Australian Timber & Trusses Pty Ltd v T&M Buckley Pty Ltd [2012] QSC 110
SUPREME COURT OF QUEENSLAND
CITATION: Australian Timber & Trusses Pty Ltd v T&M Buckley Pty Ltd
[2012] QSC 110
PARTIES: AUSTRALIAN TIMBER & TRUSSES PTY LTD
(ACN 010 275 902)
(Plaintiff)
v
T & M BUCKLEY PTY LTD (ACN 010 052 043)
(First Defendant)
and
TERENCE BUCKLEY
(Second Defendant)
FILE NO/S: BS 5318 of 2009
DIVISION: Trial Division
PROCEEDING: Trial
ORIGINATING
COURT: Supreme Court of Queensland
DELIVERED ON: 15 May 2012
DELIVERED AT: Brisbane
HEARING DATE: 30 January – 3 February, 10 February 2012
JUDGE: McMurdo J
ORDER: (1) The first defendant to pay the plaintiff $605,881.20
(2) The second defendant to pay the plaintiff $360, 384.74
(3) The counterclaim is dismissed
(4) It is declared that the plaintiff is entitled to a charge
over any real property of the first defendant to secure the
debt under the plaintiff’s judgement against the first
defendant
CATCHWORDS: CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – REMUNERATION –
RECOVERY – where the parties entered a contract whereby
the plaintiff would manufacture and supply timber trusses and
frames to the first defendant for housing – where the first
defendant gave notice to the plaintiff that further deliveries of
trusses and frames should not be made – where the plaintiff
claims the total of unpaid invoices together with associated
storage and handling costs as damages for breach of contract
-- 1 of 33 --
2
– whether the first defendant is liable to pay the unpaid
invoices and associated costs of the plaintiff
CONTRACTS – GENERAL CONTRACTUAL
PRINCIPLES – DISCHARGE, BREACH AND DEFENCES
TO ACTION FOR BREACH – REPUDIATION AND NON-
PERFORMANCE – REPUDIATION – WHAT AMOUNTS
TO REPUDIATION – where the first defendant claims that it
did not repudiate the contracts but merely „suspended‟
performance of them – where the first defendant argues that
whilst the head contract was suspended so too were the
contracts between itself and the plaintiff – where the
contracts between the first defendant and plaintiff did not
contain such a provision – whether the first defendant‟s
actions amount to repudiation of the contract between it and
the plaintiff
CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – THE CONTRACT –
LEGALITY – s42, Queensland Building Services Authority
Act 1991 - where the first defendant claims that in performing
the contract for the supply of timber, the plaintiff carried out
work which involved the preparation of a plan for the
performance of building work, for which it was unlicensed
under s42 of the Act – where the timber provided was
accompanied by a plan indicating how to install the trusses
and frames – where the plaintiff charged no or a minimal
amount for the preparation of the plan - where the first
defendant claims that in accordance with s 42(3) of the Act, it
should not be liable to pay for unlicensed building work
performed by the plaintiff – whether the contracts for the
supply of timber required the plaintiff to provide an
instalment plan or layout for which it is now seeking
consideration or whether the plaintiff seeks payment only for
the timber trusses and frames
DAMAGES – GENERAL PRINCIPLES – MITIGATION
OF DAMAGES – PLAINTIFF‟S DUTY TO MITIGATE -
where first defendant claims that plaintiff failed to mitigate
its losses for undelivered timber and frames– where the first
defendant claims that the plaintiff should have attempted to
sell the excess materials to the owner or financier of the
building site or some other related party – whether the
plaintiff failed to mitigate losses by failing to find another
buyer for the undelivered trusses and frames
SALE OF GOODS – CONDITIONS AND WARRANTIES –
IMPLIED CONDITIONS AND WARRANTIES –
QUALITY OR FITNESS FOR PARTICULAR PURPOSE –
FITNESS FOR PARTICULAR PURPOSE - where the first
defendant counter - claims that the plaintiff supplied
defective timber trusses and frames – where the first
defendant used the trusses and frames in the construction of a
-- 2 of 33 --
3
residential development which it claims it will now be
required to rectify by the governing authority – where
evidence indicated that the problems may have been caused
by incorrect installation of the trusses and frames - whether it
is more probable than not that the defects were caused by
defective timber supplied by the plaintiff rather than poor
installation of the trusses and frames
GUARANTEE AND INDEMNITY – THE CONTRACT OF
GUARANTEE – CONSTRUCTION AND EFFECT –
EXTENT OF LIABILITY - where the second defendant
signed documents entitled „Guarantor Acknowledgement‟
and „Guarantee‟ four years prior to the signing of the
contracts for the supply of timber - where the documents
signed expressly referred to a guarantee for all amounts
owing by the second defendant to the plaintiff – where
nothing was said to have occurred between the signing of the
guarantee and the entry into the supply contracts which
constitutes a withdrawal of the guarantor‟s offer - whether the
second defendant is liable for any of the amounts claimed by
the plaintiff including for some or all of the damages claimed
Queensland Building Services Authority Act 1991 (Qld), s42
Queensland Building Services Authority Regulation 2003
(Qld), s5, Schedule 2, Parts 11, 12, 13
Ankar Pty Ltd v National Westminster Finance (Aust) Ltd
(1987) 162 CLR 549, cited
Chan v Cresdon Pty Ltd (1989) 168 CLR 242, cited
Cook’s Construction Pty Ltd v SFS007.298.633 Pty Ltd
(formerly trading as Stork Food Systems Australasia Pty Ltd)
[2009] QCA 75, considered
Fitzgerald v F J Leonhardt Pty Limited (1997) 189 CLR 215,
considered
Hoenig v Isaacs [1952] 2 All ER 176, considered
Lemura v Coppola [1960] Qd R 308, cited
Murphy Corporation Ltd v Acumen Design & Development
(Queensland) Pty Ltd & Anor (1995) 11 BCL 274, cited
Puerto Galera Pty Ltd v J M Kelly (Project Builders) Pty Ltd
[2008] QSC 356, considered
Sutton v Zullo Enterprises Pty Ltd [2000] 2 Qd R 196,
considered
COUNSEL: HS Howe for the plaintiff
SB Whitten for the defendants
-- 3 of 33 --
4
SOLICITORS: McLaughlin Lawyers for the plaintiff
Mills Oakley for the defendants
[1] The plaintiff manufactures timber trusses and frames. The first defendant is a
builder. In June 2008, they agreed that the plaintiff would manufacture and supply
to the first defendant trusses and frames for the first defendant‟s construction of
houses in a development at Wakerley.
[2] The supply of these items commenced in September 2008 and continued through to
the end of February 2009, before the plaintiff received a facsimile transmission from
the first defendant, dated 12 March 2009, to the effect that its contract with the
owner had been suspended and that it was unable to carry out any further work.
There were no further deliveries by the plaintiff to the site after then. As at that
date, there were unpaid invoices, for timber delivered during February 2009,
totalling $280,455.05. The plaintiff sues for that sum as the unpaid price for goods
sold and delivered.
[3] Also at that date, the plaintiff had manufactured, but not delivered, further trusses
and frames for which the agreed price was, in total, $158,763. The plaintiff says
that it was unable to sell those items to another buyer and it claims that amount,
together with associated handling and storage of $32,284.83, from the first
defendant as damages for breach of contract.
[4] The second defendant is sued for each of those amounts as a guarantor, under a
document which he signed in 2004. He says that this does not make him liable for
any of the amounts claimed, or at least for the damages claim.
[5] The first defendant denies that it is liable to the plaintiff upon several grounds. It
says that the plaintiff‟s claim is precluded entirely by s 42 of the Queensland
Building Services Authority Act 1991 (Qld) (“the QBSAA”). This is because the
contract or contracts for the supply of the timber also required the plaintiff to supply
a document described as a “layout for both frames and trusses … for use by the
subcontractors”. It is argued that this involved the preparation of a plan for the
performance of building work, thereby constituting “building work” for the
purposes of s 42, and for which the plaintiff did not hold a licence under the
QBSAA.
[6] The damages claim is also defended upon the basis that the plaintiff failed to
mitigate its loss, by not finding another buyer for the undelivered timber.
[7] There is a counterclaim by the first defendant, which complains about the quality of
the trusses which were delivered. It is claimed that the hip trusses, as were installed
in many houses across this development, have an excessive deflection at some
points where the roof extends beyond the walls of a house. This defect, the first
defendant says, has caused it to suffer damage of the order of $432,245.
-- 4 of 33 --
5
[8] In addition, there is a counterclaim for another $624,409.89, which was the total
paid by the first defendant to the plaintiff for the trusses and frames which were
delivered to the site. Again, the point here is that the plaintiff was not entitled to
any payment by reason of s 42. Therefore, the first defendant alleges, it is entitled
to repayment because it made the payments under the mistaken belief that the
plaintiff was entitled to them.
The contracts
[9] In 2004, the plaintiff received a document described as “Application for
Commercial Credit Account” which was signed by the second defendant. The
document was in the terms of the plaintiff‟s then standard form. It set out a number
of conditions which were to apply to any sale to the applicant. It included a page
headed “Guarantor Acknowledgement” and a further page headed “Guarantee”,
each signed by the second defendant. In the “Guarantee”, the second defendant was
named as the guarantor and the first defendant was named as the principal debtor.
The first defendant was also named within other parts of this document, with a
specification also of its business name and address and of the second defendant‟s
name as its director. That part of the document which was to be completed by the
buyer was signed by the second defendant as “the applicant”, from which the
defendants now argue that no part of the document was signed by the first
defendant, and there was no person other than the second defendant who sent it to
the plaintiff. Therefore, it is contended, the document could not have bound the
second defendant as a guarantor to the 2008 transaction.
