AAD Design Pty Ltd v Paisley and Anor [2013] QCAT 15
CITATION: AAD Design Pty Ltd v Paisley and Anor [2013]
QCAT 15
PARTIES: AAD Design Pty Ltd
v
Andrew Paisley
Darren Dwyer
APPLICATION NUMBER: BDL119-12
MATTER TYPE: Building matters
HEARING DATE: 14 September 2012
HEARD AT: Brisbane
DECISION OF: Jim Allen, Member
DELIVERED ON: 14 September 2012; reasons for decision delivered
on 11 January 2013
DELIVERED AT: Brisbane
ORDERS MADE: 1. Andrew Paisley and Darren Dwyer pay to
AAD Design Pty Ltd the amount of
$3,149.86 for the existing building
drawings and $1,416.80 for the surveyor’s
fees less the deposit amount of $1,930.50
a total of $2,636.16 within 14 days.
2. AAD Design Pty Ltd is to provide to
Andrew Paisley and Darren Dwyer all
copies of the survey plan created by
Q Spatial in respect of 86 Belgrave Street,
Morningside within 7 days of satisfaction
of order 1.
3. AAD Design Pty Ltd is to provide copies
of pages 3 of 11, 4 of 11 and 5 of 11 of
AAD Design Pty Ltd’s proposed additions
and alterations to existing dwelling at
86 Belgrave Street, Morningside to the
nominated designer or architect of
Andrew Paisley and Darren Dwyer in a
format which can be used by that
professional to complete the Town
Planning requirements in respect of the
proposed work within 7 days of
satisfaction of order 1.
-- 1 of 7 --
2
CATCHWORDS: Contract for architectural services – termination
by client for failure to produce design within
client’s budget without additional cost – award
of payment for work performed which was
ongoing value to client
APPEARANCES and REPRESENTATION (if any):
APPLICANT: Mr Albert Daher, director of AAD Design Pty Ltd
appeared for the company
RESPONDENT: Mr Andrew Paisley and Mr Darren Dwyer
appeared in person
REASONS FOR DECISION
[1] AAD Design Pty Ltd was engaged by Mr Paisley and Mr Dwyer to prepare
drawings for the proposed renovation of their house at 86 Belgrave Street,
Morningside. A dispute arose and now AAD Design is claiming an amount
of $6,360.71 in respect of monies it says are owed by Mr Paisley and Mr
Dwyer for work it performed for them.
History of the claim
[2] The dealings between the parties began with a site visit by Mr Daher on
5 August 2011. This had been arranged earlier and a confirming email
and invoice for $330 was issued on 3 August 2012 by AAD Design for a
site feasibility study. Mr Daher stated that he had estimated to Mr Paisley
the costs of the renovation would start at around $400,000 and Mr Paisley
had said he did not plan to spend that much. If the building in underneath
component was left out he should expect a construction cost of $250,000
and that work could be done at a later stage. Upon request he also gave
Mr Paisley a break down of the costs. Mr Paisley is said to have
responded that he could get things built cheaper as he has friends that are
tradesman in the industry. Mr Paisley then said that he liked the ideas
and solutions provided to him by AAD Design and requested a quotation
be forwarded to him accordingly.
[3] Mr Paisley and Mr Dwyer confirmed that a meeting was held on 5 August
2011 with Mr Daher and that they had stated that the renovations were to
be completed within their budget of $150,000.00. That this had been
verbally agreed by the parties and would be the basis of proceeding with
the project. Mr Paisley denied that Mr Daher had discussed the costs of
doing the works. At the hearing Mr Daher confirmed that Mr Paisley had
said that he had a budget of $150,000.
[4] A fee proposal was forwarded to Mr Paisley and Mr Dwyer on 9 August
2011. The description of the works was “Proposed additions and
alterations to existing residence- raise, slide, restump with internal
reconfigurations and additions to rear. Provision to build under”. The
-- 2 of 7 --
3
proposal was in two stages – Town Planning and Working Drawings. The
scope of works for the Town Planning stage was:
i) Measure and draw up existing house including streetscape analysis
(setbacks plans, elevations, photographs), photographs;
ii) Concept plan, design development;
iii) Compliance report against local planning scheme;
iv) Preparation of erosion assessment report;
v) Lodgement and liaison with council.
The fee for this work was to be $6,435.00.
[5] There were also surveyor and consultant’s fees of $1,200.00 and council
development application lodgement fees of $1,335.00. A 30% deposit of
$1,930.50 was required prior to AAD Design commencing work. The fee
proposal was to be accepted by the signing and returning of the
“Acceptance of Fee Proposal” section for each stage. The acceptance was
to confirm acceptance of the fee proposal and the terms of engagement
that form part of the fee proposal. The terms of engagement relevantly
state in clause 1 that “By completing and returning the fee Proposal and/or
paying the deposit or full fee, you are acknowledging that you agree to
perform the work defined in the scope of work outlined in the fee proposal”.
