BHW Solutions Pty Ltd v Altitude Constructions Pty Ltd [2012] QSC 214
SUPREME COURT OF QUEENSLAND
CITATION: BHW Solutions Pty Ltd v Altitude Constructions Pty Ltd
[2012] QSC 214
PARTIES: BHW SOLUTIONS PTY LTD
ACN 148 187 400
(applicant)
v
ALTITUDE CONSTRUCTIONS PTY LTD
ACN 121 441 861
(respondent)
FILE NO/S: BS 6396 of 2012
DIVISION: Trial Division
PROCEEDING: Originating Application
DELIVERED ON: 16 August 2012
DELIVERED AT: Brisbane
HEARING DATE: 6 August 2012
JUDGE: Mullins J
ORDER: 1. Pursuant to s 19 of the Building and Construction
Industry Payments Act 2004 judgment is entered for
the applicant against the respondent in the amount of
$1,400,136.38 (inclusive of interest of $37,855.93).
2. The respondent must pay the applicant’s costs of the
application to be assessed.
CATCHWORDS: CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – REMUNERATION –
STATUTORY REGULATION OF ENTITLEMENT TO
AND RECOVERY OF PROGRESS PAYMENTS –
PAYMENT CLAIMS – where subcontractor served payment
claims on the contractor for the purpose of s 17 Building and
Construction Industry Payments Act 2004 (Qld) – where the
respondent did not serve payment schedules in response to
the payment claims – where the contractual provision
required a progress claim to be accompanied by a statutory
declaration as a precondition to payment – whether absence
of declaration invalidated payment claims
Building and Construction Industry Payments Act 2004, s 12,
s 13, s 17, s 18, s 19, s 99, s 100
John Holland Pty Ltd v Coastal Dredging & Construction
Pty Limited [2012] QCA 150, followed
-- 1 of 6 --
2
Reed Construction (Qld) Pty Ltd v Martinek Holdings Pty Ltd
[2011] 1 Qd R 28, considered
Spankie v James Trowse Constructions Pty Limited [2010]
QCA 355, considered
Vis Constructions Ltd v Cockburn [2006] QSC 416,
considered
COUNSEL: MH Hindman for the applicant
FG Forde for the respondent
SOLICITORS: Schweikert Harris for the applicant
JHK Legal for the respondent
[1] The applicant applies for judgment against the respondent in the amount of
$1,362,280.45 pursuant to s 19 of the Building and Construction Industry Payments
Act 2004 (the Act). The respondent opposes the application on the basis that the
applicant failed to fulfil the contractual condition precedent to any entitlement to
payment and was therefore entitled neither to any progress payment under the
contracts nor to serve a payment claim on the respondent.
[2] It is common ground that there are two construction contracts between the parties
for the supply of temporary accommodation units, described as the Moranbah
project contract and the Glenden project contract. The applicant served on the
respondent what it claims to be a payment claim for the purpose of s 17 of the Act
in relation to each contract. The respondent did not serve payment schedules in
response to either payment claim. Under s 18(5) of the Act the respondent is liable
to pay the claimed amount to the applicant for the progress payments to which the
payment claims relate. That is why to resist summary judgment based on s 19 of
the Act the respondent submits the payment claims are invalid.
The Act
[3] There are many factual disputes between the parties, but this application proceeds
on the basis that, irrespective of the resolution of those factual disputes, the
applicant seeks to show that, if the construction contracts incorporated the standard
terms and conditions which the respondent claims applied, the applicant is entitled
under the Act to receive payment of the progress payments that are the subject of
the payment claims.
[4] The nature of the scheme under the Act is relevantly described in Spankie v James
Trowse Constructions Pty Limited [2010] QCA 355 at [9]-[12]. As s 100 of the Act
makes clear, progress payments recovered under the statutory entitlement conferred
by the Act are provisional in the sense that recovery of those progress payments
does not affect any civil proceedings arising under the construction contract.