[10] However, read as a whole, this document clearly enough identified the proposed
buyer as the first defendant and the second defendant as its guarantor.
[11] The Guarantee was expressed to be in consideration of the plaintiff having “agreed
to supply and/or continue to supply to [the first defendant] with goods and/or
services from time to time …”. It contained terms which included the following
promises by the guarantor:
“1. To guarantee to you the payment by the debtor for all goods
and/or services as you may have hitherto supplied or as you
may hereafter supply from time to time at his request and
notwithstanding that we shall not have notice of any neglect
or omission on the debtor‟s part to pay for such goods
and/or services according to the terms agreed on between
you and him.
2. This guarantee shall be a continuing guarantee to you for the
whole of the debtor‟s indebtedness or liability to you in
respect of goods and/or services supplied or to be supplied
to the debtor as aforesaid or upon any other account
howsoever or whenever arising.
…
-- 5 of 33 --
6
8. This guarantee shall remain foot:
(a) Until you shall have received one hundred cents in
the dollar of all money interest costs and damages
as provided in paragraphs 1 and 2 hereof; and
(b) For at least six months and one day after the
payment of all money interest costs and damages
and in particular we do hereby jointly and severally
indemnify you against any preference claim or
claims paid or payable in the liquidation or
bankruptcy (as the case may be) of the debtor and
irrespective of whether it was subsequently proven
that you were not legally obliged to disgorge such
preference claim/s as aforesaid.
…
12. That the proper law of this guarantee and indemnity
shall be the law of the State of Queensland and we
agree and declare that any proceedings in respect of
any cause of action arising hereunder may be
instituted, heard and determined by a court of
competent jurisdiction at Brisbane and that such
court shall possess territorial jurisdiction to hear
and determine any such proceedings.”
On the page under the heading “Guarantor Acknowledgement”, the second
defendant acknowledged, amongst other things, that “this is a guarantee and
indemnity for unlimited amounts … [relating] to all amounts owing in any way by
the Debtor to Australian Timber & Trusses Pty Ltd now and in the future”.
[12] The same document included the terms upon which the plaintiff would permit the
first defendant to purchase goods upon credit and provided that those terms should
prevail over any terms otherwise governing a subsequent sale.
[13] The plaintiff‟s case, at least upon one view of it, was pleaded as based upon a
contract made by these documents in 2004. The defendants pleaded that the
relevant trusses and frames were instead the subject of contracts made in 2008.
Accordingly, they argued, the 2004 documents were irrelevant and, in particular, the
guarantee could not have secured the sums which are now claimed by the plaintiff.
[14] It is true that the plaintiff became obliged to supply the relevant goods, and the first
defendant became obliged to pay for them, by a contract or contracts made in June
2008. But that is not to say that the guarantee was inapplicable. At least insofar as
payment of the price of timber sold and delivered was concerned, the second
defendant had unambiguously agreed to guarantee what was payable under such a
future transaction. On one view, he became contractually bound in 2004, in
consideration of the plaintiff‟s agreement to supply the first defendant upon credit.
-- 6 of 33 --
7
Alternatively, by signing the guarantee, he offered to be bound as a guarantor to any
subsequent contract for the sale of timber to the first defendant. Nothing is said to
have occurred between 2004 and 2008 which would be indicative of a withdrawal of
that offer by the second defendant. Thus, when the first defendant submitted three
pages to the plaintiff in June 2008, asking it to supply the items which were there
described for the prices which were there specified, there was at the same time a
standing offer from the second defendant to guarantee the first defendant‟s
performance of that transaction. So when the plaintiff signed and returned those
documents on 18 June 2008, all three parties became bound. Either way then, the
second defendant was bound as a guarantor for the 2008 transaction.
[15] What was sent to the plaintiff in 2008 consisted of three pages, each in the form of a
purchase order. Each page dealt with a different stage of the development which
was being constructed by the first defendant. For stage one, consisting of 26
houses, the plaintiff was to provide certain items “for the lump sum of …
$627,664.40 (including GST)”. The lump sum price for stage two (25 houses) was
$559,207 and for stage three (21 houses) it was $463,128.60. The orders provided
for different periods for the supply of these items. But otherwise the pages were in
identical terms. They provided that the trusses and frames were to be made
according to certain specifications and drawings, none of which, it is clear, had been
or was to be prepared by the plaintiff. The houses had been designed by architects
and engineers.
[16] Each document provided that the plaintiff was to:
“Supply and deliver all H2-F blue pine treated timber frame and
trusses requirements as per plans and specification including but not
limited to roof trusses, triple grips, soffit battens, girder brackets,
bottom chord binders, wall brackets, valley boards, speed bracing,
trimmers, roof struts, pre-nailed frames, ply bracing, bulkhead timber
framing, connection plates, noggings, temporary bracing, stud straps,
bearers, joists, flooring, posts (90X90), supply a laminated A3 layout
for both frames and trusses to site for use by the subcontractors,
copy to be supplied to [the First Defendant‟s] office approx 5 days
before delivery onsite.”
(Emphasis added)
It also included these terms:
“• All workmanship & materials used on this project to be to
the satisfaction of the client and Shailer Constructions.
• All work to be carried out in accordance with the Head
Contract, Drawings, Specification.”
[17] The “laminated A3 layout for both frames and trusses” was to be “supplied” by the
plaintiff. It was not agreed that the plaintiff itself had to produce or, if it be
different, “prepare” that document. There was no separate price for the supply of
-- 7 of 33 --
8
this layout: rather, it was one of a number of things to be provided by the plaintiff
for the agreed lump sum price.
The s 42 questions
[18] Section 42 of the QBSAA provides, in part, as follows:
“42 Unlawful carrying out of building Work
(1) A person must not carry out, or undertake to carry
out, building work unless that person holds a
contractor‟s licence of the appropriate class under
this Act.
(3) Subject to subsection (4), a person who carries out
building work in contravention of this section is not
entitled to any monetary or other consideration for
doing so.
(4) A person is not stopped under subsection (3) from
claiming reasonable remuneration for carrying out
building work, but only if the amount claimed –
(a) is not more than the amount paid by the
person in supplying materials and labour for
carrying out the building work; and
(b) does not include allowance for any of the
following –
(i) the supply of the person‟s own
labour;
(ii) the making of a profit by the person
for carrying out the building work;
(iii) costs incurred by the person in
supplying materials and labour if, in
the circumstances, the costs were not
reasonably incurred; and
(c) is not more than any amount agreed to, or
purportedly agreed to, as the price for
carrying out the building work; and
(d) does not include any amount paid by the
person that may fairly be characterised as
being, in substance, an amount paid for the
person‟s own direct or indirect benefit.
…
-- 8 of 33 --
9
(9) A person who contravenes this section commits an
offence. Maximum penalty – 250 penalty units.”
[19] The term “building work” is defined within Schedule 2 of the QBSAA as follows:
“building work means –
(a) the erection or construction of a building; or
(b) the renovation, alteration, extension, improvement or repair
of a building; or
…
(f) the preparation of plans or specifications for the
performance of building work; or
…
but does not include work of a kind excluded by regulation from the
ambit of this definition.”
[20] The defendants argue that the “layout” was a plan for the performance of building
work and that it was “prepared” by the plaintiff. They say that accordingly the
production of this document constituted “building work” as defined in Schedule 2.
The plaintiff was not licensed to carry out that building work. Therefore, it is
argued, the plaintiff “is not entitled to any monetary or other consideration for doing
so”.1
[21] The first question is whether in producing the required layout, the plaintiff prepared
a plan for the performance of building work. The term “plan” is not defined within
the QBSAA. Several documents were provided by the plaintiff with the trusses and
frames, each of which was intended to provide some assistance for those doing the
construction work. But the three documents which became exhibit 13 were, it is
common ground, the layouts. It may be that these three documents contained more
than what the contracts required of a layout. They showed the “layout” of the
timber pieces, with each piece identified by letters and numbers. (The timber itself
was marked in the same way, enabling the carpenters to see how each was located
relative to the others.) They also contained a number of other notations and
drawings of details to assist in the installation of the trusses and frames.
[22] The question here is whether what was required by the contracts was a plan for the
performance of building work, rather than whether what was in fact supplied was
such a plan. If what was required was not a plan of the relevant kind, it would
follow that the plaintiff is not seeking any consideration for the preparation of such
a plan and the enforceability of the contract is not affected by s 42. It may be the
case that, by a course of prior dealings between the parties, the term “layout” was
1 s 42(3).
-- 9 of 33 --
10
used by them to refer to a document which contained all of the information within
what is now exhibit 13. But that point was not explored in the evidence.
[23] Unquestionably, what was required was a document which showed how the various
pieces of timber, constituting the trusses and frames, were to be installed relative to
each other. The document was “for use by the subcontractors”. The erection on site
of these trusses and frames was “building work”. Therefore a document which
depicted the location of these components, as they were to be erected, would seem
to have been a plan for the performance of building work. But this is disputed by
the plaintiff by several arguments. It argues that the layout plan lacked a necessary
element of “design”: that the design of the roof structure had instead been
undertaken by independent engineers. It is argued that the task of the “preparation”
of a plan would be more demanding than what occurred here. And it is said that
there is no category of licence which would be appropriate for this work, thereby
indicating that no licence was required.
