Crisp v 4 Cast Development [2013] QCAT 79
CITATION: Crisp v 4 Cast Developments Pty Ltd [2013]
QCAT 79
PARTIES: Gregory John Crisp
(Applicant)
v
4 Cast Developments Pty Ltd
(Respondent)
APPLICATION NUMBER: BDL234-12
MATTER TYPE: Building matters
HEARING DATE: 11 February 2013
HEARD AT: Brisbane
DECISION OF: Robert King-Scott, Member
DELIVERED ON: 15 February 2013
DELIVERED AT: Brisbane
ORDERS MADE: 1. 4 Cast Developments Pty Ltd pay
Gregory John Crisp the sum of
$21,016.05 by 31 March 2013
CATCHWORDS: BUILDING DISPUTE – where contract for sale
of land and house – where agreement that
fittings not to be installed - where cost of omitted
fittings allowed
Hissett v Reading Roofing Co (1970) 1 All ER
122, cited
Jollife v Baker (1883) 11 QBD 255, cited
APPEARANCES and REPRESENTATION (if any):
APPLICANT: Gregory John Crisp in person
RESPONDENT: Shayne Boyd as agent for the respondent
REASONS FOR DECISION
[1] By a contract dated 27 March 2008, 4 Cast Developments Pty Ltd
(‘4 Cast’) agreed to sell to Gregory Crisp land situated at Ranlily Crescent,
Coomera Springs for $600,000 (‘the sale contract’). There was a special
-- 1 of 7 --
2
condition of the sale contract that 4 Cast would complete construction of a
dwelling on the land in accordance with the plans and specifications which
form part of the sale contract. At the time of the sale, the land was vacant.
Completion date for the sale contract was 16 February 2009. Settlement
of the sale contract took place on that day.
[2] The house was constructed by Bdun Constructions Pty Ltd (‘Bdun’).
[3] It was also a special condition of the sale contract that on or before
completion, Mr Crisp would enter into a licence agreement with 4 Cast to
grant 4 Cast a licence to occupy the premises for a monthly licence of
$4,000. It was intended that the house would be used as a display home
for a period of two years. That period of two years commenced on the
date of settlement.
[4] Although the licence referred to in the sale contract was to be granted to
4 Cast, it was agreed between the parties that 4 Cast would not sublet the
house. The licence, in fact, was granted to the builder, Bdun.
[5] Mr Crisp did not inspect the house at the time of settlement. He visited on
two occasions prior to taking possession from Bdun under the licence
agreement in February 2011. Payments were made in accordance with
the licence agreement.
[6] In the application for a minor civil dispute, Mr Crisp made his claim against
the builder, Bdun. Bdun’s obligations to Mr Crisp arose not out of the
building contract as such, but out of the licence agreement. It was a
condition of the licence agreement that Bdun yield up the premises in a
state of repair and condition as they were at the commencement of the
licence.1
[7] Subsequently, 4 Cast was joined as a party in these proceedings on
8 August 2011.
[8] On 28 March 2012, the Tribunal at Southport ordered Bdun to pay $1,544
for repair and replacements in respect of items claimed in paragraphs [7]
to [11] of the application.
[9] Mr Crisp now seeks reimbursement from 4 Cast for Items 1 to 6 in his
application. These are items which he says were agreed to be provided
under the contract and which were not provided. The items were:
a) ducted air conditioning;
b) all window furnishings;
c) all fly screens;
d) granite bench tops for all vanities;
1 Exhibit 1, Licence Agreement, paragraph 6(a).
-- 2 of 7 --
3
e) Merbau2 decking to pavilion floor;
f) Merbau decking to ceiling.
