Dart Holdings Pty Ltd v Total Concept Group Pty Ltd [2012] QSC 158
SUPREME COURT OF QUEENSLAND
CITATION: Dart Holdings Pty Ltd v Total Concept Group Pty Ltd and
Ors [2012] QSC 158
PARTIES: DART HOLDINGS PTY LTD TRADING AS A DART &
CO (ABN 85 009 848 122)
(Plaintiff)
v
TOTAL CONCEPT GROUP PTY LTD
(ACN 114 572 486)
(First Defendant)
and
RICS DISPUTE RESOLUTION SERVICE
(ABN 18 089 973 067)
(Second Defendant)
and
ALAN STAPLETON
(Third Defendant)
FILE NO/S: BS 4631 of 2010
DIVISION: Trial Division
PROCEEDING: Trial
ORIGINATING
COURT: Supreme Court
DELIVERED ON: 22 June 2012
DELIVERED AT: Brisbane
HEARING DATE: 13 and 14 June 2012
JUDGE: McMurdo J
ORDER: It is declared that:
1. When entering into the contract pleaded in
paragraph 3 of the statement of claim and paragraph
4 of the defence, the first defendant was not the
holder of a contractor’s licence of an appropriate
class under the Queensland Building Services
Authority Act 1991 (Qld) in order to carry out the
building work described in cl 13.30 of the Schedule to
that contract.
2. At no time was the first defendant the holder of a
licence under that Act entitling it to perform the work
the subject of its claimed variation 50 as pleaded in
-- 1 of 15 --
2
paragraph 6(b)(iv) of the statement of claim.
3. The first defendant entered into the Contract in
breach of s 42(1) of that Act.
4. The first defendant had no contractual entitlement to
be paid any consideration for any of the work the
subject of the Contract (as originally made or as
varied).
5. The first defendant was not entitled to make a
payment claim under the Building and Construction
Industry Payments Act 2004 (Qld) for any of the work
the subject of the Contract (as originally made or as
varied).
CATCHWORDS: CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – THE CONTRACT –
LEGALITY – where the plaintiff engaged the first defendant
as a subcontractor to supply and install certain items, largely
made of glass – where an adjudicator decided that the
plaintiff was to pay the first defendant the money it claimed
under the Building and Construction Industry Payments Act
2004 – where the plaintiff challenges that adjudication on the
basis that the Contact was not enforceable because it required
the first defendant to perform work for which it was not duly
licensed under the Queensland Building Services Authority
Act 1991 – whether the first defendant was duly licensed to
perform the work it was required to perform by the Contract
CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – REMUNERATION –
RECOVERY – where the plaintiff claims that if any part of
the work which the first defendant was required to perform
under the Contact was work for which it was unlicensed, then
none of the Contact is enforceable by it and it is unable to
claim the lump sum price of the Contact – where the first
defendant relies upon the severability clause of the Contract
to sever the clause requiring the work to be performed for
which it is unlicensed – whether the clause requiring the first
defendant to perform work for which it is unlicensed can be
severed from the remainder of the Contract, allowing it to
recover the moneys owing to it for the work lawfully
performed under its licence
Building and Construction Industry Payments Act 2004 (Qld)
s 31
Queensland Building Services Authority Act 1991 (Qld),s 42
Queensland Building Services Authority Regulation 2003
(Qld)
The Australian Concise Oxford Dictionary
The Macquarie Dictionary
Cant Contracting Pty Ltd v Casella [2007] 2 Qd R 13, cited
-- 2 of 15 --
3
GEC Marconi Systems Pty Ltd v BHP Information
Technology Pty Ltd [2003] FCA 50, cited
Hopkins v Prescott 4 CB 578, cited
McFarlane v Daniell (1938) 38 SR (NSW) 337, considered
Sutton v Zullo Enterprises Pty Ltd [2000] 2 Qd R 196,
considered
COUNSEL: G Beacham for the applicant
M H Hindman for the first respondent
No appearance from the second respondent
No appearance from the third respondent
SOLICITORS: Holding Redlich for the applicant
Saal and Associates for the first respondent
[1] The plaintiff was engaged to perform some of the construction of a building on the
corner of Turbot and George Streets, Brisbane. In turn, the plaintiff engaged the
first defendant (which I will call the defendant) as its subcontractor. The plaintiff
and the defendant thereby made a contract in September 2008, under which the
defendant was to supply and install certain items, largely made of glass, for a lump
sum of $1,377,410 (“the Contract”).