[6] An email was sent by AAD Design to Mr Paisley on 26 August 2011
confirming the engagement of AAD Design for the project and noting that
the completed fee proposal had not been returned. There was also an
invoice attached in the amount of $1,930.50 for the deposit for town
planning and it was stated that work would commence once the deposit
was paid. This is stated by AAD Design to have followed Mr Paisley
verbally engaging AAD Design to perform the work. AAD Design then
commenced work in accordance with the fee proposal and its scope of
works.
[7] A survey was arranged in September and Mr Paisley is said to have
agreed to proceed with the survey at a quoted price of $1,529.00 on 6
October 2011 following a series of emails and phone calls. Mr Paisley
confirmed at the hearing that he had authorised Mr Russell to engage a
surveyor. A copy of an invoice to AAD Design for survey work at 86
Belgrave Street, Morningside from Q Spatial dated 20 October 2011 in the
amount of $1,416.80 was produced at the hearing by AAD Design.
[8] At that time neither the fee proposal acceptance nor the invoices
mentioned above had been attended to by Mr Paisley and Mr Dwyer.
Letters requesting payment of the invoices were sent on 20 October 2011
and 28 November 2011. Payment in the amount of $2,260.50 was made
by Mr Paisley and Mr Dwyer on 2 December 2011. Mr Paisley stated that
that the payments were made in the belief that the project was progressing
-- 3 of 7 --
4
according to his budget and the verbal agreement between Mr Paisley and
Mr Daher that the project would be undertaken in accordance with Mr
Paisley and Mr Dwyer’s budget.
[9] A concept plan was emailed by AAD Design to Mr Paisley on 7 December
2012 for his and Mr Dwyer’s comments. Some preliminary comments were
made by email and a meeting was then arranged between Mr Les Briant,
representing AAD Design and Mr Paisley and Mr Dwyer on 10 January
2012.
[10] Mr Les Briant stated in his written evidence that at the meeting on
10 January 2012 refinements were made to the concept plan including
larger bedrooms, an increase in living space and an upstairs laundry with
development of the ground-floor reduced to a minimum ie car
accommodation and entry stairs. The changes agreed to were emailed on
11 January 2012 to Mr Paisley for approval with a request that “you sign
the authorisation box on the plans and return them to our office with any
small changes marked up on the plans”.
[11] Mr Paisley states that at the meeting on 10 January 2012 he had requested
a copy of the plans to obtain a builder’s quote to determine if AAD Design
was proceeding with the project in accordance with Mr Paisley and Mr
Dwyer’s budget. Following receipt of the draft design plans Mr Paisley
consulted a builder who informed him that it would not be unreasonable to
assume that the cost to build in accordance with the plans would be in
excess of $300,000 on a square metre cost of between $1,400 and $2,000.
Mr Paisley provided a quote at the hearing dated 23 August 2012 from
Michael Ross Builders to perform the work set out in the plan for a lump
sum amount of $354,581.80.
[12] Emails were sent by AAD Design on 16 and 31 January 2012 requesting
feedback in regard to the revised plans. Contact was made by Mr Geoff
Russell of AAD Design with Mr Paisley on 21 February 2012. A
memorandum of the conversation was provided to the Tribunal and it was
confirmed in Mr Russell’s written evidence. The memorandum states that
“he was annoyed that clearly communicated budget of $150,000 was
obviously ignored and that the builders estimate had come in at $250,000.
He believes Albert didn’t listen to original brief. Mr Paisley suggested
where savings could be made and a meeting was organised for 27
February”. Mr Russell sent a memorandum to Mr Briant setting this out
and mentioning that Mr Paisley had wanted confirmation that there would
be no additional AAD expenses. The memorandum states “I (Mr Russell)
confirmed we would deliver service as per contract and wear time spent on
inappropriate concept design”. Mr Paisley and Mr Dwyer confirm that AAD
Design had agreed to alter the plans at no extra cost.
[13] Mr Daher states that at the meeting on 27 February 2012, Mr Paisley
claimed that he had an estimate from a builder to say that the construction
works were going to cost in the order of $250,000 and that he had
responded that was along the lines of what was discussed during the site
feasibility meeting. That Mr Paisley had claimed he advised us his budget
-- 4 of 7 --
5
was $150,000 and was asked what costs were involved with making further
changes to the design to which the response was no cost. He also was
said to have asked what was the balance still owing to complete the project
and was told the balance of the fee proposal. Mr Paisley is then said to
have advised Mr Daher that he was no longer proceeding with the job and
left the meeting. A memorandum prepared by Mr Les Briant dated
27 February 2012 states “Andrew withdrew from the project claiming issues
with the budget”.
[14] Mr Briant in written evidence stated that Mr Paisley was concerned about
the amount of money already paid and asked what costs were involved in
making further changes to the design to which Mr Daher is said to have
responded no cost. Mr Paisley is said to have then asked about the
building costs of several parts of the building like the kitchen, bathrooms
and was given the same costs as described at the site feasibility meeting.
He then expressed his opinion that the costs were considerably higher than
what he would build them for. Mr Paisley then advised that he was no
longer proceeding with the project and left the meeting.
