Domestic Maintenance Pty Ltd v Randall [2013] QCATA 31
CITATION: Domestic Maintenance Pty Ltd v Randall [2013]
QCATA 031
PARTIES: Domestic Maintenance Pty Ltd
(Appellant)
v
Peter Randall
Selinda Randall
(Respondents)
APPLICATION NUMBER: APL258-12
MATTER TYPE: Appeals
HEARING DATE: On papers
HEARD AT: Brisbane
DECISION OF: K S Dodds, Judicial Member
DELIVERED ON: 21 February 2013
DELIVERED AT: Brisbane
ORDERS MADE: 1. Leave to appeal is refused.
CATCHWORDS: APPEAL – LEAVE TO APPEAL – BUILDING
MATTER – where the applicant entered into a
contract with the respondents to pave an area
between the respondent‟s house and pool, and
around the pool – where the paving work failed,
could not be rectified and had to be removed –
where the applicant was ordered to pay for the
removal of the slab and pavers, and reimburse
the funds paid by the respondents to the
applicant – whether the contractor breached his
warranty of skill and care – whether leave to
appeal should be granted
Queensland Civil and Administrative Tribunal
Act 2009, s 142(3)(b)
Domestic Building Contracts Act 2000, ss 3, 44
Hadley v Baxendale [1854] 156 ER 145
QUYD Pty Ltd v Marvass Pty Ltd [2009] 1 Qd R
41
Randall and Anor v Domestic Maintenance Pty
Ltd [2012] QCAT 266
-- 1 of 8 --
2
APPEARANCES and REPRESENTATION (if any):
This matter was heard and determined on the papers pursuant to s 32 of the
Queensland Civil and Administrative Tribunal Act 2009 (“QCAT Act”).
REASONS FOR DECISION
[1] This is an application for leave to appeal a decision of the Tribunal in a
building matter.
[2] On 22 June 2012, the Queensland Civil and Administrative Tribunal (“the
Tribunal”) ordered the applicant pay to the respondents the sum which
they had paid to it for domestic building work viz. $10,720 together with a
sum for the removal of the domestic building work it had done viz. $7,348
being a 46m² cement slab and pavers laid upon it.
[3] I have read through the voluminous material contained in the Tribunal‟s
file provided to me, the transcript of the hearing before the Tribunal on 18
April 2012 and the exhibits received. I have read the reasons for the
Tribunal‟s decision, the application for leave to appeal or appeal and the
voluminous grounds advanced for leave. I have read the written
submissions of the parties.
Leave to Appeal
[4] Leave is required to appeal in this matter.1 Leave will only be given when
there is shown to be a reasonably arguable case of error on the part of the
Tribunal and an appeal is necessary to correct a substantial injustice to
the applicant caused by that error.2 It is necessary then to briefly consider
the circumstances, the evidence and the Tribunal‟s decision.
The Circumstances and Evidence
[5] The material site is the respondent‟s dwelling house allotment. They had
purchased it with the dwelling house upon it a relatively short time before
the domestic building work in question commenced.
[6] The allotment is rectangular with its long axis north south. The rear of the
dwelling is at the northern end of the allotment. The allotment slopes from
the front to the rear, the fall being in the order of 7m from front left to right
rear corners. It was cut and filled for construction of the dwelling. A rock
wall 3.5-4m in height is situated at or adjacent to the rear or northern
boundary with a return part way up the western side. Beyond the wall the
land slopes steeply to a gully and creek, the slope being in the order of 25-
30 degrees, total fall from rear of allotment to creek being approximately
7m. This slope was heavily vegetated at the material time. The filled land
on which the dwelling was located continued to the top of the rock wall.
1 QCAT Act s 142(3)(b).
2 QUYD Pty Ltd v Marvass Pty Ltd [2009] 1 Qd R 41.
-- 2 of 8 --
3
[7] In about August 2009 some short time after the respondents had moved
into the dwelling they arranged for a fibreglass swimming pool on the
northern side of the dwelling to be built. The pool contractor during
excavation for the pool found that the entire pool excavation area was fill
down to about 3.5-4m (i.e. below the pool depth). Consequently he
installed piers down into natural ground and poured a concrete base for
the pool tied to the piers. The pool was then installed onto the concrete
base and the pool excavation back-filled with crushed gravel. This work
was the subject of a contract variation.