[2] On 2 February 2010, the defendant served on the plaintiff a payment claim under
the Building and Construction Industry Payments Act 2004 (Qld) (“the Payments
Act”). The amount claimed was $208,767.74 which was calculated by adding to the
lump sum price an amount of $816,049 for variations and subtracting an amount for
retentions of $55,211.89 and the amount of previous payments made to the
defendant which totalled $1,963,474.90. This left a balance of $189,788.86 which
became the amount claimed with the addition of GST.
[3] The plaintiff delivered a payment schedule which disputed the whole of this claim.
The defendant made an adjudication application to the second defendant and the
third defendant became the adjudicator. On 23 March 2010, the adjudicator decided
that the plaintiff should pay the defendant the sum of $141,174.44 inclusive of GST.
[4] On 7 April 2010, the defendant obtained a judgment under s 31 of the Payments Act
in reliance upon that adjudication decision. On 7 May 2010, the plaintiff
commenced these proceedings, seeking a declaration that the adjudicator’s decision
was void and orders for the setting aside of his decision and the repayment of any
sums paid by the plaintiff by reason of it. The plaintiff did not prosecute these
proceedings until about May 2011. By the defendant’s counterclaim, the issues now
extend beyond the question raised by the plaintiff, that is to say the validity of the
adjudication.
[5] The adjudication is challenged by the plaintiff upon the basis that the Contract was
not enforceable, at least by the defendant, because the Contract required the
defendant to perform building work for which it was not duly licensed under the
Queensland Building Services Authority Act 1991 (Qld) (“the QBSA Act”). In
Sutton v Zullo Enterprises Pty Ltd, McPherson JA, with whom Jones J agreed, held
that a contract made in contravention of s 42(1) is unenforceable, at least by the
-- 3 of 15 --
4
person not appropriately licensed.1 If the Contract is unenforceable by the
defendant for that reason, it follows that the Payments Act did not apply and the
adjudicator’s decision was made beyond power and should be given no effect: Cant
Contracting Pty Ltd v Casella.2
[6] At all material times the defendant held two licences under the QBSA Act. It held a
“Building-low Rise” licence and a “Carpentry” licence. Before the adjudicator, the
plaintiff argued that neither licence authorised the performance of all of the work
required by the Contract. The adjudicator upheld that argument as to the Carpentry
licence but decided that the work was authorised under the other licence. The
defendant now concedes that the adjudicator was wrong in that respect. It relies
only upon its Carpentry licence.
[7] With the consent of the parties, it was ordered that there be a preliminary trial of the
questions defined by certain paragraphs of the statement of claim and the defence.
This judgment determines those questions. They concern whether any item of work
required by the Contract was not within the scope of what was authorised by the
defendant’s Carpentry licence.
[8] The Contract required the defendant to supply and install various items within the
ground floor and the three levels above it within this building. The work was
described in cl 13 of a schedule to the Contract, where the relevant items, that is to
say the work for which the defendant was unlicensed, were described as follows:
“13. Shopfronts, Windows, Doors & Screens Specific
Requirements
The extent of the subcontract work shall include, but not
limited to the following:
…
13.3 Allow for the supply and installation of aluminium framed
& glazed window and door systems, including all necessary
angles, fixings and fittings, flashings, sills and sub-sills, sub-
frames, trimmings, caulking and sealing on completion to
the specified areas.
…
13.19 Frameless glazed automatic sliding doors to Entry Foyer
including supply and installation of auto door operators.
