Cidneo Pty Ltd v Chief Executive, Department of Transport and Main Roads [2013] QLC 47
LAND COURT OF QUEENSLAND
CITATION: Cidneo Pty Ltd v Chief Executive, Department of
Transport and Main Roads [2013] QLC 47
PARTIES: Cidneo Pty Ltd
ACN: 105 454 064
(Applicant)
v.
Chief Executive, Department of Transport and Main
Roads
(Respondent)
FILE NO: AQL325-10
DIVISION: Land Court of Queensland
PROCEEDINGS: Application for the determination of compensation under
the Acquisition of Land Act 1967
DELIVERED ON: 26 July 2013
DELIVERED AT: Brisbane
HEARD AT: Brisbane
MEMBER: His Honour Mr WL Cochrane
ORDER: 1. Compensation is payable by the Respondent to the
Applicant for the taking on 22 February 2008 of an
area of 8.385 Ha being Lot 1 on SP218520 being
part of the land contained in Title Reference
50553649, County of Stanley, Parish of Oxley in the
sum of Six Million Nine Hundred Thousand
Dollars ($6,900,000).
CATCHWORDS: Acquisition of Land Act 1967, ss 20, 27, 28
Land Court Act 2000, s.34
Transport Infrastructure Act 1991
Commissioner of Succession Duties (SA) v Executor
Trustee and Agency Co of SA Ltd (1947) 74 CLR 358
Brisbane City Council v Mio Art (2011) LGERA 352
Turner v Minister of Public Instruction (1956) 95 CLR
245
RTA v Mosca (2006) 146 LGERA 335
Electricity Commission of New South Wales v Arrow
(1994) 85 LGERA 418
Willoughby Municipal Council v Valuer-General
Gregory v Federal Commissioner of Taxation (1971) 123
CLR 547
-- 1 of 71 --
2
Boland v Yates Property Corporation Pty Ltd (1999) 167
ALR 575
Spencer v Commonwealth (1907) 5 CLR 418
Yalgan Investments Pty Ltd v Albert Shire Council
(1997) 17 QLCR 331
Kenny & Good Pty Ltd v MGOCA (1992) Ltd (1999) 199
CLR 413
Melwood Units Pty Ltd v Commissioner of Main Roads
[1979] AC 426
Tooheys Limited v Housing Commission of New South
Wales (1952) 20 LGR (NSW) 236 at 240
Brisbane City Council v Mio Art Pty Ltd (2011) 1 83
LGERA 352
Townsville City Council v Department of Main Roads
[2003] QLCR 241
APPEARANCES: Mr MD Hinson S.C. with him Mr BD Job instructed by
Anderssen Lawyers for the Applicant.
Mr DR Gore Q.C. with him Ms JS Brien instructed by
Clayton Utz Lawyers for the Respondent.
-- 2 of 71 --
3
TABLE OF CONTENTS
Cidneo Pty Ltd v Chief Executive, Department of Transport and Main Roads [2013] QLC 47 ........... 1
Background.............................................................................................................................................. 4
1. The Subject Land .............................................................................................................................. 4
2. The Resumption Process .................................................................................................................. 4
3. Legal Issues ...................................................................................................................................... 5
4. The Hearing and Witnesses ........................................................................................................... 10
5. The Issues ....................................................................................................................................... 12
6. Lay Witnesses ................................................................................................................................. 13
7. Town Planning Issues .................................................................................................................... 16
8. Engineering Issues ......................................................................................................................... 24
Summary ................................................................................................................................. 25
9. Traffic Issues .................................................................................................................................. 26
10. Valuation Issues ............................................................................................................................. 53
11. ORDER ........................................................................................................................................... 71
-- 3 of 71 --
4
Background
[1] On or about 22 February 2008 the Respondent resumed an area of about 8.385
Ha (including about 1623 square metres being part of Easement A on
RP852753) being part of Lot 2 on SP177845, county of Stanley, Parish of
Oxley, contained in title reference: 50553649 depicted on a drawing identified
as drawing no. R13-1407LA(E).
[2] By Originating Application filed on 18 August 2010 the Applicant dispossessed
landowner seeks determination of the valuation of resumed land.
[3] In its Originating Application the Applicant contends that the Land,
Improvements, severance and injurious affection should be valued at
$36,500,000.
[4] The issue of disturbance has been resolved by agreement and there is no need
for the Court to consider that issue.
1. The Subject Land
[5] The parent parcel, prior to resumption comprised 100.477 Ha and was located at
the confluence of the Centenary Highway and the Ipswich Motorway.
[6] It has an access restricted frontage to Ipswich Road and direct accessible
frontage to Boundary Road and to Production Street.
[7] Following a Tender Program completing in May 2005 the Applicant purchased
the land from the Department of Defence and settled on it on 16 September
2005.
[8] The land from which the resumption occurred was one of three lots which
comprised the parcel purchased by the Applicant.
[9] The other two lots were Lot 1 on SP177827, with an area of 1.452 Ha; and Lot 2
on RP129729 with an area of 16.79 Ha.
[10] Lot 2 on RP129729 lies on the other side of Boundary Road to the subject land.
2. The Resumption Process
[11] By correspondence dated 2 May 2007 the then Department of Main Roads
wrote to the Applicant advising of an intention to resume the land and enclosing
the appropriate Notice of Intention to Resume.
[12] The purpose identified in the Notice of Intention to Resume was
“… to take the land described in the attached schedule and shown on
attached plan R13-1407LA(C) for the purpose of transport, in
particular, road purposes {Cunningham Arterial Road (Ipswich
Motorway)}”.
[13] The area proposed to be resumed pursuant to that Notice was 7,038 square
metres including 226.8 square metres being part of Easement A on RP852753.
-- 4 of 71 --
5
[14] An amended Notice of Intention to Resume was issued on 23 August 2007
identifying the resumed area as being 8.385 ha (including about 1623 m², being
part of Easement A on RP852753).
[15] The taking of land was formalised by AMENDING TAKING OF LAND
NOTICE (No. 1413) Published in the Government Gazette of Friday 22
February 2008.
[16] By letter 12 December 2008 the solicitors for the Applicant applied to the
Department of Main Roads as constructing authority for an advance against
compensation which was paid. A total of $3,800,000 on 8 July 2009 with a
further advance of $4,185,209 on 19 December 2011.
[17] With respect to the before resumption situation each of the valuers engaged by
the parties agrees with the other that the whole of the subject land before
resumption had a value of $60,000,000.1
[18] As indicated above an area of 8.385 ha was resumed and applying the
$60,000,000 figure to the original area of the parent parcel (100.477 ha)
produces a figure of $60/m² so that, on that basis alone, has a value of
$5,031,000.
[19] As indicated above the Applicant initially contended for a compensation figure
of $36,500,000. At the beginning of the appeal the Respondent sought leave
(which was granted) to amend the claimed figure to $25,000,000. The
Respondent for its part says that the loss is between is $6,000,000 and not more
than $6,877,000.2
[20] The task for the Court is to resolve that enormous difference of some
$18,000,000 or $19,000,000 in the valuation.
3. Legal Issues
[21] This proceeding is a determination of assessment pursuant to the provisions of
the Acquisition of Land Act 1967 (“AQL”).
[22] Section 20 relevantly provides:
“20 Assessment of compensation
(1) In assessing the compensation to be paid, regard shall in every
case be had not only to the value of land taken but also—
(a) to the damage, if any, caused by any of the following—
i. the severing of the land taken from other land of the
claimant;
ii. the exercise of any statutory powers by the
constructing authority otherwise injuriously affecting
the claimant’s other land mentioned in subparagraph
(i); and
1 See Exhibit 29, Report of Hamilton, p. 3 and Exhibit 30 Report of Brett, p. 18(?).
2 Exhibit 61, p. 7.
-- 5 of 71 --
6
(b) to the claimant’s costs attributable to disturbance.
Note—
See, however—
(a) the Geothermal Energy Act 2010, section 350D in
relation to geothermal interests under that Act; and
(b) the Greenhouse Gas Storage Act 2009, section 369D in
relation to GHG interests under that Act; and
(c) the Mineral Resources Act 1989, section 10AAD in
relation to mining tenement interests under that Act; and
(d) the Petroleum Act 1923, section 124C in relation to 1923
Act petroleum interests under that Act; and
(e) the Petroleum and Gas (Production and Safety) Act 2004,
section 30AD in relation to petroleum interests under that
Act.
(2) Compensation shall be assessed according to the value of the
estate or interest of the claimant in the land taken on the date
when it was taken.
(2A) However, in assessing the compensation, a contract, licence,
agreement or other arrangement (a relevant instrument) entered
into in relation to the land after the notice of intention to resume
was served on the claimant must not be taken into consideration
if the relevant instrument was entered into for the sole or
dominant purpose of enabling the claimant or another person to
obtain compensation for an interest in the land created under the
instrument.
(3) In assessing the compensation to be paid, there shall be taken
into consideration, by way of set-off or abatement, any
enhancement of the value of the interest of the claimant in any
land adjoining the land taken or severed therefrom by the
carrying out of the works or purpose for which the land is
taken.”
[23] It is well established by other cases which have come before the Court that,
unlike the situation in a revenue case, in a case of compensation doubts are
resolved in favour of a more liberal estimate.3
[24] In that Dixon J observed4
“I should like, however, to add for myself that there is some difference
of purpose in valuing property for revenue cases and in compensation
cases. In the second the purpose is to ensure that the person to be
compensated is given a full money equivalent of his loss, while in the
first it is to ascertain what money value is plainly contained in the asset
so as to afford a proper measure of liability to tax. … In a case of
compensation doubts are resolved in favour of a more liberal estimate,
in a revenue case, of a more conservative estimate.”5
3 See Commissioner of Succession Duties (SA) v Executor Trustee and Agency Co of SA Ltd
(1947) 74 CLR 358.
4 (1947) 74 CLR 358 Page 373-374.
5 See also Gregory v Federal Commissioner of Taxation (1971) 123 CLR 547, Boland v Yates
Property Corporation Pty Ltd (1999) 167 ALR 575.
-- 6 of 71 --
7
[25] The principal is sometimes expressed in a resumption by saying that it is the
duty of the Court to see that compensation is “the maximum amount the owner
could have obtained under the best possible circumstances”.6
[26] Kirby P (as he then was) observed in Electricity Commission of New South
Wales v Arrow7
“Valuation is not a science. It is an imprecise, opinionative activity
involving the consideration of many variables, sometimes with equally
legitimate outcomes.”
[27] Earlier His Honour had observed:
“The acceptance by the primary decision maker of one method of
evaluation, and the rejection of another, alternative evaluation adopted
by the appellants’ valuers has been held not to involve an error of law
giving rise to appeal; see Melwood Units Pty Ltd v Commissioner of
Main Roads (1979) AC 426 at 430.”8
[28] Mention must, at this point, be made of the decision in Spencer v
Commonwealth9.
[29] The dictum most frequently referred to is that of Griffiths CJ and Isaacs CSJ.
[30] Griffiths Chief Justice observed:10
“In my judgment the test of value of land is to be determined, not by
inquiring what price a man desiring to sell could actually have obtained
for it on a given day, i.e., whether there was in fact on that day a
willing buyer, but by inquiring 'What would a man desiring to buy the
land have had to pay for it on that day to a vendor willing to sell it for a
fair price but not desirous to sell?' It is, no doubt, very difficult to
answer such a question, and any answer must be to some extent
conjectural. The necessary mental process is to put yourself as far as
possible in the position of persons conversant with the subject at the
relevant time, and from that point of view to ascertain what, according
to the then current opinion of land values, a purchaser would have had
to offer for the land to induce such a willing vendor to sell it, or, in
other words, to inquire at what point a desirous purchaser and a not
unwilling vendor would come together.”
[31] Similarly Isaacs J said:11
“In the first place the ultimate question is, what was the value of the
land on 1 January 1905?
All circumstances subsequently arising are to be ignored. Whether the
land becomes more valuable or less valuable afterwards is immaterial.
Its value is fixed by Statute as on that day. Prosperity unexpected, or
depression which no man would ever have anticipated, if happening
after the date named, must be alike disregarded. The facts existing on
1st January 1905 are the only relevant facts, and the all important fact
on that day is the opinion regarding the fair price of the land, which a
hypothetical prudent purchaser would entertain, if he desired to
purchase it for the most advantageous purpose for which it was
adapted. The plaintiff is to be compensated; therefore he is to receive
the money equivalent to the loss he sustained by deprivation of his
6 Willoughby Municipal Council v Valuer-General (1934) 12 LGR (NSW) 41.
7 Electricity Commission of New South Wales v Arrow (1994) 85 LGERA 418 (at 419).
8 Ibid.
9 Spencer v Commonwealth (1907) 5 CLR 418.
10 Spencer v Commonwealth (1907) 5 CLR 418 page 432.
11 Spencer v Commonwealth (1907) 5 CLR 418 at 440-441.
-- 7 of 71 --
8
land, and that loss, apart from special damage not here claimed, cannot
exceed what such a prudent purchaser would be prepared to give him.
To arrive at the value of the land at that date, we have, as I conceive, to
suppose it sold then, not by means of a forced sale, but by voluntary
bargaining between the plaintiff and a purchaser, willing to trade, but
neither of them so anxious to do so that he would overlook any
ordinary business consideration. We must further suppose both to be
perfectly acquainted with the land and cognizant of all circumstances
which might affect its value, either advantageously or prejudicially,
including its situation, character, quality, proximity to conveniences or
inconveniences, its surrounding features, the then present demand for
land, and the likelihood, as then appearing to persons best capable of
forming an opinion, of a rise or fall for what reason soever in the
amount which one would otherwise be willing to fix as the value of the
property.”12
[32] Those two passages of Griffiths CJ and Isaacs J were specifically referred to by
learned Senior Counsel for the Applicant who also pointed to the observation in
Yalgan Investments by Member Mr Scott who observed that the hypothetical
prudent purchaser is not to be taken to be a “dewy-eyed” dreamer who will take
the most optimistic view in all matters”, nor is the purchaser taken to be taken to
be “a wilting lily who will proceed with such pessimism that all problems will
be seen to result in failure”.13
[33] Learned Senior Counsel for the Applicant then pointed to what he contended
were five important points which should be emphasised about the application of
the Spencer test.
[34] It is most efficient to simply quote what learned Senior Counsel said in that
regard:
“12. First, the market for the property is assumed to be an efficient
market in which buyers and sellers have access to all currently
available information that affects the property.14 The knowledge
attributed to the parties includes the predicted impacts of future
events as well as the experience of the past.15 But knowledge of
events subsequent to the date of taking must be ignored as recently
confirmed by the Court of Appeal in Brisbane City Council v Mio
Art Pty Ltd (2011) 183 LGERA 352 – see in particular [18], [28],
and [77]-[80].
13. Second, the parties will take a business like or practical approach in
fixing a price rather than a legal approach. In Turner v Minister of
Public Instruction (1956) 95 CLR 245 at 267 Dixon CJ said that it
is not easy to suppose that the law determines what the opinion of
the hypothetical prudential purchaser about the fair price of the land
should be. Rather, the hypothetical purchaser’s thoughts remain in
those of business life, not law. As Mr Scott said in Yalgan (at 342)
the court is to review the evidence from the perspective of the
hypothetical prudent purchaser not that of a judge of the Planning
and Environment Court, and must consider the practical issues that
would attract the attention of the hypothetical purchaser.
14. Third, the focus of the enquiry is on the buyer rather than the seller.
As Isaacs J said in Spencer, the all important fact is the opinion
12
13 Yalgan Investments Pty Ltd v Albert Shire Council (1997) 17 QLCR 331 at (341).
14 Kenny & Good Pty Ltd v MGOCA (1992) Ltd (1999) 199 CLR 413 at 436 [49]-[50].
15 Ibid.
-- 8 of 71 --
9
regarding the fair price of the land which a hypothetical prudent
purchaser would entertain, and the dispossessed owner’s loss
cannot exceed what a prudent purchaser would be prepared to
pay.16
15. Fourth, compensation cannot be claimed to the extent to which the
value of the land resumed is enhanced by the purpose for which the
land was resumed, and conversely compensation is not to be
assessed by reference to any depreciation in value of the resumed
land caused by that purpose.17 While the purpose of the acquisition
is to be put out of mind, that does not mean that the amenities and
social and economic conditions in the area are to be disregarded.
Mr Brett correctly appreciated this18 but Mr Beard did not.19
16. In RTA v Mosca (2006) 146 LGERA 335 at 344-345 it was held,
applying Woollams v Minister (1957) 2 LGRA 338, that the court is
entitled to assume that conditions in the area would have improved
to the extent there was no road proposal. In Albany v
Commonwealth (1976) 2 ALR 201, Jacobs J was dealing with a
claim for compensation for the acquisition of land for ‘the planned
development and control of the City of Darwin and its adjacent
areas’. His Honour said (at 209-210):-
‘The compulsory acquisition, or the likely compulsory
acquisition, of the land prior to or in conjunction with the
proposed development of a new town should not be taken into
account. It has been submitted that likewise the purpose of the
acquisition, the planned development and control of the city of
Darwin and its adjacent areas, should not be taken into
account. I would agree that the purpose of the acquisition as
such should not be taken into account but, in my view, the
correct approach is to take account of the fact that the town
area of Darwin would be extended in order to cater for the
increasing population and that the extension would be in
accordance with a scheme of development designed by the
Administration. It is therefore necessary to ignore the fact that
the development would be by way of acquisition but to
recognise that the development would be controlled according
to a designed and ordered planning scheme.’
17. Applying that passage to the present case, the purpose of the
acquisition (the Wacol to Darra proposal) should not be taken into
account, but account is to be taken of the fact that the major road
network including the AusLink National Road would be upgraded
to cater for the increasing population and intended development of
the area. It is necessary to ignore the fact that road upgradings
would be by way of compulsory acquisition but also to recognise
that such upgradings would be controlled and planned. That
control and planning is evident in the 2005 SEQRP20 and GARID.