[8] The female respondent (“SR”) then set about obtaining quotes for a paved
area between the rear of the house and the pool and around the pool.
According to SR, she approached three contractors. One was the
contractor who was to install the coping for the pool. He was not prepared
to do the work. Another was an elderly fellow who quoted and the third
was a principal of the applicant, Clint Jackson (“CJ”).
[9] There is some conflict in accounts about what was said in discussion
between SR and CJ. According to SR she informed CJ of the piering of
the pool because of fill. According to CJ she did not. She told him she
wanted the tiles flush with the pool coping. He advised against it. It was
best to have a small step to allow for the inevitable small movement
between the surfaces, but she rejected that advice. There was other
discussion. He asked, as he said was his practice, whether there were
any easements on the property he needed to know about and whether
„there was anything else he needed to know about the property‟. He was
not told anything materially significant. He observed the boulder wall and
looking over it saw fresh soil at its base which he thought was from the
pool excavation. At SR‟s request he wrote a quote on a business card.
She accepted it and told him she wanted the work started quickly. He said
he prepared a formal quote and contract which he left in the respondent‟s
letter box when the work started. The quote and contract was for what
had been discussed, a 100mm concrete slab between the rear of the
house and pool and around the pool and the laying of pavers supplied by
the applicant glued onto the slab and grouted, the pavers flush with the
pool coping. SR said the respondents had never received it.
[10] The work commenced on 11 August 2009 and completed some days later.
In early 2010 some subsidence of the pavers was noticed. Contact with
the applicant did not achieve a resolution and the Building Services
Authority (“BSA”) was contacted. In April 2010 the BSA made an
inspection. In May 2010 it conducted another inspection with an engineer
(Mr Beale of Hughes, Beale and Wright, consulting engineers) engaged by
the BSA.
[11] There was evidence before the Tribunal from three engineers. Mr Beale
inspected on 18 May 2010, Mr Morrison engaged by the applicant
inspected on 21 June 2011 and Mr Fox engaged by the respondents
inspected on 24 August 2011. The engineers met in an experts‟ conclave
subsequently. They agreed:
i) [t]he damage to the slab and tiling is due to subsidence of the slab
relative to the pool and coping;
-- 3 of 8 --
4
ii) the subsidence of the slab is due to instability of the ground
supporting the slab;
iii) the instability of the ground is the result of some possible combination
of the following; instability of the boulder retaining wall, settlement of
the original fill, settlement of the pool shell backfill;
iv) the measurements taken by the experts are consistent and
demonstrate ongoing movement;
v) they don‟t know the extent to which the filling is compacted.
[12] They disagreed about whether the applicant could reasonably have
assumed the ground supporting the slab was stable, Mr Beale and Mr Fox
being of the opinion CJ could not, and Mr Morrison being of the view he
could.
The Tribunal Decision
[13] The Tribunal in its reasons for its decision noted the conflict I have
referred to above. It did not explicitly address and resolve it although it
may be concluded it did so implicitly in that in paragraph [37] of its reasons
it accepted CJ honestly did not consider the site was filled 'despite it being
remarkably obvious from all physical site indicators.‟ Rather it proceeded
by considering whether a licensed contractor such as CJ should have
been alerted by his inspection of the site that the construction sought by
SR had the potential to be problematic. It considered whether a licensed
contractor such as CJ should reasonably have been alerted to the risk of
the ground upon which the slab and pavers were to be placed was
uncontrolled fill in light of the boulder wall, the apparent original natural
slope of the land and the apparent cut and fill and made specific enquiry.
[14] It had regard to the purposes of the Domestic Building Contracts Act 2000:
(a) to achieve a reasonable balance between the interests of building
contractors and building owners; and
(b) to maintain appropriate standards of conduct in the building
industry.3
[15] It also considered s 44 of the Domestic Building Contracts Act 2000 which
provides that a contractor warrants the subject work will be carried out -
(a) in an appropriate and skilful way; and
(b) with reasonable care and skill.
