Australian Laboratory Services Pty Ltd v HRL Limited [2012] QSC 236
SUPREME COURT OF QUEENSLAND
CITATION: Australian Laboratory Services Pty Ltd v HRL Limited [2012]
QSC 236
PARTIES: AUSTRALIAN LABORATORY SERVICES PTY LTD
ACN 009 936 029
(plaintiff)
v
HRL LIMITED ACN 061 930 756
(defendant)
FILE NO/S: 11180 of 2011
DIVISION: Trial Division
PROCEEDING: Application
ORIGINATING
COURT: Supreme Court at Brisbane
DELIVERED ON: 23 August 2012
DELIVERED AT: Brisbane
HEARING DATE: 13 August 2012
JUDGE: Ann Lyons J
ORDER: I will hear from counsel as to the terms of the order and
as to costs.
CATCHWORDS: CONTRACTS – GENERAL CONTRACTUAL
PRINCIPLES – CONSTRUCTION AND
INTERPRETATION OF CONTRACTS – IMPLIED
TERMS – OTHER CASES – Where applicant pursuant to a
written agreement purchased a number of properties which
allegedly, at the date of signing and Closing, in breach of the
warranties set out in the agreement held and were not free
from environmental contamination – Where applicant seeks
an order requiring the respondent to perform its contractual
obligation and jointly engage an environmental consultant to
prepare a report – Where the intention of the parties as
manifested by both the express and implied terms of the
contract was to do all such things as necessary to enable to
other party to have the benefit of the contract – Where the
respondent argues that a condition to the appointment of the
environmental consultant, confirming that the applicant and
the environmental consultant have a continuing commercial
relationship outside the terms of the agreement and that the
relationship is not a conflict of interest, is unreasonable and
inappropriate – Whether the duty to cooperate would have
been implied in the circumstances.
-- 1 of 22 --
2
EQUITY – GENERAL PRINCIPLES – RULES AND
MAXIMS OF EQUITY – CLEAN HANDS – Where
applicant pursuant to a written agreement purchased a
number of properties which allegedly, at the date of signing
and Closing, in breach of the warranties set out in the
agreement held and were not free from environmental
contamination – Where applicant seeks an order requiring the
respondent to perform its contractual obligation and jointly
engage an environmental consultant to prepare a report –
Where the agreement between the parties included a clause
which requires the parties to work together in good faith to
engage an environmental consultant to conduct an assessment
of environmental issues – Whether communications between
the applicant and the environmental consultant without the
knowledge of the respondent means that the applicant is not
coming to equity with clean hands.
PROCEDURE – COURTS AND JUDGES GENERALLY –
JUDGES – DISQUALIFICATION FOR INTEREST OR
BIAS – IN GENERAL – ORDINARY RULE – Where
applicant pursuant to a written agreement purchased a
number of properties which allegedly, at the date of signing
and Closing, in breach of the warranties set out in the
agreement held and were not free from environmental
contamination – Where applicant seeks an order requiring the
respondent to perform its contractual obligation and jointly
engage an environmental consultant to prepare a report –
Where the agreement between the parties included a clause
which requires the parties to work together in good faith to
engage an environmental consultant to conduct an assessment
of environmental issues – Where the applicant and the
environmental consultant are parties to ongoing litigation in
Victoria and have engaged in negotiations in the absence of
the respondent – Whether a fair minded observer might
entertain a reasonable apprehension of bias on the part of the
environmental consultant – Whether in relation to the
appointment of independent experts the test of apprehended
bias is one of „actual partiality‟ rather than „the appearance of
impartiality‟.
1144 Nepean Highway v Abnote Australasia Pty Ltd [2009]
VSCA 308
Ceneavenue v Martin [2008] SASC 158
Dering v the Earl of Winchelsea (1787) 28 ER 1184
Ebner v Official Trustee in Bankruptcy (2000) 205 CLR 337
FAI Insurances v Pioneer Concrete (1987) 15 NSWLR 552
Goddard v Midland Railway Company (1891) 8 TLR 126
McGrath v McGrath [2012] NSWSC 578
Secured Income Real Estate (Australia) Ltd v St Martins
Investments Pty Ltd (1979) 144CLR 596
-- 2 of 22 --
3
Spry, ICF The Principles of Equitable Remedies: Specific
Performance, Injunction, Rectification and Equitable
Damages 8th ed Thompson Reuters Australia Limited, 2010
COUNSEL: DJS Jackson QC with MJ Luchich for the plaintiff
S Robertson for the defendant
SOLICITORS: Minter Ellison Lawyers for the plaintiff
Maddocks Lawyers for the defendant
ANN LYONS J:
Background
[1] On 19 September 2007 the plaintiff, Australian Laboratory Services Pty Ltd (ALS)
agreed to purchase the defendant HRL Limited‟s (HRL) shares in ACIRL Limited
(ACIRL) for $76,756,000 pursuant to a Share Sale Deed (SSD).1 The purchase
included a number of business properties in Queensland and New South Wales. The
Closing date under the SSD was 17 October 2007.
[2] The agreement included seller‟s warranties in relation to the environmental
condition of those sites and contained a number of clauses which outlined
provisions in relation to the conduct of environmental assessments and the making
of any claims. In particular, clause 8.13(b)(i) required the parties to work together in
good faith to engage an environmental consultant to conduct an assessment of
environmental issues.
[3] URS Australia Pty Ltd (URS) was engaged to conduct that assessment and, at a cost
of almost $1 million to the parties, has produced a series of eight reports which
identify environmental issues.
[4] ALS commenced the present proceedings on 2 December 2011,2 claiming the sum
of $7,779,252.53 pursuant to a written indemnity or, alternatively, damages for
breach of contract in the same amount, alleging that, as at the date of signing and on
Closing, in breach of the warranties set out in the SSD, dangerous materials were
held but not safely stored at a number of sites and that those sites were not free from
all environmental contamination. It is also alleged that dangerous effluence had
been discharged from a number of the sites. It is alleged that as a consequence of
those breaches of warranties ALS has suffered loss and damage by way of
performing investigations and the cost of remediation work in excess of $7 million.
[5] HRL filed a Notice of Intention to Defend and Defence on 3 January 2012.3
Pursuant to paragraph 22A of the Amended Defence,4 the defendant has pleaded
that in answer to the whole of the Claim, if there is a Claim that otherwise complies
with the SSD, the defendant is only liable for loss that arises out of environmental
issues that are identified in the environmental assessment report at Closing and that
1 Exhibit TEM-1 to Affidavit of TE Mullen sworn 1 May 2012 (Vol 1) pp 1-61.
2 Claim and Statement of Claim filed 2 December 2011.
3 Notice of Intention to Defend filed 3 December 2011.
4 Amended Defence of the Defendant filed 26 April 2012.
-- 3 of 22 --
4
there is no such report identifying what environmental issues existed at the various
properties at Closing.