[5] Section 12 of the Act provides:
―12. From each reference date under a construction contract, a
person is entitled to a progress payment if the person has
undertaken to carry out construction work, or supply related
goods and services, under the contract.‖
-- 2 of 6 --
3
[6] The definition of ―reference date‖ is found in schedule 2 to the Act:
―reference date, under a construction contract, means-
(a) a date stated in, or worked out under, the contract as the date
on which a claim for a progress payment may be made for
construction work carried out or undertaken to be carried
out, or related goods and services supplied or undertaken to
be supplied, under the contract; or
(b) if the contract does not provide for the matter—
(i) the last day of the named month in which the
construction work was first carried out, or the related
goods and services were first supplied, under the
contract; and
(ii) the last day of each later named month.‖
[7] Section 17 of the Act relevantly provides:
―17 Payment claims
(1) A person mentioned in section 12 who is or who claims to
be entitled to a progress payment (the claimant) may serve a
payment claim on the person who, under the construction
contract concerned, is or may be liable to make the payment
(the respondent).
(2) A payment claim—
(a) must identify the construction work or related goods
and services to which the progress payment relates;
and
(b) must state the amount of the progress payment that the
claimant claims to be payable (the claimed amount);
and
(c) must state that it is made under this Act.‖
The construction contracts
[8] Clause 7 of the respondent’s standard terms and conditions deals with payment and
permits the subcontractor to claim payment progressively on the 25th day of each
month which is described in the clause as a ―progress claim.‖ The respondent relies
on clause 7(d) of its standard terms and conditions:
―(d) A progress claim, including a final progress claim, shall:
(i) contain details of the actual cost of work carried out
by the Subcontractor up to and including the date the
Subcontractor submits its claim;
(ii) provide copies of tax invoices for any outlays
claimed; and
(iii) a declaration in the form in Schedule Three, each of
which shall be a precondition to payment and if not
provided or incomplete or false the Contractor may
withhold payment until received.‖
[9] Although clause 7(d) is described as nonsensical by the applicant, it is clear enough
that the progress claim must comply with each of the requirements in subparagraphs
(i), (ii) and (iii), with the words at the conclusion of subparagraph (iii) intended to
-- 3 of 6 --
4
apply to each of the requirements. To comply with subparagraph (iii), the progress
claim must be accompanied by the specified declaration. The declaration in what
appears to be schedule 3 incorporates a statement to the effect that all employees,
workers, subcontractors and suppliers who at any time have carried out work or
supplied goods under the subcontract have been paid in full all that is owed to them
by the applicant up to the date of the submission by the applicant of the relevant
payment claim. It is common ground that when the applicant made the payment
claim under each of the contracts, it was not accompanied by the declaration
referred to in clause 7(d)(iii).
Whether each payment claim is invalid
[10] The only aspect of each of the payment claims relied on by the respondent to assert
they are invalid is the failure of the applicant to provide the declaration required by
clause 7(d)(iii) of the respondent’s terms and conditions.
[11] The respondent relies on the summary of Jones J of the components of the statutory
scheme set out in Vis Constructions Pty Ltd v Cockburn [2006] QSC 416 at [30]:
―Firstly, there must be a contract for construction work (as defined
by s 10 of BCIPA) or for the supply of related goods. Secondly, the
claimant must be entitled to a progress payment under the contract.
Thirdly, the payment claim must be made on a person who is or may
be liable to make payment under the same construction contract.‖
[12] The respondent submits that the second requirement set out in the above quote has
not been met as, in the absence of a declaration, the applicant has no entitlement to a
progress payment under the contract. (Although the respondent submits that
support for that interpretation is found in s 13 of the Act which specifies that the
amount of a progress payment to which a person is entitled in relation to a
construction contract is the amount calculated under the contract or, if the contract
does not provide for the matter, the amount calculated on the basis of the value of
construction work carried out or undertaken to be carried out under the contract,
s 13 is concerned with calculation of the amount of the progress payment rather than
entitlement.) The respondent submits that nothing in the Act overrides the
contractual provisions: Reed Construction (Qld) Pty Ltd v Martinek Holdings Pty
Ltd [2011] 1 Qd R 28 at [24].