[10] 4 Cast was represented at the hearing by its sole director, Mr Shayne
Boyd. 4 Cast, generally, raised four grounds of defence, in essence, they
were:
a) The applicant was late in making the claim and was confused as to
who was responsible for providing the items;
b) The contract provided in its special conditions a mechanism for
4 Cast to alter any finishes specified in the schedule to another or
equivalent quality without notice to Mr Crisp3, and such changes had
been made in accordance with that condition;
c) That as completion of the sale contract had taken place and the
matters in dispute had not been raised, then the applicant was
precluded from raising it now. This was akin to an argument of the
doctrine of merger. The respondent also referred to a special
condition that provided that if any disagreement arose in connection
with the finishes, then Mr Crisp was to give notice before the
expiration of 60 days after the date of completion and the matter was
to be referred to an expert in accordance with the clause. Mr Boyd
says this was not done, and the applicant has lost the opportunity of
now making a claim,
d) Finally, Mr Boyd referred the Tribunal to many variations made under
the contract between 4 Cast and Bdun where Mr Crisp was said to
have benefited by as much as $60,000 for additional and better
quality finishings.
DISCUSSION
[11] A document that formed part of the sale contract (Exhibit 1) was a
document described as “Inclusions for Display Home”. It had been
initialled by Mr Crisp as being part of the contract and that is not disputed
by Mr Boyd.
[12] The document provided additional items to be added to the base plan.
Those items included the ones in dispute, namely:
• supply and install one ducted air conditioner;
• all window furnishings;
• provide standard fly screens to all aluminium windows and
aluminium sliding doors;
2 I understand that to be a proprietary name for timber decking.
3 Exhibit 1, Special Condition 3(b)(ii), page 44.
-- 3 of 7 --
4
• granite bench tops to all vanities and kitchen;
• Merbau decking to pavilion floor;
• Merbau decking to pavilion ceiling.
[13] Mr Boyd conceded that these items have not been provided as specified.
For instance, variation 8.23 was ‘the installation of two split A/c systems’
at a saving under the contract of $1,400. The other saving was the
removal of the requirement of fly screens that led to a saving of $631.40.
[14] Mr Boyd agreed that these changes were not of equivalent value to what
was provided for in the sale contract.
[15] Window furnishings were understood by both parties to refer to blinds or
curtains.
[16] Mr Boyd said that instead of curtains, the premises had been fitted with
cedar shutters at far greater expense than vertical blinds. Variation 8.42
allowed for an additional $4,310 for upgrade window coverings to cedar
shutters. Mr Crisp says that a substantial number of windows were not
provided with shutters and his claim relates to those windows. He has
claimed for roller blinds which Mr Boyd says were more expensive.
Mr Boyd states in evidence that vertical blinds had been initially specified.
As the building contract was between 4 Cast and Bdun this is not a matter
that Mr Crisp would have been aware of, as Mr Boyd conceded.
Unfortunately, Mr Boyd did not obtain a quote for the cost of vertical blinds
to enable the Tribunal to compare the respective costs.
[17] Instead of granite bench tops, variation 8.29 allowed for laminated tops in
the vanity, but for stone tops in the kitchen. The variation resulted in an
extra expense of $770.88. That was for additional stone, presumably
because one variation allowed for the enlargement of the kitchen and
presumably the benches. However, the vanities in the bathroom were
changed to laminated tops which could not be said to be of equivalent
quality.
[18] Generally, variations in respect to the kitchen provided for a larger kitchen
and upgrade in quality in respect of appliances.
[19] Finally, variation 8.30 changed the Merbau decking of the floor and ceiling
to concrete and tile to the pavilion floor area and pool surround. In respect
of the ceiling, Mr Crisp said that gyprock had been used instead of Merbau
planking.
[20] Before considering whether these variations amount to equivalent
furnishings, it is necessary to refer to the provision relied upon by 4 Cast.
[21] The relevant provision provides:
ii. The Seller reserves the right without being required to give any notice
to the Buyer to :
-- 4 of 7 --
5
A. alter any finish specified in the Schedule of Finishes to another
finish of equivalent quality; and
B. alter any item to be installed in the property as specified in the
Schedule of Finishes to another item of equivalent quality.
[22] The schedule of finishes is not identified as such in the documentation
forming part of the sale contract, but the term can only refer to the
document I referred to earlier as ‘Inclusions for Display Home’ and an
additional document described as ‘Schedule of Inclusions’.