Ms Mitchell’s evidence was that planning for an upgrade to the
Ipswich Motorway began in May 1999.21
18. Fifth, in a compensation case (as opposed to a revenue case) doubts
in valuing property are to be resolved in favour of a more liberal
estimate (as opposed to a more conservative estimate in a revenue
16 See also Turner at 267 per Dixon CJ.
17 Melwood Units Pty Ltd v Commissioner of Main Roads [1979] AC 426 at 434 and 435.
18 See T7-13 LL15-30 and more generally T7-9 to T7-13.
19 See paragraph 86 below.
20 See Ex 59 particularly at p. 115 and the map at 116 identifying road improvements to the
Ipswich Motorway and Centenary Highway in a suite of road improvements. Page 106 of the
SEQRP refers to improvements to existing roads being planned to address the most congested
parts of the network.
21 Affidavit (Ex 46) paragraph 6.
-- 9 of 71 --
10
case).22 What must be ascertained is the full return which may
reasonably be expected from the sale of the land not the most
conservative value: see Turner at 264.”
4. The Hearing and Witnesses
[35] At the hearing of the matter each party called a number of expert and lay
witnesses.
[36] For the Applicant the following expert witnesses were engaged and evidence
was received from them:
a) Mr L Hamilton23, Valuer.
b) Mr Peter Cumming24, Town Planner.
c) Mr Neil Viney25, Traffic Engineer.
d) Mr David Hassall26, Ecologist.
e) Mr Scott Thomas27, Engineer.
[37] For the Respondent the following expert witnesses were engaged and evidence
was received from them:
a) Mr R Brett28, Valuer.
b) Mr David Perkins29, Town Planner.
c) Mr Colin Beard30, Traffic Engineer.
d) Mr Alan Chenoweth31, Ecologist.
e) Mr Maurice McAnany32, Engineer.
[38] The lay witnesses called by the parties were as follows:
a) The Applicant called a Mr Brian Matthews a Town Planner in the
employ of a firm called Axis33 and a Mr Alan Gregory the Director of
a company selling woodworking equipment whose office was located
in Richlands.34
b) The Respondent also called Ms Julianne Mitchell the Chief Engineer
of the Department of Transport and Main Roads who produced an
affidavit setting out effectively the history of the road works in and
22 Commissioner of Succession Duties (SA) v Executor Trustee & Agency Co of South Australia
Ltd (1947) 74 CLR 358 at 373-374 and Boland v Yates Property Corporation Pty Ltd (1999
74 ALJR 209 at 279-280 [356].
23 Exhibits 23, 25, 27, 28, 29.
24 Exhibits 18 and 19.
25 Exhibits 21, 22, 23, 24, 38, 44.
26 Exhibit 17.
27 Exhibit 18.
28 Exhibits 26, 27, 28, 30, 61, 66, 74.
29 Exhibit 19.
30 Exhibits 21, 22, 23, 25, 37, 48, 49.
31 Exhibit 17.
32 Exhibit 18.
33 Exhibit 31.
34 Exhibit 32.
-- 10 of 71 --
11
around the subject site.35 I will refer to the evidence given by Ms
Mitchell when I descend to considering the traffic engineering
evidence.
[39] The Applicant also called James Rohan Whitelaw Chartered Accountant.36 Mr
Whitelaw swore an affidavit setting out the alternative arrangements which may
be entered into by developers seeking to minimise or regularise their exposure
to Goods and Services Tax (“GST”) and also gave about staying developments.
[40] Mr Whitelaw’s affidavit exhibits a copy of the contract entered into between the
Applicant Cidneo Pty Ltd and the Commonwealth Department of Defence for
the purchase of the land.
[41] He points out that the contract for the purchase of the subject land was drawn
specifically for the transaction and reflected the terms of the “tender form”
prepared by the Department of Defence and completed by Cidneo which tender
form specifically offered an amount of $48,110,656 excluding GST for the
purchase of the land.37
[42] Mr Whitelaw drew the Court’s attention to the provisions of Clause 31 of the
contract conditions which deals specifically with the Goods and Services Tax
and pointed out “Clause 31.2 provided that, in the case of a supply which is a
taxable supply, the consideration payable or otherwise provided to the vendor
under the provisions of the contract was to be increased by the amount equalled
to the Applicable GST. The result of these contract provisions was that the
Subject Land was purchased by Cidneo on a “GST Exclusive Basis”. That is,
the purchase price was $48,110,656 plus GST of $4,811,065.60 being a total
amount of $52,921,721.60.38
[43] Accordingly, Mr Whitelaw points out, the purchase of the subject land was a
taxable supply and Cidneo was entitled to an input tax credit, that is a refund of
the GST paid, in the amount of $4,811,065.60.
[44] The expert witnesses had all participated in meetings with their peers and
produced joint reports setting out areas of agreement and disagreement.
Detailed reference will be made to those reports later.
[45] The agreement between the valuers with respect to the $60/m² or the
$60,000,000 before valuation tends to make things somewhat illusorily simple
but, as Mr Gore of Queens Counsel submitted in his observations at the opening
of the case:
35 Exhibit 46.
36 Exhibit 33.
37 Exhibit 33 page 4 para 26.
38 Exhibit 33 page 4 para 30.
-- 11 of 71 --
12
‘… $60 million doesn’t take into account the two things that I have
emphasised: (1) That on the respondent’s case the traffic problems in
the before case were relevantly no different, in assessment terms, to the
after case. I mean counter-intuitively you ask why else would the
department be doing all the major road works in the area that they did if
everything was so fine in the before case?
And secondly, it was a speculative market. I'm not taking a point about
it but it needs to be understood that the respondent's case has tried to
balance things in favour of the claimant at the point.”39
5. The Issues
[46] In its closing submissions to the Court the Applicant submitted that the
following was an apt summary of the issues which arise the determination:
(a) The nature and extent of the impact of the loss of the two Centenary
Highway ramps which were in place in the before case but which were
removed in the after case as part of the project which the land was
resumed.
(b) Whether there was any enhancement of the retained land in the after
case because of the upgrading works constituting the project for which
the land was resumed.
(c) What provision the parties to a hypothetical sale would make for
monetary contributions likely to be imposed by DTMR when
considering a development application for the highest and best use in
the before and after cases.
(d) The value of the land in the after case.
[47] The Respondent through its counsel identified the issues for determination as
those set out in the joint list of issues filed by the parties pursuant to the order of
the Court made on 1 November 2011 namely with respect to two issues:
(a) Traffic;
(b) Valuation.
[48] With respect to Traffic the joint list of issues contain the following:
TRAFFIC
1. The nature and amount of any transport infrastructure contribution or other
condition likely to be imposed by DTMR and likely to be taken into account
by the hypothetical vendor and purchaser in:
(a) the before case; and
(b) the after case.
2. The nature and extent of the effect of the loss of the two ramps between the
Centenary Highway and Boundary Road.
39 T1-60 LL 12-25.
-- 12 of 71 --
13
[49] The Respondent, in its submissions makes reference to other issues which have
arisen since the date of filing the Joint Issues List. Their submissions say as
follows:
“3. Other important issues have arisen since the Joint List was filed.
On 6 December 2011, Metroplex Management Pty Ltd
(‘Metroplex’)40 and the respondent (‘DTMR’) agreed to resolve
issues between them in respect of transport infrastructure
contributions or works relating to development proposed by
Metroplex for the land retained by Cidneo41. As foreshadowed by
the DTMR on 1 December 201142 (the last day of the hearing),
additional issues raised are:
(a) whether, in determining any compensation for injurious
affection, evidence of the settlement between Metroplex and
the DTMR is admissible;
(b) whether the assessment of compensation for any injurious
affection should be based on a cash flow analysis method, or
on some other method.”
[50] With respect to Valuation the joint list of issues contain the following:
VALUATION
3. The effect of 1 and 2 above on the assessment of compensation on the cash
flow analysis approach.
4. Other elements of the cash flow analysis approach being:-
(a) the rate of sale of the last 3 stages in the before case;
(b) the rate of sale for all stages in the after case;
(c) gross realizations in the before and after cases;
(d) the application of GST and the margin scheme;
(e) whether in both the before and after case allowance should be made for
a traffic network analysis report and the timing allowed for that report.
5. The use to be made of the direct comparison approach.
6. The amount payable for disturbance.
6. Lay Witnesses
[51] The Respondent tendered an affidavit from Mr Brian Matthews43, Mr Matthews
was a town planner and a Director of a Town Planning Consultancy known as
Axis Planning whose offices are located at 23 Overlord Place Acacia Ridge.
[52] Axis occupied those premises since 2011 and prior to that its premises were
located in Boundary Road Richlands.
[53] Mr Matthews was called to tell the Court of his experience travelling to the Axis
office located in Boundary Road at Richlands.
40 Metroplex is a company which is related to Cidneo: Whitelaw T7-64.
41 Affidavit of PR MacGregor of 17 February 2012 para 158.
42 T7-73 LL40-50; T7-78 LL20-30.
43 Exhibit 31.
-- 13 of 71 --
14
[54] He began work with Axis in July 2008 and initially had to travel to the
Boundary Road office from Paddington a central city suburb.
[55] His route of travel was along the Centenary Highway through the roundabout
across Ipswich Road and then continuing along the Centenary Highway until he
reached the Kelliher off-ramp along which he travelled to turn left into
Boundary Road to the Axis offices.
[56] On his return journey his path of travel was across Boundary Road to what was
then Bakery Road which became an on-ramp of the north bound Centenary
Highway lanes and from there travelled along the Centenary Highway to the
city.
[57] He followed a similar route towards Ipswich.
[58] His evidence was that prior to the beginning of road works which occurred
shortly after July 2008 his travel pathways were generally clear simple and
efficient.
[59] His evidence was to the effect that the road works including the construction of
the Centenary Highway interchange had a substantial and adverse impact upon
his travel to and from the Axis offices.
[60] He gave a detailed description which it is unnecessary to recite here of the path
of travel after the road works began. The important point was that the new route
of travel added about 4 km of additional travel to work in the morning. He
estimated that to add about 5 minutes to his time of travel.
[61] He also gave evidence that available alternatives were unattractive because they
also had to confront congestion on the Ipswich Motorway and had to negotiate
three merge lanes when getting onto the Ipswich Motorway from the Centenary
Highway. His evidence about other destinations including Ipswich was of a
similar tanner all of which related to increased congestion on the road system.
[62] Mr Matthews observed:44
“Since the interchange was constructed, there seemed to be a lot more
northbound car traffic travelling along Pine Street and Archerfield
Road and from there, into the local surrounds and the Ipswich
Motorway. I definitely noticed that this vehicle traffic had increased,
but I cannot say from where those vehicles are coming from, other than
from places south of Pine Street.”
44 Exhibit 31, p. 5 para 27.
-- 14 of 71 --
15
[63] Comparing the post-road works situation with the pre-road works situation Mr
Matthews observed45
“Under the previous road network, businesses in the area had easy
access to the Centenary and Ipswich Motorways and from there could
travel easily in any direction. Access is now significantly less
convenient and I have real difficulty in seeing how it can ever be
restored to the practical and functional levels that previously existed.”
[64] Earlier in his affidavit Mr Matthews had made observations about the operation
of the “new” Centenary motorway. He said:46
“I often referred to the new Centenary Motorway as being the ‘wedge’.
That is because, in my view, it has driven a wedge between Richlands
and Wacol and created two different and largely unconnected areas.
One area is bounded by Progress Road, the Centenary Motorway and
the Ipswich Motorway; and the second situation is boarded by the
Centenary Motorway, Progress Road and Archerfield Road. These two
areas have had their previous road connections removed and there
seems to me to be no capacity for an easy future connection of these
two areas.”
[65] Under cross-examination from Mr Gore of Queens Counsel, Mr Matthews upon
being taken to diagrams contained within supplementary report of Mr Beard
(Exhibit 37) and paying particular attention to traffic counts in 2008 and 2011.
[66] Mr Matthews confirmed that a fair précis of his evidence was that:
“… before the works done by the Department were carried out, there
was often congestion but after the works were carried out, it wasn’t
congested very often on the Ipswich Motorway.”47
[67] In his re-examination Mr Matthews confirmed that:
“Even without road works, you could have some congestion there.”
[68] I regard the evidence of Mr Matthews as somewhat equivocal and not of great
assistance to me.
[69] The Applicant also called Mr Alan Maxwell Gregory a Director of Gregory
Machinery Pty Ltd which has occupied and traded from premises at 807
Boundary Road Richlands since 200348.
[70] Mr Gregory’s company Gregory Machinery Pty Ltd deals in woodworking
equipment to the cabinet making industry and also to the DIY hobbyist markets
and the education systems.
[71] Mr Gregory’s evidence was to the effect that before the construction of the
Centenary Highway Interchange his business and customers had very easy and
direct access to the north, south, east and west from their premises and once the
45 Exhibit 31, p. 7 para 39.
46 Exhibit 31, p. 5 para 29.
47 T2-6 L 38.
48 Exhibit 32.
-- 15 of 71 --
16
roundabout at the intersection of the Centenary Highway and Ipswich Road was
signalised it functioned well and congestion was not a problem.49
[72] Mr Gregory gave evidence that access to his property from all points of the
compass was easy and convenient in the “before scenario”.
[73] He was not as happy with the “after scenario” and observes in his affidavit:
“In my opinion, the changes that happened to the final design of
Centenary Highway Interchange have resulted in this no longer being a
go ahead area; it has become isolated from all major arterial roads and
has lost its vibrancy. I have no doubt that the removal of the Centenary
Highway on and off ramps has had an adverse impact on my business
and many businesses in the area.50
[74] Mr Gregory’s evidence was to the effect that, in his opinion, the road works
have caused a diminution in the amount of custom his business enjoys as a
consequence of customers having difficulty finding their way to his premises.
[75] Mr Matthews gave evidence that prior to 2011 Axis Planning for whom he
works had its offices at Unit 6B, 848 Boundary Road Richlands and at the time
he lived at Paddington in the City. Mr Matthews evidence was to the effect that
he as a result of the location of his home and the then location of the Axis
offices travelled the Centenary Highway across Ipswich Motorway and along
the Kelliher Road off-ramp advance into Boundary Road.
[76] The Gravamen of Mr Matthews evidence was, at the end of the day, that in both
the before and after situation with respect to the resumption of the subject land
and the road works at the various interchanges there was in his experience
always congestion around the various interchanges.
[77] It was Mr Matthews contention as a non-expert observer of traffic affairs that
access as it presently exists was significantly less convenient than previously
particularly with respect to access to the Centenary and Ipswich Motorway51.
[78] Referring to the southbound movement on the Centenary Highway through the
Ipswich Motorway roundabout.52
7. Town Planning Issues
[79] Mr Peter Cumming the Town Planner was engaged by the Applicant. As
indicated above the corresponding expert engaged by the Respondent was Mr
David Perkins. Both Mr Cumming and Mr Perkins are experienced Town
Planners.
49 Exhibit 32 page 2 para 11.
50 Exhibit 32 page 5 para 30.
51 Exhibit 31 page 7 para 39.
52 T2-7 L 12.
-- 16 of 71 --
17
[80] Prior to the hearing Mr Cumming and Mr Perkins met for the purpose of
preparing a Joint Report53 setting out areas of agreement and disagreement and
the reasons for any disagreement.
[81] They were provided a detailed report setting out the areas of agreement and
noted54 that there were no matters of disagreement between the planners
regarding the Lands Statutory Planning Designations at the time of the
resumption.
[82] That should not be taken to suggest that there were no areas of disagreement
because later in their joint report they were able to identify and describe some
areas of disagreement.
[83] It is appropriate to identify the key areas of agreement which were reached
between the town planners as to the relevant statutory planning instruments and
designations as at the time of resumption.
[84] The planners identified the following planning instruments as being relevant at
the time of resumption:
(a) The South-East Queensland Regional Plan 2005-2026
(b) The Brisbane City Council City Plan 2000 including:
The Western Gateway Local Plan.
The Richlands Area Infrastructure Contributions Planning
Scheme Policy and;
The Draft Local Growth Management Strategy (LGMS).55
[85] Pursuant to the provisions of the South-East Queensland Regional Plan 2005-
2026 the subject land was:
(a) Within the Urban Footprint.
(b) Potentially suitable for Urban purposes.
(c) Within an area described as the “Western Corridor”.
(d) Located in Wacol which is identified in the Regional Plan as a major
economic activity area and industrial cluster and a key area for
industrial development.
(e) Affected by the Employment and Economic Activity Areas Policy to
“encourage employment growth in regional activity centres and
economic activity locations”.56
[86] The location within the Western Corridor is a matter of some significance.
[87] Within the SEQRP the Western Corridor has been identified:
53 Exhibit 19 – Joint Planning Report September 2011.
54 Exhibit 19 – page 10 section 6.8.
55 Exhibit 19 page 7 para 6.1.
56 Exhibit 19 page 7 page 6.2.
-- 17 of 71 --
18
(a) Significant growth area for South East Queensland providing major
opportunities for economic development and employment creation;
(b) Has an area to which increased economic development of population
growth is intended to be attracted and;
(c) Has an area in which employment and industry growth is supported.
[88] Reflecting its previous use as property owned by the Department of Defence the
subject land, under the Brisbane City Plan 2000 was designated as a Special
Purpose Centre (SP3) Major Defence and Communications Facility. Within the
area in which it was located it was designated for general and future industry.
[89] Clearly its uses as Defence and Communications’ Centre has been discontinued
preparatory to sale to the Applicant.
[90] It is also proximate to a Special Purpose Centre (Mixed Industry/Business Area)
Designation on the Strategic Plan.
[91] Both the Town Planners agreed that the subject site could reasonably be
expected to come under the umbrella of the Mixed Industry Business Area
Designation.
[92] They also agreed about other indicia which pointed to the subject site being
developed for industrial and related purposes.
[93] Those indicia included the inclusion of the subject land in the Western Gateway
Local Plan which contemplated major industrial development being
concentrated south of the Ipswich Motorway.
[94] Significantly the Town Planners agreed that57
“The Statutory Planning Regime in place at the time of resumption
indicated that the Wacol precinct and the subject land:
1. Was seen as a catalyst for industrial and employment growth
in the Western Corridor;
2. Was seen as an industrial area of city wide and regional
significance;
3. Industrial development on the subject land was to be
supported by specialised retail and commercial centre; and
4. The Mixed Industry and Business designation of the Ipswich
Motorway/Centenary Highway/Progress Road triangle in the
Brisbane Strategic Plan recognised the strategic potential of
the land for industry and business activities and employment.”