…
13.21 Glazed shopfronts to George Street ground level tenancies.
…
13.23 Full height glazing to Ground Floor light box.
1 [2000] 2 Qd R 196 at 204 [6], 208 [24].
2 [2007] 2 Qd R 13.
-- 4 of 15 --
5
13.24 Glazed shopfronts to Turbot Street ground level foyer and
café area.
13.25 Full height framed glazed windows and doors to Level 3
terrace.
…
13.28 Level 1 Food Hall multi-fold doors with glazing over with
S/S patch fittings.
…
13.30 Glazing to George and Turbot Street steel frame awnings
(frame by others).
…
13.32 All other aluminium framed and glazed windows, doors and
shopfronts as may be documented in the tender documents.
…”
[9] The plaintiff also alleges that some of the work within the variations, as claimed by
the defendant, was outside the defendant’s licence. Those items, as described in the
statement of claim,3 are as follows:
“(i) Variation 114 – additional costs for smoke baffles, brackets
where window extend under the slab and additional brackets
to support mullions at top of windows;
(ii) Variation 106 – reinforcing mullions to create structural
glazed element to support jamb between window frame and
column;
(iii) Variation 49 – changing window to frameless structural
glazing and stiffening aluminium mullions to create
structural window support frame;
(iv) Variation 50 – supply and install glass awning including
design, engineering, fabrication, etc;
(v) Variation 21 – changing window to frameless structural
glazing; and
(vi) Variation 121 – supply and install smoke baffles, custom
window head and sill brackets and additional engineering
and drafting to design support for the stiffened window
mullions.”
[10] Section 42 of the QBSA Act provides, in part, as follows:
3 Paragraph 6(b).
-- 5 of 15 --
6
“(1) A person must not carry out, or undertake to carry out,
building work unless that person holds a contractor’s licence
of the appropriate class under this Act.”
The term “building work” is defined within Schedule 2 to the QBSA Act as
including:
“(a) the erection or construction of a building; …”
Section 30 of the QBSA Act provides, in part, as follows:
“(1) A licence (a contractor’s licence) may be issued authorising
the licensee –
(a) to carry out all classes of building work; or
(b) to carry out building work of 1 or more classes
specified in the licence.
(2) Contractors’ licences are to be divided into classes by
regulation –
(a) according to whether the licence relates to all
classes of building work or is limited to a specified
class or specified classes of building work; and
(b) if the licence is limited to a specified class, or
specified classes, of building work – according to
the class or classes of building work to which it
relates.
(3) A contractor’s licence may be issued for any class of
licence.”
[11] The Queensland Building Services Authority Regulation 2003 (Qld) provides for
some 56 classes of licence and the necessary qualifications for the various classes.
A Carpentry licence is the subject of Part 16 of Schedule 2 of Division 3 of the
Regulation, which at the relevant time, provided in part as follows:
“Part 16 Carpentry licence
1 Licence class
Carpentry
2 Scope of work
(1) Construct and erect timber and steel wall framing
and roof structures.
(2) Construct and erect non-load bearing internal
partition walls.
(3) Install windows and doors including framing.
-- 6 of 15 --
7
(4) Erect ceiling and subfloor framing.
(5) Install timber and sheet flooring.
(6) Install exterior cladding, fascias and soffits.
(7) Install metal roofing.
(8) Construct timber stairs.
(9) Fix internal linings, panelling and mouldings.
(10) Install door and window locks and furniture.
(11) Restore and renovate doors, windows and frames.
(12) Install fitments.
(13) Concreting to simple forms, including install
formwork, reinforcement and concrete.
(14) Erect and strip formwork, including slip form and
jump form formwork.
(15) Incidental work of another class.
3 Technical qualifications
Any 1 of the following –
(a) successful completion of either of the following
courses –
(i) apprenticeship in carpentry;
(ii) Certificate III in Carpentry BCG30203;
(b) successful completion of a course the authority
considers is at least equivalent to a course mentioned
in paragraph (a);
(c) a recognition certificate as a qualified carpenter;
(d) a qualification or statement of attainment of required
competency issued by an approved authority for the
class of licence.”