The present application
[6] The present interlocutory application5 filed on 27 April 2012 essentially seeks an
order requiring HRL to perform its contractual obligation and jointly engage an
environmental consultant to prepare a report in accordance with the terms of the
SSD. The specific order that ALS seeks is an order that, pursuant to clause
18.13(b)(i) of the SSD, HRL and ALS engage URS to prepare a report to identify
which of the environmental issues identified by URS, in its reports dated 15 April
2008, 22 May 2009, 4 September 2009, 13 October 2009, 22 February 2011, 21
March 2011, 22 March 2011 and 6 May 2011 with respect to the subject properties,
existed at Closing.
[7] At the hearing of the application on 13 August 2012, the plaintiff sought leave to
amend the application to include as a term of the order a paragraph indicating that
the engagement by URS would be on the terms set out in Exhibit CLD-28 to the
affidavit of Christopher Lee Douglas sworn 10 August 20126 and that the report
identify whether:
“(a) the properties referred to in paragraph 7 of the Further
Amended statement of claim were „free from all
environmental contamination, including without limitation,
any patent or latent contamination of the Environment soil,
sub-soil, ground water or surface waters within or adjacent
to such premises‟ as at 17 October 2007; and
(b) materials, „including without limitation, effluence leachate,
emissions or hazardous materials generated on or emitted
from any of‟ the properties referred to in paragraph 7 of the
Further Amended Statement of Claim by 17 October 2007
„have caused or will cause in whole or in part any
contamination of the Environment‟.”7
[8] Significantly and contentiously, the Terms of Engagement which are proposed now
contain, as Clause 4(1)(a), a clause which provides that both ALS and HRL confirm
that URS has a “continuing commercial relationship outside the terms of this
Agreement and that relationship is not a conflict of interest”.
The terms of the SSD
[9] The terms of the SSD8 included “Seller Warranties” at Clause 8.2 whereby HRL
represented and warranted to ALS that each Seller Warranty was true and correct as
at the “Signing Date” and would remain true and correct at any time up until
“Closing”.
5 Application filed on behalf of the Plaintiff filed 27 April 2012.
6 Affidavit of CL Douglas sworn 10 August 2012 filed by leave 13 August 2012.
7 Draft Order provided by the Applicant.
8 Above n 1.
-- 4 of 22 --
5
[10] Schedule 1 contained the Seller warranties. Those warranties included warranties
about compliance with environmental laws and warranties that the business
properties were free from contamination. In Clause 17.8 the Seller warranted as
follows:
“17.8 Environment Laws
(a) (Dangerous materials): The Sale Group does not hold on the
Business Properties or otherwise control any deposit, dump,
tank or container of any dangerous, noxious or poisonous
waste, fuel, fluid, solvent, chemical or effluent, except for any
fuel, fluid or chemical used in any industrial process of the Sale
Group which is properly and safely stored, identified, labelled
and maintained in compliance with best industrial standard and
any applicable Environmental Law.
(b) (Dangerous effluents): The Sale Group does not discharge
from its land any dangerous, noxious, poisonous, toxic,
hazardous or deleterious matter, liquid or gas, whether by
way of effluent, emissions or in any other manner other than
in accordance with applicable laws.
(c) (Contamination):
(i) The Business Properties are free from all environmental
contamination, including without limitation, any patent or
latent contamination of the Environment soil, sub-soil,
ground water or surface waters within or adjacent to such
premises; and
(ii) no materials, including without limitation, effluence
leachate, emissions or hazardous materials generated
on or emitted from any of the Business Properties
have caused or will cause, in whole or in part, any
contamination of the Environment";”9
[11] Furthermore, clause 8.13(b) in the Chapter on Representations and Indemnities
provided as follows in relation to the Business Properties:
“In relation to the Business Properties other than the Exiting
Business Properties:
(i) As soon as practicable and at the latest within 3 months of
the Closing Date, the Seller and the Buyer will work
together in good faith to arrange for environmental
assessments to be conducted at the joint cost of the Seller
and Buyer, by an environmental consultant agreed by the
parties, or failing agreement, by an environmental consultant
appointed by the President from time to time of the
Institution of Engineers Australia;
9 Ibid at p 36.
-- 5 of 22 --
6
(ii) In the event that an environmental assessment reveals:
A. …
B. that an environmental issue does exist at the relevant
Business Property:
1. If the Seller elects, the Buyer must allow the Seller or
procure that the Seller is allowed, to carry out
remediation work to ensure that there will be no Third
Party Claim in relation to the environmental issues at
the Business Property; and
2. If there is a Claim under paragraph 17.8 of the Seller
Warranties which otherwise complies with this deed,
the Seller will only be liable in respect of such Claim for
Loss that arises from environmental issues that is identified
in the environmental assessments as having been
existing as at Closing.”10
[12] “Business property” was defined in Chapter 1 as meaning “each freehold or
leasehold property or premises specified in Schedule 4, and all those properties and
premises collectively.”11
[13] Clause 8.11 of the SSD allowed ALS promptly, but no later than 20 business days
after receipt of “actual knowledge” of anything that, in its reasonable opinion, “may
give rise to any Claim” under the SSD, to deliver a Claim Certificate to HRL.12
Clause 8.11 further provided that if the consultation process provided for following
delivery of a Claim Certificate does not resolve the Claim then either party may
(under clause 8.1l(e)) submit the dispute to a Court of competent jurisdiction.13
[14] Clause 8.6(a) of the SSD provided that HRL was not liable for any Claim by ALS
except where the following occurred:
1. ALS has given HRL a Claim Certificate required under and within the time
limit specified in clause 8.11 (clause 8.6(a)(i));14
2. ALS has given written notice to HRL specifying details of the Claim within
the period of 5 years beginning with the Closing Date (clause 8.
6(a)(iii)B);15
3. where ALS has given written notice HRL within the period set out in clause
8.6(a)(iii), and within 6 months of HRL receiving that notice, the Claim has
been referred to a Court of competent jurisdiction by ALS commencing and
serving any legal action or proceeding against HRL in relation to the Claim
(clause 8.6(a)(iv)C).16
10 Ibid at pp 25-26 (emphasis added).
11 Ibid at p 5.
12 Ibid at p 22.
13 Ibid at p 23.
14 Ibid at p 19.
15 Ibid at pp 19-20.
16 Ibid at pp 19-20.
-- 6 of 22 --
7
[15] By clause 8.6(b) of the SSD, HRL is not liable for any claim by ALS, to the extent
the Claim is alleged to involve a breach of paragraph 17.8 of the Seller warranties,
except where ALS has complied with the provisions of clause 8.13 which relates to
the joint appointment of the environmental consultant to conduct environmental
assessments.