[95] Having reached that level of agreement the planners then turned to considering
the impact of the resumption on plans for development. At the time they
conducted their joint meeting in September 2011 the Planners had before them
development plans before and after the resumption date which were exhibited to
the Joint Report as figures 8 and 9 and before and after preliminary approval
documents which they annexured to their report as Annexure 2.
57 Exhibit 19 page 9 para 6.7.
-- 18 of 71 --
19
[96] The Planners agreed that, with respect to the differences between the before and
after plans, the development plans show:
“1. Development staging in four stages to the east and west of a central
park which encompasses Bullockhead Creek and its environs.
2. In both Plans the green areas represent proposed public parkland
and the hatched green areas, land proposed to be held in private
ownership but where trees cannot be removed.
3. The numbered white areas in both plans indicate lots to be used for
industry and associated purposes.
4. Lot numbered 20 in both Plans is proposed as the location for a
small convenience centre with up to 6,000 m² of floorspace (the
‘Etro’).
5. The Before Plan 7096-102 in Figure 8 shows a mixture of
development land, public open space and a hatched green area
which cannot be built on in the northeast of the land adjacent to the
Ipswich Motorway.
6. Both Plans show areas of stormwater detention/retention, although
the suitability of these basins (locations, configurations and sizes)
would be subject to further detailed engineering review.
7. The After Plan shows the DMR resumption area of 8.365ha in the
northeast of the site and an increase in the Public Open Space and
green hatched areas on the remainder of the land. The latter
reflects a decision of the Planning and Environment Court in
November 2009 relating to an earlier development application,
and, subsequent Development Applications and negotiations with
Brisbane City Council.”58
[97] There was disagreement between the Planners about the sequencing of the
development and Mr Cumming took the position that the numbering of the
development stages was nominal only and that in the before case, “Stage 3” was
proposed to be developed first.59
[98] By the time the case was concluded Mr Cumming prophecies were shown to be
realistic as a number of options were advanced with respect to the sequencing of
the development stages. There was no disagreement that any development
which did occur on the subject site would be staged.
[99] The Joint Report set out a table showing the Before and After Resumption Land
Use Comparison60:
TABLE 1 – BEFORE AND AFTER RESUMPTION LAND USE
COMPARISON
Land Use Before
area
(ha)
After area
(ha)
Difference
(ha)
Stage 3 area 35.415 27.028 -8.387
Lot Yield 23 20 -3
Lot area
(developable land)
22.874 17.537 -5.337
Parkland 6.777 4.363 -2.414
Common Property 0.080 0.080 0
Road 4.954 4.385 -0.569
Private Open Space 1.881 0.720 -1.161
58 Exhibit 19, page 10 para 7.1.
59 Exhibit 19, page 10, para 7.1.
60 Exhibit 19, page 11 Table 1.
-- 19 of 71 --
20
[100] The ETRO Precinct which is referred through much of the planning evidence is
a business or commercial centre (otherwise described as a convenience centre)
with up to 6,000 m² of floor space.
[101] Mr Cumming confirmed to the Court that he, as a planner, was happy that the
6,000 m² ETRO described as a small convenience centre was congruent with the
notion of a specialised retail and commercial centre.61
[102] Mr Cumming also confirmed that Bullockhead Creek which runs through the
site has an impact on hydraulics and the staging of the various phases of
development.
[103] He had been asked about the observation by Mr Hamilton, the valuer called by
the Applicant, in his report where he observed62 said:
“A period of 18 months from the date of resumption has been adopted
in the after resumption scenario (together with an additional cost of
$100,000) to allow for necessary approvals plus a comprehensive
traffic analysis and redesign of the estate particularly in terms of the
construction of Boundary Road and the hydraulics on Bullockhead
Creek.”
[104] When asked what, in terms of the redesign of the estate and the hydraulics on
Bullockhead Creek was the difference between the before and after case that
needs to be looked at, Mr Cumming’s evidence was as follows:63
“Well the hydraulics – the difference is in the before case there was a
lot of work – a body of work done by a group of professional
consultants which could be used in the before case application. In the
after case stage one was looked upon to be from the west rather than
the east. Therefore, a lot of the hydraulic reports, a lot of the traffic
analysis, the bulk fill and earthworks would have had to have been
redone. In the case of drainage, for example ----
HIS HONOUR: Is that because of staging? -- Yes, because of the
staging detail. In the case of drainage it also relates to the resumption
area. There’s a new road alignment. The DMR doesn’t like more
water going into their roads causing flooding and drainage problems
than exists at the – at the existent time. Therefore, drainage studies
would have to reconceptualise. The eastern sector so that they fitted in
with the new road pattern and the service road provided there and also
on the western side of the stage one more detailed work would have
had to have been done, and that’s a similar exercise for bulk
earthworks, particularly because reconceptualising the bulk earthworks,
there was an assumption in the early work that cut would come from
the west and go the east. If you’re using the west as stage one that
would have to be reconceptualised, and there’s an extensive amount of
work required to do that. The other thing is in the resumption area it
falls away quite steeply to the service road in the after case, so again
the cut and fill exercise would have to take into account that some of
the cut that was going into the resumption area would no longer go into
that area. A place would have to be found somewhere else in the
subdivision. As your Honour would be aware from visiting the site, the
site is a sloping site, it’s not a flat site, so – and it’s got the creek in the
middle and the creeks at either end, so matters of drainage and cut and
fill would take some considerable time on this land, because in the end
61 T2-16 L 40.
62 Hamilton Report p 56.
63 T2-17, 2-18 LL20 – 20.
-- 20 of 71 --
21
with an industrial site you’ve got to end up with flat pads and a bench
situation. It can’t be like a residential development where you can go
with the flow of topography.
MR HINSON: The highest and most elevated part of the land was in
the north-eastern corner of the land that was resumed; is that correct? --
No. That was the resumption – the resumption area in the north-east is
lower.
The north-west, yes? -- Yes.
But in terms of its appearance from the motorway it’s visible from the
motorway in the before case? -- Yes.
And was the one of the reasons why you’d start at the east? -- The
eastern – there was some contention early on in the joint experts’ report
about staging. The office and the site office on the site is on the eastern
side for the very good reason that in the before case we had ramps to –
Metroplex had ramps to the Centenary Highway, so that was the easiest
and convenient access. It was only 3 or 400 metres away and that too -
----
HIS HONOUR: When you say Metroplex had ramps, the road system
----? -- Sorry, the road system had ramp access to the Centenary
Highway. So that also on the eastern side was the place for – if I could
show again a board and explain that.”
[105] Under cross-examination by Queens Counsel for the Respondent, Mr Cumming
conceded that as a planner in matters of traffic engineering particularly on
matters of specificity he would defer to the opinions of traffic engineers.
Relevantly Mr Cumming under further cross-examination by Mr Gore QC
conceded, with respect to the potential for a demand by the Department of
Transport and Main Roads for a $30 million road works contribution, that no
part of that $30 million was referable to the Centenary Highway, Ipswich
Interchange Motorway Upgrade and that, in the before case, he understood that
the Court has to assume that the Department did not intend to upgrade the
interchange.64
[106] The consequence of that was that in the before case the scenario involves the old
interchange with whatever problems it had.65
[107] Although not a traffic engineer, Mr Cumming was pressed by Mr Gore that
respect to the interchange prior to the road works upgrading being carried out it
was what he described as “highly problematical”.
[108] He declined to concede that the interchange was any more problematic than
other major intersections in peak hour periods.
[109] Having conceded that the project involved the loss of the Kelliher Road ramp
and the Bakery Road ramp this proposition was put to Mr Cumming and he
agreed with it.
64 T2-25 L 30.
65 T2-25 L 42.
-- 21 of 71 --
22
“So necessarily what you are saying is that motorists using the Kelliher
Road off-ramp will be coming through the old Centenary
Highway/Ipswich Motorway interchange, otherwise there is nothing to
complain about; correct?”66
[110] Similarly he conceded that those that go up the Bakery Road on-ramp are going
to go through the Centenary Highway/Ipswich Motorway Interchange.67
[111] That led to Mr Gore being able to put to Mr Cumming that:
“What you’re telling us is that on that information there will be some
major percentage of the 4,000 vehicles per hour that go through what
I’m calling the old intersection; correct?”68
[112] Mr Cumming agreed with that proposition and then this passage of cross-
examination emerged:69
“And if the old intersection is already highly congested you don’t need
to be an expert to work out that a proposal that intends to put a
significant proportion of 4,000 vehicles per hour through that heavily-
congested intersection could have approval problem? – Yes. If – sorry.
Not approval problems, I think that’s a different issue, but I’d point out
this is a contraflow development. This is a planners – what we try and
what transport planners try to achieve in the urban area, getting jobs out
to the mid range point to prevent traffic coming into the city, and also
increase contraflow. And by ----
MEMBER: By ‘contraflow’ you mean drags traffic in a opposite
direction to what might be typical of peak hour? – Exactly. So in the
morning peak the big – the big line of traffic is not going north to
Metroplex or destinations at Wacol, it’s coming south from Springfield
and residential areas, so this is a contraflow development, so in that
context ---
Do you mean heading north or coming from north in that example you
just gave? -- The big flow in the morning peak, and you could so it
then, you can see it now, and you can see it on every other road that
leads to the CBD is northbound. The big flow is not southbound.
MR GORE: You’ve got no basis at all for saying that, that’s a guess? -
-- Well, I do because I - I have visited this site since 2005.
To describe it as a contraflow development, I’m suggesting, is really
just guesswork? – It’s observation over that period of time. A long line
of traffic coming from the south ----
No, no, no -----?-- ----- and a lesser line coming from the north.
-----you’re missing the point, you ‘re missing the point. The
development that you’re describing as ‘contraflow’ doesn’t exist at the
moment; correct? -- That’s right.
And, for all you know, all the people that work there might want to live
at Springfield because it’s convenient and travel to this site in the
morning, hardly contraflow; correct? – That’s right, but it also, if they
do that, they then take off traffic from the Centenary Highway between
the Ipswich Motorway and the real point of disaster on the Centenary
Highway road system, which is the Moggill roundabout on Milton
Road.
66 T2-26 L 50.
67 T2-26 L 52.
68 T2-27 L 10.
69 T2-27, 2-29 LL 14-26.
-- 22 of 71 --
23
Let’s get back to my question. You’ve accepted that if a significant
proportion of the 4,000 vehicles per hour peak generation, identified in
table two of your report, utilise the old interchange, that’s an issue for
the approval process – I’ll try to put it in neutral terms – correct? –
Well, I – my answer to that question is perhaps, and I answer it in this
way, as a city planner: intersections since the 1980s of this ilk have
been funded by the Federal Government, usually because they need so
much money. It’s not normally part of the planning system where you
say, well, an individual developer, albeit, you know, a 60 or 70 hectare
developer, contributes to these sort of intersections. In the 1980s the
national freight system under the Hawke Government came in and the
Federal Government realised they had to fund major freight routes and
roads, and this is that – that sort of intersection. So the proposition I
think you’re pushing – putting to me is that this was important for the
approval process for Metroplex. My answer to that would be I think
it’s much more of a point for the approval of a development like
Springfield, which – Metroplex is 60 to 70 hectares of developable
land, creating employment at a point, which is desirable in city
planning terms, whereas Springfield is almost 3,000 hectares of
residential development which creates far, far greater problems. So,
you know, I think the question of whether this is an approval, whether
in the approval process this is related to Metroplex, I think it’s far more
related to much, much bigger developments within this area.
How does the 4,000 vehicles per hour generated by Metroplex compare
with the peak volumes through the old interchange as at February 2008,
do you know? -- No, I don’t, and I looked for that figure in Mr Beard’s
report for a total figure and I couldn’t find it.
You see, if it was, say – let me try to make the questions easy – if it
was a figure of, say 2,000 ----? -- Yes
-----that was using the intersection before Metroplex was taken into
account, and Metroplex is 4,000, you can forget about Springfield, this
is a problem for Metroplex if it’s going to triple the number of vehicles
gong through the intersection; correct? -- Well, the first thing is, I
thought it was agreed that the before and after scenario development
was industrial only –
No, no, no, no, don’t move away from my question. Please don’t move
away from my question?-- Well, I don’t -- I don’t -----
If the figures are as I’ve asked you to assume -----? -- Yeah.
---that’s a problem for Metroplex. That’s a problem for the approval
process, isn’t it? -- It is. It’s a consideration. Absolutely.
If 2,000 represents a heavily-congested intersection and Metroplex
wants to put 4,000 more vehicles through that intersection it’s pointless
talking about Springfield , that’s a problem for Metroplex, isn’t it? --
Well that’s not an opinion I share because Springfield is currently
23,000 people and is proposed to be a hundred and 10,000 people.
So you think that the Metroplex application would probably be
approved because even though it was increasing the traffic through the
intersection from 2,000 to 6,000 vehicles per hour, in circumstances
where it’s accepted that the 2,000 vehicles per hour represents a high
level of congestion, you don’t see that as a problem? -- You’re talking
about the approval process. That’s not necessarily to do with impact.
So in the approval process you‘re considering a whole range of things.
For example, Boundary Road. I think Mr Viney has well put the fact
that if Boundary Road is throughput, and the Department of Main
Roads knew the importance of Boundary Road, that would negate a lot
of the impact on the Ipswich Motorway and Centenary Highway
-- 23 of 71 --
24
because that creates then a major suburban route behind the highway
system which alleviates highway traffic.”70
[113] Consequent upon that passage of cross-examination Mr Gore took Mr Cumming
to the report (Exhibit 25) prepared by Mr Beard the Traffic Engineer engaged
by the Respondent.
[114] In particular he took Mr Cumming to page 10 in paragraph 6A where Mr Beard
said that:
“There is no traffic engineering basis for a claim that external road
works required pursuant to the 'after' development scenario would have
been more than those required pursuant to the 'before' development
scenario?”
[115] Mr Cumming conceded that he had read that and went on to explain that he
disagreed with the proposition in Mr Beard’s paragraphs 6A from a planning
point of view.
[116] While it might appear that the answers given by Mr Cumming under cross-
examination were evasive I think, fairly considered, they might be taken merely
to reflect his particular skill set as a town planner and not an adoption by him of
any particular traffic engineering point of view.
[117] His apparent view of the road works after the removal of the ramps was that
contributions were sought for the cost of removing the ramps rather than the
contribution being sought because of a need to upgrade the various intersections
in and around the subject site. If that is his view then, in my opinion, he is
incorrect from a traffic engineering point of view.
[118] Mr Cumming’s evidence71 was unconvincing with respect to his apparent lack
of awareness of what constituted an unacceptable queue length or an
unacceptable degree of saturation of an intersection’s capacity.
[119] With respect to completing the “missing link” Boundary Road Mr Cumming
agreed, in response to a question from me, that from a planning perspective it
much more preferable to complete the “missing link”.72
[120] He also confirmed that that preferable outcome applied in both the before and
after case.73
8. Engineering Issues
[121] Scott Thomas, Engineer acting on behalf of the Applicant and Robert Marshall
an Engineer acting on behalf of the Respondent met together to consider a
conceptual design layout for works which were identified by the Respondent to
provide additional east-bound capacity to Progress Road to better accommodate
70 T2-27-29 L
71 T2-33,34 and 35.
72 T2-39 LL 15-30.
73 T2-39 L 41.
-- 24 of 71 --
25
the traffic exiting from the Ipswich Motorway south-bound off-ramp. That
conceptual design layout was shown in two Cardno sketches, No. CEB06133-
022-SK001 Revision B and No CEB06133-002-SK002 Revision A74.
[122] Cardno (Queensland) Pty Ltd also supplied opinion with respect to cost dated
14 February 2012, Version 3 for the construction of the works.75
[123] Thomas and Marshall agreed:
“That the attached opinion of cost dated 14 February 2012, Version 3
(Final) is a realistic assessment of anticipated development costs for the
works depicted on the aforementioned conceptual design layout”.
[124] They also agreed if the extent of works assumed in the opinion of costs of 14
February 2012 was altered by the opinions of experts and other disciplines then
the costs would have to be re-evaluated. The costs identified in the opinion of
costs are as follows:
Summary
Schedule A: Consultants Fees = $127,500.00
Schedule B: Civil Works = $470,051.19
Schedule C: Bridge Works = $268,500.00
_______________
Sub-Total = $866,051.19
Project Contingency (20% of
Construction Costs) = $173,210.24
Provision For Cost Escalation (5% of
(Construction Cost) = $43,302.56
Q-Leave (0.525% of Total Cost) = $4,546.77
_______________
Total = $1,087,110.76
[125] Engineers engaged by the parties Mr Thomas (Applicant) and Mr Maurice
McAnany (Respondent) met to consider civil engineering matters.
[126] They had earlier been provided with proposed development layouts in respect of
the properties and reached a number of points of agreement. It is convenient
and useful to set out those points of agreement here because they inform the
opinions and reports of other experts engaged by the parties. There was
unanimity between these two engineers and no points of disagreement emerged
in the course of their meeting. Accordingly there was no need for them to be
called either to give evidence or to be cross-examined.
74 Exhibit 71.
75 Exhibit 71.
-- 25 of 71 --
26
76
9. Traffic Issues
[127] It is appropriate to describe in some detail the road system within which the
subject site is located.
[128] I borrow from the Report prepared by Mr Beard the Traffic Engineer engaged
by the Respondent when he says77:
“The subject site, having a total area of approximately 101.4 hectares,
is located in the north-east corner of the triangle of land which is
largely industrial in nature between the Ipswich Motorway, the Logan
Motorway and the Centenary Motorway. Progress Road and Boundary
Road are the primary roads providing access to and through the
triangular area. Progress Road is classified by Brisbane City Council in
the City Plan as an Arterial Road, while Boundary Road is classified as
a suburban route (essentially a sub-arterial road). … Between the
northern and southern portions of the subject site, Boundary Road is
unconstructed, with no bridge over Bullockhead Creek. Historically,
the land was owned by the Commonwealth (Defence Department) and
used as barracks. It was classified in the City Plan as Special Purposes
Centre reflecting its previous use.”