[12] The plaintiff argues that this work was instead within the scope of that licence
described as a “Glass, Glazing and Aluminium licence” (which I will call a “glazing
licence”), for which Part 34 within the Regulation provides as follows:
“Part 34 Glass, glazing and aluminium
1 Licence class
Glass, glazing and aluminium.
2 Scope of work
(1) Glaze and reglaze buildings.
(2) Fabricate and install windows and doors in
buildings.
(3) Fabricate and install shower screens and metal
framed sliding wardrobe doors whether mirrored or
otherwise.
-- 7 of 15 --
8
(4) Fabricate and install security screens and doors.
(5) Fabricate, install and reglaze commercial glazing
including shopfronts, windows, doors, toughened
glass assemblies, aluminium glazing systems, curtain
walling systems, balustrading and watertight glazing.
(6) Fabricate and install fixed mirrors.
(7) Fabricate, install and reglaze architectural engineered
glazing including suspended and overhead glazing
and structural balustrading.
(8) Construct and repair leadlight panels.
(9) Apply film patterns and designs to glass.
(10) Incidental work of another class.
3 Technical qualifications
Any 1 of the following -
(a) successful completion of either of the following
courses -
(i) an apprenticeship in glass and glazing;
(ii) Certificate III in Glass and Glazing
LMF30602;
(b) successful completion of a course the authority
considers is at least equivalent to a course mentioned
in paragraph (a);
(c) a recognition certificate as a qualified glazier;
(d) a qualification or statement of attainment of required
competency issued by an approved authority for the
class of licence.”
[13] The plaintiff does not suggest that the respective scopes of work for these licences
are mutually exclusive. It concedes that in some circumstances, certain work might
be authorised by each licence. But it argues that the terms of Part 34 are relevant in
the interpretation of Part 16 and that they tend to confirm what the plaintiff suggests
is the natural meaning of words and expressions within Part 16.
[14] It is necessary then to consider each item of work against the scope of works
authorised by a Carpentry licence. Before doing so, however, I will discuss some
more general points raised by the submissions.
[15] The first is the defendant’s argument that it is not what was required by the
Contract, but what was the work actually performed by the defendant, which is
relevant in the comparison of that work with the scope of what was permitted by the
licence. This is said to follow from s 42(3) of the QBSA Act, which provides that
subject to s 42(4), a person who carries out building work in contravention of
s 42(1) is not entitled to any monetary or other consideration for doing so. Section
42(4) provides for the recovery of some limited remuneration for the performance
of unlicensed building work, although in no case more than the amount agreed to, or
purportedly agreed to, between the parties. The defendant is correct in submitting
-- 8 of 15 --
9
that it is the work actually performed which is relevant for the purposes of s 42(3)
and s 42(4). But the present question, as defined by the pleadings, is whether the
Contract required the performance of work for which the defendant was not
licensed. If the plaintiff can prove that the defendant, by the Contract, undertook to
perform unlicensed work so that the Contract was unenforceable, then it would
follow that the Payments Act did not apply and the adjudication was of no effect.
[16] Therefore, the present enquiry concerns the work which was agreed to be performed
rather than that which was performed. The difference, however, does not appear to
be significant. The defendant’s submissions refer to an item of work within the
Contract which was subsequently deleted by the agreement of the parties.4 The
respective arguments did not address that item of work against the Carpentry
licence. It is irrelevant because the Contract, as varied, did not require it.
Otherwise, the defendant’s submissions did not identify any significant difference
between the work agreed to be performed (including by a variation to the Contract)
and that which was performed. The evidence of the work as performed, and in
particular the photographic evidence of that work as completed, is therefore
relevant.