The history of the environmental reports
[16] An environmental consultant was appointed pursuant to clause 8.13(b)(i) of the SSD
in November 2007. URS was the environmental consultant appointed.
[17] URS produced eight reports or environmental assessments which were paid for
jointly by the two parties at a cost of almost $496,393.58 to each party.
[18] Two of the reports, namely those titled "Final Report, Phase II Environmental Site
Assessment, ACIRL NSW and Qld; dated 22 May 2009” (May 2009 Report) and
“Final Report, Phase I1 Environmental Site Assessment, ACIRL Emerald; dated 13
October 2010” (October 2010 report), identified environmental issues
(contamination) at the following business properties:
1. Acirl Street, Riverview, Queensland (Riverview Property);
2. Junction Street, Telarah, New South Wales (Telarah Property);
3. Darling Street, Carrington, New South Wales (Carrington Property);
4. Industrial Close, Muswellbrook, New South Wales (Muswellbrook
Property); and
5. Foundry Road, Emerald, Queensland (Emerald Property).
[19] URS also recommended remedial action at the five properties in its report entitled
"'Final Report, Post Phase II ESA, ACIRL Emerald" dated 22 March 2011 (March
2011 Report). The report entitled "Site Management and Remedial Cost Estimates
Report" dated 6 May 2011 and issued on 9 May 2011 (May 2011 Report)
confirmed that the Five Properties contained concentrations of contaminants of
concern and required remediation and provided a cost estimate for the performance
of the remediation at those properties.
[20] On 23 June 2009 ALS gave a claim certificate to HRL. The certificate was rejected
by the solicitors for HRL as not being a valid claim certificate, because it considered
that its obligation was confined in terms of clause 8.13(b)(ii)B2 of the SSD.
History of the proceedings
[21] On 27 April 2012 the plaintiff filed the present application. The matter was initially
heard on 9 May 2012. The plaintiff applied for leave to amend its Reply to the
Amended Defence of the Defendant and the matter was transferred to the civil list.
[22] An Amended Reply was filed on 29 May 2012, with a further Amended Reply filed
on 6 June 2012. On 6 June 2012 the matter came on for hearing before Margaret
Wilson J. At the hearing, counsel for HRL indicated to the Court that there was
agreement to the joint appointment of URS by the parties provided the terms of the
appointment could be agreed. Counsel for HRL also indicated to the Court that it
was prepared to offer an undertaking to negotiate in good faith with the plaintiff and
with URS with a view to agreeing terms pursuant to which URS would be jointly
appointed to prepare a report that identifies which of (and the extent to which) the
-- 7 of 22 --
8
environmental issues identified by URS in its reports dated 15 April 2008, 4
September 2009, 22 February 2011 as well as the May 2009 Report, the October
2010 Report, the March 2011 Report and the May 2011 Report.
[23] The matter was then adjourned until 26 June 2012 to allow the parties time to
discuss the terms of the engagement with URS before any formal order of the court
was made binding on URS. It was clear therefore that the only issue raised at that
hearing was the question of the reasonableness of the terms of the engagement of
URS.
[24] As at 26 June 2012 URS had failed to agree on the terms of the joint appointment
and was not willing to provide the additional services sought by the parties.
Accordingly, the matter was adjourned to a date to be fixed.
[25] Since 26 June 2012 there have been extensive negotiations between the parties and
URS with no resolution. On 27 July 2012 HRL, however, had received a letter from
the plaintiff‟s solicitors indicating that URS had now agreed to undertake the
services on the basis of terms and conditions which were enclosed in that letter.17
[26] Schedule 1 to the general conditions which were enclosed in that 27 July letter then
listed, at Item 3(a)1, the five properties at Riverview, Telarah, Carrington,
Muswellbrook and Emerald. The Schedule also provided at item 3(a)2 that the
report was to be prepared by 24 August 2012 and it was to identify, by reference to
the environmental issues identified by URS in its eight previous reports, whether:
1. the properties were free from environmental contamination including
without limitation, any patent or latent contamination of the Environment
soil, sub-soil, ground water or surface waters as at 17 October 2007; and
2. materials including without limitation, effluence leachate, emissions or
hazardous materials generated on or emitted from any of the properties by
17 October 2007 have caused or will cause in whole or in part any
contamination of the Environment.
[27] The proposed report also required URS to identify any assumptions made in
preparing its report (and the basis of those assumptions) and to identify any facts
(and the basis of those facts) and to identify any reasons for its conclusions in the
report.
[28] On 6 August 2012 the solicitors for HRL wrote to the solicitors for ALS, querying
the fact that URS had now agreed to undertake the services and stating “our client is
very concerned as to whether URS is capable of acting as an „independent and
objective consultant’ and ‘maintaining its independence from [ALS] and [HRL]‟ as
will be expressly required in the event that the Proposed Terms are executed.”18 The
letter continued:
“Frankly, our client does not understand how URS could regard it as
appropriate to conduct negotiations regarding a proposed „joint
appointment‟ in the absence of (and without the knowledge of) one
of the parties to the proposed joint appointment. This is particularly
the case in circumstances where ALS, HRL and URS had previously
17 Exhibit CLD-16 to Affidavit of CL Douglas sworn 10 August 2012 (Above n 6).
18 Exhibit CLD-18 to Affidavit of CL Douglas sworn 10 August 2012 (Above n 6) at 5.
-- 8 of 22 --
9
participated in a joint telephone conference with a view to reaching
agreement on the terms of a further „joint appointment‟ of URS and
in circumstances where there is ongoing litigation between ALS and
HRL (including litigation regarding whether or not URS should be
engaged to produce a further report.).”19
[29] In a letter sent to both ALS and HRL on 9 August 2012,20 URS indicated that all
previous offers, proposals and negotiations were withdrawn and that, if orders were
made by the Queensland Supreme Court that URS must provide services to ALS
and HRL, URS would only provide those services pursuant to an attached
agreement for the provision of consulting services. It was indicated that although
URS had previously agreed to make amendments no such amendments would be
entertained at the time of the writing of the letter.
[30] The letter of 9 August also referred to the fact that a subpoena had been requested
by HRL in relation to a discussion which took place between the managing director
of URS and the managing director of ALS. The letter from URS continued “[a]s
discussed on 7 August 2012, that discussion was in relation to an unrelated matter,
which is not relevant to this matter.”