76 Exhibit 18, page 2.
77 Exhibit 25, page 2.
-- 26 of 71 --
27
[129] There were a number of meetings between Mr Beard and Mr Viney the Traffic
Engineer engaged by the Applicant.
[130] Mr Viney had been engaged by the Applicant since it purchased the site and has
calculated a range of various design traffic generations relevant to different
developments scenarios which had been advanced at various times.
[131] A detailed description of the background traffic planning from the Department
of Transport and Main Roads was provided to the Court in an affidavit from
Julianne Mitchell who between 2005 was the Manager, Transport Planning in
the Metropolitan Region in the Respondent Department.
[132] Ms Mitchell’s affidavit also sets out in some detail the background to the
changes which occurred to the site as part of the project for which the subject
land was resumed.
[133] It is unnecessary to set out in detail all of the matters set out in the affidavit of
Ms Mitchell. Counsel for the Respondent has, in their submission to the Court
summarised what they have described as the problems prior to the project being
undertaken. They expressed them in these terms which they acknowledge are
extracted mostly from the affidavit of Ms Mitchell but also from the report of
Mr Beard.78 They said this:
“The Ipswich Motorway was declared as a motorway in 1994. It is part
of the national highway network. From 1999, both the Federal
Government and the State Government began to plan an upgrade to the
Ipswich Motorway. Key reasons underpinning the need for an upgrade
identified in a planning study undertaken between 2000 and 2002
included the heavy demand on the network evident in congestion, the
low standard geometry of the existing road, high accident rates and
strong growth. In 2005 the Prime Minister announced an allocation of
$320 million to upgrade the Wacol to Darra section of the Ipswich
Motorway including the Progress Road and Centenary Highway
interchanges. The Centenary Highway also had sub-standard
geometry. Both the Ipswich Motorway and the Centenary Highway
carried significant (and similar) traffic volumes during the years prior
to the resumption.79
[134] Ms Mitchell’s affidavit sets out the scope of the Ipswich Motorway Wacol to
Darra Upgrade project. She says this:
“22. In 2006 the Ipswich Motorway Wacol to Darra Upgrade project
scope included:
an upgrade of the Ipswich Motorway from the Logan Motorway
interchange to Jervis Street in Darra to six lanes;
associated service roads in this section;
an upgrade of the Centenary interchange to three tiers with both
right turns, north to west and south to east are grade separated
out of the roundabout; and
minimum amendments to the Progress Road interchange.
78 Mitchell affidavit Exhibit 46. Beard Exhibit 48 Table 16.
79 Outline of submissions of the Respondent paragraph 26.
-- 27 of 71 --
28
24. A locality plan with the proposed extent of the Ipswich Motorway
to Darra Upgrade works is attached at ‘JM-2’. A photomontage of
the 2006 proposed layout of the Centenary Highway Interchange is
attached at ‘JM-3’.
25. The 2006 three-tier Centenary Interchange Upgrade proposal was
to provide the following advantages:
(a) enable independent turning movements;
(b) provide a new overpass for movement from the Centenary
Highway to the Ipswich Motorway;
(c) provide connectivity across the Ipswich Motorway in Darra;
(d) provide Centenary Village residents with access to the north,
south, east and west;
(e) separate through traffic from local traffic; and
(f) provide service road connections between residential and
industrial areas.
26. The proposed benefits of the Ipswich Motorway Wacol to Darra
Upgrade project included improved travel time on the Ipswich
Motorway, a target of 50% reduction in accident frequency,
reduced motorist complaints and more efficient freight movements.
The cost benefit analysis for the Ipswich Motorway Upgrade at the
time had a calculated Benefit/Cost Ratio of 6.27.”80
[135] Ms Mitchell also identifies a number of other projects she describes as being in
either close or strategic vicinity to the Ipswich Motorway Wacol to Darra
Upgrade those included:
“27. In 2006 there were also other projects in either close or strategic
vicinity to this project that were either in the short term planning
stage or were being undertaken, including:
(a) the Logan Motorway Interchange at Goodna with
construction to begin in September 2006 and completed in
2008.
(b) the South West Transport Corridor (SWTC) being an
extension of the Centenary Highway. The State
Government announced funding to extend the Centenary
Highway from Springfield to Yamanto. The project was
estimated at $270 million with construction to begin mid
2006 and completed by 2009.
(c) the Kelliher Road Upgrade at Darra being the
construction of a short section of high standard motorway
link from the Centenary Highway at Darra to Brisbane’s
south-western suburbs started in September/October 2005
with the project taking 15 months. The project was
jointly funded by the Department and the Brisbane City
Council at a cost of $44 million. That section of the
Centenary Highway was and still is under the control of
Brisbane City Council and the section is in the process of
being declared a State controlled road and eventually
declared a motorway.’81
[136] As submitted by counsel for the Respondent subsequent to the filing of the joint
list of issues other issues arose and in particular the Respondent points to the
fact that on 6 December 2011 some three and a half years after the resumption
the then developers of the subject land and the respondent reached agreement
for resolution of issues between in respect of transport infrastructure
80 Exhibit 46, paragraphs 22, 23, 24, 25.
81 Exhibit 44, paragraph 27.
-- 28 of 71 --
29
contributions or works relating to development proposed by Metroplex for the
land. I will return to this matter later.
[137] That agreement then raised the following additional issues namely:
(a) Whether in determining any compensation for injurious affection,
evidence of the settlement between Metroplex and the Department is
admissible? and;
(b) Whether the assessment of compensation for any injurious affection
should be based on a cash flow analysis method, or on some other
method?82
[138] An issue had also arisen as to the nature of the project for which Cidneo’s land
was resumed in the first place.
[139] That issue was resolved by correspondence from the Respondent’s solicitors to
the Applicant’s solicitors of 14 October 201183 which was exhibited to the
Traffic Report prepared by Mr Viney for the Applicant.
[140] That letter provided, in part,
“As you are aware, the issue of the separation of the various projects is
a complex one and our client has been investigating the issue for some
time. Our instructing client has recently met with various officers and
project managers from the Department and has reached the conclusion
that:
planning for each of the various projects in the area was
undertaken to accommodate each other project;
there was never any planning undertaken for the Darra to
Springfield Transport Corridor which did not also contemplate the
upgrading up the Ipswich Motorway Upgrade;
the upgrade of the Centenary Highway on its own would have
required a systems interchange on the Ipswich Motorway and
Centenary Highway interchange (and therefore a resumption of
land from your client).
On the basis the Department is prepared to accept that the loss of the
Centenary Highway ramps were caused by the Ipswich Motorway
Upgrade Project (Project), being the project for which your client’s
land was resumed.
Our client’s current position in the ‘before’ scenario is that the ramps
were in place and the road network had not yet been upgraded as part
of the Project. This accords with Scenario 1 set out in the further joint
report prepared by the traffic engineers.
Our client’s position in the ‘after’ scenario is that the ramps were lost
and the road network had been upgraded as a result of the Project. This
accords with Neil Viney’s Scenario 4A in the further joint report
prepared by the traffic engineers.”
82 Respondent’s outline of submissions para 3.
83 Exhibit 24 page 85.
-- 29 of 71 --
30
[141] In the second Joint Report Mr Beard’s position with respect to the before
scenario was expressed as follows:
“Without the Ipswich Motorway and the Centenary Highway
Interchange Upgrading, the major road network in the area would be
seen as heavily congested, so the proposed development would be seen
as premature. However, approval of a stages development spread over
(say) ten years could probably have been negotiated subject to
construction of Boundary Road sooner rather than later, and works at
the Progress/Ipswich Interchange of $2.0 to $3.0 million. The
application history would have been an impediment to negotiations.84
[142] The acknowledgement by the Respondent in the correspondence of 14 October
2011 somewhat but not completely simplifies the traffic analysis because it is an
acceptance that the loss of the ramps was caused by the project for which the
subject land was resumed.
[143] Mention should also be made of the works constructed on Boundary Road to
complete the “missing link”.
[144] As I perceive the evidence it was acknowledged by both parties that in each of
the before and after cases it was necessary to construct parts of Boundary Road
to accommodate traffic generated by the proposed development of the subject
land and adjoining land to achieve its highest and best use.
[145] The Boundary Road works was important not only to the Applicant in the
development of the subject land but also to the resuming authority, the local
government and business in the area to be able to make better use of the road
network.
[146] In my view the evidence is compelling that in the before situation i.e. prior to
the resumption, anybody seeking to develop the subject land would have to have
confronted the serious traffic congestion already extant in and around the
subject site as well as having to recognise that development of the subject land
to achieve its highest and best use would necessarily have been a significant
generator of additional traffic into the existing already congested system.
[147] The evidence, in my view, is similarly compelling that development of the
subject land would require more than the Boundary Road road works and that,
at very least, an attempt would have been made by the Respondent to extract
some contribution for road works in the area. This would be particularly
emphasised if Mr Beard’s point was accepted that any development prior to
works aimed at reducing the existing congestion would be regarded as
premature.
[148] This is confirmed by the traffic engineer for the Respondent, Mr Viney, who on
11 April 2007, in response to an information request issued by the Department
84 Exhibit 22 page 2.
-- 30 of 71 --
31
of Main Roads and Transport in relation to any earlier proposal for development
of the subject site, wrote as follows:
“In relation to increased traffic flow, the site will be a significant traffic
generator. However, the Ipswich Motorway is to be upgraded to a six
lane facility and the upgraded facility will be able to accommodate the
additional traffic flows. The development of the site will be dependent
on the concurrent construction of the motorway upgrade.
Similarly, the Centenary Highway extension will be increasingly of
importance in providing access to expanding residential areas being
proposed for development by the State. The site will become an
important employment node for the expanding residential areas to the
south-west and will consequently reduce the need for travel further
inbound for employment purposes for those residents.
Provided the intersection upgradings that are required for the ultimate
site generation are completed, there is no reason that general
construction traffic should cause unacceptable levels of congestion.
There will be a need to stage the infrastructure improvement
programme to suit site development and management of construction
traffic will be a part of this staged upgrading process.
In relation to late night truck noise, it is noted that the type of
development proposed for the Metroplex @ Westgate project does not
generate high heavy vehicle flows at those times. Truck terminals,
large warehousing or heavy manufacturing operations are generally not
the type of uses that would be permitted to establish in Metroplex @
Westgate.
Consequently, it is expected that the uses proposed will be controlled to
ensure that late night traffic is not significant.”
[149] Apparently as a result of reconsideration of that particular development
application there was a reduction in the scale or intensity of the proposed
development which led to Mr Viney meeting with another traffic engineer and
Mr Beard for the purpose of a Planning and Environment Court Appeal.
[150] That meeting occurred on 1 May 2008 and one of the points of agreement
between those three traffic engineers (i.e. Mr Viney, Mr Beard and another) was
that:
“While it appears that at least some part of the subject development
could be approved now subject to appropriate conditions, it is also
likely that the total development cannot reasonably proceed until other
network upgradings, by both Council and DMR, are committed. It is
likely that the subject development should be making some
contribution to some of those upgradings; and … Irrespective of the
subject development, the connection of the missing section of
Boundary Road through the subject site is increasingly important in the
local road network.”85
[151] It seems to me that if the position in May 2008 was such that the development
of the subject site would be seen as premature until such time as upgrading of
the road network occurred that points to the high likelihood of the Department
of Main Roads seeking a contribution to Road Upgrading in the before situation
that may have been satisfied by the Boundary Road works.
85 Exhibit 47 Tab 3 page 1 – Report on Meeting of Experts – Traffic, 1 May 2008.
-- 31 of 71 --
32
[152] How much that contribution would be is another question.
[153] Mr Beard had also prepared, subsequent to his primary report a number of other
tables notably Table 1786 which was an analysis of the impact of Metroplex
generated traffic on the north-eastern intersection at the “before” roundabout at
the Ipswich/Centenary Interchange.
[154] Table 17 showed in respect of each of the morning and afternoon peak hours
that the average delay was generally doubled and the queue lengths increased by
between 10 and 60%. In each case the intersection degree of saturation rose
from 1.53 and 1.50 to 2.05 and 2.35 respectively.
[155] That document summarised the impact of Metroplex generated traffic on the
north-eastern intersection at the ‘before’ roundabout at the Ipswich/Centenary
Interchange which was based upon the generation rates proposed by Mr Viney
for directional distribution adopted in his evidence-in-chief given on 24
November 2011 and the traffic volumes derived from a 2011 traffic count87.
[156] That Table 1788 showed the nominated traffic generation and the traffic
movements through the critical north-eastern intersection to be 14.3% higher
over the 2007 base volume of 3,129 vehicles per hour.
[157] Mr Beard contended in his Table that that would increase, in the morning peak
hour the intersection degree of saturation 1.53 to 2.05, the east bound queue
from 86 to 91 metres, the south bound queue from 1,765 metres to 2,784 metres
and an average south bound delay from 8.6 minutes to 16.5 minutes.
[158] Similarly for the afternoon peak hour Table 17 demonstrated that there would be
an 11% increase in traffic movements through the critical north-eastern
intersection over the 2007 base volume of 3,537 vehicles per hour.
[159] Mr Beard contended that those figures would increase the intersection degree of
saturation from 1.50 to 2.35, increase the east-bound queue from 56 to 82
metres, increase the southbound queue from 2,176 metres to 3,509 metres and
cause an average southbound delay to increase from 8.1 minutes to 21.0
minutes.
[160] When those figures were put to Mr Viney he conceded that the approach taken
by Mr Beard in producing that document was a valid approach89.
[161] In essence Mr Viney accepted the validity of the calculations done by Mr Beard
to produce his Table 17 and further accepted that if they came to fruition they
86 Exhibit 49.
87 Exhibit 48.
88 Exhibit 49.
89 T3-33 L 48.
-- 32 of 71 --
33
would constitute significant increases but Mr Viney’s position was that those
increases would not necessarily occur.
[162] The following appears in the cross-examination of Mr Viney90
“So do you accept that those increases in the degree in saturation in the
queue lengths and in the delay are significant increases?-- I accept that
they would be significant increases, but I - I would say that they
wouldn't necessarily occur.
And is this what you wanted to add-----?-- Yes.
-----earlier? And why do you say they wouldn't necessarily
occur?-- Because once you get a saturated intersection - and Mr Beard's
figures show that even before Metroplex is applied in the before case,
the intersection is - is way over saturation with long queues. The - the
normality is that once you get to a certain point, no matter how much
extra traffic you think you're going to put onto that intersection, it
doesn't increase that much because people find alternative
arrangements. They either come earlier, or - it's called peak spreading.
Either - like, most tradesmen will refuse to travel at peak hours, they -
they arrive at your doorstep if you're going to do some work at your
place at 6 o'clock or 7 o'clock, and they leave at - before 3 o'clock
because they wish - wish to meet - to avoid the peak, so there's - the
peak spreading would come into effect. There would be avoidance
techniques, people would avoid the intersection. So although what Mr
Beard has done is technically correct, that you would get a much longer
queue length, in practice, I don't think it would happen because of peak
spreading and avoidance techniques. And really, what the department
has done with building a systems interchange here, has - has forced
those impacts on Metroplex generation. Instead of being able to go
through the interchange, you - you would probably find some other
way of getting there. That - that's why, in their - in their approval, the
concurrence agency's response, they ordered upgradings for other
intersections because they realised that they would be pushing traffic
through other intersections or interchanges.”
[163] Notwithstanding the contentions of Mr Viney with respect to the peak spreading
and avoidance behaviour by people seeking to avoid congestion it remains clear
that the development of the Metroplex site both in the before and after situation
would have significant impact on traffic in the adjacent road system.
[164] Prior to any cross-examination about Mr Beard’s Table 17 Mr Viney had been
cross-examined about the contents of Mr Beard’s Table 15a91.
[165] It was put to Mr Viney in the context of Table 15a that:
“So, the first step I want to emphasis is that it's 000 for degree of
saturation delay and queue length at the Centenary-Ipswich Motorway
interchange in the current situation?”
To which Mr Viney responded:
“Yes. Can I just make that one other point, you're talking only about a
- a peak hour. If you look at any other time during the day there is no
delay at that interchange on any approach. And we're talking about - if
you're talking about Metroplex you're talking about a - a place where
the commerce of the industrial development takes place during the day,
not at peak hour. So the peak hour delay is placed on the people that
90 T3-35 L 32 T3-36 L9.
91 Exhibit 37 page 6.
-- 33 of 71 --
34
work there. For the trucks that are bringing goods and so forth to the
site they don't have this delay. So it is a peak hour problem.”92
[166] That passage seems to demonstrate that the project for which the land was taken
had some significant positive impacts upon the congestion which existed prior
to those road works being carried out. However, the analysis of both traffic
engineers supports the contention that serious degrees of peak hour congestion
still remain compared to the significant queue lengths and delay times prior to
the project.
[167] I am of the view that the analysis and contentions advanced by Mr Beard should
be preferred over those of Mr Viney.
[168] I do however accept the opinions expressed by Mr Viney that achieving access
to the subject site may now be somewhat more circuitous than it was previously.
That is, in my view, not an unusual circumstance in areas developed for
industrial estates which necessarily involve, from time to time high levels of
heavy vehicular traffic.
[169] Mr Viney in Appendix 6 to his 9 August Joint Traffic Report develops a Table 1
which sets out the changes in site accessibility between the before and after
cases93.
92 T3-28 L 48 T3-29 LL1-2.
93 Exhibit 21 Appendix 6 Table 1.
-- 34 of 71 --
35
[170] Counsel for the Respondent contends that that Table, with which Mr Beard
agreed94, demonstrates that access between the subject land and the main arterial
routes being the Ipswich Motorway and the Centenary Highway is significantly
less convenient in the after case compared to the before case.
[171] The Joint Traffic Report of the traffic engineers of 20 September 2011 was
prepared at a time prior to the Respondent conceding that the loss of the
Centenary Highway ramps was a consequence of the project for which the land
was resumed.
[172] In that report the traffic engineers agreed as follows:
“5. Impact on Accessibility of the Subject Site of the Removal of
the Centenary Highway Ramps
It was agreed that a significant proportion of total vehicle trips generated by
development of the subject site would utilise the Centenary Highway ramps
(northbound on-ramp from Bakery Road and southbound off-ramp to
Kelliher Road) if they were in place. Further it was agreed that more
generated traffic would utilise the interchange between Progress Road and
the Ipswich Motorway if the ramps were not in place.”95
[173] While they agreed in the terms set out above there was a considerable difference
of view between the traffic engineers as to the consequence of the loss of the
ramps.