[17] The next of these general issues is the relevance of the prescribed qualifications for
a Carpentry licence and the evidence of the content of the course prescribed in
Part 16 as a “Certificate III in Carpentry BCG30208”. The defendant led evidence
as to the content of that course in order to demonstrate that a person who had
completed the course would have received adequate training to perform the work in
question. I accept that because Part 16 must be read as a whole, there is some
relevance in its requirements for technical qualifications to the question of the scope
of work authorised by the licence. However, I do not accept that this should affect
the meaning of words or expressions within the 15 items which define the scope of
the work, if those words have a clear meaning.
[18] The evidence as to these courses was provided within the affidavits of two
witnesses and the oral evidence of a third witness, who is Mr Boyle, the Executive
Manager of Regulatory and Resolution Services at the Queensland Building
Services Authority. One affidavit was by an apprentice carpenter, who said that
during his training he received instruction in and had been required to demonstrate
knowledge of and competency in the various types of glass and their suitability for
various applications, the manufacturing and installation of doors and windows, the
glazing of windows and doors either before or after installation, the safe and proper
handling of glass and approved and correct methods for glazing windows, doors,
shopfronts and frameless glass installations. The second affidavit was sworn by
Mr McGee, a director of the defendant. He completed an apprenticeship in
carpentry in 1996 and obtained a Certificate IV in Building in 2001. He said that
his training equipped him with a knowledge of various glass types, procedures for
the safe and correct handling of glass and glass products and correct techniques for
the glazing of windows, doors, shopfronts and other frameless glass assemblies. I
admitted each of those affidavits over the objection of the plaintiff. Neither
deponent was required for cross-examination. Mr Boyle qualified as a carpenter
under what he said was an equivalent to a Certificate III, before obtaining further
qualifications. Through him the defendant tendered a description of the relevant
4 Being the work described in paragraph 4(d) of the statement of claim and originally required by
cl 13.22 of the Contract.
-- 9 of 15 --
10
course of training (which became exhibit 4). Amongst the “core (essential) units”,
there is a subject of “install and replace windows and doors” but nothing else of
apparent relevance here. Amongst the elective units, there are subjects including
that of “glaze/reglaze residential windows and doors”.
[19] From this evidence, I accept that those who have the necessary qualification for a
carpentry licence would have some knowledge about working with glass. But this
evidence does not establish that completion of this work, regardless of the particular
elective subjects studied, would qualify a person to perform the work which is in
question. Ultimately then, this evidence as to the content of the required training,
has no impact upon the outcome.
[20] The defendant attempted to lead evidence as to the opinion of the Queensland
Building Services Authority as to the scope of work authorised by this licence. I
upheld the objection to that evidence. The proper interpretation of this regulation is
a question of law.
[21] There was also some evidence as to the meaning of certain terms, as appearing in
Part 16. This evidence was led in an attempt to prove some meaning in the building
and construction industry of these terms. The defendant hoped that by aggregating
the testimony of several witnesses in this respect, some general industry usage could
be established. Over the plaintiff’s objection, I admitted the evidence for that
purpose. However, ultimately the evidence did not appear to demonstrate that any
particular term had a meaning different from that which someone outside the
industry would attribute to it.
[22] In essence, the plaintiff’s argument is that the various items of work appearing in
Part 16 under the heading “Scope of work” must be understood in the context that
this is a licence for carpenters. Part 16 describes it as a licence for “carpentry” and
the prescribed qualifications are expressed by reference to “carpentry” and
“carpenter”. The plaintiff refers to these Dictionary definitions:
“Carpenter … A person skilled in woodwork, esp of a structural
kind.
Carpentry … The work or occupation of a carpenter, timber-work
constructed by a carpenter.”5
To that could be added this definition from the Macquarie Dictionary:
“Carpenter … A person who erects and fixes the wooden parts, etc,
in the building of houses and other structures.”
So it is said that the essence of carpentry is working with wood, whereas the work
required of the defendant involved glass and other materials. At one point the
submission seemed to go so far as to say that the various items of work described in
Part 16 had to involve working with wood. Of course that could not affect at least
-- 10 of 15 --
11
the express authority to “construct and erect … steel wall framing” and to “install
metal roofing”. Ultimately the plaintiff argued for a less restrictive interpretation of
Part 16, which was that the items of work within a carpentry licence had to be
interpreted as work of a kind within the ordinary notion of carpentry. Therefore, it
was said that the installation of large glass panels, as a curtain wall should not be
understood as falling within the item “(6) install exterior cladding …”.