[13] The applicant relies on the approach in John Holland Pty Ltd v Coastal Dredging &
Construction Pty Limited [2012] QCA 150 where the issue was the effect of clauses
in the subcontract requiring a statutory declaration to be included in the payment
claim as to payments having been made to subcontractors and employed workers
and providing for a warranty by the subcontractor that, if the payment claim did not
comply with the conditions (including the provision of the statutory declaration), the
payment claim was void and the reference date for the purposes of the Act would
become the same day on the following month. The subcontractor had not provided
the relevant statutory declaration with the payment claim. The contractor sought to
rely on the subcontractor’s warranty to withhold payment on the basis there was no
reference date for the payment claim.
-- 4 of 6 --
5
[14] Fraser JA who delivered the leading judgment in John Holland explained the nature
of the statutory entitlement to progress claims conferred by s 12 of the Act at [18]:
―Section 12 confers upon a person who has undertaken to carry out
construction work a statutory entitlement to recover a progress
payment from each ―reference date under a construction contract‖,
which is defined to mean, so far as is presently relevant, ―a date
stated in, or worked out under, the contract as the date on which a
claim for a progress payment may be made for construction work
carried out or undertaken to be carried out, ...under the contract...‖.
Accordingly, the contractual provisions to which reference may be
made for the purpose of ascertaining the ―reference date‖ are those
which state, or provide for the working out of, the date on which a
progress payment claim ―may be made‖. The latter expression refers
to an entitlement to make a progress claim. It does not comprehend
reference to warranties which concern the form and content of
progress claims or the consequences of breaching warranties about
the form and content of progress claims.‖
[15] Fraser JA concluded at [21] that if the impugned clauses operated to defer what
would have been the subcontractor’s statutory entitlement to a progress payment
from the reference date ascertained in accordance with the Act, they would be void
under s 99 of the Act. It is also relevant to refer to the statement made by Fraser JA
at [19]:
Bearing in mind the statutory object and the role of s 12 and the
definition of ―reference date‖ in giving effect to that object, those
provisions are incapable of justifying an implication that the date
upon which the statutory entitlement to a progress payment accrues
may be qualified by contractual provisions other than those captured
by the unambiguous terms of the definition of ―reference date‖.
[16] The analysis of the operation of the provisions of the Act in conferring the statutory
entitlement to a progress payment in John Holland shows that the words of s 12 of
the Act are important. The summary of the effect of s 12 in Vis for the purpose of
that case should not be used to put a gloss on the words and meaning of s 12 for the
purpose of determining in other cases the relationship between the statutory
entitlement and relevant contractual provisions.
[17] Clause 7(d) of the respondent’s standard terms and conditions is concerned with
how to make a ―progress claim‖ under the contract, and is not concerned with
regulating a payment claim under the Act. Section 17 of the Act regulates the form
of a payment claim under the Act for the purpose of pursuing the statutory
entitlement to a progress payment from each reference date under the construction
contract where the claimant has carried out construction work under the contract.
There is no requirement in the Act for payment claims to be accompanied by such a
declaration. The applicant’s payment claims in this matter are therefore not invalid
in the absence of a declaration under clause 7(d)(iii).
Orders
-- 5 of 6 --
6
[18] There is no impediment to summary judgment for debt being given for the applicant
against the respondent for the outstanding amount under the payment claims of
$1,362,380.45 in accordance with s 19 of the Act. Interest was calculated in the
schedule attached to the applicant’s submissions up to 6 August 2012. at 10 per cent
per annum. I will extend the calculation of interest to the date of giving judgment.
That results in a total amount of interest of $37,855.93.
[19] The orders which I make are:
1. Pursuant to s 19 of the Building and Construction Industry Payments Act
2004 judgment is entered for the applicant against the respondent in the
amount of $1,400,136.38 (inclusive of interest of $37,855.93).
2. The respondent must pay the applicant’s costs of the application to be
assessed.
-- 6 of 6 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2012/214