Alavi-Moghaddam v Woolworths Limited [2012] QDC 138
DISTRICT COURT OF QUEENSLAND
CITATION: Alavi-Moghaddam v Woolworths Limited [2012] QDC 138
PARTIES: ELHAN ALAVI-MOGHADDAM
(Applicant)
v
WOOLWORTHS LTD (ACN 000 014 675)
(Respondent)
FILE NO/S: BD 5109/11
DIVISION: Civil
PROCEEDING: Application for costs
ORIGINATING
COURT:
District Court, Brisbane
DELIVERED ON: 8 June 2012
DELIVERED AT: Brisbane
HEARING DATE: 17 May 2012
JUDGE: Farr SC DCJ
ORDER: No order as to costs
CATCHWORDS: PROCEDURE – COSTS – application for costs – whether
the application was brought as a consequence of unreasonable
delay by the respondent – where the primary consideration
involves a determination of what is fair and just in the
circumstances
Earnshaw v Loy (No 2) [1959] VR 252, cited
Workers’ Compensation and Rehabilitation Act 2003 (Qld),
ss 279, 316, 318C
COUNSEL: GJ Cross for the applicant
JB Rolls for the respondent
SOLICITORS: AK Compensation Lawyers for the applicant
DLA Piper Australia for the respondent
[1] The decision of the court in this application was delivered on 17 May 2012. The
applicant now seeks her costs of the application.
-- 1 of 3 --
2
[2] The determination of costs is regulated by the provisions of ss 316(1) and 318C of
the Workers’ Compensation and Rehabilitation Act 2003 (Qld) (WCRA) which
state:-
“316 Principles about orders as to costs
(1) No order about costs, other than an order allowed
under this section, is to be made by the court in the
claimant’s proceeding.
318C Costs order under div 2 for an interlocutory
application
An order about costs for an interlocutory application
may be made under division 2 only if the court is
satisfied that the application has been brought
because of unreasonable delay by 1 of the parties.”
[3] The terms of s 318C are clear. No costs order can be made unless the court is
satisfied that the application has been brought because of unreasonable delay by one
of the parties. The applicant submits that this application was brought as a
consequence of unreasonable delay by the respondent. The respondent disputes that
claim.
[4] The applicant sought orders requiring the respondent to produce information,
documentation and to allow an inspection of the respondent’s premises.
[5] The application for an order to produce documentation was unsuccessful as I found
that the respondent had already complied with the applicant’s request for such
documentation at an earlier time.
[6] Regarding the request for information, I ordered the respondent to provide the
information requested by the applicant (pursuant to s 279(1)(b)) in correspondence
dated 11 January 2012. Section 279(4) WCRA requires a party to respond to a
s 279(1)(b) request within 21 business days. The respondent’s failure to comply
with that provision is a relevant consideration (although not conclusive) to the issue
as to whether or not there has been unreasonable delay. No satisfactory explanation
has been offered for that failure. The respondent argued that it had previously
responded to a request by the applicant in identical terms to the January request. A
cursory examination of the two requests however, quickly revealed that each request
sought different categories of information. I accept therefore that the respondent’s
delay was unreasonable and that the application for an order to produce information
was brought because of that delay.
[7] In relation to the application to inspect the respondent’s premises, the respondent
submitted that a legitimate disagreement existed over the applicant’s entitlement to
conduct such an inspection i.e. this was a bona fide dispute as to whether an
inspection was necessary under the rules and whether any such inspection ought to
have occurred before the compulsory conference was held under WCRA. Whilst
the respondent’s argument on this point was ultimately unsuccessful, it was
nevertheless a reasonable argument supported by authority. It identified that there
was a genuine dispute between the parties that required resolution by the court. In
-- 2 of 3 --
3
those circumstances, it could not be said that there had been “unreasonable delay”
on the part of the respondent.
[8] Also, whilst I note that the provision to the applicant of the photograph of the
subject ladder and a document entitled “Safety Basics” on the day before the
application was heard, could have been provided earlier, there is no evidence before
this court to suggest that the application was brought because of the non-provision
of those two documents.
Conclusion
[9] The fact that the application seeking an order for the production of documents was
unsuccessful when considered in combination with there having been no
unreasonable delay by the respondent in not agreeing to allow an inspection to
occur is significant to the issue of costs. Determining whether or not to order costs
requires the exercise of discretion.1 The primary consideration involves a
determination of what is fair and just in the circumstances.2 In my view, whilst the
criteria as prescribed by s 318C WCRA has been fulfilled in relation to the
application for information, the counterbalancing considerations as identified above,
are considerable. In my opinion, a fair and just outcome in these circumstances
would be for each party to bear their own costs and that there should be no order as
to costs.
[10] For these reasons I make no order as to costs.
1 Workers’ Compensation and Rehabilitation Act 2003 (Qld), s 318C: “An order about costs for an
interlocutory application may be made.”
2 Earnshaw v Loy (No 2) [1959] VR 252 at 253.
-- 3 of 3 --
Official source: https://www.sclqld.org.au/caselaw/QDC/2012/138