[31] The agreement for the provision of consulting services enclosed in the 9 August
2012 letter significantly included as clause 4.1(a), under the heading General
Obligations, a provision which required the clients to “acknowledge that the
Consultant and ALS have a continuing commercial relationship outside the terms of
this Agreement and that relationship is not a conflict of interest”.21
HRL’s opposition to the present application.
[32] The submissions of the defendant indicate that one of the reasons why URS
originally indicated it was not willing to provide the additional services was that
there was ongoing litigation between ALS and URS in the Victorian Supreme
Court. Counsel for the defendant argues that, in the absence of full and proper
explanations as to why URS and ALS considered it appropriate to engage in
negotiations in relation to the joint appointment in the absence of the defendant
without its knowledge and full particulars, a fair minded observer might
consequently entertain a reasonable apprehension of bias on the part of URS. It is
argued that the apprehension of bias is a sufficient and proper basis for the Court to
refuse to exercise a discretion to make the order sought by the plaintiff.
[33] Counsel for the defendant also submits that the plaintiff is in breach of clause
8.13(b)(i) of the SSD, which requires the parties to work together in good faith to
arrange for environmental assessments. In this regard it was argued that because the
plaintiff had arranged for environmental assessments independently they therefore
had not worked together in good faith, pursuant to that clause. The defendant
indicates that it does not know what other matters are sitting behind the issues
between ALS and HRL and is unaware of the nature and extent and the content of
the discussions between URS and ALS.
19 Ibid at 6.
20 Exibit CLD-28 to Affidavit of CL Douglas sworn 10 August 2012 (Above n 6).
21 Ibid.
-- 9 of 22 --
10
[34] The defendant argues that the plaintiff is in fact seeking an order enforcing clause
8.13(b)(i) of the SSD and therefore the order is necessarily an application for final
relief. The defendant argues that the two issues the Court needs to consider are first
whether the defendant has breached or anticipatorily breached clause 8.13(b)(i) and
secondly whether, in the exercise of its equitable jurisdiction, the Court should
make the order.
[35] The defendant denies that it has breached the SSD and argues that this is not an
occasion for the Court to grant equitable relief. It is further argued that, even if the
Court was satisfied that there was a breach or anticipatory breach of the SSD, the
Court should not make the order because if the order was made it would require the
defendant to engage a person who is ostensibly biased and, further, ALS has come
to Court with „unclean hands‟ because it seeks to enforce an obligation of which it
itself is in breach.
The ‘unclean hands’ argument
[36] Counsel for the defendant essentially argues that the fact that communications have
taken place between URS and ALS without the knowledge of the defendant means
that the plaintiff is not coming to equity with clean hands. Counsel for the defendant
relies on the fact that during the hearing on 6 June 2012 HRL indicated through
Counsel it was prepared to give an undertaking to undertake negotiations in good
faith with ALS and with URS with a view to agreeing on terms. Counsel for HRL
argues that there are continuing obligations pursuant to clause 8.13(b)(i) for both
ALS and HRL to work together in good faith.
[37] Counsel for HRL contends that ALS has breached that obligation by its conduct
since the last return date. Whilst the defendant accepts that FAI Insurances v
Pioneer Concrete22 indicated that general “naughtiness” was insufficient and that
the alleged wrongful conduct must have “an immediate and necessary relation to the
equity sued for”,23 particular reliance is placed on the decision of Goddard v
Midland Railway Company,24 where the Court declined to enforce a restrictive
covenant arising under a common building scheme where the plaintiff was in
serious breach of the same covenant sued upon.
[38] It is necessary to turn to the conduct of ALS since the last hearing. The affidavit of
Mathew Stulic sworn 12 August 2012 sets out his dealings with legal counsel for
URS.25 That affidavit attaches his file note, which records Mr Stulic‟s record of
what Simon Barrett, legal counsel for URS, informed him:
“• He said that there is „another matter between URS and ALS
sitting behind this‟. I asked him what the matter was - he said
„commercial in confidence‟. He said the „other matter‟ between
ALS and URS needed to be resolved before URS could
consider taking on this further engagement. He said that other
matter between URS and ALS was resolved and following its
resolution he received a telephone phone call from Chris
Douglas of Minter Ellison asking him to send the terms URS
22 (1987) 15 NSWLR 552 at 552.
23 Dering v the Earl of Winchelsea (1787) 28 ER 1184 at 1185.
24 (1891) 8 TLR 126.
25 Affidavit of MP Stulic sworn 12 August 2012 filed by leave 13 August 2012.
-- 10 of 22 --
11
would be prepared to sign up to. He said he didn‟t have the
exact date, but thinks Chris Douglas called him on or about 25
July 2012.
• I asked him whether he was involved in the discussions which
resolved the „other matter‟ between URS and ALS. He said he
wasn‟t. He said that the discussions took place as he
understood it between the MD of ALS and the MD of URS.
He then „got the all clear‟ from the MD of URS that they could
take on this engagement. He said he doesn‟t know what those
discussions were, they just filtered down to him.”26
[39] The affidavit of Paul Napier, legal counsel for ALS, sworn 13 August 201227
indicates that there are currently proceedings commenced by URS against the Port
of Melbourne Corporation in the Supreme Court of Victoria. In those proceedings
URS sought and was granted leave to join ALS as a party. URS pleads that ALS is a
concurrent wrongdoer as contemplated by Part IVAA of the Wrongs Act 1958 (Vic).
[40] Mr Napier swears that the discussions between the ALS representatives and URS
representatives have resolved URS‟s objection to its continued retainer by ALS and
HRL in the current proceeding to the extent that objection had as its basis the
Victorian litigation. He further swore that those discussions were conducted on a
without prejudice basis.
[41] The affidavits of Christopher Douglas, a solicitor employed by the firm acting for
ALS, sworn on 10 August28 and 13 August 201229 set out his dealings with URS.
Mr Douglas swears that he was informed by legal counsel for URS on 25 June 2012
that there was another matter affecting URS‟s willingness to provide the services
sought and that the other matter involved a claim in Victoria involving URS and
ALS. Mr Douglas swears that he was later informed by Paul Napier that one of the
parties in the other matter was the Port of Melbourne Corporation and that that
corporation was a client of the Melbourne office of the solicitors for ALS.
Accordingly, Mr Douglas swears that he is not aware of the details of the other
matter and that, so far as that other matter affects URS‟s willingness to undertake
the further services sought in relation to this matter, that is something which has
been dealt with directly between ALS and URS.