[24] The first of those arguments sought to draw support from a statement by
Chesterman J (as he then was) in Puerto Galera Pty Ltd v J M Kelly (Project
Builders) Pty Ltd:2
“The essence of „building work‟ as defined in the dictionary to the
[QBSAA] is the erection of a structure or part of a structure, and
designing a structure for construction and, in connection therewith,
preparing tender documents and building contracts.”
The question in that case was whether the superintendent appointed under the
building contract between the parties carried out, or undertook to carry out, building
work within the meaning of s 42. The superintendent had not prepared any
document which was said to be a plan. The argument which was there considered
was whether the work of the superintendent was within the extended meaning of
“building work”, then provided by s 42(2)(a),3 by which a person could “carry out
building work” by causing a structure to be built. That case involved no
consideration of the present argument, which is whether a document apparently
meeting the description of a plan for the performance of building work, is a plan in
the relevant sense only if it has been produced by the application of skill and
originality which would characterise it as a work of design.
[25] The undisputed evidence is that these layouts are produced by the application of
certain software, provided to the plaintiff by the company which supplies the
plaintiff‟s requirements of nail plates, called MiTek Australia Ltd. This software is
applied by employees of the plaintiff who are described as detailers. A former
employee of the plaintiff, Mr Whiteley, gave evidence of his supervision of the
plaintiff‟s detailers, describing their work as “part draftsman, part quantity surveyor,
part engineer and part builder”. He said:
2 [2008] QSC 356 at [43].
3 Since repealed.
-- 10 of 33 --
11
“… What a detailer does is he gets a plan off a client, he appraises
the plan, identifies what parts of the plan are required to be
assembled and manufactured by his company he‟s working for, he
generates costings for that and some supply installation paraphernalia
that goes with it. …
You appraise the [approved] plans, you identify and quantify the
particular items that you want to take off, such as roof trusses or
frames, you then have to make sure that they‟re input into a
computer program, which is designed by engineers according to the
Australian Standard, and once you have input the plan into the
computer program you then work out the best way to achieve the aim
of the builder and the best way for installation.”4
[26] The application of the MiTek software by a detailer serves several purposes. The
work is necessary in order for the plaintiff to assess precisely what pieces of timber
will make up the frames and trusses for a particular roof, which enables the plaintiff
to calculate a price to be quoted for their manufacture.5 As Mr Whiteley explained,
the MiTek software is used also to produce all necessary drawings for the plaintiff‟s
manufacturing process. Thirdly, the same work produces a layout plan.
[27] The structural design of this roof was originally undertaken by independent
engineers. The engineering drawings, together with other material representing the
work of architects and engineers, was used by the plaintiff‟s detailer, Mr Molloy,
with the application of the MiTek software, in order to quantify precisely what
timber was required for these purchase orders. As Mr Whiteley and others
explained in evidence, the work of the detailer in this way is, in effect, to provide a
more detailed version of the plans for the roof structure. The work involves the
application of skill on the part of the detailers who are trained not only in the use of
the software, but in building construction in some respects. Accordingly, the
production of these layouts is not simply the downloading of a document prepared
by MiTek. The layout plans are produced by the plaintiff‟s employees with a
degree of skill and effort which could be well described as the “preparation” of
these documents.
[28] The plaintiff seeks to draw support from the category or categories of licence which
are relevant for the preparation of plans or specifications. The types of licences
which may be issued for the purposes of the QBSAA are prescribed by the
Queensland Building Services Authority Regulation 2003 (Qld) (“the Regulation”).
They include licences as prescribed by Parts 11, 12 and 13 of Schedule 2 to the
Regulation, under which a licensee is permitted to “prepare plans and
specifications” for buildings of certain descriptions. Such licences are described by
the Regulation as “building design – low rise”, “building design – medium rise” and
“building design – open”. That use of the term “building design” is consistent with
the way in which the expression “design work” is used within the QBSAA, where it
is defined to mean “the preparation of plans or specifications for building work”, as
well as to include “professional advice in relation to building work”. The plaintiff
4 T 1-28.
5 As explained by Mr Beverland, the plaintiff‟s CEO at T 4-80.
-- 11 of 33 --
12
says that all of this demonstrates that there is a necessary element of “design” in the
preparation of a plan for the performance of building work. However, the definition
of “design work” does not provide much assistance here because what it does is to
give a particular statutory meaning to “design work”. But the point here is whether
the word “plan”, which is not defined, is used in a way which is limited to the
product of what, in ordinary speech, is a process of design. Such a limitation is not
expressed and nor, in my view, must it be implied.
[29] The term “building work” is not defined to include the design of a building or part
of it. It is relevantly defined to mean the preparation of a document to be used by
those who will perform the construction work. There is an evident importance in
such documents being competently prepared and by appropriately qualified persons,
although such documents might not involve that quality of creativity which would
make them a design of a building.
[30] It is further submitted for the plaintiff that the preparation of these layouts does not
fall within any category of licence for which provision is made by the QBSAA or
the Regulation. The plaintiff contends that there is no type of licence which can be
issued which would authorise specifically work of this kind, as distinct from work
more generally described as the preparation of plans or specifications. If the
plaintiff requires a licence to prepare these layouts, it is said that the relevant
personnel would have to be qualified beyond the demands of their employment.
Accepting that to be the case, it does not follow that the relevant part of the
definition of “building work” should be deprived of its ordinary meaning. It cannot
be said that it is impossible for someone in the plaintiff‟s position to comply with
the QBSAA, in that it is impossible to obtain a licence which would authorise this
work. The submission does no more than identify a case for an amendment to the
Regulation, to provide a licence which is more specific to work of this kind.
[31] According to the definition of “building work” in s 2 of the QBSAA, it does not
include work of any kind which is excluded by regulation. The categories of
excluded work, as set out in s 5 of the Regulation, include work performed by an
architect, an engineer or a licensed surveyor in the course of that person‟s
professional practice. The apparent policy behind those exclusions is that other
statutory regimes should govern the work of those persons. The exclusions do not
suggest that where a building plan is prepared by someone outside those categories
of professional, the QBSAA has no effect.
[32] The layout plans can be described as a more detailed drawing of the roof structure,
as designed here by engineers. Nevertheless, they are distinct plans, serving the
particular purpose of assisting those who undertake the actual construction work.
There is evidence here, which I would accept, that it is possible for competent
builders to install these trusses and frames without the benefit of a layout. That is
not to say that the document serves no purpose.
[33] In my conclusion, the layout plan required by each contract was a plan for the
performance of building work and was prepared by the plaintiff. It follows that the
-- 12 of 33 --
13
plaintiff‟s production of the layout plan constituted “building work” as defined in
the QBSAA and as that term is used in s 42.
[34] What must then be considered is the effect of s 42 upon the plaintiff‟s entitlement to
be paid by the first defendant for the goods which it delivered, as well as its
entitlement to damages for breach of contract. As already noted, the contract did
not require the layout to be prepared by the plaintiff. Rather, it required the plaintiff
to supply a layout. It was open to the plaintiff to perform that contract by having
someone else prepare the layout. Accordingly, by these contracts the plaintiff did
not undertake to carry out (unlicensed) building work. The position here is thereby
different from that in, for example, Sutton v Zullo Enterprises Pty Ltd.6 The
performance of a contract in a manner which is illegal does not make the contract
one which was itself forbidden by the relevant statute.7
[35] What then was the effect, if any, of s 42 upon the plaintiff‟s entitlement to be paid
under these contracts? According to the defendants‟ case, the effect was drastic
indeed, for it deprived the plaintiff of a right to be paid anything at all for what was
supplied to and accepted by its buyer. Each contract provided for one lump sum
price. There was not a distinct consideration for the layout plan. According to
s 42(3), the plaintiff was not entitled to any consideration for preparing the layout
plan. By claiming the contract price, it is said, the plaintiff is claiming,
inconsistently with s 42(3), an amount for both the timber and the layout. It cannot
claim the agreed price consistently with s 42(3), the defendant argues, unless its
claim can be seen to be within s 42(4). In Cook’s Construction Pty Ltd v SFS
007.298.633 Pty Ltd (formerly trading as Stork Food Systems Australasia Pty Ltd),8
it was held that it is for the party in the position of the present to prove that the
amount of its claim is within the bounds of s 42(4). The defendants argue that the
plaintiff has failed to discharge that onus.
[36] The present case is unusual, because although the plaintiff performed unlicensed
work, in substance it does not seek to be paid for that work but rather for the goods
which it sold and delivered. The matter might be considered in this way: had the
plaintiff not delivered the layout plans, under its contract would it be entitled to be
paid the lump sum price? The answer would not be provided simply from the fact
that this was a lump sum price. Rather, it would turn upon whether, absent the
provision of the layout, the contract would have been substantially performed. The
fact that it was a lump sum contract does not mean that entire performance by the
plaintiff was a condition precedent to payment. In Hoenig v Isaacs, Denning LJ
said:9
“When a contract provides for a specific sum to be paid on
completion of specific work, the courts lean against a construction of
the contract which would deprive the contractor of any payment at
6 [2000] 2 Qd R 196.
7 Fitzgerald v F J Leonhardt Pty Limited (1997) 189 CLR 215.
8 [2009] QCA 75.
9 [1952] 2 All ER 176 at 180 as applied in Queensland in Lemura v Coppola [1960] Qd R 308 at 314;
Murphy Corporation Ltd v Acumen Design & Development (Queensland) Pty Ltd & Anor (1995) 11
BCL 274.
