and added silicone.
[71] Originally the owners had specified a flush valve toilet system which required
no cistern. That system required, unbeknownst to the builder at time of
installation, a 25 mm diameter water supply. The house had a standard 19
mm water supply. The flush valve systems didn’t work properly. The BSA
directed the builder to install in-wall cisterns in lieu. The builder's obligations
to exercise reasonable care and skill continue to apply to the rectification
work associated with installation of the in-wall cisterns.
16 17 January 2012.
17 Ex 1 Page 51.
18 Ibid Page 49.
-- 10 of 17 --
11
[72] Whilst the two plumbers mentioned were not called to give evidence the
Tribunal is entitled to inform itself of matters in any way it considers
appropriate19. The Tribunal is not bound by the rules of evidence20.
[73] Considering the reports by those plumbers and noting Mr Richards evidence,
I conclude the cistern in the powder room was not installed with due care and
skill and was defective work. Mr McCarthy's estimate includes the cost of
possible replacement of the cistern. I do clearly understand why the system
requires yet additional work, however, I conclude in the circumstances with
the apparent ongoing problems the appropriate thing to be done is replace
the unit entirely. Alternatively the costs associated with rectification by the
two independent plumbers should be refunded to the owners. Those costs
appear to be very close to the cost of replacement now claimed in any case.
I accept Mr McCarthy’s estimate of cost of replacement of $598 as moneys
due the owners under this head of claim.
Dwarf Walls
[74] The complaint here seems simply to be that the plans call for walls of 1200
mm in height and the walls are actually 1270 mm high.
[75] Mr Richards says the cisterns eventually fitted into those walls required the
full 1270 mm space anyway. I consider that a most fortunate circumstance
for the builder but nothing more. Mr McCarthy admitted in his evidence there
was no visual impact to a viewer with the wall at 1270 mm rather than 1200
mm. I note the problem was not the subject of any complaint to the BSA.
[76] Mr Bakker added in his evidence that more tiles were thereby required to be
used, which is probably correct.
[77] In my opinion what loss of amenity has resulted to the owners is marginal if
anything and for some considerable time after construction must not have
been considered sufficiently detrimental to warrant them complaining to the
BSA about it. I have no evidence suggesting the walls constructed at 1270
mm height rather than 1200 mm height will result in a lessening of the value
of the premises. Nor is there any evidence as to the additional costs incurred
with respect to use of extra tiles.
[78] The proposed remedy by Mr McCarthy of demolishing the walls and
rebuilding them 70 mm lower is in my opinion an unreasonable and an
unnecessary one in the circumstances21. No award is made in respect of this
item of claim.
Moisture Entry to Garage
[79] There is a complaint that moisture is entering the garage at weep holes
covered by part of a concrete path. The builder says this was an extra to the
contract and he was asked to build up to that level by Mr Bakker for
landscaping purposes. I conclude that was probably so, however the
outcome is water penetration into the building.
19 Queensland Civil and Administrative Tribunal Act 2009 s 28(3)(c).
20 Ibid s 28(3)(b).
21 Bellgrove op cit at [617].
-- 11 of 17 --
12
[80] Also of potential significance however is that this height of slab may have
compromised the efficacy of the termite protection barrier of the dwelling.
There is potential access to the building by termites via the weep holes. Mr
Richards and Mr Corn talked about filling the weep holes with silicone,
however one wonders how that can be done without the concrete being
removed. In the Final Site Advice document from the certifiers22 dated 16
March, 2011, specific advice is given that all ground levels must be 75 mm
below the termite barrier. Given the build-up of soil beneath the concrete at
the weep holes one assumes this requirement has been breached.
[81] Mr Bakker says that depending on the atmospheric conditions, the water
entry into the garage can be severe. Water also enters the garage at another
point, however that water entry is not the subject of complaint.
[82] To my mind the construction of the path at its present height amounts to
defective building work. The path must be removed, the weep holes exposed
and the integrity of the termite barrier maintained.