94 T3-70 LL28-32.
95 Exhibit 22 page 5.
-- 35 of 71 --
36
[174] As set out in the 20 September report (which it might be noted was not signed
off on until 28 September 2011) their views were articulated as follows:
[175] As indicated elsewhere in this decision in September 2006 an application was
made over the subject land for a preliminary approval to override a planning
scheme.
[176] The initial application in September 2006 was amended on at least two
occasions. The traffic documents from Planning and Environment Court
proceedings relevant to that application for a preliminary approval were
tendered before the Court. Contained within those documents is a Traffic
Engineering Report prepared by Colin Beard who gave evidence in these
proceedings.
[177] Mr Beard's report contains a description of each of the forms of application for
preliminary approval.96 The first form of development proposal had the
following characteristics:
96 Exhibit 47 Document 7 page 3.
-- 36 of 71 --
37
(a) Industrial Development 250,000 m²
(b) Commercial/Office Development 160,000 m²
(c) Large Format Retail Centre 90,000 m²
Total 500,000 m²
[178] Mr Viney produced a Traffic Impact Assessment Report in respect of that first
proposal and calculated the following peak hour traffic generations:
(a) AM Peak Hour Traffic Generations 4,599 vehicles per hour
(b) PM Peak Hour Traffic Generations 6,219 vehicles per hour
[179] Apparently the initial application resulted in an Information Request being made
by the Department of Main Roads and as a consequence the application was
amended.
[180] The characteristics of the second form of the proposal were as follows:
(a) Industrial Development 386,000 m²
(b) Commercial/Office Development 98,000 m²
(c) ETRO Precinct (Centre Activities) 6,000 m²
Total 490,000 m²
(a) AM Peak Hour Traffic Generations 3,946 vehicles per hour
(b) PM Peak Hour Traffic Generations 3,946 vehicles per hour
[181] Those figures emerged from a Transport Report in response to the Information
Request dated 11 April 2007.97
[182] The proposal was further amended in April 2008 with the following
characteristics:
(a) Industrial Development 337,259 m²
(b) Commercial/Office Development 98,000 m²
(c) ETRO Precinct (Centre Activities) 6,000 m²
Total 441,259 m²
(a) AM Peak Hour Traffic Generations 3,551 vehicles per hour
(b) PM Peak Hour Traffic Generations 3,551 vehicles per hour98
[183] The Department of Main Roads was a referral agency and on 11 July 2007 they
provided a referral agency response setting out the conditions of approval
mandated by the Department of Main Roads as a concurrent agency.99 Included
in the various conditions imposed on that preliminary approval were the
following:
97 Exhibit 47 Document 2 page 3.
98 Exhibit 47 Document 7 page 3.
99 Exhibit 7.
-- 37 of 71 --
38
-- 38 of 71 --
39
"
[184] The parties agree that one of the issues for determination is for the Court to
decide what would be the nature amount of any transport infrastructure or
contribution or other condition likely to be imposed by the Department of
-- 39 of 71 --
40
Transport and Main Roads and likely to be taken into account by a hypothetical
vendor or purchaser in each of the before case and the after case.
[185] In addition to the total of $30,000,000 sought by way of contributions set out
above the referral agency the response also contained other conditions.
[186] Senior counsel for the Applicant in his submissions to the Court aptly
summarised those other conditions as follows:
(a) The land proposed to be resumed to be excluded from the proposed
development (condition 8(i));
(b) For further development applications a traffic engineering assessment
demonstrating the traffic generated by the proposed use or
reconfiguration applied for can be accommodated by existing capacity
in the road network (condition 13(i) and (ii)); and
(c) Construction of the missing link at Boundary Road to a minimum two
lane two-way pavement and dedication of land to accommodate an
ultimate six lane cross section (condition 1).
[187] Mr Beard in his Report to the Court100 made the following observations:
"The 2007 DTMR Concurrence Agency Response is claimed to be of
importance in this matter. The design weekday PM peak traffic
generations of the development proposed at the time of that response
were 5,434 vehicles per hour. The now claimed 'before' development
scenario would have designed Traffic Generations calculated on the
same basis of 2,550 vehicles per hour and those of the 'after'
development scenario calculated on the same basis would be only 2,335
vehicles per hour.
That is, the design traffic generations of the development scenarios now
advanced are less than half those of the development proposed at the
time of the 2007 Concurrent Agency Response. Naturally, a
substantially different Concurrent Agency Response would be expected
to a development proposal with these substantially lower design traffic
generations."
[188] In the Joint Report of 9 August 2011 (prepared before the concession by the
Respondent that removal of the ramps was a consequence of the Project for
which resumption had taken place), the Traffic Engineers gave consideration to
Principal 3 of the Guidelines for Assessment of Road Impacts of Development
(GARID) published by the Department of Main Roads in March 2006.101 That
principal provides as follows:
"In general, Main Roads considers a development's road impacts to be
insignificant if the development generates an increase in traffic on
SCRs of no more than 5% of existing levels. (Traffic is measured by
either AADT or ESAs, terms which are defined in Appendix A.)
However, there may be circumstances where an increase in traffic of
less than five per cent might have significant road impacts (e.g. a road
100 Exhibit 25 page 4.
101 Exhibit 50 Chapter 1 – page 5.
-- 40 of 71 --
41
with low levels of ESAs, traffic growth or poor safety record). In other
cases, an increase in traffic of more than five per cent might be possible
without having a significant impact. Main Roads can advise the
development proponent whether their proposals cold have a significant
impact on the affected road and requires an RIA.
The significance of a development's road impacts depends on the
functional hierarchy of the roads involved. For example, planning for
AusLink National Roads (formerly National Highways) takes into
account their important role in freight transport and long distance travel
and therefore assumes traffic will grow (significantly on some road
sections). In contrast, local district roads may possibly experience little
or no traffic growth. Consequently, AusLink National Roads and state
strategic roads are expected to cope with greater increases in AADT
and ESAs, except in extraordinary circumstances."102
[189] Having regard to the Principal 3 from the GARID document and Mr Beard's
analysis which became Exhibit 49 the following was put to Mr Viney:
"The exercise carried out by Mr Beard in Exhibit 49 involving only
those two movements that, in effect, the south-bound flow and the east-
bound flow for this particular intersection, given the configuration of
the intersection, and the volumes involved is an entirely legitimate
traffic engineering exercise?"103
[190] Mr Viney responded:
"I think you're right that the department would do that exercise, it
would say that you must look at the impact on this interchange of your
proposal, and if I was responding to the department saying 'Yes, you
know, the right to ask us to look at the impact in that intersection or
that interchange', then I would look at the benefits involved in putting
Boundary Road through, and I would say that if Boundary Road was
constructed through, then the volumes going through the Centenary
Highway, Ipswich Motorway interchange would drop, and the only
impact on that interchange would be less, because that's the result that
we found with the recent modelling."104
[191] Some controversy arose with respect to Mr Beard's final report for the appeal in
the context of matters that were set out in what has come to be referred to as the
"September 2011 Joint Report"105 and the "Third Joint Report" which was
compiled with the valuers.106
[192] At page 2 of the "September 2001 Report" Mr Beard made reference to:
"Approval of the staged development spread over (say) 10 years could
probably be negotiated subject to construction of Boundary Road
sooner rather than later, and works at the Progress/Ipswich Interchange
of $2.0 to $3.0 million."
[193] In his opening Mr Hinson of Senior Counsel took the Court to the Third Joint
Report (Traffic Engineers and Valuers) and to the second paragraph on page 2
of that Report107.
[194] At page 2 the following appears:
102 Chapter 1-p5.
103 T3-38 LL 1-10.
104 T3-38 LL 12-28.
105 Exhibit 22.
106 Exhibit 23.
107 Exhibit 23 page 2.
-- 41 of 71 --
42
"This further Joint Report is in part dependent on understanding and
adopting the contents of the recently received second joint traffic
engineers report. This Joint Report was prepared on Thursday 20
October 2011 and addresses the construction of Boundary Road and the
Boundary Road bridge as part of the 'before' development scenario."
[195] Mr Hinson then took the Court's attention to page 3 of the Report and the
absence of any reference to works at the Centenary/Ipswich Motorway
Interchange.
[196] Mr Hinson asserted that the contents of the Third Joint Report constituted an
abandonment of any reliance upon requirement to perform works at Progress
Road Ipswich Interchange and at the Centenary/Ipswich Interchange.
[197] Mr Hinson was clearly working towards the proposition that had been advanced
in earlier Orders made by this Court that save with the leave of the Court parties
would be precluded from adducing evidence inconsistent with agreements set
out in Joint Reports of Experts.
[198] In cross-examination by Mr Gore of Queens Counsel Mr Viney appeared to
accept that Mr Beard had not resiled from his view that the 'before' case could
be viewed as premature and that he had abandoned any assertion about
contribution of 3 to 5 million dollars for Progress Road Upgrading.
[199] Mr Viney conceded that the only matter discussed in the context of the
preparation of the Third Joint Report was the works on Boundary Road.108 He
also acknowledged that Mr Beard had not in any sense stated that he had
abandoned his view with respect to the $2 or $3 million contributions.109
[200] In the context of the formulation of the Third Report110 Mr Beard said the
following in response to the query:
"… Now what his Honour is interested in, amongst other things, is
whether in that joint report you have departed - sorry, in your appeal
report you have departed from anything in that joint report?"111
[201] Mr Beard replied
"Well, in my mind I haven't, but I happily concede that the third joint
report, which was put together in the context of the mediation, probably
didn't explain the context in which those discussions were held,
anything like satisfactorily, because it's pretty clear that the parties to it
now have different views of what the context of those discussions were.
To my mind, what we were discussing arose out of a specific question
that - that the mediator put to us, and it really related to the question of
- of prematurity, and particular in the situation of - we were talking
about the myth of - of the before situation where you effectively have
to pretend that the project isn't happening, has never even been thought
of, just put it completely out of your mind, and we talked about what
was closer to the reality being - well, obviously the existing situation is
heavily overloaded, we have to do something about it, there's a demand
108 T3-45 LL1-15.
109 T3-45 L25.
110 Exhibit 23.
111 T3-66 LL47-50.
-- 42 of 71 --
43
for an upgrading that's been recognised, we haven't actually done the
planning yet, we don't know when we're going to build anything, but
we recognise that we're going to have to do something about that
interchange. So it was - it was a discussion about how we deal with the
- this sort of a myth of this before, because as we've seen, the planning
for that interchange upgrade started in 1998, a long time before the
resumption occurred, 10 years before. Every decision that's been made
by Cidneo in this matter, since they first bought the site, has been in the
basis of the upgrading would occur. So when we discussed this
specific issue, it was simply arising out of a - a comment that I'd made
in either the first or the second joint report that in the before situation
you would have the added cost penalty of being required to construct
Boundary Road soon rather than later. And this joint report was really
to discuss that specific issue. And as you can see from the reporting of
it, what we concluded was that, yes, you would have to build it sooner
in the before situation than you would in the after, but, in fact, the
community benefits that Mr Viney's been talking about, associated with
that upgrading, was such that the department would probably meet, in
effect, the bring forward costs. So that's why the valuers were involved
in the discussion. As they described it, that issue became cost neutral,
which was the question that we were sent away to answer. Was there a
cost impost associated with building Boundary Road sooner than later.
Now, as Mr Viney said, we simply didn't discuss the upgrading of
either the Progress Road interchange, or Centenary/Ipswich
Interchange, or anything else. The only thing we discussed was the
timing of the construction of Boundary Road. And that's all that's
documented in that report."112
[202] It is not unusual for two highly qualified and experienced experts in the same
area to come to opposing views about the outcome of development in an area
where prior to that development there were already extant traffic problems.
[203] That is a situation here.
[204] I accept the proposition advanced by Mr Beard that his approach to the
formulation of the Third Joint Report was one of focus only on the Boundary
Road link and that he had not abandoned his other views. In any event, were it
necessary having regard to the considerable period of time for which the
Applicant had been in possession of Mr Beard's final Report, I would have
granted leave to the Respondent to adduce the additional evidence.
[205] The propositions advanced by Counsel for the Respondent in submissions
regarding Mr Beard's approach is, in my view, persuasive.
[206] Those submissions said as follows:
"27. Mr Beard has consistently expressed views to the effect that:
(a) the Cidneo property would have been reasonably perceived to
be in an area where the major road network was congested,
potentially making the development approval of major traffic
generating uses on that property difficult;
(b) no traffic engineer could submit a traffic impact assessment
report which would conventionally demonstrate that a major
traffic generating use could be approved without having
unacceptable impacts on the adjacent road network."113
112 T3-66 L52 to T3-67 L41.
113 Para 204 Ref #15 – see e.g. ex. 21 p.13; ex.22 pp.2, 5-6; ex.25 pp.6-7, p.10; ex.47 tab 5 pp.1-
2.
-- 43 of 71 --
44
[207] I have also taken into consideration the purchase price of $50,390,655 for the
total area of 101.36 Ha in May 2005 and the subsequent valuation as at the date
of resumption in the 'before' context of $60,000,000.
[208] A hypothetical purchaser would have been, had it bothered to take proper and
sound traffic engineering advice, equipped with advice from its traffic engineer
(for example Mr Viney) that in that traffic engineers opinion there was no
proper basis for the Respondent to demand any contribution to external road
works beyond the Boundary Road road works. In that circumstance I think it
unlikely that any prudent purchaser would have paid $60,000,000 for the land
burdened by a contingency of paying $30,000,000 by way of road works
contribution to the Respondent.
[209] With respect to the likelihood of a contribution being required in the 'before' or
in the 'after' scenarios Mr Viney has consistently expressed the view that a
request from the Respondent for any contribution for external road works save
for the Boundary Road connection would be unreasonable but he also
recognises that, given the conduct of the Respondent in its response to the
preliminary approval application where in it sought a contribution of $30
million, it is likely to seek some contribution.
[210] On a proportional basis Mr Viney calculates that to be a minimum figure of
$16.55 million.114
[211] Similarly, Mr Viney expresses the view that no contribution should be sought in
the 'after' case either he says:
"In my opinion, no monetary contribution should have been sought by
the Respondent (above and beyond the completion of Boundary Road)
in either the 'before' or 'after' case."115
[212] Mr Beard in his report116 takes what he describes as a pragmatic approach.
[213] He said referring to the background circumstances:
"In those circumstances, a potential developer of the 'before'
development scenario would need to enter into what would essentially
be negotiations with DTMR on a pragmatic basis rather than a technical
traffic engineering basis, although the traffic engineers would probably
remain involved in the negotiations. This is essentially what actually
occurred in similar circumstances in respect of consideration of the
impact of what was effectively the 'after' development proposal on the
Ipswich/Progress interchange.
That was the scenario which was raised in the preceding mediation and
addressed in the joint report of the traffic engineers and valuers dated
20th October 2011. Effectively, this scenario was based on the
proposition that DTMR knew that the existing network was over-
loaded, it had preliminary plans to complete the necessary upgradings,
114 Exhibit 24 page 9.
115 Exhibit 24 page 11.
116 Exhibit 25 page 7 and 8.
-- 44 of 71 --
45
but nothing was committed. It is my understanding that this not
consistent with legal advice that 'the project' must be completely
ignored in the 'before' development scenario, but it was a fiction
adopted to allow a more realistic assessment of what would have
happened in 2007/08 in that hypothetical circumstance."117
[214] Given Mr Beard's favourable inclination towards negotiating an infrastructure
agreement it is appropriate to consider what would probably have been
included. He says in his Report that the infrastructure agreement will probably
have included the following:
" ● Details of development staging;
● Details of external roadworks staging'
● Early construction of the Boundary Road link, as a two-way
two-lane road except where it needed to be wider to
accommodate development access intersections. This work
would have reduced traffic loadings on the adjacent four-lane
Ipswich Motorway;
● Works at the Centenary/Ipswich interchange – probably the
construction of an additional southbound lane on the northern
approach to the roundabout, to function as a roundabout bypass
lane. It is possible that upgrading of the Kelliher Road off-ramp
and the Bakery Road on-ramp would also have been required;
● Works at the Progress/Ipswich interchange, of the same basic
type, but of lesser magnitude, as those being negotiated at this
interchange in respect of the 'after' development scenario. As set
out in Table 13 attached, traffic generations of the 'before'
development scenario through this interchange would have been
approximately 62.5 percent of the generations of the 'after'
development scenario, including the traffic diversions associated
with the closure of the Centenary Highway ramps. Therefore, if
works of $3.0 to $5.0 million were required for the 'after'
development scenario, then works for a lesser amount
(approximately 62.5 percent, or $1.875 to $3.125 million) could
reasonably be anticipated for the 'before' development
scenario."118
[215] Mr Beard asserts
"There is no traffic engineering reason to expect that the total cost of
works required at the Ipswich Motorway interchanges for the 'before'
development scenario would be lower than those for the 'after'
development scenario which would have lower design traffic
generations."119
[216] On being pressed under cross-examination by Mr Gore, Mr Viney's evidence
was that he disagreed with the proposition advanced by Mr Beard in the Second
Joint Report of September 2011 that there should be some contribution in the
'before' case for the Upgrading of the Progress Road Interchange.
[217] Mr Viney's position, he summarised this way.120
"I do have a disagreement with that because the work that's been done
with Bitzios Consulting recently indicates that if Boundary Road is
constructed through, as is the premise for all - I'm saying about any
approval for this site Boundary Road will be constructed through and
the bridge constructed. But that Boundary Road will attract a lot of
117 Exhibit 25 Beard Traffic Engineering Pty Ltd page 7.
118 Exhibit 25 Beard Traffic Engineering Pty Ltd page 8.
119 Exhibit 25 page 8.
120 T3-50 LL20-35.
-- 45 of 71 --
46
traffic from the surrounding area. It will reduce the traffic on Ipswich
Motorway. It will reduce the traffic on Centenary Highway and it will
reduce the traffic on some of those critical elements of the Progress
Road interchange. So, you've got to take that into the context of
building Boundary Road. So, I do not accept Mr Beard's assertion that
we must contribute to that upgrading."