-- 13 of 33 --
14
all simply because there are some defects or omissions. The promise
to complete the work is, therefore, construed as a term of the
contract, but not as a condition. It is not every breach of that term
which absolves the employer from his promise to pay the price, but
only a breach which goes to the root of the contract, such as an
abandonment of the work when it is only half done. Unless the
breach does go to the root of the matter, the employer cannot resist
payment of the price. He must pay it and bring a cross-claim for the
defects and omissions, or, alternatively, set them up in diminution of
the price. The measure is the amount which the work is worth less
by reason of the defects and omissions and is usually calculated by
the cost of making them good.”
In my view, had the plaintiff not delivered the layout plans, nevertheless it would
have been entitled to payment of the price upon the doctrine of substantial
performance. A failure to supply the layout plan would have been a breach of
contract, entitling the buyer to be compensated for the loss (if any) in consequence.
But that breach would not have made the frames and trusses impossible to erect and
it would not have entitled the buyer to reject the timber and to refuse to pay for it.
The plaintiff cannot be worse off for having prepared and supplied the layout plan
than it would have been had it not done so. Accordingly, the plaintiff does not need
to rely upon its preparation of the layout in order to recover the agreed price.
Because the making of the contract was not illegal, the plaintiff can enforce the
contract as long as it does not do so in a way which relies upon an illegal act.10 That
entitlement to the price is not inconsistent with s 42 because the plaintiff is not
seeking a consideration for the illegal work, the preparation of the plan. It is
entitled to the agreed price for that which it provided legally.
[37] Alternatively, if the plaintiff is not entitled to enforce the contract, then it is entitled
to recover a quantum meruit, subject to the limitations in s 42(4). The plaintiff
argues that on this alternative basis, it would still be entitled to something which is
equivalent to the agreed price.
[38] The defendants do not suggest that the lump sum price was excessive and, more
particularly, that it was more than a reasonable amount for all of that which was to
be supplied. But they say that the remuneration (if any) claimed for the preparation
of the plan cannot be assessed by reference to s 42(4) without it being distinctly
quantified. They emphasise that according to Cook’s Construction, it is for the
plaintiff to prove that its claim accords with the limitations within s 42(4).
[39] Any cost to the plaintiff of producing the layout plans has not been quantified. It
may be inferred that there is some cost, from the fact that it involves some work for
the detailer. But very little work is involved in producing a layout plan, beyond that
of producing the drawings used by the plaintiff for its manufacture of the trusses
and frames and arriving at the other details used for its quotation of a price. The
evidence of Mr Beverland is that in calculating its quoted price, the plaintiff does
not include any charge for a layout. He explained that:
10 Fitzgerald v F J Leonhardt Pty Limited (1997) 189 CLR 215 at 220 per Dawson and Toohey JJ.
-- 14 of 33 --
15
“Is any charge made for the layout plans or----?-- No. We don‟t –
our – we don‟t charge for layouts. That‟s part of the function of – of
supplying the trusses to site or the – or the designs and the
production. The best way to describe it would be if a – if a client
came in and wanted an estimate, ie a quotation, prior to the
production of those trusses, they can actually ask for a layout of that
time and, at that point, we don‟t even - we provide them as free –
free of charge.
All right. What about in terms of the work that‟s carried out by staff
to get the layout together and so forth? You‟re paying staff to detail,
I suppose. Do you build that into the profit?-- No. That‟s a cost to
the company. The profit – the profit comes by what is actually
manufactured at the – at the jigs.”11
He adhered to that evidence in cross-examination:12
“All right. And it is your case, is it, that the production of the layouts
doesn‟t attract any charge?-- That‟s correct.
And it is your case, is it, that the production of the layouts is a cost
which has not been allowed for in any charge to T & M Buckley?--
It is a service to the client. Yes, it is a free charge.
It is a free charge?-- Mmm. Sorry, unfortunately we are not
draftsmen so we can‟t charge for these layouts.
You have a number of detailers working for you?-- Yes, we do.
And you pay them a wage?-- Yes, we do.
And so that is a labour cost to your company?-- That is a labour
cost.
And those detailers have duties which require them to design the
layouts?-- No, they design the trusses with the layouts being an
offshoot of the design.
…
The work that is produced by these detailers is the production of the
layout plans?-- It is the work that is provided – or the work that is
produced by the detailers is for the construction of the – for the
manufacture of the roof trusses and the plant.”
[40] I see no reason to reject Mr Beverland‟s evidence. The defendants suggest that I
should reject it having regard to some evidence given by another of the plaintiff‟s
witnesses, Mr Monement. His title is Administration Co-ordinator for the plaintiff,
11 T 4-62.
12 T 4-74-75.
-- 15 of 33 --
16
with responsibility for credit management, setting up accounts for customers and
issuing tax invoices. Importantly, he is not involved in fixing a price to be quoted to
a customer: that is the responsibility of Mr Beverland. In the cross-examination of
Mr Monement he was asked whether there was a margin which had been charged
for the design of the trusses to which he answered:
“There is no charge for the actual design. The design and
manufacture – I suppose there is a charge in a sense, but how you
differentiate it, I have no idea. In other words, I couldn‟t dissect it
for you.”
His evidence continued:
“You couldn‟t dissect it for me?-- No.
But consumed and hidden inside, somewhere inside those lump sums
that are in the purchase orders, are the charge by AT&T for the costs
of producing – of designing the trusses; do you agree with that
proposition?-- Well, there would be within the costing of the trusses,
there would be a component in there relevant to the use of the MiTek
programme to create the design.
And also for the labour costs?-- And the labour costs, yes.
Yes, and also, within that lump sum contract, which you accept it
contains a profit element, within that profit element there‟s also some
margin of profit allowed for the design work?-- I think we‟re going
back to the same question.
Yes or no?-- Second go around. Well, the design work is part of the
trusses, so, obviously, there would be the time of the person doing
the design, there‟d be a margin on his time.
Thank you, and just to be clear, the margin that – you‟re referring to
a profit, aren‟t you?-- That‟s right.”13
To the extent that there is an inconsistency, this evidence should not be preferred to
that of Mr Beverland. Mr Monement did not appear to be speaking from an actual
knowledge of these things but was speculating. It is Mr Beverland who does know
about the subject.
[41] It is necessary for the plaintiff to produce something which converts a more general
engineering drawing of the roof structure into a document or documents which
detail the pieces of timber to be used in the manufacture of the trusses and frames,
for the purposes of pricing and manufacture. It is very likely then that the extra cost
which is involved in the electronic production of a layout is so small as to be
immaterial to the plaintiff in arriving at its price.
13 T 4-10-12
-- 16 of 33 --
17
[42] If the plaintiff cannot enforce its contract, it must establish the reasonableness of the
amount claimed. There is no suggestion that the plaintiff enjoyed some power in
the market which enabled it to make an excessive profit. The defendants, as
experienced builders, chose to deal with the plaintiff and at these prices. I infer that
the prices were within a range of amounts which would be reasonable for that which
was supplied. As I have said, the defendants do not suggest otherwise. As appears
from Mr Beverland‟s evidence, there is no component of the plaintiff‟s claim which
is constituted by an allowance for any labour, costs or profit, for carrying out the
work constituted by producing the layout plan, of a kind within s 42(4)(b).
[43] In Cook’s Construction, the appellant argued that the contract rates provided
evidence of reasonable rates from which a reasonable remuneration for its
unlicensed work could be assessed. That argument was rejected, because those
rates were struck on the basis that the contract included building work as well as
other work and the rates must have contained some allowance for the appellant‟s
profit.14 In the present case, the plaintiff does not claim a distinct consideration for
preparation of the layout plan and nor does it seek to establish what would be a
reasonable remuneration for that work alone. In substance, the plaintiff does not
seek to be remunerated at all for the unlicensed work. Alternatively to its
contractual claim, it seeks to be paid for the goods which it supplied to the first
defendant and which were built into the houses. The claim which it makes for the
supply of those goods has not been increased for the fact that a layout plan was also
provided. Its claim accords with its quoted price and that price was calculated
without regard to any cost in producing the layout plan. Upon the preferable view
of this alternative common law claim, the plaintiff is not claiming any remuneration
for the plan so that the claim is unaffected by s 42. Alternatively, if the plaintiff‟s
claim is to be characterised as one to be remunerated for delivery of the goods
together with the production of the layout, the plaintiff has established the
reasonableness of its claim. Because nothing has been added in the quantification
of that claim for the production of the layout, it might be said that the claim for the
layout is as reasonable as it could be.
[44] It follows that the plaintiff has established its case against the first defendant for the
sum of $280,455.05.
[45] The second defendant has guaranteed the payment of such a sum. Accordingly, he
is also liable to the plaintiff for it.
[46] It is convenient at this point to discuss the impact or otherwise of s 42 upon the
balance of the plaintiff‟s claim, which is for damages for breach of contract. As I
have held, the plaintiff did not contravene s 42 by entering into the relevant contract
or contracts. Clearly it did not breach s 42 by manufacturing the frames and trusses
which were not delivered because of the advice by the first defendant that work
under its building contract had been suspended. At no time did the first defendant
say that it had resumed construction or seek the delivery of anything further from
the plaintiff. Its position was that it could not and would not perform its contract
with the plaintiff.
14 [2009] QCA 75 at [81].
-- 17 of 33 --
18
[47] The plaintiff seeks damages quantified as the agreed price together with some
storage expenses. It says that there are the amounts which must be paid to it in
order to place it in the position it would enjoy had the contract been performed.