[83] Mr McCarthy’s cost estimate for this is $2,624. Neither Mr Richards nor Mr
Corn gave any estimate for this work. That cost of removing the path
concerned, though only an area of 1 m x 2 m, seems high but in the
circumstances it is the only estimate to hand. Accordingly I award to the
owners that amount in respect of this item of claim.
[84] That Mr Richards may have been asked to lay the slab at the wrong height
by Mr Bakker does not change the fact that this is defective building work.
To shift responsibility to the owner in such circumstances the builder needs
point to written advice by him recommending against such23. Mr Richards
has not done that.
Bowed Doors
[85] The owners complain the laundry and garage internal doors are bowed and
do not open correctly. Mr McCarthy estimates a bow of 10 mm, whilst Mr
Corn says there is no more than 4 mm and a bow under 4 mm is acceptable.
A photograph of one of the doors24 clearly shows, to my eye, a significantly
greater bow than 4 mm. The experts agree that if the doors must be
replaced the reasonable costs of replacement is $300. There was mention
made at hearing that this may be a warranty item, but no evidence on that
point was led. I conclude the doors should be replaced. The cost of
replacement of $300 is allowed the owners.
Front Entry Door
[86] The owners complain the front door has not been painted with weather
resistant paint and the paint is peeling. Mr McCarthy suggests given the age
of the paint it should not be in the state it is if appropriate paints were used.
He says the door should be removed, cleaned, sanded and repainted. His
estimate of the cost of that is $370.
22 Ex 20.
23 Domestic Building Contracts Act 2000 s 51(2).
24 Ex 16 item 22.
-- 12 of 17 --
13
[87] Mr Corn says this is a normal maintenance problem and the problem is
attributable to normal wear and tear – sun damage. I accept that. Mr Corn
said surfaces exposed to the sun should be painted annually. That does not
appear to have been done.
[88] The Tribunal makes its findings in relation to disputed issues on the balance
of probabilities. The Tribunal must be reasonably satisfied about the
correctness of a decision reached about an issue25. I cannot be satisfied that
the damage to the paint here is due to use of incorrect paint. Mr Richards
denies that the wrong paint was used. Mr McCarthy reaches his conclusion
because of the level of peel. Mr Richards and Mr Corn both say it is
exposure to the elements which is the problem, and there is nothing unusual
here.
[89] I cannot conclude the builder has failed to use appropriate product in the
circumstances. This item of claim is not allowed.
[90] On similar reasoning of not being appropriately persuaded I do not allow the
claim for 3 extra remote control keys26 for the garage doors.
Paint and Render
[91] The owners also complain that certain rendering and paintwork has not been
completed. There are two separate heads of claim concerning such
referable to different areas of the home. The dispute here is about the costs
of rectification. Mr McCarthy has quoted estimates of the repair based on a
tradesman performing each set of repairs as distinct jobs on different days.
That builds the costs of repair.
[92] Mr Corn says the painter would complete both jobs on the same day and the
cost saving should be recognised. I accept Mr Corn's submissions on this
point. I would be surprised if the course proposed by Mr McCarthy occurred
in practice.
[93] Mr McCarthy added to his calculations of costs the price of scaffolding, a
cherry picker and other sundry items which Mr Corn says would be
unnecessary. All the painters will need, says Mr Corn, will be roller
extensions. I accept Mr Richards evidence that the rendering has effectively
been done and all that remains is painting. The photographs27 tendered by
the owners bear this out. I agree with Mr Corn that colours today can be
fairly easily matched. Mr McCarthy expressed great concern about colour
matching. I allow the owners rectification costs under these heads of claim in
the amount of $550 as proposed by Mr Corn.
Garden PowerPoint
[94] The owners say the builder failed to provide external electrical power points
in accordance with the contract. They point to a diagram28 indicating such
25 Briginshaw v Briginshaw (1938) 60 CLR 336 at 361-2.
26 Scott Schedule item 25.
27 Ex 16.
28 Ex 13.
-- 13 of 17 --
14
were to have been installed. The diagram is not initialled or signed by the
parties.
