Feenix Queensland Pty Ltd v Grocon Constructions (QLD) Pty Ltd [2012] QDC 346
DISTRICT COURT OF QUEENSLAND
CITATION: Feenix Queensland Pty Ltd v Grocon Constructions (QLD)
Pty Ltd [2012] QDC 346
PARTIES: Feenix Queensland Pty Ltd ACN 007 940 170
(Applicant)
v
Grocon Constructions (QLD) Pty Ltd ACN 120 476 495
(Respondent)
FILE NO: 156/2012
PROCEEDING: Application for Judgment
ORIGINATING
COURT: District Court, Southport
DELIVERED ON: 19 June 2012
DELIVERED AT: Southport
HEARING DATE: 5 May 2012
JUDGE: Judge C F Wall QC
ORDER: Application for judgment dismissed with costs assessed on
standard basis unless agreed
LEGISLATION: Building & Constructions Industry Payments Act 2004,
Sections 7, 8, 12, 13(a), 17, 18, 19,
CASES: Trysams Pty Ltd v Club Constructions (NSW) Pty Ltd [2008]
NSWSC 399
Nepean Engineering Pty Ltd v Total Process Services Pty Ltd
(2005) 64 NSWLR 462
Brookhollow Pty Ltd v R & R Consultants Pty Ltd, unrep,
[2006] NSWSC
Simcorp Developments & Constructions Pty Ltd v Gold
Coast Titans (Property) Pty Ltd & Others, unrep, [2010]
QSC 162
CATCHWORDS: BUILDING & CONSTRUCTION – application for judgment
pursuant to s19 Building and Construction Industry Payments
Act 2004 (Qld) – payment claims by applicant previously
paid by respondent – whether applicant able to rely on further
(second) payment claims for the same subject matter by using
a different reference date in circumstances where respondent
did not serve a payment schedule in respect of those claims –
whether second payment claims valid.
COUNSEL: Mr G Beacham for the applicant
Mr M Steele for the respondent
SOLICITORS: Cronin Litigation for the applicant
Norton Rose Australia for the respondent
-- 1 of 8 --
2
DISTRICT COURT OF QUEENSLAND
REGISTRY: SOUTHPORT
NUMBER: 156/12
Applicant: FEENIX QUEENSLAND PTY LTD
ACN 007 940 170
AND
Respondent: GROCON CONSTRUCTIONS (QLD) PTY LTD
ACN 120 476 495
JUDGMENT
Delivered the 19th day of June 2012
[1] This is an application for judgment pursuant to s.19 of the Building &
Construction Industry Payments Act 2004 (“the Act”) for $218,698.
[2] The applicant relies on 3 payment claims served on the respondent on 14
December 2011 (the second payment claims). Leaving aside the plaintiff‟s
contention that the second payment claims lacked the particularity required
by s.17(1) of the Act, payment claims by the applicant for the same subject
matter and amounts dated 1 November 2010 (the first payment claims) had
previously been served on the respondent and paid by the respondent. In
respect of the first payment claims no payment schedule was served on the
claimant applicant by the respondent.
[3] The reference date for the first payment claims was end October 2010 and
for the second payment claims, end November 2011.
[4] Section 12 of the Act provides:
“12 Rights to progress payments
From each reference date under a construction contract, a
person is entitled to a progress payment if the person has
-- 2 of 8 --
3
undertaken to carry out construction work or supply related
goods and services, under the contract.”
[5] The Dictionary in Schedule 2 of the Act provides:
“reference date, under a construction contract, means –
(a) a date stated in, or worked out under, the contract as
the date on which a claim for a progress payment may
be made for the construction work carried out or
undertaken to be carried out, or related goods and
services supplied or undertaken to be supplied, under
the contract; or
(b) if the contract does not provide for the matter –
(i) the last day of the named month in which the
construction work was first carried out, or the
related goods and services were first supplied,
under the contract; and
(ii) the last day of each later named month.”
[6] So far as is relevant s.13(a) of the Act provides that the “amount of a
progress payment to which a person is entitled in relation to a construction
contract is the amount calculated under the contract”.
[7] The “reference date” definition refers to “a claim for a progress payment…
for construction work carried out… under the contract”.
[8] Section 17 of the Act provides that a payment claim:
- may be served on the person who is liable to make the
payment (s.17(1))
- must identify the construction work to which it relates
(s.17(2)(a))
- may include an amount that has been the subject of a
previous claim (s.17(b))
[9] In my view it is an implicit requirement of s.17(b) that the “previous claim”
had not been paid.
-- 3 of 8 --
4
[10] The object of the Act is to “ensure that a person is entitled to receive and
recover progress payments if the person undertakes to carry out
construction work under a construction contract” (s.7). The object is to be
achieved by “granting an entitlement to progress payments” (s.8(a)).
[11] If the respondent does not serve a payment schedule on the claimant the
respondent is “liable to pay the claimed amount to the claimant” (s.18(4) and
(5)).
[12] If the respondent then fails to pay the claimed amount the claimant may
recover it from the respondent as a debt owing to the claimant (s.19). In the
present case this was not necessary in the case of the first payment claims
as the respondent paid those claims.
[13] The issue here is whether in these circumstances the claimant can claim
again for the same amounts by serving the second payment claims.
[14] What happened between the first and second payment claims was that the
respondent recovered amounts it paid to the applicant under the applicant‟s
bank guarantee relating to the contract.
[15] This aspect is summarised as follows in para 16 of the applicant‟s written
outline
“16. …In the present case, there is an additional overlay in that
the claims are made in respect of sums that were originally
held as retention monies, then released to Feenix in return for
bank guarantees. Those bank guarantees have now been
called upon (Feenix asserts wrongly) with the result that the
payment of the retention monies has, effectively, been
reversed by Grocon.”