[23] That submission became more difficult to develop when considering the item
“(3) Install windows and doors including framing”. As counsel for the plaintiff
accepted, there is no apparent reason to limit the licensee to the installation of
windows in which the glass is surrounded by timber as distinct from, for example,
aluminium. Similarly, the “framing” referred to in that item is unlikely to have been
intended to be only timber framing.
[24] The plaintiff then relied upon the scope of work defined for a glazing licence,
pointing to differences in some of the terms which there appear. In particular, it
referred to the expressions “shopfronts”, “aluminium glazing systems”, “curtain
walling systems”, “architectural engineered glazing” and “suspended and overhead
glazing”. It was said that the inclusion of these items within the glazing licence, in
contrast to their non-inclusion for the carpentry licence, shows that the work within
these items was not within the intended scope of a carpentry licence.
[25] However, there is another difference between the respective definitions of the scope
of work. The holder of a glazing licence is entitled not only to “install” certain
items, such as windows and doors, but to “fabricate” them. But within the scope of
work for a carpentry licence, there is a deliberate distinction which is made between
“install” and “construct”. The holder of that licence is entitled to construct things
such as roof structures and timber stairs but not to construct or fabricate windows or
other pieces of glazing.
[26] I turn then to the items of work within the original contract which the plaintiff says
were outside the scope of a carpentry licence. The first is that in cl 13.3, which is
the installation of aluminium frames and glazed window and door systems and
associated work. I conclude that this is within item (3) in the scope of work for a
carpentry licence.
[27] Similarly the installation of glass doors, required by cl 13.19, is within (3). In the
same way the installation of the doors to the entry foyer (cl 13.19) and the glazed
shopfronts to the George Street frontage (cl 13.21) are within item (3). The
shopfronts are windows although the glass cannot be opened.
[28] The ground floor light box (cl 13.23) is a fitment and therefore within (12) of the
defined scope of work.
5 The Australian Concise Oxford Dictionary.
-- 11 of 15 --
12
[29] The shopfronts to the Turbot Street frontage (cl 13.24) are windows and therefore
within (3) of the scope of work.
[30] So too are the “full height framed glazed windows and doors” to the terrace on
level 3 (cl 13.25).
[31] The multi-fold doors on level 1, with the glazing above them, are doors and
windows within (3).
[32] Clause 13.32 referred to other “aluminium framed and glazed, windows, doors and
shopfronts”, which again are within (3) of the scope of works.
[33] The position with respect to the item in cl 13.30 is different. It is described as
“glazing to George and Turbot Street steel framed awnings”. This required the
defendant to fix horizontal sheets of glass which would act as awnings, extending
from outside the exterior face of the building across the footpath. The defendant
argued that they were within item (1) of the scope of work, in that they constituted
“roof structures”. They do provide shelter but I do not accept that they could be
described as part of the roof. Of course commonly the roof of a building will
extend beyond the property boundary providing shelter to the footpath. But that
does not mean that every part of a building which extends from the boundary across
the footpath is part of the roof. Further, there is an apparent difference between
“roof structures”, which are within (1), and “roofing”, which is within item (7). It is
only roofing which is metal roofing which the holder of this licence can install. The
defendant’s alternative argument was that these awnings were within item (3), on
the basis that they could be described as “windows”. That cannot be accepted.
[34] The outcome is that the defendant was licensed to perform the work required by the
original contract, save for what was required by cl 13.30. That outcome could be
described as curious, because there would appear to be no practical difference in the
nature and difficulty of that work and that of the other work required by this
contract, much of which involved the installation of even larger pieces of glazing.
But it is the result of the drafting of this regulation.