[95] Mr Richards responds that the diagram referred to was simply a preliminary
document and what was agreed changed by the time of contract. Mr
Richards points to a different diagram, signed by both parties, which does not
show any external power points away from the house29. I accept the
contracted electrical drawing is that as indicated by Mr Richards. It is not
disputed electrical connections in accordance with the drawing produced by
Mr Richards was not provided. I determine the builder is not in breach on
this matter.
[96] On this point I also note the document entitled "Construction Selections and
Specifications – page 7 of 9" which forms part of the contract provides
"electrical inclusions – 5 off (sic) waterproof double power points onto house
(nil underground)". This supports Mr Richards argument and refutes that of
the owners.
Tile Cleaning
[97] Finally the owners complain that the floor tiles have been laid with a wax
coating from the manufacturer and that wax coating should have been
cleaned away "as per contract". At hearing Mr Corn pointed out there was
only the standard builder’s clean referrable to this item and such did not
extend to cleaning wax from tiles before grouting. I accept this was not a
task falling within a builders clean.
[98] Mr McCarthy said there was a school of thought, apparently in the United
Kingdom, which said a builder should remove wax from tiles before grouting.
Mr McCarthy's evidence was very general on this point and he also admitted
"no one is on it too much" which I took to mean builders in Australia do not
generally do it.
[99] I do not accept this work fell to the builder under the contract. It was not
noted in the contract as an extra and it would have had to have been to be
the builder’s responsibility. The owners claim here fails.
Agreed Items
[100] Certain items of complaint were agreed to by the parties as requiring
rectification and the costs associated therewith. In this regard fall items 7, 8,
9, 18, 19 and 23 of the Scott Schedule totalling $637.
[101] Additionally some items were agreed as being warranty claims rather than
the responsibility of the builder. In this category come items 16, 17, 28, 29
and 30 of the Scott Schedule.
[102] I therefore total the moneys due to the owners by the builder in respect of
defective work at $6,469.
The Builders Claim
29 Ex 6 Item C4B24.
-- 14 of 17 --
15
[103] The builders claim in the minor debt proceedings was for balance owing
under the contract of $13,070 plus interest at 20% on outstanding monies
and the costs of supplying two in-wall toilet systems for $1724. Mr Richards
seems to allude to additional costs of $1400 for the plumber and $712 for the
tiler in other documents30 but those additional amounts are not included in his
minor debt claim document.
[104] The minor debt proceeding was transferred to the building list and ordered to
be heard together with the owners building claim.
[105] By e-mail dated 3 April, 201131 the owners freely admitted they owed
$13,235 to the builder. Subsequently the owners advised the BSA officer
who attended for inspection on 29 August, 2011 they owed $13,300 to the
builder under the contract including variations. In his minor debt claim the
builder’s claim was for $13,070. I accept that latter amount is the extant
under the contract and outstanding to the builder by the owners before setoff.
[106] I should note I accept that a credit for bored piers not used because of the
change in construction of the garage was agreed to between the parties after
offsetting the cost of the retaining walls. I accept Mr Hillery's evidence on
this point32. The credit was an amount of $178 which is set out in variation 5
signed by the parties dated 23 December, 201033. The owners are due
nothing more in respect of that item.
[107] As to the claim for the cost of the in-wall toilet systems by the builder, Mr
Richards said the builder before him had already installed a 20 mm water
service to the property. Mr Richards did not make clear just what that meant
however and what cost would have been entailed in replacing the 20 mm
water service with a 32 mm water service. The 32 mm service was
necessary to supply the flush valve toilet systems wanted by the owners. All
that is said in the builder’s minor debt claim particulars is that the previous
builder "abandoned the project at site preparation stage after arranging the
water and sewerage connections". That additional cost of changing the 20
mm service to 32 mm service would have been a cost to be paid by the
owners.