This damages claim is not affected by s 42. The plaintiff is not thereby seeking any
monetary or other consideration for preparing the layout plan. It is seeking
compensation because it was deprived of the first defendant‟s performance of the
contract. It lost the entitlement to be paid the price, because it was entitled to the
price only upon delivery. But as I have held, under these contracts the plaintiff
would have been entitled to the price, without supplying the layout plan, upon
delivery of the timber and other items. Accordingly, in seeking damages which are
quantified in this way, the plaintiff is not making a claim which is inconsistent with
s 42. I shall return to other questions relating to this component of the plaintiff‟s
claim.
[48] At this point it is convenient to discuss the first defendant‟s counterclaim for
moneys paid, it claims, under the mistaken belief that the plaintiff was in all
respects duly licensed. The first defendant claims repayment of all which it had
paid under these contracts, a total of $624,409.89.
[49] Fundamental to this counterclaim is the premise that the plaintiff had no entitlement
to receive or retain these moneys, as a result of s 42. But just as the plaintiff has
established its entitlement to the unpaid price of goods supplied to the first
defendant, so the plaintiff is entitled to these moneys. The counterclaim therefore
fails at that threshold.
[50] In case it becomes relevant, it is appropriate to say something more about this
counterclaim. The first defendant assumed an onus to prove that it made the
payments under a mistake, which was that it believed that the plaintiff was entitled
to those payments. According to the judgment of Keane JA in Cook’s
Constructions, it was unnecessary for the first defendant to prove that mistake.
Rather, the payer has a prima facie entitlement to repayment if what was paid was
money to which the payee had no entitlement. Keane JA said:15
“[58] [M]istake on the part of the payer as to its obligation on the
payee‟s entitlement is not an essential element of the
builder‟s disentitlement to receive or retain payment or the
payer‟s reciprocal entitlement to recover. … unless the
respondent was in pari delicto with the appellant, the
respondent was entitled to recover the moneys paid to the
appellant as moneys had and received by the appellant to the
use of the respondent.”
The first defendant sought to discharge that onus by the evidence of Mr Gregory
Buckley. He said that he caused the payments to be made without any knowledge
of whether the plaintiff held any necessary licence but with the assumption that the
15 [2009] QCA 75 at [58].
-- 18 of 33 --
19
plaintiff held any necessary licence. When asked what he would have done had he
discovered prior to making the payments that the plaintiff was not “appropriately
licensed”, he said that he would not have made the payments but instead would
have sought legal advice. The first defendant‟s case is then argued upon the basis
that the legal advice would have been that the plaintiff had no entitlement to any
payment. From this it was argued that the payments were made under the mistaken
belief that the plaintiff was entitled to them.
[51] I would be prepared to accept Mr Buckley‟s evidence. It is inherently likely that the
payments were made with a belief on the part of the relevant person representing the
first defendant company that they were payments to which the plaintiff was entitled.
The plaintiff argues, however, that Gregory Buckley‟s belief was irrelevant because
it was the second defendant, Terence Buckley, who was the sole director of the first
defendant. It says also that Gregory Buckley‟s belief was irrelevant because he had
no involvement with the making of the contract or contracts. However, his state of
mind is the relevant one because he was the person who caused the first defendant
to make the payments. Accordingly, the relevant belief on the part of the first
defendant was proved although not through the second defendant.
The plaintiff’s damages claim
[52] The first defendant argues that it did not repudiate the contracts but instead
“suspended” performance of them. It says that this was the consequence of the
suspension of its contract with the owner, a company called 57 Moss Rd Pty Ltd.
On 12 March 2009, the first defendant sent a fax to the plaintiff advising that work
for stage two and three on the project had been suspended by the Superintendent
under that contract, pursuant to its sub-clause 33.1(a)(i). That clause provided as
follows:
“The Superintendent may direct the Contractor to suspend the
carrying out of the whole or part of WUC for such time as the
Superintendent thinks fit, if the Superintendent is of the opinion that
it is necessary:
(a) because of an act, default or omission of:
i) the Superintendent, the Principal or its employees,
consultants, agents or other contractors (not being
employed by the Contractor) …”
Each of the contracts between the plaintiff and the first defendant provided as
follows:
“All work to be carried out in accordance with the Head Contract,
Drawings, Specification.”
The first defendant argues that this term had the consequence that once its contract
with the owner was suspended, so too was the contract between the present parties.
-- 19 of 33 --
20
In that fax, the second defendant purported to direct the plaintiff “to immediately
suspend the carrying out of your work, including the supply of any goods and
materials”. This argument cannot be accepted. That reference to the “Head
Contract” did not have the effect which is contended. Rather, it required that all
work, (meaning what was to be supplied by the plaintiff) was to accord with the
requirements of the Head Contract and the relevant drawings and specification. It
affected how the plaintiff‟s product was to be manufactured. It did not make the
performance of the contract between the present parties dependent on the status of
that other contract.
[53] The first defendant further argues that there was nothing on its part which evinced
any intention to not comply with the contract or contracts at all: rather, it said that it
would not perform them whilst work under the head contract was suspended. But
by that fax of 12 March 2009, the first defendant effectively said that the contracts
with the plaintiff would be performed only upon a certain event (the resumption of
work under the head contract), whereas its contracts with the plaintiff did not
contain that condition. It thereby stated an intention not to comply with these
contracts according to their terms.
[54] It further argues that there was no repudiation by it because the relevant goods were
not delivered by the plaintiff. It makes the curious submission that although, in
consequence of the suspension order, the plaintiff was to suspend “the carrying out
of [the plaintiff‟s] work, including the supply of goods and services”, that was not a
requirement of the plaintiff to desist from delivering goods already manufactured.
The notion underlying this submission seems to be that the goods could have been
supplied without being delivered. The submission must be rejected. The plaintiff
was given a purported instruction to cease performance of the contract until some
further notice. The first defendant says that the plaintiff should have delivered these
goods to the site and had they then been rejected, there would have been a
repudiation. However, that was, in effect, what the first defendant told the plaintiff
not to do.
[55] The goods in question are described in the evidence of Mr Monement. In his
statement,16 he identifies the trusses and frames which had been manufactured and
were ready for delivery as at 12 March 2009. I accept that evidence from which it is
established that the subject goods had a contractual price of, in total, $158,763. I
accept also Mr Monement‟s evidence that the plaintiff incurred handling and storage
fees of $23,814.45 and that it incurred a further handling fee for certain material
which had to be returned to the supplier, in consequence of the fax of 12 March
2009, in the amount of $8,470.38. I find also that the plaintiff disposed of these
trusses and frames in the first few months of 2011. It simply sent them away to be
dumped and received no payment for them. Subject to the submissions discussed
below, the plaintiff has established that it suffered losses totalling $191,047.83.
[56] The defendants argue that the plaintiff unreasonably failed to mitigate its loss. In
particular, they complain that the plaintiff failed to attempt to sell these trusses and
frames to the owner of this development, or to any successor or financier of the
16 Exhibit 18.
-- 20 of 33 --
21
owner. There is evidence that the owner was itself unable to complete the
development and that the site came under the control of other parties. The
defendants say that the plaintiff should have looked to sell these items to whoever it
was who was completing the project.
[57] I accept that the plaintiff did not offer to sell the items to anyone else who might
have been concerned with the completion of this project. But beyond this, the
evidence is scant in this respect. As was ultimately conceded for the defendants,17
there was no evidence to assist the Court as to whether these goods could have been
put to use on the project in the hands of someone else. There was evidence that new
builders were engaged late in 2009. But there was no attempt to prove a likelihood
that those builders would have been minded to buy these particular items from the
plaintiff and, if so, at what price. Perhaps the plaintiff did miss an opportunity to
reduce its loss in this way, although having seen Mr Beverland and Mr Monement, I
think that it is unlikely that the plaintiff was so neglectful of its own interests that it
missed that opportunity. Consistently with the absence of an evidentiary foundation
for the defendants‟ argument, nothing was put to Mr Beverland as to what steps the
plaintiff should have taken to dispose of the goods elsewhere. He was cross-
examined along the lines that the plaintiff had not told the first defendant that it was
holding these undelivered goods, as to which he responded by saying that the
plaintiff had provided the first defendant with the proposed delivery schedules
which had informed the first defendant, by 12 March 2009, that these goods were
ready. Mr Beverland was not asked to explain why the plaintiff did not attempt to
sell them to someone else concerned with the project. Indeed, the cross-examiner
chose to stop him from doing so in this passage:18
“Did you note that – and no attempt was made to dispose of these
goods beforehand?-- No.
No?-- We – can I just – can I explain further on that?
Well, I think you‟ve answered the question?-- Okay.”
[58] The cross-examination of Mr Monement, which was relevant to this point, was as
follows:19
“You didn‟t try and sell them to the owner of the project?-- I think
there might have been.
…
MR WHITTEN: Thank you, your Honour. Now, I was talking to
you yesterday about these undelivered goods?-- Yes.
Which you have complained about, and there was some discussion
after you left the room about the line of questioning that I was taking.
I just wanted to clarify with you please that it was never the case that
17 T 6-13.
18 T 4-80.
19 T 2-17-18, T 4-6.
-- 21 of 33 --
22
AT&T attempted to sell the goods to anybody else?-- I believe that
not to be the case, however, I believe that they did try to find out if
anyone was going to complete the project and possibly then on-sell
them to them, but nothing was ever forthcoming in that area.
And there was never any attempt to – there was never an offer made
to sell those goods to the project owner?-- Never.
And never an offer to sell those goods to the new builder that was on
site?-- No.
After the end of 2009?-- Not that I am aware of because I don‟t
believe we could ascertain who the new builder was.”
[59] On this state of the evidence, the possibility of a reduction in the plaintiff‟s loss by a
sale of the items to someone concerned with completing the project, remains a
matter of speculation. It cannot be concluded that the plaintiff failed to avoid or
reduce its loss by that means.
