Cullen v Gabriel [2012] QCATA 121
CITATION: Cullen v Gabriel [2012] QCATA 121
PARTIES: Stephen Cullen t/as Cullen Earthmoving
(Applicant/Appellant)
v
Mr Marten Gabriel
(Respondent)
APPLICATION NUMBER: APL381-11
MATTER TYPE: Appeals
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Mr Charles Brabazon QC, Member
DELIVERED ON: 16 July 2012
DELIVERED AT: Brisbane
ORDERS MADE: a) Dismiss the appeal;
b) Affirm the decision of the
adjudicator;
c) Claims 287/11 and 413/11 are both
dismissed;
d) No order as to costs, including the
costs of this appeal.
CATCHWORDS: Contract – variation – additional claim not
allowed
APPEARANCES and REPRESENTATION (if any):
This matter was heard and determined on the papers pursuant to s 32 of
Queensland Civil and Administrative Tribunal Act 2009 (QCAT Act).
REASONS FOR DECISION
[1] Mr Cullen did some landscaping work for Mr Gabriel, around his house.
They have had a falling out, about some of the work. Mr Cullen says that
Mr Gabriel has to pay him for two or three days work he did just before
leaving the job. He asks for $1,450 plus some legal costs – $1,592.10, in
total. The adjudicator dismissed his claim, so he now appeals to QCAT.
-- 1 of 4 --
2
[2] Mr Gabriel said that Mr Cullen did not do the work properly, and caused
some damage. He asked the adjudicator to award him $4,705.98. The
adjudicator dismissed his claim. He has not appealed against that order.
[3] So, is Mr Cullen entitled to recover the $1,592.10? That is the issue in
this dispute.
[4] They had signed a contract for minor domestic building work, on
19 January 2011. Mr Cullen was to do the work for $22,000. There was
no preliminary deposit. Rather, Mr Gabriel agreed to pay, “$10,000 when
job 50% complete … when site cleared and rocks on site … the balance
of $12,000 at practical completion.”
[5] Work started on 29 January. Most of the land was cleared, and some of
the rocks were on site. Mr Cullen said that he had done the work by
4 February. Mr Gabriel disagreed. Mr Cullen stopped work. Reluctantly,
Mr Gabriel paid him $10,000 on 8 February.
[6] Work on the rock walls then began on 9 February, and continued for three
days. Mr Gabriel said he was not happy with Mr Cullen’s work.
[7] Mr Cullen knew another landscaper Gene Fewings and his wife worked as
Currumbin Earthmoving. On 11 February, they discussed the job. Mr
Cullen asked him if he could take over the job. Mr Cullen said that he
agreed that Fewings would do the work to finish building the rock walls.
Mr Cullen says that he agreed to supply the rocks, to complete the job.
Mr Cullen was to get $2,000, and Fewings was to get $10,000. Mr Gabriel
would still be paying the agreed $22,000 for the job.
[8] Mr Cullen told Mr Gabriel that Fewings would complete the job. Fewings
called to see Mr Gabriel on 12 February. Mr Gabriel agreed to pay him
the $12,000 to finish the job. Their agreement was on the basis that Mr
Cullen had agreed to supply the rocks.
[9] Mr Gabriel and Fewings signed a new contract. Work was to start on
14 February. It said, “the work … involves labour and machinery hire
only. All materials are to be supplied by Steve Cullen Earthmoving”. The
agreed price was $12,000, which was duly paid.
[10] On 14 February Mr Gabriel sent an email to Mr Cullen – “just a short note
to confirm we are both agreed to cancel the contract between us and it is
to be completed by Currumbin Earthworks. I have agreed to pay the
balance of $12,000 for the remainder of the work.”
[11] It seems that the present dispute between them then erupted. On
14 February Mr Cullen saw that Fewings was working on the site.
According to Mr Gabriel, he became agitated and belligerent, “telling me
to stick the …. job up my arse, and screamed abuse”. He then emailed
Mr Gabriel, saying that he wanted $2,000 for work he had done.
-- 2 of 4 --
3
[12] Mr Gabriel responded by saying that Mr Cullen had been overpaid by
$3,000 because he had not supplied materials he had been paid for.
Their tense exchanges are the basis of the present dispute. Is Mr Cullen
entitled to an extra payment?
[13] It is necessary to identify the work that was the basis of Mr Cullen’s claim.
According to Mr Gabriel, it was work done after his $10,000 payment was
made – “after three more, much interrupted days Mr Cullen had completed
just 4.7 metres of walls, that is only 27 bush rocks in total had been put in
portion by February 11th, and it was evident Mr Cullen did not have the
skill or equipment to complete the job satisfactorily.” He said, “If all the
walls look like that I won’t be satisfied with the job.” He became irate and
“left the jobsite returning later with (Fewings).”
[14] After 14 February, when Fewings was working on the site, Mr Cullen
asked for $2,000, based on an hourly rate for his work over three days.
Mr Gabriel declined to pay it, saying he was owed around $3,000 for
materials not supplied. (As it happened, Mr Cullen did not supply the
further rocks to the site).
[15] It seems that the three days claimed were over 9, 10, 11 and 12 February,
according to Mr Cullen. That is consistent with Fewings first meeting with
Mr Gabriel, on 12 February according to Mr Cullen.
[16] The adjudicator explained why she could not accept Mr Cullen’s claim.
Her reasons can be summarised this way – it was not reasonable for Mr
Cullen to claim an hourly rate; he was the one who terminated the contract
with Mr Gabriel, Fewings had a contract with Mr Gabriel, that did not
include Mr Cullen; Mr Gabriel had the job completed for the $22,000 so
there was no contractual obligation to pay anything more to Mr Cullen;
there was no evidence about how the claim was calculated; the contract
did not provide for an hourly rate; Mr Cullen had taken it upon himself to
ask Fewings to finish the job; no records were kept to support the claim;
and Fewings gave evidence that he was on site and that Mr Cullen was
not there. (That last statement seems to be unhelpful, as the days
claimed were before Fewings’ arrival on site).
[17] Ultimately, the adjudicator found that Mr Cullen walked away from the job,
because of the clash with Mr Gabriel, and took it upon himself to arrange
Fewings to complete the work.
[18] In my opinion, the adjudicator’s conclusion was correct. The first point is
the effect of the original contract between Mr Cullen and Mr Gabriel. It
was still in force up to 12 February when Mr Cullen says his work on the
wall was done. A claim for an hourly rate is inconsistent with the contract
they had made and was still in force.
[19] Secondly, Mr Cullen allowed, and supported, the idea of a new contract
with Fewings. It is likely, as he says, that he agreed with Fewings that he
would be paid $2,000 and that Fewings would get $10,000. As he also
says, with regret, he did not participate in the discussions between Mr
-- 3 of 4 --
4
Gabriel and Fewings. If Fewings took advantage of his absence, then that
is not something for which Mr Gabriel was responsible.
[20] Thirdly, the overall effect of the arrangements between the three men,
was to maintain the original $22,000 agreement, with Fewings coming in
to replace Mr Cullen. If Mr Gabriel was to pay more than the $22,000,
then there had to be an agreement to that effect. That did not happen.
[21] These will be the orders of the Tribunal:
a) Dismiss the appeal;
b) Affirm the decision of the adjudicator – claims 287/11 and 413/11 are
both dismissed;
c) No order as to costs, including the costs of this appeal.
-- 4 of 4 --
Official source: https://www.sclqld.org.au/caselaw/QCATA/2012/121