Baxter v Wright [2012] QCAT 606
CITATION: Baxter v Wright [2012] QCAT 606
PARTIES: R D Baxter
v
Geoff Wright t/as Wright Tiling
APPLICATION NUMBER: BDL364-11
MATTER TYPE: Building matters
HEARING DATE: 20 July 2012
HEARD AT: Southport
DECISION OF: Christine Trueman, Adjudicator
DELIVERED ON: 30 November 2012
DELIVERED AT: Southport
ORDERS MADE: [1] THAT the Application is dismissed.
CATCHWORDS: Building Dispute – alleged defective tiling
works – disputed rectification costs –
whether agreement to settle rectification
costs by retention monies – whether
retention monies correctly applied to prior
rectification works
Domestic Building Contracts Act 2000
Queensland Building Services Authority Act
1991
APPEARANCES and REPRESENTATION (if any):
APPLICANT: Mr Robert David Baxter
RESPONDENT: Mr Geoff Wright
REASONS FOR DECISION
[1] This is an application for domestic building dispute filed by the builder Mr
Baxter relating to rectification of defective works performed by Mr Wright at
a residential property located at 58 Bennett Road, The Gap in Brisbane.
Mr Baxter signed a domestic building contracti to build the residence for the
owners on 14 May 2010; works commenced on 7 June 2010 and were
completed on 24 December 2012. Mr Wright performed the works under a
contract with the building contractor.
-- 1 of 7 --
2
[2] Mr Baxter seeks orders from the tribunal for compensation for the cost of
rectification of defective works carried out by Mr Wright in the sum of
$2,023.70. There were three invoices for the work.ii He also claims for
compensation to be paid to him for his expenses and time to organise
materials, tradesmen and co-ordination of the rectification works in the sum
of $495.00.iii The total claim is for the sum of $2,518.70.
[3] This tribunal has the jurisdiction to hear and determine a building dispute
by virtue of the Queensland Building Services Authority Act 1991.iv By
definition a “building dispute” means a domestic building dispute and
“building contractor” means a person who carries on a business that
consists of or includes carrying out building work, and includes a
subcontractor who carries out building work for a building contractor.v
[4] This case is a domestic building dispute arising between 2 or more building
contractors relating to the performance of domestic work under a contract.vi
The works are domestic building works which is defined as work
associated with the erection, construction, removal or resiting of a
detached dwelling; and work associated with the renovation, alteration,
extension, improvement or repair of a home.vii
[5] In this case the domestic building dispute arises between Mr Baxter (a
builder) and Mr Wright (a tiling subcontractor) and alleged defects of tiling
works performed by Mr Wright at a residence being built by Mr Baxter
pursuant to a domestic building contract.
[6] Mr Wright states that he should not be liable for the costs of the
rectifications works as he had already agreed and settled the issue of
rectification costs on 1 February 2011. He alleges that an amount for
rectification costs were agreed, deducted from the payment owed to him
and that these further rectification costs are a second attempt by the
builder to pursue him for the same issues. Mr Wright claims that he settled
matters with Mr Baxter and that he was no longer liable for any of the tiling
areas in the property as other tiling contractors had worked onsite after
him. He said that the further works by other tilers had effectively negated
any liability for any tiling works falling back on to him. Mr Wright claims that
the further tiling problems and rectification works should not be his
responsibility.
[7] The tiling works were performed by Mr Wright. The total cost was
$6,568.65.viii Mr Wright states that a dispute arose shortly after the tiling
works were completed and rectification works were required. Mr Wright
stated that he went back to the property and tried to attempt to rectify the
issues raised by Mr Baxter. He said that he partly rectified some of the
issues that included refitting tiles to the external corner of the bathroom
between the door and shower. He said that after a heated discussion he
did not wish to remain on site, he walked off the job and told Mr Baxter to
find another tiler to rectify the tiling issues. It is not disputed that Mr Baxter
engaged tilers from the Gold Coast to rectify the tiling works. That
-- 2 of 7 --
3
evidence was contained in a letter sent by Mr Baxter to Mr Wright detailing
the rectification works and costs.ix
[8] Mr Wright stated that the amount sought in this claim was for further
rectification costs that did not form part of the first dispute relating to
rectification works. Mr Baxter stated that the defects subject to the claim
were not evidenced at the time when the other defective works were
identified and rectified. Mr Baxter said that when the owners moved in on
Christmas Eve they noticed some things that they thought were defective
and gave a list to Mr Baxter. Mr Baxter states that he originally disputed
some of the defects with the owners as trivial and minor. Mr Baxter stated
that this claim related to those defects raised by the owners and not
originally noticed by him and those items that could not be agreed.
[9] Mr Wright stated that the area subject to this dispute was in the ensuite and
not the area of the second bathroom in the previous rectification works. Mr
Wright states that the agreement reached between the parties on
1 February 2011 distinguished each party’s entitlement to claim against the
other and that included further payment to Mr Wright and claims for defects
by Mr Baxter.