[60] It is further argued that the plaintiff should have attempted to resell the timber to its
supplier. Mr Monement‟s evidence on this possibility, and a related possibility of
selling the timber to someone else, was as follows:20
“Now, it is the case also that you didn‟t attempt to sell the timber
itself?-- No, we didn‟t.
And you made no attempt to try and sell the timber back to Hynes &
Co from which the timber was delivered?-- No, we didn‟t, because
the timber is a manufactured product and is not returnable to a
supplier. It is in an altered form to the way it arrived.
…
MR WHITTEN: Thank you. I put it to you there was a salvage
value in the timber?-- I believe there wasn‟t because it was at
disposal time in a deteriorated state so it was not salvageable and the
cost to break it down into anything if it was salvageable would make
it a nonviable proposition.
I put it to you that no attempt was made to determine whether or not
there was anybody willing to purchase the timber items
themselves?-- Obviously not, because they were in a structured
form.”
The frames and trusses had been manufactured for these particular houses. They
had no value for any other project unless, coincidentally, it had buildings of an
identical design. On the evidence, that was no more than a theoretical possibility.
20 T 4-6.
-- 22 of 33 --
23
[61] The defendants are critical of the evidence for the plaintiff as to why, ultimately, it
chose to dispose of these items. They suggest a disparity between the respective
explanations of Mr Beverland and Mr Monement. Each said that he had discussed
with the other the disposal of the items. Mr Beverland said that the
recommendation for Mr Monement to dispose of them was made for a combination
of reasons: the ongoing storage costs, the deterioration of the product and the
interference with the use of the plaintiff‟s premises from these items being stored
there.21 Mr Monement‟s evidence did not refer to a concern about the deterioration
of the items, although he did refer to the burden of the plaintiff having to
continually cover them with plastic to protect them. To that extent there is a
difference in the respective explanations, but it does not cast doubt upon the
veracity of the plaintiff‟s claim, as the defendants suggest.
[62] It was further submitted that at least the handling/storage and other costs should be
denied “for lack of any probative documentary evidence of that part of the loss”.
However, Mr Beverland explained the storage costs, and the absence of some
contemporaneous record of the plaintiff‟s estimate of the costs of storing this
material upon its own premises does not provide a basis for rejecting his evidence.22
I accept it.
[63] It was further submitted that the plaintiff failed to mitigate its loss by not telling the
defendants that these items existed and were being held by it. It is said that this
deprived the first defendant of an opportunity to do something with the goods. The
first defendant returned to the site briefly in 2009, but engaged by the financier and
for the limited purpose of installing some cladding and lining.23 But just what
would have been done in that respect was not explained. The defendants claim that
they might have sought an injunction to prevent the plaintiff from disposing of the
items. A basis for such an application is not revealed.
[64] The result is that the plaintiff has established an entitlement to damages against the
first defendant in the sum claimed.
[65] The next question is whether the second defendant is liable under his guarantee for
that part of the plaintiff‟s claim. The relevant terms of the guarantee are set out
above at [11]. By cl 1, the payment by the first defendant for all goods “hitherto
supplied” is guaranteed. It also guarantees payment for goods “as [the plaintiff]
may hereafter supply from time to time”. At least read alone, that limits the
guarantor‟s liability to amounts unpaid for goods delivered to the first defendant.
Clauses 20 and 25 of the conditions of sale, within that 2004 document, made it
clear that the price of goods would be payable by the first defendant only upon
delivery.
[66] Clause 2 of the guarantee provided that it should be a continuing guarantee “for the
whole of the debtor‟s indebtedness or liability to [the plaintiff] in respect of goods
… supplied or to be supplied … or upon any other account howsoever or whenever
21 T 4-71.
22 T 4-79.
23 T 5-34.
-- 23 of 33 --
24
arising”. Although that clause refers to a liability in respect of goods to be supplied
to the first defendant, in the context of the guarantee as a whole, and in particular
cl 1, I am not persuaded that it extends the scope of the guarantee to a liability for
damages for non-acceptance, as distinct from a liability for payment of the price of
goods supplied. In other words, the intention of cl 2 is to make it clear that it is a
continuing guarantee, rather than to extend the scope of the guarantee, as defined by
cl 1, to a liability for damages. Had it been the intention of the parties to include a
liability of the present kind, that intention would have been expressed within the
primary provision which is cl 1. If there is some ambiguity in cl 2, it should be
construed in favour of the guarantor and strictly against the creditor: Ankar Pty Ltd
v National Westminster Finance (Aust) Ltd;24 Chan v Cresdon Pty Ltd.25
[67] There is no other provision which is in the form of an indemnity against a loss of
the present kind. Within the guarantor‟s acknowledgement, it was recorded that
“this is a guarantee and indemnity for unlimited amounts …”. But that “indemnity”
is an apparent reference to the limited indemnity within cl 8 of the guarantee as I
have set out at [11].
[68] Accordingly, I accept the submission for the second defendant that the guarantee
does not extend to the first defendant‟s liability for damages for breach of contract.
Defective trusses?
[69] The first defendant‟s case is that in very many of the houses which it constructed,
the hip trusses excessively sag or deflect (downwards) where they overhang the
sides of the building. This is said to be the result of a defect in the timber which the
plaintiff supplied rather than the fault of the first defendant as the builder. The first
defendant claims that 25 houses are defective in that way, involving, in total, 167
hip trusses. The overall counterclaim on this basis is for $432,245.
[70] These houses were constructed, of course, by the time the first defendant left the site
in 2009. There is no evidence of any demand upon the first defendant, by the party
with whom it contracted or anyone else, such as the Queensland Building Services
Authority, to rectify these trusses. For the first defendant, it is argued that it is more
likely than not that it will be required by the Authority to either rectify these defects
or to pay the cost of their rectification. I am not persuaded to make that finding.
That is firstly because the evidence as to the extent of the deflections is very
general, save in respect of four of the houses. Secondly, the likelihood that the first
defendant would be called upon to either rectify or pay for the rectification of even
those four houses is affected by the fact that there is no evidence that anyone,
especially an owner of the house, has complained about it. As it happens, however,
I am not persuaded that any of the houses has a roof truss with an excessive
deflection for which the plaintiff is legally responsible.
24 (1987) 162 CLR 549.
25 (1989) 168 CLR 242.
-- 24 of 33 --
25
[71] Undoubtedly, some of these houses do contain a hip truss with an unsatisfactory
extent of deflection. Evidence to that effect came from Mr Porchun and
Mr Whiteley, each called in the plaintiff‟s case and from Mr Wilson and Gregory
Buckley called in the defendants‟ case as well as from the second defendant. The
evidence of each of the independent engineers, Mr Porchun and Mr Wilson,
focussed upon only a few of the houses. There is a question as to whether a larger
number of houses is affected by the same defect and a question whether each of the
roof trusses within those few houses is so affected. But for the moment I will
discuss the evidence of the engineers in relation to the particular trusses where the
extent of the deflection was measured.
[72] I begin with the evidence of Mr Wilson, upon which the counterclaim depends. He
wrote two reports. The first was dated 12 December 2011 after an inspection of
three houses on 12 September 2011. His second report is dated 30 January 2012
(the first day of the trial) following an inspection on the previous day. For the most
past the second report is a word for word repetition of the first report.
[73] For his first report he inspected the houses numbered 46, 47 and 48, they having
been selected by the first defendant. The hip capping was removed from the front
lower level roof of each house. He measured the extent of the deflection on this one
roof truss on each of the houses. The deflection measured on house 46 was 16 mm;
on house 47 it was 31 mm and on house 48, 24 mm. In the way the evidence and
arguments proceeded, there was no challenge to the accuracy of those
measurements. Mr Porchun had written in his report, dated 10 August 2011, that
the deflection which he had measured on that truss on unit 47 was about 22 mm.
But for present purposes the measurements by Mr Wilson can be accepted.
[74] Some deflection on such a truss is to be expected because of the weight of that part
of the truss which is overhanging the sides of the building and of that which it is
supporting. This is described as the dead weight and it is a combination of the
weight of the relevant truss (described as the top chord), the roofing and battens and
the ceiling. Mr Wilson undertook an analysis of the expected deflection given the
circumstances of this design of the roof structure and, in particular, a top chord of
these dimensions and of a quality or stiffness of timber described in the industry as
MGP12. The result of this analysis was that the extent of deflection which was to
be expected in the case of these particular trusses, was initially 7.92 mm. He
explained that this would increase over one - two years from construction, so that
the expected long term deflection would be double that figure, being 15.8 mm.
Consequently, he wrote, the truss on house 46 correlated well with that analysis, but
those on houses 47 and 48 were 196 per cent and 151 per cent higher than the
expected deflection.
[75] He wrote that the accepted industry standard for an overhanging deflection was in
the range of 10 – 12 mm. Therefore, even the truss on house 46 had an excessive
deflection. This meant that the expected deflection from this design exceeded what
was acceptable, meaning that the design was wrong. The implication was that some
higher standard of timber than MGP12 grade should have been used, ie a stiffer
grade, although he did not say so specifically in either of his reports. However in so
far as houses 47 and 48 were concerned, the extent of the deflection was not only
-- 25 of 33 --
26
beyond the industry standard of 10 – 12 mm, but also far beyond the predicted
deflection. How was that to be explained? Mr Wilson referred to three
possibilities. One was that these hip truss chords on houses 47 and 48 had a “lower
than the average MGP12 stiffness”. Another was that bowed timber had been used
in the fabrication of those hip truss top chords. The third was that the timber which
had been used had been graded as MGP12 but incorrectly because it, in truth, was a
lesser grade.