[16] The applicant‟s argument is then stated as follows in paras 17-19
“17. Section 17(3)(b) of the Payments Act provides:
„The claimed amount may include any amount –
(a) …
(b) that is held under the construction contract by the
respondent and that the claimant claims is due for
release.‟
-- 4 of 8 --
5
18. In Trysams Pty Ltd v Club Constructions (NSW) Pty
Ltd [2008] NSWSC 399 at [64] McDougall J
considered the equivalent provision in the New South
Wales version of the Payments Act. His Honour held
that this section permitted a claimant to include in a
payment claim a claim for a retention fund held under
a construction contract.
19. By parity of reasoning, where the security under the
construction contract is a bank guarantee, rather than
a retention fund, s.17(3)(b) permits a claimant to
include in the payment [sic] a sum that has been
obtained by the respondent pursuant to that bank
guarantee. The effect of the respondent‟s call under
the bank guarantee is exactly the same as a refusal to
release a retention fund. The legislature can be taken
to have known that security under a construction
contract is sometimes provided by way of a bank
guarantee rather than a retention fund. It would be
passing strange if a [sic] legislature intended to
provide only for one but not for the other. In addition,
were it otherwise, principals could avoid the operation
of the Payments Act in respect of the security by
providing in the contract only for the provision of bank
guarantees, and refusing to allow security to be
provided by way of a retention fund. That cannot
have been the legislative intention. In fact, in
Trysams, McDougall J said:
„[73] It is correct to say that the effect of the
adjudicator‟s decision is to deprive Trysams of the
practical protection afforded by the retention fund.
That, however, is a necessary consequence of [the
relevant section], and the power given to adjudicators
to decide disputes as to payment claims, including a
dispute as to a retention fund.‟”
-- 5 of 8 --
6
[17] The applicant also relies on what Ipp J said in Nepean Engineering Pty Ltd v
Total Process Services Pty Ltd (2005) 64 NSWLR 462 at [76] as follows:
“[76] In regard to the issue the subject of this application for
leave to appeal, for the reasons given by Hodgson JA I would
construe the Building and Construction Industry Security of
Payment Act 1999 as follows. Provided that a payment claim
is made in good faith and purports to comply with s.13(2), of
the Act, the merits of that claim, including the question whether
the claim complied with s.13(2), is a matter for adjudication
under s.17 and not a ground for resisting summary judgment in
proceedings under s.15. In particular, if no adjudication is
sought summary judgment cannot be resisted on grounds that
could have been raised by way of a payment schedule leading
to adjudication” (emphasis added by the applicant).
[18] The applicant submits that the second payment claims relate to a different
reference date and that the respondent did not serve a payment schedule in
relation to them and has not paid the claims and therefore is liable for them.
[19] The applicant also relies on a decision of Palmer J in the New South Wales
Supreme Court in Brookhollow Pty Ltd v R & R Consultants Pty Ltd, unrep,
[2006] NSWSC 1 at paras [41] – [49].
[20] Ipp J in Nepean recognised that a valid payment claim is one which is made
in good faith and which purports to comply with (s17(2)) of the Act.
[21] I agree with McDougall J that a claim for a retention fund may be included in
a payment claim but only if the amount claimed has not already been paid
and I do not understand His Honour to say otherwise.
[22] Likewise a claimant may include in a payment claim a sum that has been
obtained by the respondent pursuant to a bank guarantee but only if the
amount claimed has not already been paid.
[23] In my view, notwithstanding the use made by the respondent of the
applicant‟s bank guarantee, a payment claim in respect to an amount paid
by the respondent under a previous payment claim is not one made in good
faith or in purported compliance with s.17(2). In other words a second
-- 6 of 8 --
7
payment claim cannot be made for the same work/amount which has been
paid by the respondent merely by using a new or additional reference date
for that purpose.
[24] The second payment claims are not, in my view, even apparently valid
claims to which the remarks of Palmer J in Brookhollow at paras [46] – [48]
could be said to apply. Because the amounts the subject of the second
payment claims have in fact been paid, the respondent is, in my view, able
to resist an application for judgment notwithstanding that it did not serve a
payment schedule in respect of the claims.
[25] I agree with the respondent‟s submission that the second payment claims in
these circumstances are not valid claims and that no amount claimed by the
applicant remains unpaid.
[26] The respondent also relies on clause 22.2 of each contract which is in the
following terms:
“22.2 Once each month, by the date stated in the Appendix,
the Subcontractor must submit to the Builder:
(a) its progress claim for payment of that part of the
subcontract Amount which, in the Subcontractor‟s
opinion, is due for work completed up until the date of
the progress claim;
(b) all amounts which the Subcontractor believes is due to
the Subcontractor arising out of or in connection with
the Subcontract.”
[27] The second payment claims seek payment again for the work referred to in
clause 22.2 and already paid by the respondent. In my view a payment
claim which purports to do this is not a valid claim.
[28] The respondent also relies on Simcorp Developments & Constructions Pty
Ltd v Gold Coast Titans (Property) Pty Ltd & Others, unrep, [2010] QSC 162
at para [35] where Douglas J held that a second claim covering the same
work referred to in earlier claims could not be relied on as it would breach
s.17(5) of the Act and Neuman Contractors Pty Ltd v Traspunt No 5 Pty Ltd,
unrep, [2010] QCA 119 at para [49]. These decisions are relevant by
-- 7 of 8 --
8
analogy provided it is appreciated that in them the same reference date was
relied on for all payment claims.
[29] The second payment claims being invalid for the reasons I have explained,
it is not necessary to consider the other arguments relied on by the
respondent.
[30] The application for judgment will be dismissed with costs to be assessed on
the standard basis unless agreed.