[10] The agreement that was reached between the parties was contained in an
attachment to the letter sent by Mr Baxter to Mr Wright on 1 February 2012.
The agreement sets out the cost of the works and rectification costs, it
stated:
24m2 Floor tiling and bedding $2,040.00
50m2 Wall tiling $3,250.00
15 L/M skirting $ 405.00
(silicone sealing(replaced and deducted)
$5,695.00
Plus GST 569.50
$6,264.50
Rectification:-
2 men 2 days (32 hours@$60/hr +GST) $1,920.00
Liquidated Damages (2 weeks2$550/wk) $1,100.00
Repairs to Plasterboard $ 180.00
Repairs to Waterproofing $ 126.00
Supply of additional tiles $ 113.00
$3,439.00
Builders margin to organise normally 15% no charge
Plus GST $ 343.90
TOTAL $3,782.90
Total to be paid $2,481.60
[11] Mr Wright said he accepted the payment of $2,481.60 based on the fact he
did not want to have to go back to the property. He said he felt frustrated
as he had fixed the rectification work but it was not to the satisfaction of the
owners. He said the owners were “extremely difficult, had lived next door
to the building works while the job was being done, came on site daily and
-- 3 of 7 --
4
were generally demanding and difficult, often directed the tiler what to do,
where to lay tiles and how to lay them”. Mr Wright said that he felt he had
done the rectification works to a suitable standard, had replaced the tiles
that were identified as needing to be relaced and then the owners said to
him that they wanted other tiles pulled up and replaced. Mr Wright said he
felt the owners were being difficult and no matter what he did they would
not be satisfied. He said there were some minor issues with the grout. He
said as soon as he fixed one problem the owners found something else
needing to be done. Mr Wright said he agreed to leave the site and allow
Mr Baxter to get other tilers to finish off the works and to reduce the
payment to him accordingly.
[12] Mr Wright said that although he reluctantly agreed to accept the final
payment, he disputed some of the items. As an example he said that he
was charged liquidated damages due to the extra time it took to rectify the
tiling works and yet he disputed the delay was caused by him. He said that
in fact he was delayed in starting his job by some 2 weeks because other
“tradies” had not finished their work. He said as he was late starting his
tiling job that he alone did not cause delays in the completion of the house.
He said that there was no evidence to prove that the builder actually had to
pay liquidated damages to the owners for being late and for any delays.
He further stated that the charges for the labourers to undertake the works
was excessive, was likely to have been done on a “do and charge” basis
and so therefore expensive. He also stated that there was no proof or
invoice for the rectification cost of the labour component of two men and
the cost of $1,920.00 and he challenged the amount that Mr Baxter had
actually paid.
[13] Mr Wright said he met with Mr Baxter to discuss the payment and
rectification works and that he was presented with the letter of 1 February
2011 with an attached summary. He said that there was a part of the letter
where the parties were to sign as agreement reached and payment
received. Mr Wright said he was not given any invoices to prove the
amounts claimed, he just took the cheque and “walked away”. Mr Wright
stated that he already felt ripped off by Mr Baxter but agreed to the much
lesser payment just to have it “all go away”.
[14] The agreement signed by the parties stated:
“I, Geoff Wright of Wright Tiling accept payment of $2,481.60 as payment in
full for tiling works carried out at 58 Bennett Road, The Gap…….No further
payment claim for tiling works will be the responsibility of RD Baxter. Yours
faithfully….R.D. Baxter.”
[15] The agreement did not particularly exclude the liability of Mr Wright and
any further tiling rectifications if necessary.
Findings
-- 4 of 7 --
5
[16] The evidence was clear and unambiguous that there were defective tiling
works. The BSA had conducted an inspection of the property to investigate
various complaints made by the owners. The owners claim that they
became aware of the defects on 24/12/2010. The parts of the BSA report
and photos of the ensuite that were relevant to the claim were provided.x
The report identified “inadequate grading of tiles to the floor water troughs
in the ensuite bathroom, causing undrained ponding water remaining on
the floor tiling in the ensuite shower cubicle… creating slippery
conditions…. Described as a health and safety issue."
[17] I find from the evidence that there were other rectification works that were
required to be undertaken.
[18] At the conclusion of the hearing it was evident that Mr Baxter should have
provided to the tribunal the evidence to support the monies he retained
from paying to Mr Wright for the initial rectification works and as such the
decision was reserved and leave was granted for him to file further
evidence. The order stated that Mr Baxter must file on or before 24 August
2012 a copy of the evidence of the rectification works as outlined in the
offer to settle letter dated 1 February 2011 in the sum of $3,782.90. Mr
Baxter elected not to file any further evidence in relation to his application.
[19] I could therefore not determine what actual tiling works had been
completed by the Gold Coast tilers during the first rectification works and if
the actual labour cost had been the sum of $1,920.00. I could not make
any findings that Mr Baxter was required to pay liquidated damages to the
owners, being a further cost he passed on to Mr Wright in the sum of
$1,100.00. I find that if those costs cannot be substantiated then it would
be unfair to order that Mr Wright pay further costs for rectification works
when he has already paid them.