[108] By the time the flush valve systems were found to operate inadequately
however, the systems had already been installed with the 20 mm water
service throughout the house.
[109] In the circumstances there was no warranty by the builder that the toilet
systems nominated by the owners would be suitable for the purpose for
which they were intended34. The flush valve toilet systems were supplied by
the owner without recommendation by the builder.
30 Ex 6 Document B – Response to Experts Report.
31 Ex 1.
32 Ex 23.
33 Ex 6 Item C27.
34 Domestic Building Contracts Act 2000 s42(1), 42(5).
-- 15 of 17 --
16
[110] The owner supplied flush valve systems were delivered by the owners at fit
off time35. As stated however, the 20 mm water service had already been
installed through the house by that stage.
[111] According to affidavit evidence of Mr Lance Stevenson, the builder’s
supervisor of construction, at the time of installation the plumber installing the
flush valve systems was concerned that they would not work satisfactorily36.
It seems to me that there was an obligation on the builder to make all
necessary enquiries about this novel system before fitting. That was not
done. The choice would then have been left with the owners as to whether
they would bear the cost of installing 32 mm water service to the flush valve
systems or choose to install a standard cistern system.
[112] It is perhaps arguable that all due enquiries should have been made about
these systems at time of contract, though given the plethora of product
names there was nothing to indicate this was other than a common cistern
system commonly used in Australia. There was perhaps an obligation on the
owners to bring that to the attention of the builder from outset. The matter
does not have to be decided given my conclusions following.
[113] The owners were obliged under the contract to provide toilet systems,
regardless of type. They had to bear that cost. They did when they
purchased the flush valve toilets. Once installed they could not be returned
to the supplier.
[114] Accordingly though the builder paid for the replacement in-wall cistern
systems eventually used, in proceeding to install the flush valve systems
though aware they might not perform appropriately, the builder failed to act
with reasonable care and skill. Because of that failure the owners lost the
opportunity to return the flush valve systems for refund and suffered loss of
amenity in the change of systems. In my opinion it is not appropriate to now
allow the builder the cost of supplying the in-wall cistern systems without
taking into account the loss borne by the owners with the costs of the flush
systems thrown away. Accordingly I make no allowance in respect of that
item of claim, either as to the cost of the actual systems or the plumbing and
tiling costs on install.
[115] In end result, reducing the final moneys owed to the builder under the
contract of $13,070 by the costs of rectification of $6,469, the owners owe
the builder $6,601.
[116] By clause 11.9 of the general conditions of contract if the owner fails to pay
the builder as required under the contract the builder is entitled to interest at
the rate specified in item 19 of the schedule. The rate specified in item 19 of
the schedule says 20% per annum. Pursuant to the terms of the general
conditions37 the owner was not entitled to hold any retentions for defects and
omissions, and the moneys due the builder was to be paid 5 days after the
builder submitted a claim38. The certificate of practical completion is dated
35 Ex 6 Document B entitled Response to Experts Report item 13 and Ex 6 Addendum to
Specification “Items Supplied by Owner”.
36 Ex 6.
37 Clause 11.8.
38 Schedule item 20 (progress claims including practical completion stage).
-- 16 of 17 --
17
14 January 2011 and the builder claims interest as and from January 2011. I
calculate interest is due at 20% on the sum of $6,601 from 1 February, 2011,
which on my calculation totals $3,135.92.
[117] The builder seeks costs. There are no costs awarded in minor debt claims,
or only very limited costs, and though this matter was heard together with the
owners building claim in my opinion it remains a minor debt matter though
given a building list number. The order in the minor civil dispute matter was
simply that it be transferred to the building list and heard together with the
owners domestic building dispute matter BDL048-12. The owners also seek
costs. They have been largely unsuccessful in their claim however given
they sought at time of hearing $120,315. In the circumstances I believe it is
only appropriate that each party bear their own costs.
-- 17 of 17 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2013/388