[218] Although, Mr Viney did acknowledge that he could see that Mr Beard could
adopt the position he did even though he disagreed with it.
[219] Mr Gore sought to summarise the position between Mr Beard and Mr Viney in
this way.
"So, accepting his evidence about that, just for the purposes of my
questions, do you agree that the two of you as traffic engineers have
this in common, that the two of you do not see any difference between
the before and after cases from a traffic engineering perspective, albeit
that there is some difference between you about the steps that you go
through to get to that point? By that I mean this, that you say that in
both the before and after case the contribution should be the same,
namely the upgrading of Boundary Road in the manner that you've
described."
[220] Mr Viney agreed with that proposition.
[221] Mr Gore continued:
"Mr Beard says that in the before and after case that should occur plus,
in the before case, there should be a contribution to two intersections,
Centenary and Progress interchanges and in the after case a
contribution to one intersection, Progress, in an amount that, in the after
case, would be roughly equivalent to the total amount in the before case
given the change from 20 per cent to 35 per cent of the generated trips
using the Progress Road after change. Now, I'm sorry it's such a long-
winded question?-- No, I understand your question. I - I agree with
your question. I'd just like to add that there is a rider to all that that you
haven't mentioned and that is the $30 million. So, I agree with the
premise that that's - that's where we are, but we have a disagreement
about the $30 million."121
[222] Mr Beard summarised his position quite clearly in his evidence-in-chief when
he said:
"… Scenarios in this case that have true financial implications?-- I
think in terms of traffic engineering issues, I don't think there's a
significant difference in terms of the contributions. Now, Mr Viney, as
he said, he believes that it's zero, apart from Boundary Road, in the
before and after. My personal view is that that's unrealistic. I think
that given the magnitude of the development we're talking about, you
would have been required to make some contributions. In my view
they would have been roughly equal in the before and after. So, in
terms of impact on value of the property, both of our positions as traffic
engineers are essentially identical. There's no difference between the
before and after in terms of traffic engineering issues. There are still
minor issues associated with, in the after, you could argue that the local
accessibility, or the - it's not so much local access, it's access to the
regional road network direct from the subject site. It is less direct than
it was with the ramps to and from the Centenary Highway. I accept
that it was, and I believe that the valuers have taken some account of
that. But that's not really a traffic engineering issue, that's a valuation
exercise. In terms of the traffic engineering issues and the
121 T3-51 LL1-18.
-- 46 of 71 --
47
contributions that would you be required to make, really there's nothing
between Mr Viney and I at the end of the day.122
[223] And then in response to questioning from myself the following is recorded123:
"HIS HONOUR: So - can I just interrupt, Mr Gore, just so that I
understand. Mr Beard, you're saying that before resumption, the
develop of this site required Progress Road, Ipswich Road, Centenary
Highway/Ipswich Road, intersection upgrades, you needed the
completion of Boundary Road. The extra traffic that might have been
generated, consequent upon development of the resumed land, was
inconsequential in terms of traffic impacts compared to the impacts of
the development of the residual land?-- The - the-----
Is that right or wrong?-- That's pretty right, your Honour. It's - there's
only eight per cent difference in the design traffic generations between
the before and after scenarios. So in terms of the - the order of - of
accuracy that Mr Viney and I are talking about, that's the same
basically, an eight per cent difference in - in that traffic generation
overall would not be seen as a significant impact. So I - and again, I
believe that's taken in account of in respect of the valuations in that
they have looked at the total costs, in effect, being spread over a
smaller development component in the after, and I'm not for an instance
suggesting that's not legitimate, what I'm saying is that the total
contribution levels that they would have had to make, despite the after
being eight per cent less traffic, I believe they would have been making
roughly similar contributions."
[224] An issue arises with respect to the use that might be made of the knowledge
placed before the Court in an affidavit of Mr McGregor that in the recent past
the Respondent and the Applicant have been able to resolve the conditions of
approval on two applications made in respect of the subject land which were
made in respect of the western part of the site on 17 December 2009 and in
respect of the eastern part of the site in February 2010124.
[225] In each case the Department of Transport and Main Roads imposed a condition
requiring a contribution to the upgrade of the Progress Road Interchange with
the Ipswich Motorway based on traffic generated by the development and a
preliminary cost for the initial stage of the Interchange Upgrade. That
contribution was in the sum of $13.7 million.125
[226] Ultimately those approvals went to the Planning and Environment Court and
shortly before one of the matters was scheduled to begin a Hearing (7 December
2011)126 the parties agreed on an Amended Condition which required the
Applicant to complete works on the Progress Road and Ipswich Motorway
outbound off-ramp and Progress Road approach in accordance with a specified
set of drawings.127
122 T3-70 LL 12-36
123 T3-70 L38 to T3-71 L3.
124 Affidavit of Peter Robert McGregor (Exhibit 72) at paragraphs 28 and 93.
125 Affidavit of Peter Robert McGregor at paragraphs 77, 78, 126 and 127.
126 Affidavit of Peter Robert McGregor at paragraph 153.
127 Affidavit of Peter Robert McGregor at paragraph 158.
-- 47 of 71 --
48
[227] Those works as set out under the heading "Engineering Issues" earlier in this
decision have been costed and agreed between the parties in the sum of
$1,087,110.76.
[228] The question then arises as to what use, if any, the Court is entitled to make of
that information which is sought by the Respondent, to be relied upon to
confirm an earlier foresight.
[229] The Applicant in its submissions says the Court is not entitled to apply weight
to that knowledge to confirm any foresights and in doing so quite properly draw
the Court's attention to the Spencer test of the determination of market value.128
[230] The Respondent points in particular to the dicta of Isaacs J which is recited
earlier in this decision.129
[231] The Respondent also points to the observations of Sugerman J in Tooheys
Limited v Housing Commission of New South Wales where His Honour said130
"As I have pointed out more than once, there is no general rule entitling
the Court to have regard to events which have happened after the
relevant date and before hearing. The concept which is sometimes
expressed in the phrase 'that facts when they are available, should be
preferred to prophecy, it is not universally applicable. The question is
one of relevance to the issue in each set of circumstances which arises."
[232] The Respondent also points to the observations of Fryberg J in a Queensland
Court of Appeal decision in which it was confirmed that events subsequent to
the date of resumption cannot be taken into account in assessing market
value.131
[233] In the Mio Art decision Fryberg J (with whom McMurdo P and Fraser JA
agreed) observed:
"The Spencer test postulates hypothetical parties in full possession of
knowledge generally available on the date of acquisition. That
knowledge includes knowledge of future possibilities, but only as
possibilities, and with the weight which prudent persons would ascribe
to them. It is difficult to imagine how the fact that a possibility
subsequently became a reality could be directly relevant to that
knowledge.
I see no inconsistency between this approach and that which enables
subsequent sales to be taken into account in assessing market price.
Those sales are not taken into account as matters which would be
present in the minds of the hypothetical parties. They are simply
evidence of an event from which an inference can be drawn about the
position at an earlier (but not very much earlier) time. The implicit
assumption is that nothing material has changed in the meantime or that
if it has, allowance can be made for the change. Consequently they are
probative of the earlier position. There will probably be other cases in
which inferences about the position on the date of acquisition might
logically be drawn from subsequent events. For example, suppose in
128 Spencer v Commonwealth (1907) 5 CLR 418.
129 See [32].
130 Tooheys Limited v Housing Commission of New South Wales (1952) 20 LGR (NSW) 236 at
240.
131 Brisbane City Council v Mio Art Pty Ltd (2011) 183 LGERA 352.
-- 48 of 71 --
49
circumstances similar to those in this case an acquiring authority denied
that a change in building heights was under consideration at the date of
acquisition. Publication of a document which would have taken six
months to prepare on that topic only three months after the date of
acquisition might tend to prove the falsity of the denial; it might
support an inference that the topic was under consideration. But it
would still be necessary to prove what would have been known by the
hypothetical vendor and purchaser."132
[234] In the present case the knowledge of the actual cost of compliance with the
condition imposed by the Respondent came more than 3.5 years after the date of
resumption.
[235] In the light of the observations of Fryberg J set out above and the cases referred
to both by the Applicant and by Fryberg J in coming to his decision I have
formed the view that I, as a matter of law, am not entitled to take into account
the knowledge of the exact contribution ultimately accepted by the Respondent
in resolving the appeals involving the two sites which constitute the subject site.
[236] I should hasten to add that there are numerous authorities which entitle me to
take into account events which occur after the date of resumption when trying to
ascertain what might be the injurious affection damage visited on a dispossessed
landholder by the project for which that landholder's property was resumed.
[237] Counsel for the Respondent points out in their submissions133:
"Cidneo's case, as revealed through the 2011 valuations of Mr
Hamilton, assumes that there are significant differences between the
before and after case scenarios with respect to external roadworks.
However, from a traffic engineering perspective, that assumption is not
supported by either Mr Viney or Mr Beard."
[238] The Respondent's submissions then go on to summarise, I think in a fair way,
the common ground between the two traffic engineers. The submissions say:
"37. It was common ground between the 2 traffic engineers that there
was no difference between the before and after cases from a traffic
engineering perspective, even though there was some difference
between them about what was common to both the before and after
cases.134 It was common ground that the construction of the
Boundary Road link (including the bridge over Bullockhead
Creek) was required in both the before and after scenarios. The
basic point of difference between the 2 engineers was that, in Mr
Viney's view, that was all that was required whereas, in Mr Beard's
view, more was required in both cases (in the before case, a
contribution to 2 intersections – Centenary /Ipswich &
Progress/Ipswich – and, in the after case, a contribution only to the
Progress/Ipswich interchange, but at a higher amount; in simple
terms, but realistically practical terms, Mr Beard viewed the
differences between the before and after cases as cancelling out).
38. This is an important area of common ground between the 2 traffic
engineers. It is one of several indicators that Cidneo's reliance
132 Mio Art Pty Ltd paragraphs 78 and 79.
133 Outline of Submissions of the Respondent page 11 para 36.
134 Viney T3-50 line 45 to T3-51 line 15; Beard T3-70 line 10 to T3-71 line 5.
-- 49 of 71 --
50
upon the $30M contribution in the 2007 Concurrence Agency
Response ('CAR') is flawed."135
[239] On the question of how I should approach the issue of what if any monetary
contribution may have been sought by the Respondent in response to any
application of development of subject land the Respondent draws the Court's
attention to a decision of Member Scott in Townsville City Council v
Department of Main Roads136.
[240] That was a case which dealt with a question of enhancement of the residual land
in the unusual circumstances where in the before case a developer would have
been required to contribute towards the cost of a bridge but no such contribution
was likely to be sought in the after case.
[241] In the course of that decision137 Member Scott says:
"[73] … There needs to be an argument based on the evidence
that the material circumstances would have been seen by
a hypothetical prudent purchaser as so similar in each
scenario that the Chief Executive would not be expected
to require a contribution in the before, given that he had
not in the after. The only similarity adverted to by the
claimant is that there is a bridge as part of the Douglas
Arterial in the after and a suggested developer bridge in
the before. I cannot, based on those facts alone,
appreciate an argument that confidently suggests the view
that a hypothetical prudent purchaser would take."
[242] Later in the decision the His Honour said:
"… I think that a purchaser in 1994 would ascertain as best he could
what the prospect would be for DMR requiring a contribution for the
developer bridge on the assumption that the development would have a
significant adverse impact on a State-controlled road. In ascertaining
that prospect he would look to the marketplace for examples and he
would seek to know what, if any, policy was employed by DMR in
considering the application of s.40."138
[243] The only truly objective evidence of the likelihood of a contribution is the
matter of the $30 million condition imposed on the preliminary approval
application for a similar but larger development.
[244] Both Mr Viney and Mr Beard agreed from a traffic engineering perspective that
no contribution should have been sought by the Respondent either in either the
'before' or the 'after' case.
[245] As Counsel for the Respondent has submitted it was common ground between
the two traffic engineers that there was no difference between the 'before' and
135 Outline of Submissions of the Respondent page 11 paras 37 and 38.
136 Townsville City Council v Department of Main Roads [2003] 24 QLCR 241.
137 Townsville City Council v Department of Main Roads [2003] 24 QLCR 242 page 255 para
[73].
138 Section 40 of the Transport Infrastructure Act 1991 came into effect on 7 March 1994 and
deals with the impact of certain local government decisions on State-controlled roads and
obliged the local government to obtain the Chief Executive's written approval in some
circumstances which approval may have required the carrying out of works or changes on a
State-controlled road.
-- 50 of 71 --
51
'after' case from a traffic engineering perspective, even though there was some
difference between them about what was common to both the 'before' and 'after'
cases. It was common ground that the construction of the Boundary Road link
including the bridge of Bullockhead Creek was required both in the 'before' and
'after' scenarios.
[246] The Respondent goes on to point out that the basic point of difference between
the two engineers was that, in Mr Viney's view, the construction of the
Boundary Road link was all that was required whereas in Mr Beard's opinion in
the 'before' case the contribution to both the Centenary and Ipswich and
Progress Road and Ipswich intersections and in the 'after' case the contribution
only to the Progress Road Ipswich Road interchange but at a higher amount.
[247] Mr Viney's analysis of the circumstances surrounding the $30 million
contribution demand led him to the view that the Applicant should not be liable
for any part of the $30 million contribution made up by the five elements
comprising the $30 million which were contributions for:
1. Progress Road Ipswich Road Motorway Interchange $12,000,000
2. Boundary Logan Interchange $12,000,000
3. Acanthus Street $3,000,000
4. Cycling Infrastructure $2,000,000
5. Intelligent Transport System $1,000,000
[248] Under cross-examination in response to the following question:
"And it's a fact, is it not, that you have taken the view up until today,
without change, that Cidneo should not be responsible for a single
dollar of monetary contribution towards any road works, be it the
development application, the subject of the Planning and Environment
Court proceedings that were heard by Judge Rackemann, albeit the
subject of the development application, the subject of the proceedings
to be heard next month. You have consistently taken the view and
advised the world at large - not just your client but the world at large
that Cidneo should not be responsible for a single dollar, correct?"139
[249] To which Mr Viney answered:
"Mr Gore, can I say, 'Correct', but can I just add that that was - that
correctness was subject to my client building Boundary Road."140
[250] Cross-examination in that vein continued in the following way:
"And your client has consistently taken the position to the world at
large - I'm talking about anything confidential - but to the world at
large its position has been exactly the same as yours, that it should not
pay a single dollar to any of the Department's upgradings subject to the
Boundary Road upgrading?-- Yes.
And you're aware that its position in this Court that it should
nevertheless be compensated to an amount of about $20 million on a
139 T3-20 LL21-31.
140 T3-20 LL32-33.
-- 51 of 71 --
52
different hypothesis, on the hypothesis that a prudent purchaser would
have to factor in about $20 million in the after case. You're aware of
that?-- I'm aware of that."141
[251] With respect to the $1 million sought for the Intelligence Transport System
which is a monitoring system Mr Viney acknowledged that:
"It's got nothing to do with the development as far as I can see."142
[252] That concession was reinforced when Mr Gore asked Mr Viney
"And it would be your strongly held professional opinion that this
Intelligent Transport System condition had virtually no prospects of
being upheld by the Department. That would be your personally
strongly held professional opinion?"143
[253] Mr Viney answered:
"Yes."
[254] With respect to the design and construction of the Cycling Infrastructure within
the Ipswich Motorway corridor between the Centenary Highway and the
Progress Road interchange Mr Gore put to Mr Viney:
"And it would be your professional opinion that the provision of such
infrastructure did not have a sufficient nexus with the proposal, as to
justify the imposition of the condition?
[255] Mr Viney confirmed that it was his view that that condition was
unsupportable.144
[256] With respect what was described as the 'Acanthus Street' roadworks Mr Viney
explained that that claim was required because of the proposal to form a
Systems Interchange at Centenary Highway and the Ipswich Motorway and
therefore generated traffic from the site would be dispersed to other
interchanges. Mr Viney expressed the view that in his opinion that is the
Department's fault for doing that so the Department should pick up the tab for
changing the road network.145
[257] With respect to the contribution of $12 million in respect of the Boundary Road
Logan Motorway Interchange Mr Viney confirmed that in his view that
upgrading or changing was not required because of any development of the
Metroplex site.146
[258] In summary Mr Viney informed Mr Gore that in the context of giving the
theoretical prudent purchaser the benefit of specific experienced views relating
to, for example, the Boundary Road Logan Motorway Interchange his opinion
would be that if the Department persisted in asking for a contribution for such
141 T3-20 LL35-48.
142 T3-22 L32.
143 T3-22 LL41-44"
144 T3-23 L12.
145 T3-23 LL26-32.
146 T3-23 L48.
-- 52 of 71 --
53
works and that contention was challenged the prospects were high that it could
be overturned.
[259] I prefer the approach contended for by Mr Beard who suggests a figure of
$3,000,000 being contemplated by way of contingency to allow for additional
but unsustainable demands being made by the Respondent for external road
works contributions.
[260] With respect to traffic generation and traffic flows there is really, at the end of
the day, not a substantial difference between the two traffic engineers with
respect to the impacts and traffic flow generation. In my view the differences
between flows consequent upon the development may appear to be substantial
but when taken into the context of the total traffic flows in and around the
subject site the differences are inconsequential.
[261] I prefer, however, the approach of Mr Beard to the question of traffic generation
and traffic flows.
[262] I came to the view that he was somewhat less pessimistic and more pragmatic
than Mr Viney.
[263] It is inescapable that there is some increased traffic congestion and conflicts on
some trips but, at the same time, the evidence is inescapable that in other
respects traffic flows to and from the subject site are improved.
[264] My preference for the approach of Mr Beard with respect to the traffic impacts
leads me also to prefer his approach in the context of likely contributions that
might be required apart from the Boundary Road works.
[265] I am unwilling to accept the direct relevance of the $30 million contribution
which was raised back in 2007 in the light of the application later largely
abandoned for preliminary approval for a much larger project with much higher
traffic generation features.
[266] In my view that demand should be regarded as a 'first offer' and somewhat
speculative in the light of an absence of substantial detail about what final form
of the proposed development would have taken.147
10. Valuation Issues
[267] As indicated above at the outset the valuers had agreed upon the 'before'
valuation of the subject property valuing it at $60/m² so that given the area of
the land in the 'before' case at 100.477 Ha the value of the land in the 'before'
case is $60,286,200 which the valuers have generally rounded down to $60
million.