[16] It agreed with the view expressed by Mr Fox and Mr Beale that the
physical characteristics of the site should have alerted CJ there was likely
quite extensive fill under the potential slab area and thus a real potential
risk of unsatisfactory performance of the slab and pavers. It agreed with
the evidence of Mr Clayton, an experienced builder and representative of
the BSA, that this site with a 3.5-4m retaining wall 900mm from the edge
of the concrete slab to be constructed required a determination about fill
there.
The Grounds of Appeal
3 Domestic Building Contracts Act 2000 s 3.
-- 4 of 8 --
5
[17] As observed earlier the material which is said to be the grounds of the
application for leave is voluminous. It contained much material more in
the nature of submissions.
[18] In summary they were as follows. I will deal with them seriatim:
a) The work done was exempt building for approval purposes;
The applicant‟s trade contract licence did not require the applicant
to have competency to prepare plans and specifications for
concrete slabs.
Regarding these they do not materially address the Tribunal‟s
findings that CJ should have been alerted to the potential problem
for the required construction on the site.
b) The applicant did not at the time of the hearing appreciate the
weight the Tribunal would give to the boulder wall in its decision.
When CJ had looked at it on the day he gave his quotation his view
was limited and he thought it was only about 1m in height.
As to this there was considerable reference to the boulder wall in
the evidence at the Tribunal hearing and in the engineers‟ reports.
There was ample opportunity for CJ in his evidence to the Tribunal
to say what he wished about his observation. Nothing emerges
from a reading of the transcript of the Tribunal hearing which could
reasonably be regarded as requiring the Tribunal member to
question CJ about his observations.
c) The other quotation by the elderly fellow was of a similar value to
CJ‟s quotation, an indication that person saw no problem with the
site. The pool builder only discovered on excavation for the pool,
the deep fill.
As to these, the fact that the other fellow who quoted may not have
perceived a problem with the site is of little, if any, material
relevance. The Tribunal has concluded from all the evidence that a
licensed contractor such as the applicant should have. As for the
pool builder it appears that the pool contract allowed for variation in
the circumstances that eventuated. What was found on excavation
was fill to a depth beyond the depth of the pool and appropriate
engineering followed.
d) There was no evidence a 4m high retaining wall was evidence of
fill, certainly not uncontrolled fill. Mr Morrison was the only
engineer who thoroughly investigated the wall and it was his
opinion the subsidence was due to northward movement of the
retaining wall. The excavation for the pool was very close to the
wall. The boulder wall was not supported during the excavation.
Crushed gravel fill for back filling the excavation after the pool was
in place was not compacted properly.
As to these, the height of the boulder wall was an indicator but not
the only indicator of the need for enquiry. That the boulder wall
may have moved contributing to soil movement does not impact on
-- 5 of 8 --
6
the Tribunal‟s findings. The Tribunal accepted, as it was entitled to
do, the evidence of Mr Fox and Mr Beale.
e) An earth moving contractor preparing a house platform is required
by regulation to compact fill to a specification. There was no
evidence this was not done. The applicant was entitled to expect
this was done.
As to this, there was evidence during the hearing before the
Tribunal touching upon this. It seems apparent the Tribunal did not
agree. It does not seem to me to materially bear on the Tribunal‟s
conclusion.
f) The opinions of Mr Beale and Mr Fox rely on hindsight because
they were provided with engineering reports etc. before forming
their opinions. The applicant did not have this sort of material when
quoting.
As to this, it does not appear from the evidence that the opinion of
the engineers about what should have been apparent to CJ was
influenced by hindsight. Apart from that, this could have been
pursued if thought necessary at the hearing and in submissions. It
cannot be assumed their opinions were infected by hindsight.
g) The Tribunal allowed two experts, Mr Beale and Mr Fox, for the
respondents, and one, Mr Morrison, for the applicant. This was
contrary to QCAT Practice Direction 4 of 2009 which provides a
limit to the number of experts in a particular area of expertise. The
applicant should be or have been allowed to call another expert.