[76] Mr Wilson also considered the strength of the truss under a live load applied to the
very end of the truss overhang and concluded that it was structurally inadequate.
That point was outside the case pleaded in the counterclaim. Nevertheless,
Mr Porchun was asked to address that point and others and disagreed with
Mr Wilson‟s conclusion. In particular, Mr Porchun was critical of Mr Wilson‟s
calculating the live load by assuming a particular load at the very end of the truss,
upon the basis that in reality there would be no prospect of anyone standing on the
very tip of the corner of the roof. That debate need not be resolved, although
Mr Porchun‟s point appeared to be well made. Ultimately the counterclaim was not
put upon the basis of a need to rectify these houses in order to make them safe under
some live load. The complaint is that there is an excessive deflection under the so-
called dead weight of the roof and ceiling, which unduly affects the appearance of
the buildings.
[77] Beyond houses 46, 47 and 48 (and on those houses only one of the trusses),
Mr Wilson made no measurements of any truss overhang. But in his first report he
added this comment:
“Note that the inspection carried [out] was limited to the hip truss
framing. Other hip roofs in this developments [sic] were viewed
from the streets and similar deflects were observed though no other
measurements were taken.”
That second sentence did not reappear in his second report but he there added the
following:
“During the follow up inspection on the 29th January, another
twenty-two (Houses 1, 2, 5-12, 35-45 & 49) were viewed from the
ground. I viewed parts of the upper and lower roofs of each of these
buildings. No measurements were taken however it appeared from
my visual inspection that similar hip overhang deflections were
evident on these additional buildings.”
[78] Upon evidence as general as that, the first defendant claims for the cost of rectifying
each and every hip truss in each of those houses. However, that evidence has little
weight and is quite inadequate in order to establish the counterclaim. As is clear
from Mr Wilson‟s evidence, some deflection is to be expected. Of the three trusses
which he measured, that on house 46 was to be distinguished from the others for
which the extent of the deflection could not be explained as easily as Mr Wilson felt
-- 26 of 33 --
27
that he was able to do with house 46. In saying about 22 other houses and every
roof truss on each of them that there were “similar hip overhang deflections”, was
he likening what he saw on each of those houses to house 46 or more to houses 47
and 48? Particularly if it was the former, the evidence is unreliable because of the
difficulty which anyone would have in judging by the eye the extent of a deflection
with a margin for error of as little as 4 mm.26 All of these houses were viewed by
Mr Wilson from the ground.
[79] Moreover, the design of the roof trusses throughout each house was not uniform.
The trusses which he measured at numbers 46, 47 and 48 were in the same part of
the lower roof. But it far from appears that his analysis of the dead weight load for
that truss would equally apply to each and every truss in those houses and across all
of the 25 houses for which the counterclaim is made. An analysis of predicted
deflection of other trusses could have been made without a close examination of
them. But Mr Wilson was not asked and did not see fit to perform that exercise to
assess whether, beyond the three trusses for which he did make the calculation of
prediction deflection, the design was defective. It does not follow from
Mr Wilson‟s analysis of the predicted deflection of these three trusses that other
trusses in those houses, or the corresponding trusses in the other houses, would have
an excessive deflection. More generally, the counterclaim for these other trusses,
either within those houses or throughout the 25 for which the claim is made, is
unpersuasive because of a lack of evidence of some measured comparison between
the actual deflection and an acceptable deflection according to industry standards.
[80] I go then to Mr Porchun‟s evidence. He inspected the overhangs on houses 1, 47
and 48. In his report of August 2011, he wrote that the:
“… hip truss overhang deflections at the lower level of Unit 47 were
noticeable and were measured and found to be approximately
22 mm. It was not possible to estimate the hip truss overhang
deflections at the upper end as no scaffold was present to provide
access for measurement. When viewed from below the hip truss
overhang deflections at the upper level did not appear excessive.”
He wrote of the upper hip trusses on house 47 that “when viewed from below the
deflections at the hip overhangs appear to be considerably less than the deflections
at the lower level. The overhang distance at the upper level is 610 mm from the
wall frames which is 140 mm less than the overhangs at the lower level which are
750 mm from the wall frames for the jack and creeper trusses”.27 It is to be noted
that the reports of Mr Wilson did not comment upon the apparent extent of
deflection at the upper levels of houses 46, 47 and 48 although when referring to the
other houses in his second report, he purported to describe both the lower and upper
levels.
26 A deflection of 16 mm compared with an acceptable deflection of 12 mm.
27 In his oral evidence, Mr Porchun agreed that his reference to 750 mm should have been 760 mm, but
said that the difference was not significant.
-- 27 of 33 --
28
[81] Mr Porchun‟s reference to the shorter overhang at the upper level shows at least one
reason why Mr Wilson‟s calculation of a predicted deflection would not be reliable
for the trusses at that level.
[82] At house 48 Mr Porchun said he found deflections which were “similar to that
measured above the Garage in Unit 47”. That observation is consistent with the
measurements taken by Mr Wilson.
[83] At house 1 he found that the hip truss above the garage was approximately 18 mm
in its deflection. He wrote that the overhangs at the upper level did not appear to
have excessive deflection.
[84] In his report Mr Porchun was critical of the absence of back-strutting to the lower
level overhangs. He said that the deflections would have been negligible had back
struts been installed. He wrote also that “the fixing of the timber fascias may have
contributed towards some of the existing deflections”.
[85] As to the design of these trusses, Mr Porchun wrote:
“A design check had been carried out [by him] on the hip truss
overhangs at the lower level and the expected overhang deflection
has been calculated as 8 mm. The deflection on site is 2.75 times
greater than the expected deflection.28 It is my opinion that the roof
trusses were designed in accordance with the relevant Australian
Standards.”
Mr Porchun‟s calculation of the expected deflection from the dead weight load was
thereby about one half of that calculated by Mr Wilson (8 mm against 15.8 mm). In
his oral evidence, Mr Porchun explained that the difference was at least mainly
attributable to the assumed weight of the top chord which was used in the
calculation. Mr Wilson used a figure for the weight of the top chord which was
almost three times that used by Mr Porchun. Mr Wilson was not asked to explain
how he chose his figure as the assumed weight of the chord. But Mr Porchun‟s
figure, he explained, was derived from the application of a loading code under an
Australian Standard. Mr Porchun was not challenged in cross-examination on his
adoption of his figure for the weight of the top chord.
[86] I am not persuaded to reject Mr Porchun‟s calculation of the expected deflection
under a dead weight load. There is no reason to conclude instead that Mr Wilson‟s
calculation, and more particularly his adoption of a certain self weight for the top
chord, was the correct one. The fact that houses 1, 47 and 48 have excessive
deflections does not mean that Mr Wilson‟s calculation of the predicted deflection is
correct. Rather, the extent of the deflections in the particular truss in those three
houses shows that there was something which went wrong either with the quality of
the timber or in the builder‟s installation of the trusses.
28 A reference to the deflection of 22 mm measured on house 47.
-- 28 of 33 --
29
[87] Once Mr Wilson‟s evidence as to the predicted deflection under a dead weight load
is not preferred to that of Mr Porchun, there is no support for the case that the
design of the trusses was inadequate and, in particular, a higher grade of timber
should have been used. However, I should add that the engineers were not entirely
in agreement as to what deflection is acceptable according to industry standards.
Mr Wilson said that the range was 10 – 12 mm. In his report, Mr Porchun referred
to an Australian Standard which specified a deflection for rafter overhangs of
10 mm as an acceptable maximum. But he pointed out that there was not yet an
Australian Standard which specified a maximum deflection for a hip truss overhang.
In his oral evidence, Mr Porchun suggested that the range might have a higher
maximum, perhaps approaching 15 mm. Absent some published standard or
something else more authoritative than Mr Wilson‟s statement of what the industry
as a whole considers to be acceptable, I would not be persuaded to find that the
maximum acceptable deflection is no more than 12 mm. It may be a little higher
than that although it is clear from Mr Porchun‟s evidence that something more than
20 mm would be excessive. This means that the overhang on house 46, which is
measured at 16 mm, is probably just beyond an acceptable range. It would seem,
however, unrealistic to suggest that some thousands of dollars would be spent in
rectifying that truss for the sake of a couple of millimetres.
[88] What then is the explanation for the excessive deflection found on this lower level
truss above the garage at houses 1, 46, 47 and 48? Beyond the suggestion of a poor
design, and in particular the wrong standard of timber being prescribed, as I have
noted, Mr Wilson suggested that the trusses were not actually built from MGP12
grade (or an average difference within that grade) or that the timber was bowed.
Each of those was expressed by Mr Wilson in terms of a possibility.
[89] Mr Porchun said that bowed timber could not be “ruled out”.29 He said that bowing
was not unusual and that all timber has some bow or spring in it to some extent and
that it is up to the fabricators of the trusses and frames, in sorting and cutting the
timber, to reject timber which has an excessive bow.
[90] There is other evidence relevant to bowing. Mr Anderson, who at the relevant time
was employed by the plaintiff as a sales representative and who was closely
involved with the supply of these goods, said that he received no complaints from
the first defendant as to timber quality and in particular as to bowing. Mr Whiteley
gave evidence that it is impossible for a badly bowed piece of timber to be used in
the plaintiff‟s manufacturing process as the timber would not fit into the jigs had it
been bowed to this extent.30
[91] As to the grade of this timber, Mr Whiteley gave evidence that the timber used to
manufacture the trusses was marked by the timber supplier as MGP12. Mr Porchun
gave evidence to the same effect. It is theoretically possible that the timber supplier
made those markings in error and that the timber was, in truth, of a lower grade.