[23] I am satisfied that the provision of laminated bench tops for the vanities is
not of an equivalent quality to granite tops. I note Mr Boyd’s assertion that
had the granite been installed at the same time as the kitchen, then there
would not have been much difference in price. I find that difficult to accept
as there appeared to be no other justification for using a laminated surface
for the vanities other than the fact that a laminate top would be cheaper.
[24] In respect of the Merbau timber, I do not think that a gyprock ceiling is of
equivalent value to a timber plank ceiling. I would allow that part of the
claim. However, I do not allow the timber decking for the pavilion floor as I
consider the concrete and tiled floor, which was constructed at
considerable additional expense, to be of an equivalent quality.
[25] The respondent opposed the application on several grounds. Firstly, he
argued that there had been no contact with the applicant who appeared to
deal mainly with the proprietors of Bdun. Mr Boyd said that he was
unaware of the claims made until recently. The applicant conceded that he
had mainly dealt with the proprietors of Bdun, but he believed it had been
a collaborative effort between 4 Cast and Bdun and the clear inference
from his evidence was that he believed that Bdun was acting as agent for
4 Cast.
[26] It is largely irrelevant what the applicant or Mr Boyd believed and whether
the applicant initially made demands upon Bdun that should have been
made upon 4 Cast. The contract is clear in what was to be provided and
who the contracting parties were and the respondent was in breach of the
sale contract by either not supplying items or not supplying items of an
equivalent value.
[27] The respondent further relied upon clause 3(b)(iii) which provided:
iii. If any disagreement arises in connection with paragraph a.i,
paragraph b.i or both:-
A. the Buyer may not make any objection, requisition or claim,
delay completion of or rescind or terminate this contract; and
B. either the Seller or the Buyer may before the expiration of sixty
(60) days after the date of completion refer the disagreement to
an Architect appointed by the Royal Australian Institute of
Architects, New South Wales (called “the Expert”) for
determination, acting as an expert and not as an arbitrator and
the Expert’s determination will be final and conclusive and
-- 5 of 7 --
6
binding on the parties and the cost of the determination must be
borne by the party against whom the Expert’s determination is
made or if there is no such party then by the party or parties who
the Expert determines is or are to bear the costs.
[28] The clause refers to paragraphs (a)(i) and (b)(i). The clauses referred to
are irrelevant to clause 3(b)(iii). I suspect the draftsman intended to refer
to (b)(ii)A and/or B, however it is not necessary for me to refer to the
clauses further. The applicant was entitled to bring his application before
the Tribunal.
[29] Further, it was argued that essentially the contract had merged in the
conveyance, that is, that the applicant did not inspect the property at the
time of settlement and did not object to changes and omissions from the
original contract. The doctrine of merger is limited to questions of title and
not the quality and quantity of the subject matter.4 Clause 10.6 of the sale
contract provides:
Despite settlement and registration of the transfer, any term of this contract
that can take effect after settlement or registration remains in force.
The respondent fails on this point.
[30] The respondent argues that Mr Crisp has benefited because of the
substantial improvements that were made to the house as variations
under the contract and that in some way these should be set off against
his claim. There is no basis in law for these items to be set off and I
suspect that the variations were not made for Mr Crisp’s benefit but rather
for the mutual benefit of 4 Cast and Bdun in promoting the display home.
[31] The applicant claims the following items as being omitted from the
contract:
• Ducted air conditioning $12,358.00
• All window furnishings $2,015.00
• All fly screens $770.00
• Granite bench tops to vanities $962.50
• Merbau decking $12,100.00
[32] In respect of the last quote, there is no apportionment of cost between the
floor and ceiling. As extra work would be required (as is apparent from the
quote) to prepare the tiled floor for decking, I have reduced the quote to
$3,000 as an approximate cost of applying the Merbau decking to the
ceiling.
[33] Therefore, the total claimed is $19,105.50. I will allow interest on that sum
at 5% for 2 years. That amounts to $1,910.55.
4 Jollife v Baker (1883) 11 QBD 255; Hissett v Reading Roofing Co (1970) 1 All ER 122.
-- 6 of 7 --
7
[34] I order the respondent pay the applicant the sum of $21,016.05 by
31 March 2013.
-- 7 of 7 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2013/079