[42] Counsel for HRL argues that there are continuing obligations pursuant to clause
8.13(b)(i) for both ALS and HRL to work together in good faith in relation to the
environmental reports. The essence of HRL‟s argument would seem to be that any
contact with URS by ALS to progress the preparation of the environmental reports
had to be done jointly and that any contact apart from a joint contact would be in
breach of the obligation of good faith.
[43] I am not, however, satisfied that any contact between URS and ALS would be in
breach of the continuing obligations in clause 8.13(b)(i). That obligation is “to work
together in good faith to arrange for environmental assessments to be conducted at
26 Exhibit MPS-1 to Affidavit of MP Stulic sworn 12 August 2012 filed by leave 13 August 2012
(Above n 25).
27 Affidavit of PM Napier affirmed 13 August 2012 filed by leave 13 August 2012.
28 Above n 6.
29 Affidavit of CL Douglas sworn 13 August 2012 filed by leave 13 August 2012
-- 11 of 22 --
12
the joint cost of the Seller and the Buyer, by an environmental consultant agreed by
the parties”. Significantly, the seller and the buyer had in fact already arranged for
assessments to be conducted by URS and had jointly paid the significant costs to
date. I do not consider that the contact with URS by ALS was to arrange for those
environmental assessments to be prepared but rather the contact was to remove
objections to URS‟s continuing involvement due to issues which lay behind the
scenes and which were entirely unrelated to the present matters. Notably, URS and
ALS have a continuing commercial relationship involving many matters beyond the
scope of the present issues. In my view ALS was not in fact actually unilaterally
progressing the environmental reports but, rather, was involved in trying to remove
obstacles to URS‟s continued involvement.
[44] Furthermore I cannot see how the involvement of HRL in the resolution of issues
between ALS and URS would have meant that ALS and HRL were working “in
good faith to arrange for environmental issues to be conducted”, as clause 8.13(b)(i)
requires.
Is URS ostensibly biased?
[45] The defendant argues that clause 8.13(b)(i) contemplates that the assessments will
be conducted by a consultant who is independent of the parties and that the evidence
presently available raises a reasonable apprehension of bias on the part of URS. In
this regard it is argued that there is a relationship between URS and ALS which is a
relationship beyond the connection with the SSD and, whilst that relationship might
be innocuous, in the absence of full disclosure a fair-minded observer would
apprehend that URS might not bring an impartial mind to the resolution of the
questions.
[46] In this regard, the defendant argues that it is clear that at 25 June 2012 URS was not
willing to provide the services and then between 25 June 2012 and 27 July 2012
there were discussions between the parties in the absence of the defendant which
resolved those objections. On 27 July, the plaintiff‟s solicitors advised that URS had
reversed its position. The defendant argued there is an unexplained inconsistency in
the positions taken by URS.
[47] The test of apprehended bias was examined in detail in the High Court decision of
Ebner v Official Trustee in Bankruptcy,30 as follows:
“The apprehension of bias principle admits of the possibility of
human frailty. Its application is as diverse as human frailty. Its
application requires two steps.
First, it requires the identification of what is said might lead a judge
(or juror) to decide a case other than on its legal and factual merits.
The second step is no less important. There must be an articulation of
the logical connection between the matter and the feared deviation
from the course of deciding the case on its merits. The bare assertion
that a judge (or juror) has an “interest” in litigation, or an interest in a
party to it, will be of no assistance until the nature of the interest, and
30 (2000) 205 CLR 337.
-- 12 of 22 --
13
the asserted connection with the possibility of departure form
impartial decision-making, is articulated. Only then can the
reasonableness of the asserted apprehended bias be assessed.”31
[48] However, in relation to the appointment of independent experts, “actual partiality”
rather than “the appearance of partiality” has been held to be the test in a number of
cases. In this regard Debelle J, in the Supreme Court of South Australia in
Ceneavenue v Martin,32 made the following observations:
“In Macro Robert Walker J expressed the view that actual partiality
rather than the appearance of partiality is the crucial test. He justified
that conclusion in this way:
Otherwise auditors (like architects and actuaries) who have a
long-standing professional relationship with one party (or
persons associated with one party) to a contract might be
unduly inhibited, in continuing to discharge their professional
duty to their client, by too high an insistence on avoiding even
an impression of partiality.
With respect, there seems to be much to commend that view. The
task of the valuer is not infrequently assigned to a person such as an
auditor or accountant who has a professional or other association
with one of the parties. To apply the test of the appearance of
partiality could, therefore, have a real potential to invalidate the
valuation made by such a person. In Beevers at [300], Dodds-
Streeton J adopted a different view from that of Robert Walker J. She
said:
[300] Given the sometimes fine distinction between an
appearance of partiality and a finding of partiality on the
balance of probabilities, I am not persuaded that the parties
would intend to be bound by a valuation attended by a credible
appearance, or soundly based apprehension, of partiality. It is
not necessary, however, to determine that question in the
present case, because I conclude, on the balance of
probabilities, that although Mr Ryan was not guilty of
collusion, dishonesty or conscious partiality, he did not
perform the valuation with the degree of independent skill and
judgment and impartiality required of an expert acting between
two parties.
Those remarks suggest that an appearance of partiality will invalidate
the valuation. It is clear that her Honour was not expressing a
concluded view. On this appeal, neither party addressed this question
in their submissions. It is undesirable, therefore, to express a
concluded view on this aspect of the question of impartiality.”33
31 Ibid at [8].
32 [2008] SASC 158.
33 Ibid at [71].
-- 13 of 22 --
14
[49] In this regard Pembroke J, in the recent decision of the New South Wales Supreme
Court of McGrath v McGrath,34 examined the relevant issues in the following way:
“Apprehended bias is altogether different. In truth, it constitutes the
real juridical basis for the defendant's resistance to the remedy of
specific performance. The defendant said that he was concerned
about "whether any valuation by Mr Collins would be carried out in a
truly independent way." His counsel submitted that the engagement
of Mr Collins would be "in breach of an implied term ... that the
valuation be made honestly and impartially". These are statements of
apprehension. The fulcrum of the defendant's concern is the
unilateral contact that Mr Collins had with the plaintiff and his
solicitor in February 2011, contact which I will shortly explain. As I
said, it occurred in connection with Mr Collins' attempt to negotiate
his terms of engagement. Stretching the defendant's case to its limit,
there is an apprehension that Mr Collins' valuation, if and when he is
appointed, and if and when it is completed, will not have been made
impartially and will be affected by a bias towards the plaintiff. The
practical apprehension must be that Mr Collins will not decide the
question of valuation on its merits and that the result might favour
the plaintiff.