Conclusion
[20] Although this is a claim for the recovery of costs for rectifications works
relating to a BSA report and defect notices, it is necessary to revisit the
original rectification costs already conceded by Mr Wright, the facts and
circumstances surrounding that agreement when considering if the further
claim for rectification costs are fair and reasonable in all the circumstances.
I have done that and concluded that the funds initially retained by Mr
Baxter in the sum of $3439.00 were not substantiated. I find that the
rectification works were performed as clearly Mr Wright conceded he left
the site and there were some works that required completion. As to the
extent of those works I am unable to assess what was required to finish the
initial defective works and what would be a reasonable cost for such
completion.
[21] I find that the agreement between the parties reduced to writing and dated
1 February 2011 had the intention to finalise all the disputed matters
between the parties. I find that it would be reasonable for Mr Wright to
assume that the agreement to accept a greatly reduced payment for the
-- 5 of 7 --
6
tiling works would end his liability in relation to any defective works either
identified or otherwise. I find that the payment made by Mr Baxter to Mr
Wright was intended to be a final payment for all the tiling works. In light of
the fact that the ensuite defects as identified by the owners had already
been brought to the attention of Mr Baxter as the BSA report and Mr
Baxter’s evidence was that the defect list was prepared by the owners on
Christmas Eve in 2010. I am therefore satisfied that Mr Baxter was aware
and knew of the other defects and that if he contemplated any further
rectification costs that he would have withheld any final payment to Mr
Wright. The fact that the final payment was made, I find, suggests, that Mr
Baxter also considered the matter as final and the payment was in full and
final satisfaction of all matters in dispute between the parties. The
involvement of other tiling contractors on site, payment of prior rectification
work and a dispute as to the actual cost of the works that were paid only
adds confusion to the issues in dispute in this claim and as to liability. I find
there is merit in the proposition that without the evidence of the actual work
that the Gold Coast tilers did for the rectification works it may be that they
worked on the shower floors in the ensuite and are therefore liable for
defects.
[22] On the basis that Mr Baxter has been unable to substantiate his claim, in
that he could not provide any explanation or evidence that the initial
retention monies of $3,782.90 were not sufficient funds to cover all the
rectification works performed, that no invoices were provided for the
alleged rectification works including the repairs to plasterboard and
waterproofing, the labour costs of 2 men and the liquidated damages, the
finding is that those funds were withheld by Mr Baxter without justification.
[23] I find that there are two main reasons that the claim must fail. The first
reason is that the retention monies of $3,782.90 set off against any
payment to Mr Wright was done so without sufficient or any evidence, proof
or explanation that the costs were justified, fair and reasonable. In that
case Mr Wright has already paid more than the current amount claimed for
rectification costs for further tiling works. The second reason, that the
claim would fail, even if I found that the rectification costs already paid were
justified is based on the evidence that would support a finding that the
agreement on 1 February 2011 was a settlement and a conclusion of all
matters in dispute between the parties. I find that the payment eventually
made to Mr Wright was in full and final satisfaction to resolve the dispute
between parties in relation to all matters and to finally conclude all rights,
obligations and liabilities between them. I find that the final payment by Mr
Baxter to Mr Wright was confirmation that there was an expectation and
agreement that there would be no further dispute between the parties.
Although the written agreement did not particularise the ceasing of Mr
Wright's obligations to further defects, I find that the parties had agreed to
such a condition, it was an oral term that formed part of their agreement to
the settlement and that it was the intention of the parties that the
agreement and payment of 1 February 2011 would finalise all matters
between them.
-- 6 of 7 --
7
[24] As Mr Baxter’s claim for the reimbursement of rectification costs in the sum
of $2,023.70 has failed so, therefore, must his claim for his costs and
expenses in the sum of $495.00.
[25] After considering all of the evidence of the parties, and having carefully
considered the content of all the exhibits provided to the tribunal and for the
reasons set out above I make the following decision and order as follows:
ORDERS
[1] THAT the Application is dismissed.
i Domestic Building Contracts Act 2000, section 7.
ii Prompt Tiles Invoice dated 13/11/11 for $1,611.50, Superior Glass Tax Invoice dated
28/11/2011 for $297.00 and Tiles World Tax Invoice dated 27/10/2011 for $115.20
annexed to the Alleged Defective Work schedule.
iii R D Baxter Master Builder Tax Invoice dated 9/12/2011.
iv Section 77.
v By definition in Schedule 2 and section 4 of the Queensland Building Services Authority
Act 1991.
vi By definition in Schedule 2 of the Queensland Building Services Authority Act 1991.
vii Domestic Building Contracts Act 2000, section 8(3).
viii Document 3 of Respondent's submissions.
ix Document 1 of Respondent's submissions.
x BSA Report, photos and Defect notices annexed to the Alleged Defective Work
schedule.
-- 7 of 7 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2012/606