[35] I turn to the work claimed by way of variations. Variations 114 and 106 are in the
nature of work concerned with the installation of windows. The work within
variation 49 also involved the installation of windows within (3), although it was
described as a change from a window to frameless structural glazing. I accept, as
Mr Morrison of the defendant said in an affidavit, that this was something of a
misdescription in the claimed variation.6 As he explained, structural glazing is a
term referring to a glass panel secured into the window frame using tape and a type
of silicone rather than inserting a glass panel into a pocket or channel within the
frame. This work was within (3). Variation 21 was within (3). Similarly variation
121 was work in the nature of the installation of windows.
[36] Variation 50 was for a change to the George Street glass awning. That awning, as
originally designed, was deleted and was replaced by one of a different design,
which was installed under, rather than on top of, the steel frame. This work was not
within the Carpentry licence.
6 His supplementary affidavit, paragraph 4(c)(i).
-- 12 of 15 --
13
[37] It follows that the defendant breached s 42(1) by undertaking to perform the work of
the installation of the glass awning, both within the original contract and by
variation 50. The next of the issues to be determined at this stage of the
proceedings is the impact of that breach upon the Contract, and in particular, upon
the defendant’s entitlement to be paid according to the Contract.7 In reliance upon
Sutton v Zullo Enterprises Pty Ltd, the plaintiff argues that none of the Contract is
enforceable, at least by the defendant, although most of the work which the
defendant agreed to perform was work for which it was licensed. That complication
did not exist in Sutton. The defendant argues that the term which required the
performance of unlicensed work, namely the term requiring the installation of the
glass awning, is to be severed and the Contract consisting of the remaining terms is
enforceable by it. The defendant says that this follows from cl 43 of the Conditions
of Contract which provided:
“43. SEVERABILITY
If any provision in the Subcontract is voidable or unenforceable that
provision will be severed and the rest of the Subcontract will remain
in full force and effect.”
[38] According to the defendant’s argument, the only provision affected by s 42 of the
QBSA Act is cl 13.30 of the Schedule, because it was only by that provision that the
defendant undertook to perform unlicensed building work in contravention of
s 42(1). Therefore, the defendant argues, cl 43 has the effect of removing that term,
but only that term, from the Contract. On this argument, the provisions as to the
agreed lump sum price would be unaffected. Now the contribution made by the
awning to the lump sum price could be relatively small. But upon this argument, a
builder would be entitled to recover the price agreed for both licensed and
unlicensed work, regardless of their relative values.
[39] The defendant’s reliance upon cl 43, in my view, misunderstands the effect of
s 42(1) of the QBSA Act. Where s 42(1) is engaged, it is not simply the promise by
which the builder undertakes to carry out unlicensed work which is affected. Rather
it is the contract by which that promise is made. As McPherson JA said in Sutton,
in such a case, s 42(1) “prohibits the very process of formation of a contract”.8 The
consequence of this statutory prohibition is that a court will not enforce the
contract, at least in favour of the party which contravened the prohibition.9 As the
agreed price here was a lump sum price, it could not be said that there was a distinct
agreement for the performance of and payment for the awning. Therefore nothing
could be recovered pursuant to the Contract without enforcing that term which
required a payment to be made for work which included unlicensed work. The
parties did not within this Contract or otherwise agree to apportion the
consideration. Therefore, this was an entire contract in that complete performance
by one party was a condition precedent to payment or counter performance by the
other.10 This then is a case of the kind described by Jordan CJ in McFarlane v
Daniell as follows:
“If, according to the terms of a contract, a party cannot be called
upon to pay money except upon the performance by the other party
7 Being the question raised by paragraph 14(a) and (b) of the statement of claim.
8 [2000] 2 Qd R 196 at 203 [4].
9 Ibid.
10 See the discussion of entire contracts in GEC Marconi Systems Pty Ltd v BHP Information
Technology Pty Ltd [2003] FCA 50 at [702]-[706]; (2003) 128 FCR 1 at 164-165 per Finn J.