But Mr Porchun explained that if, for example, the timber was of a stiffness of the
next grade below MGP12, which is MGP10, the expected difference in deflection
29 T 4-20.
30 T 2-27.
-- 29 of 33 --
30
would be about 27 per cent and would not nearly explain the extent of the
deflections at houses 1, 47 and 48.31 That evidence would also dispose of the
possibility that the deflection was caused by timber of a stiffness which was within
but at the low end of the range of the MGP12 grade.
[92] For the first defendant it was suggested that all three of Mr Wilson‟s suggested
possibilities might have been acting in combination. In response and with some
reference to calculations, Mr Porchun assessed that the combined effect might have
made for a deflection which was as much as 17 or 18 mm. But again, that
combination does not provide a likely explanation for what occurred here on houses
1, 47 and 48. For that assessment, Mr Porchun assumed 4 mm “for a bit of bow in
the timber”, saying that it was “unlikely that the carpenters would erect a hip truss
with more than that amount of bow”.32
[93] Mr Porchun‟s evidence was that the more likely explanation for the excessive
deflection, where it was found, was poor installation on the site. He was critical of
the installation of the piece described as the structural fascia, which he said was
installed in a way which he had not encountered previously. The structural fascia
should be built so as to be fixed with the top of the hip truss. That was not the case
with these hip trusses where the top chord of the hip truss was lower than the top of
the creeper rafters.33 He also referred to the possibility of imperfections in the level
of the slab and, in turn, the walls, leading to distortions in the roof structure.
Mr Wilson rejected this possibility, saying that he measured his deflections simply
upon the basis of a departure from a straight line in the top of the chord. Still,
Mr Porchun maintained that “the installation of structural fascias has had some
impact on the actual deflected shape of the hip truss top chord”.34 Although he was
not permitted to say so in examination in chief, in cross-examination he explained
that if there was some undue weight on the overhang during the period of
installation, then the installation of the fascia would lock the overhang into that
deflected shape.35 But he added that this fixing of the structural fascia “would not
account for 100 per cent of that deflection”.36
[94] At this point it is necessary to discuss back strutting. This involves the fixing of a
piece of timber, placed horizontally between the face of the wall and the underside
of the overhanging truss. The effect is to transfer loads from the truss overhang to
the wall. The engineers agreed that the installation of back struts to the lower level
roofs above the garages would have put paid to the prospect of any significant
deflection. Mr Wilson wrote that as an alternative to the use of stronger and stiffer
top chords, the chords which were used should have been “installed with a
horizontal prop to the wall frame”. Mr Porchun said that back strutting should not
have been necessary: that the design and in particular the grade of timber was
sufficient to avoid undue deflections without back strutting. But had back strutting
been used, he said that there would have been effectively no problem as now exists.
31 T 4-42.
32 T 4-43, 44.
33 See Mr Porchun‟s drawing at exhibit 21 and the evidence of Mr Whiteley at T 2-25.
34 T 4-29.
35 T 4-30.
36 T 4-41.
-- 30 of 33 --
31
[95] In the layout plans, back strutting was not shown. Indeed the layout plans would
have indicated, if read alone, that no back strutting was necessary. That is because
the notes to those plans refer to a “strut overhang” as being designated by the letter
“S”, but that letter did not appear at any relevant part on the layout plan. However
at the same time as the layout plan was delivered along with the frames and trusses,
the plaintiff delivered a document consisting of a series of drawings showing details
of and containing instructions for a “fully trussed hip end” (as was the case here).37
I accept the evidence that this document was routinely supplied by the plaintiff and
that it was supplied on these occasions.38 In one of the drawings on that page,
headed “Roof Plan – Truss Setout”, there is the instruction against the location of
the hip truss overhang to “back strut hip rafter as per drawn detail”. In another
drawing on the same page, there is a detail of the back strut. Thus according to this
document, the first defendant was instructed to back strut the hip trusses.
[96] On the upper level roofs, it would seem that the soffits were raked rather than
horizontal, so that a back strut would have been evident rather than being concealed
by the soffit. Therefore a back strut would not have been an apparently acceptable
installation at the upper levels. Originally the soffits for the lower levels were also
raked, although they had been changed to horizontal soffits by the time of the
delivery under these contracts between the parties. Back struts could easily have
been applied without being visible at these lower levels. This one page document,
which instructed on the use of back struts, did not distinguish between the upper and
lower levels. When it is also considered that the layout plans indicated, if anything,
that back struts were not to be used, it could not be said that the excessive
deflections are simply the result of the first defendant failing to follow a clear
instruction from the plaintiff. I accept Mr Porchun‟s evidence that back struts
should not have been necessary. The result is that they would be relevant to the
rectification of any excessive deflection (if ever that is to occur), but their absence
does not explain the extent of these deflections.
[97] Overall, it is for the first defendant to establish some breach of contract which has
led to the excessive deflections, insofar as such deflections have been demonstrated,
which is only those particular trusses at the lower levels on the garages of houses 1,
46, 47 and 48. I have rejected the case that the design was inadequate and, in
particular, that the specified grade of MGP12 for the top chord was insufficient. I
am not persuaded that it is more probable than not that the excessive deflection was
caused by the timber not being of that grade, not being of an average within a range
of stiffness for that grade or being excessively bowed at the time of fabrication of
the trusses. Those possibilities are no more likely, even acting in combination, to
have caused these deflections than poor installation, as described in the evidence of
Mr Porchun. Notably there was no evidence which was led to gainsay
Mr Porchun‟s evidence that the installation of the structural fascia on these houses
was quite exceptional. Therefore ultimately I am not persuaded that even for the
four trusses for which an excessive deflection has been proved, this was in
consequence of a breach of contract.
37 This page became exhibit 12.
38 Exhibit 12.
-- 31 of 33 --
32
[98] There is a further argument for the first defendant, which relies upon the term of
each of the contracts which was as follows:
“All workmanship & materials used on this Project to be to the
satisfaction of the client and [the first defendant].”
The argument is that the first defendant, having installed these trusses in building
the houses, is now dissatisfied with them. Of course it does not seek to return them
to the plaintiff. It says that it should be compensated, by an award of over
$400,000, in order to make it satisfied with the trusses. Therefore, without proof of
the grounds for dissatisfaction, but simply upon the assertion of actual
dissatisfaction, it seeks the same damages as if the counterclaim had otherwise been
made out. This cannot be accepted. The term which is relied upon might have
entitled the first defendant to reject the trusses when they were delivered to the site.
For example, had they been delivered with evident and excessive bowing, they
could have been rejected. But it cannot be thought that this term could be relied
upon once the builder had constructed the houses.
[99] Therefore this counterclaim must be dismissed. It is necessary however to say
something about the amount claimed. Evidence was given by Terence Buckley, the
second defendant, that the likely cost of rectification was $2,225 per hip truss,
which is the amount claimed. He gave that evidence having consulted his employed
estimator, who did not give evidence. The first defendant had sought to adduce
expert evidence from a quantity surveyor, whose report was written only in the
week preceding the trial and well outside the time prescribed by the Court‟s
direction for expert reports in this case. Mr Buckley‟s evidence was of little weight.
He was unable to give any persuasive explanation of how that figure of $2,225 was
calculated. The plaintiff recalled Mr Porchun who was allowed to give evidence not
only of the means of rectification, which was to back strut the overhangs to the wall,
but of the likely cost which was $900 per hip end. Had I been persuaded that the
first defendant was entitled to damages for the cost of rectifying any of the trusses
on this project, I would have allowed $900 per truss. That means that had I allowed
the counterclaim for the truss which was measured in houses 1, 46, 47 and 48, I
would allowed something of the order of no more than $4,000.
Conclusion
[100] The result is that the plaintiff succeeds entirely in its claim against the first
defendant. It succeeds in part against the second defendant because the guarantee
does not extend to the first defendant‟s liability for damages for breach of contract.
The counterclaim will be dismissed. The amount of the plaintiff‟s claim against the
first defendant is made up of $280,455.05 for what was supplied and $191,047.83 as
damages for breach of contract. In each case, the cause of action accrued on or
about 12 March 2009. Interest was not claimed at any particular contractual rate. It
-- 32 of 33 --
33
will be awarded at nine per cent for a period of 38 months, amounting to
$134,378.32. Accordingly, there will be judgment for the plaintiff against the first
defendant in the sum of $605,881.20. Interest on the claim against the second
defendant will be at nine per cent for 38 months on $280,455.05, which is an
amount of $79,929.69. Accordingly, there will be judgment for the plaintiff against
the second defendant in the sum of $360,384.74.
[101] Under the conditions of sale within the 2004 documents, by cl 24 the first defendant
charged all of its real property in the amount of its indebtedness to the plaintiff and
consented to a caveat to be lodged by the plaintiff. Beyond the arguments to which
I have already referred in this judgment, the first defendant did not make any
submission against this part of the plaintiff‟s claim. It will be declared that in
accordance with cl 24 of those conditions of sale, within the document which is
exhibit FHM2 to exhibit 18, the plaintiff is entitled to a charge over any real
property of the first defendant to secure the debt under the plaintiff‟s judgment. The
amended claim seeks relief in the form of a declaration that the plaintiff has a
caveatable interest in a particular piece of land. I will hear the parties as to whether
that more specific declaration is still sought and is necessary.
-- 33 of 33 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2012/110