Not only does this contention have no factual foundation (to which I
will come) but it confronts several legal difficulties. The first is that
the test for apprehension of bias requires articulation of the supposed
rational connection between the relevant conduct and the possibility
in the mind of a reasonable observer that the decision-maker might
be diverted from deciding the question on its merits: Ebner v Official
Trustee in Bankruptcy [2000] HCA 63; (2001) 205 CLR 337 at [6] -
[8] and [30]. That legal standard has not been met in this case. No
plausible argument has been advanced that articulates the necessary
logical connection between the conduct of Mr Collins and "the feared
deviation from the course of deciding the case on its merits": Ebner
at [8]. The bare identification of a unilateral communication between
Mr Collins and the plaintiff or his solicitor in connection with the
negotiation of his terms of engagement, even together with Mr
Collins' later email of 21 September, do not rationally suffice to
answer that question: Ebner at [30].
The second difficulty is that the principle of apprehended bias will
rarely, if ever, have a role to play in relation to independent experts.
In Ebner, the plurality confined the discussion of the application of
the principle of apprehended bias to "a judge (or other judicial officer
or juror)": at [6] - [8]. In Macro v Thompson (No 3) [1977] 2 BCLR
36, Robert Walker J (as he then was) expressed the view that actual
partiality rather than the appearance of partiality is the crucial test for
independent experts. In Ceneavenue Pty Ltd v Martin at [71],
Debelle J said that there seems much to commend this view. In
Candoora No 19 Pty Ltd v Freixenet Australasia Pty Ltd (No 2)
34 [2012] NSWSC 578.
-- 14 of 22 --
15
[2008] VSC 478 at [25], Hargrave J referred with apparent approval
to the finding in Macro that actual partiality, rather than the
appearance of partiality, was necessary in order to set aside a
contractual determination. In Kenros Nominees Pty Ltd v Tipperary
Group Pty Ltd [2009] VSC 524, Hollingworth J also appears to have
approved this reasoning, observing at [95]:
„The plaintiffs cannot point to any case in which an injunction
has been granted to prevent a valuation by a person acting as
expert, or even where an actual valuation has been set aside, on
the basis of apparent bias. All of the cases to which the parties
referred deal with the setting aside of a valuation after it has
been performed, on the basis of actual bias.”35
[50] I agree with the proposition that with independent experts the principle of
apprehended bias will rarely have a role to play. Accordingly in the present case,
without any evidence of actual partiality and without any evidence of the connection
between the actual conduct which occurred and the feared deviation, I am not
satisfied that there is any substance to the argument that URS would be actually
biased.
The nature of the relief sought by the plaintiff
[51] ALS seeks a mandatory injunction compelling HRL to join with ALS to engage
URS to produce a report to answer a specific question as to whether environmental
issues existed at the business properties at Closing.
[52] ALS argues that Clause 8.13 of the SSD did not place any limit on the number of
reports or environmental assessments that the parties could commission to ensure
compliance with the clause. Furthermore it is argued that the existence of
environmental issues at Closing underpins an important part of the Seller warranties
and HRL‟s liability under the indemnity it gave ALS. Accordingly the mechanism
of the appointment of the consultant to conduct the assessment is how the parties
agreed that that liability would be determined.
[53] I consider that clause 8.13 of the SSD requires HRL‟s continued co-operation in
relation to the appointment of the environmental consultant to complete the reports
required by the SSD. In my view, even if there is not an express term, the duty to
cooperate would in fact have been implied in the circumstances of the current case.
In Secured Income Real Estate (Australia) Ltd v St Martins Investments Pty Ltd36
the High Court held that whilst there is a general duty to cooperate in the doing of
acts necessary for the performance of the contract where the acts in question are not
essential to the performance of the contract, the correct interpretation of the contract
depends on the intention of the parties. In particular, Mason J held:
“Was the respondent's rejection of the appellant's offer to take a lease
of the vacant space in the building a breach of contract? This is the
next question to be considered. Clause 1 (d), which required the
approval of the respondent purchaser to leases after the date of
35 Ibid at [17] - [19].
36 (1979) 144 CLR 596.
-- 15 of 22 --
16
execution of the contract, provided that its approval should not be
capriciously or arbitrarily withheld. This sub-clause dealt with the
grant of leases before the respondent became the owner, when the
appellant was granting leases of parts of the building, subject to the
approval of the respondent.
But it is common ground that the contract imposed an implied
obligation on each party to do all that was reasonably necessary to
secure performance of the contract. As Lord Blackburn said in
Mackay v. Dick:
“as a general rule… where in a written contract it appears that
both parties have agreed that something shall be done, which
cannot effectually be done unless both concur in doing it, the
construction of the contract is that each agrees to do all that is
necessary to be done on his part for the carrying out of that
thing, though there may be no express words to that effect.‟
It is not to be thought that this rule of construction is confined to the
imposition of an obligation on one contracting party to co-operate in
doing all that is necessary to be done for the performance by the
other party of his obligations under the contract. As Griffith C.J. said
in Butt v. M'Donald:
„It is a general rule applicable to every contract that each party
agrees, by implication, to do all such things as are necessary on
his part to enable the other party to have the benefit of the
contract.‟
It is easy to imply a duty to co-operate in the doing of acts which are
necessary to the performance by the parties or by one of the parties
of fundamental obligations under the contract. It is not quite so easy
to make the implication when the acts in question are necessary to
entitle the other contracting party to a benefit under the contract but
are not essential to the performance of that party's obligations and are
not fundamental to the contract. Then the question arises whether the
contract imposes a duty to co-operate on the first party or whether it
leaves him at liberty to decide for himself whether the acts shall be
done, even if the consequence of his decision is to disentitle the other
party to a benefit. In such a case, the correct interpretation of the
contract depends, as it seems to me, not so much on the application
of the general rule of construction as on the intention of the parties as
manifested by the contract itself.”37)
[54] I consider that the intention of the parties, as manifested by both the express and
implied terms of the contact, was to do all such things as are necessary to enable the
other party to have the benefit of the contract.
[55] I consider that HRL was therefore under a continuing obligation in relation to the
requirement to do all things necessary in relation to the engagement of the
37 Ibid at 607-608.
-- 16 of 22 --
17
environmental consultant to prepare the environmental assessments and to answer
the questions which were required to be obtained pursuant to the SSD.
[56] In my view, HRL has failed in that continuing obligation. It is clear that the parties
have each paid $496,393.58 to date for the environmental assessments. It is also
clear, however, that a vital assessment contemplated by the SSD in relation to what
environmental issues existed at Closing has still not been obtained. URS has given
an estimate of $15,000 to $20,000 for the further report and has indicated that such
a report can be obtained in space of weeks. Given that the reports to date do not
address the issue as to what environmental issues existed at Closing and as HRL has
taken the view that the determination of all liability hinges on such a report, I do not
consider that it can be sensibly argued that a further report is not required in the
circumstances.