-- 13 of 15 --
14
of the whole consideration, then if any part of the consideration is
illegal the money cannot be recovered: Hopkins v Prescott.”11
Consequently s 42(1) affects the Contract as a whole, rendering it unenforceable at
least by the defendant. More particularly, s 42(1) has the consequence of precluding
the enforcement of such provision or provisions of the Contract which would
otherwise entitle the defendant to payment.
[40] It follows that cl 43 of the Contract cannot assist the defendant because it would
extend to those provisions for payment, and the end point of the defendant’s
argument would be that the severance to be effected by cl 43 would remove also
those provisions. Therefore, the effect of s 42(1) in this case is, as it was in Sutton v
Zullo Enterprises, to deny the builder a contractual entitlement to payment. It may
be noted that although the entire contractual entitlement to payment is lost, the
impact of s 42(3) and (4) is not as extensive in a practical sense. That is because the
limitations as to the amount which can be claimed, consistently with s 42(4), applies
only to the building work for which the contractor did not have the appropriate
licence. They would not affect the defendant’s entitlement to be paid, upon a
restitutionary basis, for the work which it lawfully performed under its licence.
[41] At this point it is convenient to set out paragraph 14 of the statement of claim:
“14. In the premises:
(a) the entry in to the Contract by the first respondent
was in breach of s 42 of the QBSA Act;
(b) the first respondent had:
(i) no entitlement to be paid any monetary or
other consideration under the Contract;
(ii) only a statutory entitlement to be
remunerated in accordance with s 42(4) of
the QBSA Act in respect of such work;
(c) the first respondent was not entitled to make a
payment claim under the Payments Act because:
(i) it had no entitlement to be paid any
monetary or other consideration pursuant
to a construction contract, within the
meaning of the Payments Act;
(ii) the statutory entitlement to remuneration,
pursuant to s 42(4) of the QBSA Act, did
not give rise to, or create an entitlement to
make a payment claim under the Payments
Act.”
[42] It follows that the plaintiff has proved the allegations in paragraph 14(a) and (b)(i).
But it has not proved the allegation in paragraph 14(b)(ii) because, as discussed
11 (1938) 38 SR (NSW) 337 at 346, citing Hopkins v Prescott 4 CB 578 at 595-6.
-- 14 of 15 --
15
above at [41], it has a restitutionary entitlement, unaffected by s 42(4), for most of
the items of work which together are described in the statement of claim as “such
work”. It also follows, from Cant Contracting Pty Ltd v Casella,12 that the plaintiff
has proved the allegation in paragraph 14(c)(i). The allegation in paragraph
14(c)(ii) is one of law and is correctly stated. It follows from these reasons that the
defendant had no entitlement to make a payment claim under the Payments Act.
[43] What I have said determines the questions for separate determination. I should note
that amongst the remaining issues in these proceedings, are the discretionary
defences pleaded within paragraphs 32 through 47 of the Defence. Without
determining those issues, the Court could not grant all of the relief sought by the
plaintiff.
[44] The appropriate relief is to make declarations as to the contravention of s 42(1) and
its impact upon the Contract and a right to be paid under the Payments Act.
Accordingly, there will be declarations as follows:
1. When entering into the contract pleaded in paragraph 3 of the statement of
claim and paragraph 4 of the defence, the first defendant was not the holder
of a contractor’s licence of an appropriate class under the Queensland
Building Services Authority Act 1991 (Qld) in order to carry out the building
work described in cl 13.30 of the Schedule to that contract.
2. At no time was the first defendant the holder of a licence under that Act
entitling it to perform the work the subject of its claimed variation 50 as
pleaded in paragraph 6(b)(iv) of the statement of claim.
3. The first defendant entered into the Contract in breach of s 42(1) of that Act.
4. The first defendant had no contractual entitlement to be paid any
consideration for any of the work the subject of the Contract (as originally
made or as varied).
5. The first defendant was not entitled to make a payment claim under the
Building and Construction Industry Payments Act 2004 (Qld) for any of the
work the subject of the Contract (as originally made or as varied).
12 Supra.
-- 15 of 15 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2012/158