As to this Mr Beale was engaged by the BSA and Mr Fox engaged
by the respondents. Their reports were in evidence before the
Tribunal. There was no objection to all three engineers‟ reports
being evidence before the Tribunal. There is nothing in this ground.
h) In its reasons in paragraph [4] the Tribunal, speaking of the nature
of the failure of the works, referred to the slab and paving having
sunk below the level of the pool coping to the extent of some
200mm causing substantial cracking.
On the face of it this appears to misrepresent the evidence. A
complete reading of the Tribunal‟s reasons however indicates it
was truly seized of the extent of the subsidence. There is correct
reference to it throughout. The reference to 200mm in paragraph
[4] would appear to be an inadvertent mistake. There is nothing in
this ground.
Decision
[19] The Tribunal was not prepared to accept Mr Morrison‟s evidence about
the obligation of a „finishing trade‟ such as that of the applicant. It
expressed its view in this way:
[33] I find in this matter that the siting of a substantial concrete slab within
some 1.2 metres of a 4 metre retaining wall is not works undertaken in
an appropriate and skilful way or with reasonable care and skill if the
construction of such works fails to take account of the likelihood of
-- 6 of 8 --
7
those works being the subject of subsidence because of the existence
of fill.
[34] I am persuaded in this regard by the evidence of Mr Fox, Mr Hughes
and Mr Clayton. Whilst I am mindful of the evidence of Mr Morrison
concerning the obligations of a finishing trade I do not accept that a
person licensed to construct substantial concrete structures which are
meant to be robust and perform as building works can in these
particular circumstances accept blindly that the soil upon which he
stands is either properly compacted or will not be the subject of
subsidence. Particularly when he is standing just a metre away from
a 4 metre boulder wall over which he has already looked.
[35] He is not in those circumstances entitled as a finishing trade to
assume that the ground is natural ground and sufficient to accept and
support the structure he constructs. At the very least he should have
perceived the problem and brought it to the attention of the owners.
[36] … He was constructing very substantial works where the potential
damage of those works failing is great and is in fact now great
because they have failed.4
[20] There is no doubt the slab and paver construction is unsatisfactory. Both
vertical and horizontal movement has occurred and is continuing.
Cracking and separation has occurred. The pool fence and gate is
compromised. The work that was done under the contract and the state it
has been reduced to is unsightly and unsafe. There was no evidence to
support any finding that it was of any residual value to the respondents.
Nor for that matter to the applicant.
[21] The Tribunal‟s finding that this was not a case for rectification of the works
appears to be correct. On the evidence, as the Tribunal observed, even if
it was possible it could not be achieved at reasonable expense.
[22] It seems to me that the findings of the Tribunal based on the evidence it
accepted were open to it. It is not shown they were affected by error. It
was entitled to accept the evidence it accepted and come to the
conclusions it did. Because another person (i.e. Mr Morrison) expressed
some contrary view does not mean the conclusion of the Tribunal is
shown to be wrong.
[23] The Tribunal ordered the applicant pay to the respondents the cost of
removal of the slab and pavers plus reimbursement of money paid by the
respondent to the applicant. It declined to order payment for removal and
reinstatement of the fence, a reasonably substantial amount. In view of
the findings of the Tribunal, its orders seem to me to be a fair and
reasonable assessment of the damage to the respondents arising
naturally from the applicant‟s breach of the contract.5 The Tribunal put it
another way; as an entire contract where the consideration, the slab and
pavers contracted for, had entirely failed.
[24] In the end result, I am not satisfied it has been shown there is an
appealable error on the part of the Tribunal.
4 Randall and Anor v Domestic Maintenance Pty Ltd [2012] QCAT 266 at [33]-[36].
5 Hadley v Baxendale [1854] 156 ER 145 at 151.
-- 7 of 8 --
8
[25] The application for leave to appeal is refused.
-- 8 of 8 --
Official source: https://www.sclqld.org.au/caselaw/QCATA/2013/031