[57] URS has now agreed that it will accept an appointment and has indicated the terms
of such an appointment which are now agreeable to them. That was communicated
to HRL by letter on 27 July 2012,38 but HRL argued it would not enter into such an
agreement on the basis of a concern about an apprehension of bias on the part of
URS. As I have indicated, I do not consider there is any evidence of actual bias,
which is the relevant test,
[58] Furthermore I do not consider that the continued opposition to the appointment of
URS pursuant to the terms of the Agreement when the basis of the communications
between ALS and URS was explained both orally and in writing by the legal
practitioners for the relevant partiers was reasonable in the circumstances. I
consider full and proper explanations were offered.
[59] The history of negotiations between the parties is set out in the submissions of
Counsel for the plaintiff. Having considered that background and the refusal to
jointly engage URS following the letter of 27 July 2012, even after those
explanations were offered, satisfies me that HRL is in breach of the terms of Clause
8.13 of the SSD.
[60] The next question which arises is whether the Court should grant the injunction
sought so as to compel HRL to enter into the agreement with ALS and URS in the
terms proposed. In his text on equitable remedies,39 Spry states “Hence, although
prima facie a prohibitory or mandatory injunction, as may be necessary, may issue
for the enforcement of contractual rights and it is prima facie sufficient that the
plaintiff is able to show a continuing or impending breach on the part of the
defendant, it must be accepted that the court may, in its discretion, according to well
established principles, confine the plaintiff to such rights to damages or other
remedies as he may have.”40
[61] The 2009 Victorian Court of Appeal decision of 1144 Nepean Highway v Abnote
Australasia Pty Ltd (Nepean Highway)41 involved the granting of an injunction to
compel a landlord to execute an agreement appointing an expert. It was held that
by adopting the particular form of the contract, the parties had agreed that they
38 Above n 17.
39 Spry, ICF The Principles of Equitable Remedies: Specific Performance, Injunctions, Rectification
and Equitable Damages 8th ed Thompson Reuters Australia Limited, 2010.
40 Ibid, p 574.
41 [2009] VSCA 308.
-- 17 of 22 --
18
would be bound by the selection of the expert by the President of the Law Society,
provided that the expert‟s terms were not unreasonable. It was held that the
requirement that the terms of the appointment be reasonable arose by necessary
implication from the silence of the agreement. The Court held:
“29. The silence of the agreement on the question of the expert‟s
terms gives rise to a necessary implication that his
appointment will be on terms which are reasonable having
regard to the qualifications he has, the function he is to
perform, the expertise he is to bring to his task and the
responsibility which he is to undertake. Without such a term,
this agreement would be unworkable. The fact that, on the
evidence, the content of such a term can be readily
ascertained lends weight to a conclusion that it should be
implied and answers any contention that it is uncertain. The
fact that the agreement is silent as to the expert‟s terms
indicates the necessity for the implication of the term
suggested. It is reasonable and equitable. It is necessary for
the effective operation of the agreement. On the evidence, it
is so obvious that it „goes without saying‟. It is capable of
being clearly expressed and it contradicts no express term of
the contract.
…
“32. The evidence before Pagone J was convincing that terms of
the type sought by Mr Nunns were probably universally
required by persons prepared to act as experts in the
resolution of disputes of the nature with which this case is
concerned. Not only did Dr Croft and Mr Heaton seek
similar terms, but terms to like or similar effect were to be
found in a number of draft agreements exhibited to an
affidavit filed by the tenant. These draft agreements,
designed for use by experts such as those with which we are
presently concerned, were published by organisations such
as the Australian Commercial Dispute Centre, the London
Court of International Arbitration, the Academy of Experts
(London) and the Rail Industry Dispute Resolution (UK).
No evidence contradicting that affidavit was filed and
counsel for the landlord conceded, in argument, that he was
unable to put forward any examples of experts being
retained on other than terms similar to those sought by Mr
Nunns.”42
[62] Similarly, in this case there is silence as to the terms of the appointment of the
environmental consultant. The further affidavit of Mr Douglas sworn 13 August
201243 attaches an email from legal counsel for URS confirming that “URS can
agree to undertake the work in question provided that it is done so under the terms
42 Ibid at [29]-[32].
43 Above n 29.
-- 18 of 22 --
19
as attached to our 9 August 2012 letter.”44 That Reply was in response to an email
as follows:
“Can you please confirm that URS‟ current position is that it will
undertake the further work, on the terms attached to your letter of 9
august 2012, in the event that:
(a) The Court orders URS to do so; or
(b) If the Court orders that the terms and conditions attached to
your letter of 9 August 2012 are reasonable.”45
[63] In oral argument on 13 August 2012, Counsel for HRL argued for the first time that
condition 4(1)(a) in the terms of agreement attached to the letter of 9 August is
“unreasonable and otherwise inappropriate”46 and that accordingly HRL refuses to
be party to those terms of agreement. In particular, Counsel argued that the decision
in Nepean Highway indicated that the terms sought to be included in that case were
“universally required”. I note, however, that the report of the case indicates the
terms were “probably universally required” and the Court also indicated that
Counsel in that case had been “unable to put forward any examples of experts being
retained on other than terms similar to those sought by Mr Nunns”.47 The Court
considered that the terms of engagement were on any view of the evidence
reasonable.
[64] I accept that there is no evidence before me that a clause such as that sought by URS
at clause 4(1)(a) is typical. It may or may not appear in some terms of engagement
but I do not consider that such a term is common or „typical‟. The defendant argues
therefore that because the term is not „typical‟ it is thereby necessarily not a
„reasonable term‟. I do not accept that proposition. Many terms in the circumstances
of a particular case could indeed be unique but also reasonable in the circumstances.
[65] In the present case Counsel for HRL has not indicated why Clause 4(1)(a) is
unreasonable. I accept that he has established that the term is not typical. I do not
consider, however, that there can be any real argument that the first part of the
clause is in any way unreasonable. It simply states that ALS and HRL
“acknowledge that the Consultant (URS) and ALS have a continuing commercial
relationship outside the terms of this Agreement”. I do not understand why that
statement of fact is in any way contentious or why HRL cannot acknowledge that as
a fact.
[66] It is clear that ALS is a testing laboratory. That much is indeed obvious by its name.
Furthermore it is clear that the reports which have already been prepared by URS
recite many instances of samples taken by URS being delivered to ALS‟s laboratory
for analysis.48 The evidence also indicates that in the eight reports which have been
prepared to date HRL have not objected to the fact that ALS will test the samples
sent by URS. HRL have known about that arrangement since at least early 2008 and
have not objected to that commercial relationship.