[268] The land taken had an area of 8.385 Ha.
147 See the evidence of Mr Beard at 3-71.
-- 53 of 71 --
54
[269] The application of simple mathematics to that area of 8.385 Ha at $60/m²
produces a figure of $5,031,000 for the land taken.
[270] In his Report148 Mr Brett takes the agreed pre-resumption en-globo value of
$60,877,800 and divides it by the 80.2 Ha of developable area to generate a
figure of $75.90/m² for developable land. Applying that figure of $75.90/m² to
what Mr Brett says is the developable area of the resumed land, its value
unaffected by injurious affection and/or severance impacts is $4,535,000.
(5.973 Ha at $75.90/m²)
[271] The Applicant claims an amount of $25,000,000 plus disturbance and interest
whereas the Respondent contends for a valuation of $6,800,000 plus disturbance
and interest.
[272] It is thus a matter of finding on what basis the value of the land taken should be
elevated from something just in excess of or regarding developable area just
under $5,000,000 as a bare valuation exercise to a figure of somewhere between
$6,800,000 and $25,000,000.
[273] In addition, the other common ground between the valuers was that each of
them adopted as the appropriate valuation methodology a before and after
assessment of market value.
[274] There is a useful discussion of the before and after method in Hyam.149
[275] The learned Author makes the general observation about the extent of judicial
approval which has been given to the approach in several decisions. He says
this:
"This method has received judicial approval in several decisions and its
effect and application were explained by Reynolds JA in Gosford Shire
Council v Green (1980) 48 GLRA 201 at 208:
This question refers to a method of arriving at the amount of
compensation payable under s 124 of the Public Works Act where
part only of the claimant's land is resumed. It has been pointed out
by Walsh J in Parkes Developments Pty Ltd v Burwood Municipal
Council (1969) 17 LGRA 257 at 264 that the whole provision
deals with a single concept of compensation in which the figure
arrived at takes account of damages caused by severance as well as
enhancement and the reference in the question is to a convenient
method of arriving at this sum of compensation and dealing with
both damages for severance and enhancement in value at one
stroke. It is a method which was expounded by Roper J in Realty
Corp Ltd v Commissioner for Main Roads (1940) 14 LGR 204 as
being the easiest and proper way to ascertain the compensation to
be paid. [See also Kerswell v Commissioner for Main Roads
(Court of Appeal, 13 July 1978, unreported)]. If the whole parcel
is valued at the time of resumption and then the residue is valued,
the difference is the ascertained amount of compensation and
severance damage and enhancement of the value of the residue are
comprehended without any necessity for specification.
148 Exhibit 30 page 18.
149 The Law Affecting Valuation of Land in Australia, Alan Hyam, Federation Press 4th Ed. 2009
pages 174 -178.
-- 54 of 71 --
55
It was also applied by Cripps J in Manufacturer's Mutual Insurance.
Ltd v Gosford City Council (1981) 27 The Valuer 214. That case was
concerned with a claim for compensation following the resumption of
part of the plaintiff's land for the purpose of providing, controlling and
managing a car parking station."
[276] And then later in the same section the Author observes:
"The method was further explained by Tobias JA, with whom McColl
JA and Hunt AJA agreed, in Roads & Traffic Authority of NSW v Muir
Properties Pty Ltd [2005] NSWCA 460 at [103], in the context of s
55(f) of the Land Acquisition (Just Terms Compensation) Act 1991
(NSW):
It is often the case that when only part of a dispossessed owner's
land is compulsorily acquired, a 'before' and 'after' valuation
exercise of the whole of the owner's land is conducted. In other
words, the market value of the land before acquisition is
determined (including the acquired land) as is its value after
acquisition (excluding the acquired land). In this way the
difference between the two values determines not only the market
value of the acquired land but also captures any injurious affection
to the retained land by reason of the acquisition for the public
purpose."150
[277] The 'before' and 'after' method in the presence case adopted by each valuer
involved a cash flow analysis.
[278] It needs to be remembered in assessing the outcomes of 'before' and 'after'
exercises conducted by valuers in the manner in which it was done in this case
that it is effectively a modelling exercise.
[279] It is trite to observe that the reliability and accuracy of the output of a modelling
exercise is only as accurate and realistic as the assumptions and inputs
underlying the modelling exercise are also accurate and realistic.
[280] In the present case there a number of inputs, subtle changes in each of which
can have a significant impact on the figure finally generated by the modelling
exercise.
[281] So much is highlighted in the submissions of the Applicant who points to eight
areas of disagreement with respect to the cash flow analyses.
[282] Those areas of disagreement are:
(a) The gross realisations;
(b) Accounting for GST;
(c) The internal rate of return;
(d) Rates of development and sale of the four stages of the development;
(e) The quantification of the loss of access;
(f) The amount of DTMR contributions;
(g) What allowance should be made for a traffic network analysis report;
150 Hyam p. 177.
-- 55 of 71 --
56
(h) Whether an additional 6 months should be allowed in the after case
before the start of construction.151
[283] For example, things like general economic conditions, interest rates, take-up
rates of land developed and available for sale, conditions specific to particular
industry and government policies are all imponderables which cannot be known
with any certainty. The occurrence of the global financial crisis is good
evidence of this.
[284] Mr Hamilton in his Report152 identifies his assessment approach in the
following terms:
"Compensation is considered best assessed by valuation of the property
both before and after the resumption, with the difference between the
two values being the quantum of compensation, to which applicable
interest and disturbance costs are additional.
I have adopted the direct comparison approach as my initial
methodology. This approach provides a broad pattern of values from
which I then via various adjustments required due to differences in land
area, location, planning status etc establish a value for the subject
property.
I have utilised the cash flow analysis methodology as it has the
flexibility to take into consideration changes in development costings,
development timeframe and development yields."
[285] To facilitate his direct comparison approach Mr Hamilton considers both some
en-globo land sales as well as some developed industrial land sales.
[286] Mr Hamilton contemplated four en-globo land sales which he felt were of
assistance in a valuation exercise which he undertook.
[287] En-globo land sale #1 was of an area of 12.95 Ha otherwise described as Lot 2
on WD4654 which is land located at 222 Staplyton-Jacobs Well Road at
Staplyton 36 radial kms from the Brisbane CBD. That sale occurred in
November 2007 at a sale price of $11,655,000 excluding GST.
[288] That Staplyton land was in a future industrial precinct under a Local Area Plan.
[289] Mr Hamilton said "It is of an inferior location without highway exposure".
[290] His analysis of that sale yielded a calculation of $90/m² for the gross land area
and $97.98/m² of approximate development land area of 119,062 m².
[291] From that en-globo sale it calculates a range for the subject land of between $65
and $75/m².
[292] Mr Hamilton's second en-globo land sale involved land with an area of 30.09
Ha described as Lot 3 on SP134124 located at Lot 3 Peachy Road at Yatala
some 36 radial kms from the Brisbane CBD. That sale occurred in November
2007 at a sale price of $19,090,100 excluding GST.
151 Applicant's submissions page 39 para 165.
152 Exhibit 29 page 55.
-- 56 of 71 --
57
[293] That land was in the General Industry Zone within the Yatala enterprise area
Local Area Plan.
[294] As with his first sale Mr Hamilton says "That land had an inferior location and
no direct access to the highway".
[295] For the purpose of his valuation exercise Mr Hamilton analysed that en-globo
land sale to generate a figure of $63.45/m² of gross land area and $85.54/m² for
the approximate developable land area of 245,500m².
[296] Applying those values to the subject land Mr Hamilton generates a range
between $60 and $70/m².
[297] Mr Hamilton's third en-globo land sale involved land with an area of 61.51 Ha
otherwise described as Lot 281 on W31523 located at 281 Peachy Road Yatala
some 36 radial kms from the Brisbane CBD.
[298] The sale occurred in March 2007 at a price of $29,300,000 excluding GST.
[299] Again the land the subject of the third sale was identified by Mr Hamilton as
having an inferior location and no direct access to the highway.
[300] His analysis of that third en-globo land sale generated a rate of $47.63/m² of
gross land area and $75.37/m² of approximate developable land area of
427,600m².
[301] Having regard to en-globo land sale #3 Mr Hamilton calculated a rate range for
the subject property between $55 and $65 per m².
[302] Mr Hamilton's sale #4 was of an area of 21.23 Ha of land located at Beaudesert
Road (Mt Lindesay Highway) at Parkinson some 21 radial kms from the
Brisbane CBD. The sale occurred in February 2006 and was at a price of
$21,000,000 excluding GST.
[303] Again the land had an inferior location to the subject.
[304] The analysis of that en-globo land sale #4 produced figures of $98.91/m² of
gross land area and $141.89/m² of approximate developable land area of
148,000m².
[305] Applying the information from his en-globo land sale #4 to the subject land Mr
Hamilton calculates a range between $60 and $80/m².
[306] Mr Hamilton also considered developed industrial land sales in the period
January 2007 until March 2008 across five different industrial estates.153
[307] The first sale considered by Mr Hamilton was in the Buildev Yatala Industrial
Estate located at Stanmore Road Yatala which area had been developed as a
primarily warehouse estate since 2005.
153 Exhibit 29 pages 34-43.
-- 57 of 71 --
58
[308] Across a 14 month period the estate achieved sales of 1.25 sales per month but
Mr Hamilton identifies it as an inferior estate to that proposed for the subject
land. I note from his Report154 the Buildev Estate achieved prices ranging from
$200/m² for a 1.172 Ha site to $357/m² for a site which was just under half a
hectare. Generally the higher prices per m² reflected smaller lot sizes.
[309] The second developed industrial land sale considered by Mr Hamilton were
located in the Access Business Park at Stanmore Road Yatala a Business Park
Area predominantly approved with good quality warehouses and factory units.
[310] Between May and August 2007 three lots sold in that estate all of comparable
sizes and prices ranging between $280/m² and $340/m². Mr Hamilton noted
that the Access Building Park was in direct competition with land sales from the
Buildev Estate considered earlier.
[311] The third developed industrial land sale considered by Mr Hamilton were in the
Motorway Business Park located on the Pacific Motorway Service Road at
Ormeau. The Motorway Business Park is very well located and has good
exposure to the Motorway. Between August 2007 and March 2008 there were
four sales of land in that estate ranging from $330/m² for a 0.7426 Ha site to
$370/m² for a 2,500m² site.
[312] The fourth developed industrial land sale considered by Mr Hamilton was in the
Southlink Estate at Johnson Street and Beaudesert Road Parkinson. Like the
Motorway Business Park it has good access and is located just off Beaudesert
Road.
[313] During January and February 2008 there were six sales of land in that estate
ranging from $430/m² for a 2,949m² lot down to $360/m² for three other sales
all of the order of a half hectare.
[314] The uptake rate in that estate overall up to the date of resumption Mr Hamilton
says was 3 lots per month.
[315] The fifth developed industrial land sale considered by Mr Hamilton were in the
State Government Developed Lytton Industrial Estate at Lytton Road Lytton.
[316] This is in a sense a Special Purpose Estate because it was developed
predominantly to attract port related industries. During April 2007 and January
2008 there were 10 sales of lots in that estate ranging in price from $330/m² for
a 2.18 Ha site to $375/m² for a 4,111m² site.
[317] In respect of all those developed industrial land sales Mr Hamilton makes the
following observations:
154 Exhibit 29, page 35.
-- 58 of 71 --
59
"1. 'Buildev Yatala' was achieving values in excess of $300/m² and this estate is
significantly inferior to the Metroplex at Westgate estate due to:
Inferior location and exposure;
Many blocks are subject to retaining walls;
Lower quality premises being constructed; and
Limited open space.
2. 'Access Business Park' and 'Motorway Business Park' were achieving values
in excess of $340/m². These estates are located close to grade separated
interchanges to the Pacific Motorway.
Metroplex would achieve higher values due to:
Metroplex has a superior location;
It has a more attractive environment proposed; and
There is limited competition in immediate locality.
3. 'Southlink' was achieving values in excess of $360/m². Metroplex would
achieve higher values due to:
Metroplex has a superior location;
Metroplex has a superior access and exposure;
It has more attractive environment; and
There is limited competition in the immediate locality.
4. 'Lytton Industrial Estate' was achieving values in excess of $360/m².
Metroplex would achieve higher values due to:
Metroplex has superior location at the junction of Centenary
Highway and Ipswich Motorway;
There is limited competition in the immediate locality; and
The proposed environment is more attractive."155
[318] Consequent upon his analysis of all of those sales both developed and en-globo
lots Mr Hamilton adopts a developed value of $385/m² for Stages 3 and 4 of the
proposed development before resumption.
[319] Mr Hamilton says that that price of $385/m² for Stages 3 and 4 reflects the
following advantageous factors:
" ● Metroplex propose to establish a high quality estate similar to the successful
Metroplex at Gateway. They are proposing to develop the best industrial
estate in the Western Gateway region.
● The subject site has a sought after location only 16 kilometres from
Brisbane Central Business District within the western development corridor.
● Good access is available to Centenary Highway and henceforth to Ipswich
Motorway and the regional road network.
● Relatively low density development with attractive open space.
● Etro centre to offer a range of convenience and service outlets.
● There is limited directly comparable vacant industrial land available in the
immediate vicinity." 156
155 Exhibit 29 page 44.
156 Exhibit 29 page 44.
-- 59 of 71 --
60
[320] Mr Hamilton also157 usefully sets out a summary of the 'before' and 'after' plans
of subdivision which should be read in conjunction with Exhibit 18 the Joint
Statement prepared by Messrs McAnany and Thomas.
"5.1 Before Resumption
Prior to resumption it was proposed to develop the site from east
to west. To achieve this the display office had been constructed
on the eastern entry to the site. Set out below is a summary and
staging for the development of the site as per the agreed highest
and best use.
Stage No. Total Developed
Area (m²)
No of Lots Average Lot Size
(m²)
3 228,740 23 9,945
4 148,880 14 10,630
1 158,490 11 14,440
2 130,560 8 16,320
Total 666,670 56 11,905
5.2 After Resumption
After resumption, as a result of the loss of the eastern access, the
property has to be developed from west to east. Set out below is
a summary and staging of the proposed subdivision as per the
agreed highest and best use.
Stage No. Total Developed
Area (m²)
No of Lots Average Lot Size
(m²)
1 158,490 11 14,440
2 130,560 8 16,320
3 173,370 20 8,768
4 148,880 14 10,630
Total 613,300 53 11,572
158
[321] The figures in the above table were adopted and relied upon by each of the
valuers.
[322] Mr Brett contemplated seven en-globo sales including the four considered by
Mr Hamilton and three others namely:
(a) Land at 255 Archerfield Road Richlands;
(b) Land at 3277 Beaudesert Road Parkinson; and
(c) Land at Bognuda Street Bundamba.
[323] He provides in his Report159 a schedule of the en-globo sales together with some
observations about the value on a per m² basis and the amount of open space.
[324] He makes the point160
"The Cidneo land is considerably larger than any of the sales, a
circumstance with generally results in a lower per m² value."
157 Exhibit 29 page 24.
158 Exhibit 29 page 24 section 5.1 and 5.2.
159 Exhibit 30 page 17, Attachment 6.
160 Ibid.
-- 60 of 71 --
61
[325] The figures produced by the cash flow analysis in the hands of the valuers give
the appearance of accuracy and precision but in fact, in my view, are, at best,
sophisticated estimations and predictions and at worst wild guesses.
[326] Mr Brett161 identifies the basis upon which he has proceeded to construct his
valuation exercise.
" ● Had this resumption and its related works not occurred a
purchaser of this land would need to have commissioned a
traffic report addressing the proposed development's impact on
the surrounding road network, including the Centenary Highway
interchange, the Kelliher and Bakery Roads off and on ramps
and the intersections between these two.
● There would be a degree of uncertainty in respect of the outcome
of negotiations with the Department of Transport and Main
Roads addressing these impacts but an infrastructure agreement
would be successfully negotiated. I have adopted 12 months in
both cases.
● That the traffic report and infrastructure agreement would
necessarily occupy part of the time preceding the start of a
development had there been no resumption, and that time, would
be commensurate with the pre-development time required after
resumption. I have adopted 12 months in both cases.
● That infrastructure charges addressing necessary works would
have been substantially the same with or without the now
completed road works. I have adopted $3,000,000.
● That if it is the case these works are part of the purpose of this
resumption enhancement is to be considered."
[327] The reservations I expressed earlier about the precise reliability of the cash flow
figures generated from a modelling exercise were really acknowledged by Mr
Hamilton under cross-examination when Mr Gore "put to him" that developing
a cash flow was an 'iterative process'.162
[328] Mr Hamilton agreed that it was a detailed process which relied upon different
inputs.
[329] Mr Gore said:
"Different inputs, you changed some of the assumptions to see what
effect those changed assumptions have on the results and on other
outcomes?"163
[330] Mr Hamilton acknowledged that the modelling exercise relied upon changed
inputs until such time as there was an internal rate of return which was
comparable to the 'before' case internal rate of return.
[331] That figure from Mr Hamilton's point of view was 21.67%.164
161 Exhibit 30 page 12.
162 T6-12 L30.
163 T6-12 L38.
164 T6-12 L50.
-- 61 of 71 --
62
[332] The consequence of the foregoing as acknowledged by Mr Hamilton was that if
you put in to the modelling exercise a higher land value you get a lower rate of
return and conversely putting in a lower value of land generates a higher rate of
return.
[333] Further Mr Hamilton acknowledged that the $42,000,000 valuation was, in his
case a function of his goal to obtain an internal rate of return which was
equivalent or roughly equivalent to the 'before' case.
[334] He also acknowledged that Mr Brett's analysis was no different just that his
rates of return were lower.165
[335] I also formed the view that while Mr Hamilton's approach was driven by an
internal rate of return Mr Brett's approach to the valuation exercise was more
driven by attempting to reflect the reality of the market place in the values
ascribed by Mr Brett to both input costs and land sales revenues.
[336] In the 'before' case it was thought that there was agreement that the base rate for
Stages 1 and 2 was $370/m² and for Stages 3 and 4 it was $385/m².