[15] Mr Paisley in his written and oral evidence states that at the meeting on
27 February 2012 he said that the estimate for building the renovations
would be in excess of $300,000 as mentioned above. That Mr Daher had
suggested alterations to the plans in accordance with Mr Paisley’s budget.
Mr Daher then advised that AAD Design would have to recoup costs to
amend the design to the original request and they then advised AAD
Design that they were no longer proceeding with the project as there
should be no additional costs for the amendment as the design in
accordance with their request that the cost of the renovations in
accordance with the plan were to be to the value of $150,000.00.
[16] Following this an invoice in the amount of $6,064.16 for work completed to
date, surveyor and consultancy fees was emailed to Mr Paisley on
29 February 2012. The invoice was said to be in accordance with
paragraph 10 of the terms of engagement. It was noted that more time had
been expended on the project than has been allocated and the invoice was
based on pro rata costs for the work done to date which was said to be
80%. The time sheet showed total costs of $7,224.85.
[17] Clause 10 of the terms of engagement relates to payment for work done to
date when termination occurs before the completion of the work or the work
is placed on hold for more than a month. Payment is to be made for work
completed based either on the proportion of the work completed or on a
time basis in accordance with the hourly rates set out in the terms of
engagement. A 10% penalty rate is said to apply in these instances.
Discussion
[18] AAD Design has performed work for Mr Paisley and Mr Dwyer in respect of
the design of renovations for the property at 86 Belgrave Street,
Morningside. Although a written agreement was prepared by AAD Design
this document was not signed by either party and the work proceeded on
-- 5 of 7 --
6
the basis of Mr Paisley paying the deposit and giving instructions in respect
of changes to the drawings and authorising the engaging of a surveyor.
[19] There is disagreement as to whether it was a term of the agreement that
the plans produced were to be able to be built on a budget of $150,000. Mr
Paisley claims that this was made known to Mr Daher at the initial meeting
on 5 August 2011 and was accepted by him. Mr Daher saying that while
discussions were had about the cost of doing the works there was no
agreement that the works contemplated in the plans could be built for that
amount. At the hearing Mr Daher did acknowledge that Mr Paisley had
said that his budget was $150,000. Clearly then the plans drawn should
have had regard to this as plans which would have required expenditure in
excess of this amount in particular where the budget was $150,000 and the
work was later quoted at a price of $354,000 would have been of little utility
to Mr Paisley and Mr Dwyer.
[20] The contract was terminated on 27 February 2012 by Mr Paisley he says
because he was told that the necessary changes to the drawings to bring
them within his budget would be charged to him and Mr Dwyer in addition
to the agreed amount. Again there is disagreement as Mr Daher states
that he told Mr Paisley that there would be no further charge. While Mr
Daher’s recollection of this meeting is confirmed by his colleague, Mr Briant
the Tribunal has difficulty with the fact that Mr Paisley who had already
invested $2,260.50 in terms of the feasibility study and deposit would walk
away without some justification. Mr Paisley’s position is also confirmed by
the memorandum from Mr Russell in regard to his conversation with Mr
Paisley on 21 February in regard to the $150,000 budget and Mr Daher not
listening to the original brief and the promise by Mr Russell that any
changes would be at no extra charge and this was then advised to Mr
Briant. The Tribunal is satisfied that Mr Paisley had a right to terminate the
contract due to AAD Design’s failure to honour the commitment to absorb
the costs of the necessary changes to the plans to bring them within Mr
Paisley and Mr Dwyer’s budget.
[21] While Mr Paisley and Mr Dwyer should not then be liable to pay for the
work done in regard to the concept plan as it has not been done in
accordance with instructions there was work performed by AAD Design in
regard to the plans drawn of the existing building and the surveyors fees.
This work will be able to be used by Mr Paisley and Mr Dwyer when they
subsequently renovate the property.
[22] The fees for the surveyor were as mentioned in the amount of $1,416.80
and a perusal of the time sheet for the work done by AAD Design discloses
an amount $3,149.86 in respect of the preparation of plans of the existing
building less the deposit of $1,930.50, a total of $2,636.16. This amount is
to be paid by Mr Paisley and Mr Dwyer to AAD Design within 14 days.
[23] In exchange for the payment of this amount AAD Design is to provide Mr
Paisley and Mr Dwyer with all copies of the survey plan created by
Q Spatial in respect of the property at 86 Belgrave Street, Morningside
within seven days of the satisfaction of the payment order. AAD Design is
-- 6 of 7 --
7
also to provide copies of pages 3 of 11, 4 of 11 and 5 of 11 of AAD Design
Pty Ltd’s proposed additions and alterations to existing dwelling at
86 Belgrave Street, Morningside to the nominated designer or architect of
Mr Paisley and Mr Dwyer in a format which can be used by that
professional to complete the town planning requirements in respect of the
proposed work within 7 days of the order for payment to AAD Design by Mr
Paisley and Mr Dwyer.
-- 7 of 7 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2013/015