44 Exhibit CLD-2 to Affidavit of CL Douglas (Above n 29).
45 Exhibit CLD-1 to Affidavit of DL Douglas, (Above n 29).
46 T1-44 line 13
47 Above n 42 at [32].
48 See, for example, the May 2009 Report at 3.3.3 and 4 September 2009 Report at 5. 4.
-- 19 of 22 --
20
[67] The evidence before me in this case also indicates that HRL is aware of the
litigation involving ALS and URS in the Victorian Supreme Court whereby ALS
has been joined as a concurrent wrongdoer by URS in litigation involving the Port
of Melbourne Corporation. That must be further evidence of the fact that HRL
indeed „knows‟ that there is a continuing commercial relationship between the
parties In my view clause 4(1)(a) simply requires HRL to acknowledge what they
have actually accepted as a fact to date.
[68] The real contention must arise in relation to the final words of the clause which
provide “and that relationship is not a conflict of interest.” In this regard, Counsel
for the plaintiff has made it clear that the acknowledgment is limited and relates to
the final report only as follows;
“So the proposition is that the parties - the parties have a continuing
commercial relationship outside the terms of the agreement. This
agreement is only about the narrow appointment for the purpose of the
report, this final report, and that relationship is not a conflict of interest.
Now, what is important to take first in mind is what is an acknowledgment
that there isn‟t a conflict of interest. It is an acknowledgment that by virtue
of an engagement there isn‟t a breach of fiduciary obligation. Now, there is
no suggestion that as between our learned friend‟s client, HRL and URS
there is some other engagement of URS that might create ant kind of
relevant conflict. The conflict would be between, on the one hand, this
engagement which is ....to prepare a report that expressly has to be-and it is
acknowledged has to be honest and independent.
That‟s one engagement. The other engagement, what would create a
conflict of interest is, that URS engages ALS in carrying out testing
services. Would the continuing nature of doing that cause any conflict with
this engagement? Would there be any breach of confidentiality involved in
that? One would expect not. There is no reason to anticipate that would be
so”49
[69] Counsel for the plaintiff also drew my attention to correspondence from the
solicitors for ALS to HRL dated 21 March 2012,50 which set out the history of
communications with respect to URS and the issue of a conflict of interest. In
particular, in that letter specific reference was made by the solicitors for ALS to a
letter from URS dated 14 August 2009 in which URS “sought to have both our
clients indicate that no actual conflict existed which arose or any perceived conflict
was waived in respect of our clients request to have URS carry out, under a separate
contract, additional works.” The letter also noted that in its response dated 31
August 2009 the then solicitors for HRL clearly indicated that they wished to
continue with the continued engagement of URS. The letter from the solicitors for
ALS concluded;
“So notwithstanding receipt of the 14 August 2009 letter from URS, your
client proceeded, jointly with our client, to engage URS to undertake Final
49 T1-65, lines 40-57, to T1-66, lines 1-6.
50 Above n 1 (Vol 2) at p 445.
-- 20 of 22 --
21
Report Addendum for the Phase II Environmental Site Assessment dated 4
September 2009(and subsequent reports).
It is difficult to identify a basis for concern on your client‟s behalf given
the above background and our client‟s position remains that there is simply
no basis to assert that some conflict of interest arises by reason of the 14
August 2009 correspondence that precludes URS from further involvement
in conducting environmental assessments as proposed by our client.”51
[70] That is further evidence therefore that HRL has been well aware of the continuing
commercial relationship between ALS and URS and has not objected to that
relationship. In terms of the specific objection to the clause 4(1)(a) which is now
made, Counsel for HRL simply indicated that “I don‟t have instructions to accept
that as a proposition of fact, but if the order sort (sic) by my learned friend is made,
my client would be ordered to make that acknowledgment”.52 Counsel also
indicated “My client doesn‟t want to sign up to that”.53 When specifically asked
what the „disadvantage‟ to the defendant was, Counsel replied:
“If the order was made it would be forced to acknowledge the
nonexistence of a conflict of interest in circumstances where in point
of fact it doesn‟t acknowledge that.”54
[71] In my view, the defendant has not established why, in the circumstances of this
case, such a clause as the one proposed is in fact unreasonable. He argues,
essentially, that it „might‟ affect his client in some way. I have not been shown any
particular prejudice to the defendant if such a clause was inserted or how it could
possibly affect the defendant.
[72] Counsel for HRL has also indicated that clause 4(1)(a) is the only basis for his
objection that there is an unreasonable term in the Agreement.
[73] In Nepean Highway, the Court held that:
“By imposing an injunction on the landlord, Pagone J ensured that
the dispute resolution procedure would be carried out to its
conclusion. It was an appropriate exercise of the court‟s equitable
auxiliary jurisdiction in aid of legal rights.”55
[74] There is no doubt that “a court of equity must exercise its discretion according to
established principles, so that relief is refused if in all circumstances it would be
unjust for the court to intervene.”56 In the present case I consider that it is an
appropriate exercise of the Court‟s equitable jurisdiction to ensure the continued
engagement of URS to complete the task the SSD contemplated, which is to answer
the questions posed in relation to the environmental issue which existed at Closing.
51 Ibid at p 446.
52 T1-54 at lines 30-33.
53 T1-55 at line 19.
54 T1-55 at lines 36-39.
55 Above n 42 at [39].
56 Above n 39 at p 574.
-- 21 of 22 --
22
[75] I consider that the terms proposed have not been shown by the defendant to be
unreasonable and that, in the circumstances of this case, the justice of the case
requires the engagement of URS by ALS and HRL jointly on those terms. In my
view the proposed clause is reasonable in the circumstances and it is also necessary
for the effective operation of the agreement.
[76] There will therefore be an order in terms set out in Exhibit CLD-28 to the affidavit
of Christopher Lee Douglas sworn 10 August 2012 and that the report identify
whether –
(a) the properties referred to in paragraph 7 of the Further
Amended statement of claim were „free from all
environmental contamination, including without limitation,
any patent or latent contamination of the Environment soil,
sub-soil, ground water or surface waters within or adjacent
to such premises‟ as at 17 October 2007; and
(b) materials, „including without limitation, effluence leachate,
emissions or hazardous materials generated on or emitted
from any of‟ the properties referred to in paragraph 7 of the
Further Amended Statement of Claim by 17 October 2007
„have caused or will cause in whole or in part any
contamination of the Environment‟
[77] I will hear from counsel as to the exact terms of the order and as to costs.
-- 22 of 22 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2012/236