[337] It was also agreed that a number of the Lots which were to be developed would
have designated tree retention and rehabilitation buffer areas on them which
would require an adjustment to be made to the full value per m² area of the Lot
where the area encumbered by tree retention and rehabilitation buffer areas was
15% or less of the Lot area and otherwise a rate of 10% of the full value was
applied to that encumbered part exceeding 15% of the Lot area.166
[338] The agreement about the $370 and the $380 rate per m² was illusory because on
Mr Hamilton's analysis they were GST exclusive and on Mr Brett's analysis
they were GST inclusive.
[339] An Exhibit tendered to the Court clarified the position and enabled the Court to
compare Lot prices before adjustments for tree rehabilitation areas etc but after
corrections for GST so the prices were shown to be exclusive of GST.167
[340] In the 'before' case the figures were:
Hamilton Brett
Stage 1 370 336
Stage 2 370 336
Stage 3 385 350
Stage 4 385 350
165 T6-13 L22.
166 Taken from the Applicant's submissions page 40 para 166.
167 Exhibit 64.
-- 62 of 71 --
63
[341] In the 'after' case the relevant figures were:
Hamilton Brett
Stage 1 360 328
Stage 2 360 328
Stage 3 355 333
Stage 4 355 333
[342] The figures for Hamilton are of course those for which he originally contended
and which exclude GST. Mr Brett's figures are reduced because of his inclusion
of GST.
[343] Ultimately it was agreed between the valuers and the parties that Cidneo the
Applicant had not utilised the benefits of what is referred to as the "margin
scheme" in dealing with GST and accordingly the figures that were referred to
were GST exclusive.
[344] Once the issue of whether the Lot prices in the 'before' and 'after' on a per m²
basis are GST inclusive or exclusive it is appropriate then to turn to the differing
approaches taken by the two valuers to the staging of development of the
subject site. As both parties submitted it was common ground that in the
'before' scenario there were 56 proposed Lots in the hypothetical sub-division
which would be developed in the order of Stage 3 (23 Lots), Stage 4 (14 Lots),
Stage 1 (11 Lots) and Stage 2 (8 Lots).
[345] It was common ground that the Lot yield was reduced by 3 Lots to 53 Lots as a
consequence of some ingenious reconfiguration of the balance land so that
development would proceed in the order of Stage 1 (11 Lots), Stage 2 (8 Lots),
Stage 3 (20 Lots) and Stage 4 (14 Lots).
[346] Each of the sales rates, arranged in the order in which the Stages were to be
developed were set out in Reports of the valuers.168 Those sales rates were as
follows:
Before169:
Hamilton Brett
Stage 3 6ps + 2pcm 6ps + 2pcm
Stage 4 4ps + 1pcm 2ps + 1pcm
Stage 1 3ps + 1pcm 4ps + 1pcm
Stage 2 3ps + 1pcm 1ps + 1 pcm
168 Exhibit 29 page 56 (Valuation Report of Mr Hamilton) and Exhibit 30 page 20 (Valuation
Report of Mr Brett).
169 ps = presales, and pcm = per calendar month.
-- 63 of 71 --
64
After:
Hamilton Brett
Stage 1 5.5ps + 1.5pcm 5ps + 1pcm
Stage 2 3ps + 1pcm 1ps + 1pcm
Stage 3 5ps + 1pcm 5ps +2pcm
Stage 4 4ps + 1pcm 2ps + 1pcm
[347] The difficulty with the evidence of the valuers with respect to both sale prices
and take up rates is that they are, in each case and with greatest respect to the
valuers premised upon speculation and estimation.
[348] It is informed speculation and estimation but at the end of the day it remains just
that.
[349] On the one hand anticipated sales can be wildly optimistic, prices extravagantly
high and profits commensurately high. On the other hand a conservative
approach to the highly speculative sales exercise may yield lower prices, slower
take up rates and hence reduce profits and thereby a reduced value on the land.
[350] A great deal of time and cerebral energy was spent considering the issue of
staging, the time at which project works might be begun, the number of lots
which might be held in reserve and the manner in which economic conditions
may change several years down the track after development has begun.
[351] I am somewhat sceptical as to the utility of such an exercise in attempting to
produce a result which has an aura of accuracy and objectivity about it but
which, upon careful analysis (it being the outcome of a modelling exercise) is
shown to be merely the product of speculation and estimation.
[352] The best that the Court can do is to prefer one approach over another.
[353] In addition to sales and take up rates one other issue which required clarification
was the staging and timing of development. In the 'before' scenario Mr
Hamilton allowed 61 months for the development and in the 'after' scenario he
allowed 76 months.
[354] A part of that timing is that in the 'after' scenario six months is allowed for
approvals, a comprehensive traffic analysis, a re-design re-conceptualisation of
the overall development responsive to the Boundary Road works and hydraulic
issues caused by utilisation of cut and fill between the east and the west sections
of the whole site.170
170 T5-26 LL15-30 and T5-36 LL30-55.
-- 64 of 71 --
65
[355] Part of the extension in the 'after' scenario to 76 months Mr Hamilton explains
was caused by his smoothing out of cash flows and a response to the Joint
Engineers Report.171
[356] Each of the valuers has attempted to reflect what they identify as the injurious
affection to the balance land after resumption and as a consequence of the road
works carried out as part of the project.
[357] For example Mr Hamilton in his Report identifies the following Adjustments:172
"I have reduced the base rate (before adjustments) for Stages 3 and 4
from $385/m² in the before resumption case to $355/m² after
resumption. This is a reduction of $30/m² or 7.8%. The reasons for
this reduction are:
Loss of direct Centenary Highway access and thus inferior
access to the regional road system;
Loss of Ipswich Motorway exposure;
These are now the latter stages of the project and are thus
unable to establish strong momentum; and
These stages are inferior to Stages 1 and 2.
I have reduced the base rate (before adjustments) for Stages 1 and 2
from $370/m² to $360/m². This is a reduction of $10/m² or 2.7%.
This reduction has been undertaken to reflect:
Inferior access arrangements due to the public works;
No benefits are derived from Stages 3 and 4 as these are now
to be developed later;
The standard of development will be reduced compared to that
which could have been achieved pre-resumption; and
There is no benefit from the proposed Etro Convenience
Centre"
[358] The sales rates which are set out above in an extract from Exhibit 29 and 30
were acknowledged by each of the valuers to reflect the Lot prices.
[359] In its submissions to the Court the Respondent summarised that matter this way:
"As identified by Mr Brett, the main issue in relation to the sales rates
was really an issue in relation to the Lot prices, because Mr Hamilton
uses higher Lot prices and sales rates than were achieved at the estates
which the valuers used to develop their assumption. Lot prices and
sales rates have an inverse relationship and, in Mr Brett's opinion, Mr
Hamilton's Lot prices were too high to achieve the sales rates that Mr
Hamilton assumed."173
[360] Unsurprisingly Mr Hamilton defends his prices and the take up rate on the basis
that as he says, "the developed land would have had the following features":174
" ● Metroplex propose to establish a high quality estate similar to the
successful Metroplex at Gateway. They are proposing to develop
the best industrial estate in the Western Gateway region.
171 T6-15 LL15-20. Exhibit 29 page 57 section 12.4.
172 Exhibit 29 page 50.
173 Outline of Submissions of the Respondent paragraph 66.
174 Exhibit 29 page 44 section 8.4.
-- 65 of 71 --
66
● The subject site has a sort after location only 16 kms from
Brisbane Central Business District within the Western
Development Corridor.
● Good access is available to Centenary Highway and henceforth to
Ipswich Motorway and the regional road network.
● Relatively low density development with attractive open space.
● ETRO centre to offer a range of convenience and service outlets.
● There is limited directly comparable vacant land available in the
immediate vicinity."
[361] Mr Hamilton goes on to acknowledge that he had adjusted his adopted rates for
Stages 3 and 4 in the 'before' case to reflect their inferior position. He made
similar adjustments in the 'after' resumption case.175
[362] In his evidence Mr Hamilton acknowledged that he had generally picked prices
which are at the top end of the market176. That reflects his view that the subject
site was the estate of any of estates considered by either him or by Mr Brett.
[363] I did not understand Mr Brett at any point in his evidence to suggest that the
subject site was in some inferior to the estates considered by him and by Mr
Hamilton but he did not seem to emphasise any suggestion that they were
significantly superior either.
[364] It is noteworthy of course that the Lot sizes on the subject land were going to be
substantially larger than the Lots in each of the estates being compared. The
Lots are generally in excess of 1 Ha in area.
[365] In that context it is noteworthy that also Mr Hamilton conceded177 that as a
general rule the price of a Lot decreases with an increase in the size of the Lot.
[366] It appears that in Mr Hamilton's mind that is offset by other factors such as, for
example, the availability of open space.
[367] Mr Hamilton was also taken to page 20 of Mr Brett's primary Report which
contained a convenient summary of Lot sizes in the 'before' and 'after' cases.
[368] Reference to that Exhibit shows that each Stage had the following average areas
for Lots:
1. Stage 1 - 14,444m²
2. Stage 2 – 16,295m²
3. Stage 3 – 9,944m²
4. Stage 4 – 10,634m²
[369] For the 'before' resumption Lot areas and 'after' resumption only in Stage 3 does
the average area of the Lot reduce to 8,767m².
175 Exhibit 29 page 45.
176 T5-60 L 21.
177 T5-47 LL 3-18.
-- 66 of 71 --
67
[370] Mr Gore put to Mr Hamilton that in his application of the Motorway Business
Park figures that he derived from his own analysis he had not made sufficient
allowance for the dramatic difference in Lot sizes between that estate and the
subject site.178
[371] Mr Hamilton's response to that was to say:
"The design of the estate allows flexibility in lot size and shape. So, it's
only a matter of redesigning the layout. So, there's no fixed amount of
land per lot. It can be varied, depending on the demand of the owner -
of the potential purchaser. So, there is some flexibility available to the
developer to accommodate potential buyers and the second point, these
estates are ribbon estates down the highway, motorway. I would have
thought - and as I say in my report - the Metroplex would have been
able to establish a more attractive environment that would attract bigger
users of land than the mum and dad or the spec builders that these other
estates were attracting."
[372] That evidence from Mr Hamilton seems to reflect a higher degree of flexibility
than the rest of his Report revealed. It also suggests a movement away from
what had previously been agreed between the parties with respect to Lot layout
in both the 'before' and 'after' situation.
[373] I found that aspect of Mr Hamilton's evidence less than persuasive.
[374] There is some tension between Mr Hamilton's utilisation of the sales of
developed Lots in each of the estates which he considered and his comments
about the comparability of those estates.
[375] With respect to the Buildev Development at Yatala which was achieving values
in excess of $300/m² Mr Hamilton said that that development was significantly
inferior to the subject because of:
" 1. Inferior location and exposure;
2. Many blocks are subject to retaining walls;
3. Lower quality premises being constructed; and
4. Limited open space."
[376] Similarly with respect to the Access Business Park and the Motorway Business
Park where sales were in excess of $340/m² Mr Hamilton expressed a view that
the subject would attract higher values due to a superior location a more
attractive environment proposed and limited competition in the immediate
locality.
[377] Similarly the Southlink Estate where values were in excess of $360/m² was said
by Mr Hamilton to have an inferior location, inferior access and exposure, a less
attractive environment and more competition in the immediate locality.
[378] He expressed similar views with respect to the Lytton Industrial Estate where
sales reflected values in excess of $360/m².
178 T5-47 L 35.
-- 67 of 71 --
68
[379] I cannot glean in Mr Hamilton's report any concession on a m² basis for the fact
that the Lot sizes are typically substantially greater than in the estates he
considered.
[380] One consequence of the larger Lot size in the both the 'before' and 'after'
redevelopment of the subject site is that each individual Lot will command a
large absolute figure to achieve a sale.
[381] Reference to Mr Brett's first Supplementary Report179 shows in the 'before' case
a significant number of Lots valued at above $5,000,000 and, indeed, one priced
at $14,414,400.
[382] In the 'after' the prices are similarly high with 14 Lots selling for prices above
$5,000,000 with the most expensive selling for $13,693,680.
[383] In the Buildev Yatala Industrial Park the highest price gathered was just over
$5,000,000 for a Lot with an area of 1.967 Ha with four other Lots having areas
in excess of 1 Ha selling for just under $5,000,000.
[384] Interestingly, each of those sales yielded a per m² rate of less than $300/m².180
[385] In the Motorway Business Park Estate none of the four sales was for a Lot with
an area in excess of 1 Ha with only two sales exceeding $1,000,000.181
[386] Similarly the Southlink Estate in which there were six sales had no sale of a
block in excess of 1 Ha and no sale exceeding $3,000,000 as a price.182
[387] The Lytton Industrial Estate was the only estate of four which had Lots with an
area in excess of 1 Ha (3 Lots) and one sale at a price of $8,550,000 for a 2.375
Ha Lot.
[388] Taken as a whole that developed industrial land sale evidence seems to my mind
to be more consistent with the approach taken by Mr Brett in his Report than the
approach taken by Mr Hamilton.
[389] With respect to the take up or sales rates and the rates of development they are
reflected in the table above at paragraph [339]183, as Counsel for the Applicant
point out even though the positions as between the valuers are slightly different
this has no great impact on the overall result given the overall timeframes of 61
months adopted by Mr Hamilton and 67 months adopted by Mr Brett.
[390] So much is reflected in the evidence of Mr Brett who, when that proposition
was put to him, agreed that the difference of six months had no great impact.184
179 Exhibit 61 page 16.
180 Exhibit 29 page 35.
181 Exhibit 29 page 39.
182 Exhibit 29 page 41.
183 Exhibit 29 page 56.
184 T7-20 L 45.
-- 68 of 71 --
69
[391] Counsel for the Applicant urges upon me that I should reject Mr Brett's analysis
because he, it is said, failed to regard the internal rate of return as an input into
his cash flow analysis in order to determine as an output the value of the land or
what a prudent purchaser could afford to pay for the land.185
[392] Mr Brett explained his approach in the course of cross-examination by Mr
Hinson of Senior Counsel.
[393] Mr Brett confirmed that in carrying his analysis he used the land value as an
input and the software generated an internal rate of return. He also
acknowledged that normally he would do that the other way around.186
[394] His reasoning he explained this way187
"Well, that's what I did in the first instance. Then after the discussions
with Mr Hamilton and a review of those en-globo values and accepting
that the speculative market continued to February '08, that I should run
with the level of values demonstrated by the market irrespective of
whether that resulted in what I would think is an unreasonably low
return."
[395] Mr Brett went on though to deny that the rate of return produced by his cash
flow analysis would turn an intending purchaser away.
[396] He said:
"No. I mean, again if we look at those sales, those en-globo sales, in
the year 2007, which are referred to in our various reports, if you are
using those as a benchmark and accepting that as applying to how
much someone would pay for this in its en-globo state, the only way in
which that level can be justified is indeed if people were paying that
money in a speculative market in anticipation of values rising and
really get their return by capital return rather than a direct return on the
development."
[397] He asserted, I think sensibly, that
"You just can't pump the realisations in order to satisfy the bottom line,
the level of return that you think will justify the investment. Those
realisations still have to be viewed in a proper context of how far they
might accede anything. That is presently historically achieved."188
[398] Mr Brett's view of the gross realisations was that they would be lower than
those contended for by Mr Hamilton.
[399] Mr Hinson put to Mr Brett that:
"If the realisations on sales were higher than you have allowed your
internal rate of return would come up."189
185 See T7-34 LL40-50 and T7-63 LL55 to T7-64 L1, T6-.56 LL30-35 and T7-69 L40.
186 T7-35 LL40-50.
187 T7-34 LL50-60.
188 T7-35 L20.
189 T7-36 L20.
-- 69 of 71 --
70
[400] Mr Brett agreed but said:
"Yes, but it still won't come up as far as Mr Hamilton's because of the 3
million dollar infrastructure charge but if my lot prices go up and you
didn't incur the 3 million dollar infrastructure charges, I would be more
or less on a par with Mr Hamilton but the risk isn't accommodated in it
going up, the risk is in accommodating it in going down. That is why
there is a risk component to accommodate some unforeseen
downside."190
[401] Each of Mr Brett and Mr Hamilton produced reports which dealt with the
possibility that the road works contributions may have to have been
contemplated as being as low as $1,087,110 based upon the Joint Statement of
the Civil Engineers Thomas and Marshall.191
[402] For the reasons set out earlier in this Report I feel unable to apply that figure to
the likely road works contribution. The reasons for that are set out elsewhere in
this decision.
[403] I am however satisfied that the appropriate figure to apply to a prudent
purchaser contemplating a likely demand by the Respondent for a contribution
to road works external to the site and apart from the completion of the Boundary
Road link would be $3,000,000.
[404] Because of the reservations I have expressed above with respect to the evidence
of Mr Hamilton and because of my acceptance for most of the evidence of Mr
Brett and because I accept that Mr Brett's assessment of economic conditions
relevant to the setting of prices and the uptake of developed land is to be
preferred to Mr Hamilton's. I am accordingly satisfied that compensation
should be ordered in accordance with the figures advanced by Mr Brett in his
Supplementary Report of 24 November 2011.192
[405] Accordingly, I find that the appropriate compensation to be paid by the
Respondent to the Applicant is $6,877,800.
[406] I acknowledge that Mr Brett's check valuation calculations produce a somewhat
lower figure of $6,000,000 but in line with the liberal estimate principal I am
satisfied that the loss should be rounded up to $6,900,000.
[407] That figure is exclusive of disturbance items which I am told have been agreed
between the parties.
[408] I will hear the parties with respect to interest.
190 T7-36 LL21-28.
191 Exhibit 71.
192 Exhibit 61 page 5.
-- 70 of 71 --
71
11. ORDER
1. Compensation is payable by the Respondent to the Applicant for the
taking on 22 February 2008 of an area of 8.385 Ha being Lot 1 on
SP218520 being part of the land contained in Title Reference 50553649,
County of Stanley, Parish of Oxley in the sum of Six Million Nine
Hundred Thousand Dollars ($6,900,000).
HIS HONOUR, WL COCHRANE
MEMBER OF THE LAND COURT
-- 71 of 71 --
Official source: https://www.sclqld.org.au/caselaw/QLC/2013/047