Better Homes Queensland Pty Ltd v O'Reilly [2012] QCATA 37
CITATION: Better Homes Queensland Pty Limited v
O’Reilly & Anor [2012] QCATA 37
PARTIES: Better Homes Queensland Pty Limited
(Applicant)
v
Scott O’Reilly
Meilyn O’Reilly
(Respondents)
APPLICATION NUMBER: APL224-11
MATTER TYPE: Appeals
HEARING DATE: 26 October 2011
HEARD AT: Cairns
DECISION OF: Judge Fleur Kingham, Deputy President
Mr Peter Apel, Member
DELIVERED ON: 23 February 2012
DELIVERED AT: Brisbane
ORDERS MADE: 1. The Appeal is dismissed.
CATCHWORDS: APPEAL – ERROR OF LAW – REASONS –
where reasons did not state a critical finding
APPEAL – ERROR OF LAW –
STATUTORY INTERPRETATION – whether
the test for unreasonable hardship in the
Domestic Building Contracts Act 2000 is
objective or subjective or contains both
elements
APPEAL – ERROR OF LAW – whether
appeal should be allowed – where evidence
did not establish exceptional circumstances
or unreasonable hardship – where error did
not vitiate the decision
Domestic Building Contracts Act 2000,
s 84(4)
Queensland Civil and Administrative
Tribunal Act 2009, s 142
-- 1 of 12 --
2
Attorney-General v Kehoe [2001] 2 Qd R
350
Calin v Greater Union Organisation Pty Ltd
(1991) 173 CLR 33
Commissioner of Taxation v Baffsky (2001)
122 A Crim R 568
Poiner v Quirk [2007] QDC 299
Stead v State Government Insurance
Commission (1986) 161 CLR 141
Tully v McIntyre [2001] 2 Qd R 338
REASONS FOR DECISION
JUDGE FLEUR KINGHAM
[1] The Tribunal refused a claim by Better Homes Queensland Pty Limited
against Mr and Mrs O’Reilly for the cost of constructing a large deck
between the pool and the canal frontage of a residential block. The
specification of works in the building contract provided for a 20 square
metre deck. Later, the owner requested and the builder constructed a 74
square metre deck.
[2] The parties agree they did not document the variation to the contract in
the way required by the Domestic Building Contracts Act 2000.
[3] It is common ground that Better Homes could not succeed in its claim
unless the Tribunal allowed it under section 84(4) of the Domestic
Building Contracts Act 2000.
[4] Briefly stated, the section allows recovery for the costs of a non-compliant
variation to the building contract if:
(a) either:
(i) there are exceptional circumstances that warrant
recovery of an amount; or
(ii) the builder would suffer unreasonable hardship by the
section being applied; and
(b) it would not be unfair to the building owner to allow the
builder to recover an amount.
[5] The learned Member determined the claim against Better Homes, finding
the criteria in s 84(4) were not fulfilled.
[6] Better Homes appealed the decision, arguing the learned Member erred
in law or misdirected himself in interpreting s 84(4) or in applying that
section to the circumstances of this case. Because the appeal is brought
on an error of law, leave to appeal is not required.1
[7] Better Homes alleged the learned Member erred in his consideration of
the alternative criteria of exceptional circumstances and unreasonable
hardship.
1 Queensland Civil and Administrative Tribunal Act 2009, s 142.
-- 2 of 12 --
3
[8] It submitted the learned Member failed to properly consider the evidence
of exceptional circumstances because he improperly conflated two
distinct questions – whether there were exceptional circumstances and
whether Better Homes would suffer unreasonable hardship.
[9] In relation to the criterion unreasonable hardship, Better Homes argued
the learned Member failed to exercise his statutory discretion, because
he, wrongly, considered he was bound by the decision of his Honour
Judge McGill in Poiner v Quirk [2007] QDC 299.
[10] It also alleged the learned Member wrongly applied a subjective rather
than an objective test in determining whether Better Homes had
established unreasonable hardship if it could not recover its claim.
[11] The O’Reillys contested each of those propositions.
Exceptional Circumstances
[12] Although the notice of appeal states a few distinct questions, they each
involve the same enquiry: did the learned Member properly consider and
decide whether Better Homes had established exceptional circumstances.
[13] Better Homes argued he did not, either because he conflated two distinct
questions (exceptional circumstances and unreasonable hardship) or
because he failed to consider the evidence of exceptional circumstances.
[14] In support of those arguments, Better Homes relied on the reasons given
by the learned Member.
[15] The learned Member, commendably, delivered oral reasons at the
conclusion of a four day hearing. This accords with the spirit and purpose
of the Queensland Civil and Administrative Tribunal Act 2009 to resolve
disputes as quickly as is consistent with a proper consideration of the
matter.
[16] The nature and extent of the obligation to provide reasons varies
according to the nature of the case.2 The Appeal Tribunal should have
regard to the circumstances in which he gave them and the nature of the
submissions made during the original hearing, which provide the focus for
the decision. It is not appropriate to parse and analyse judgments given
on an ex tempore basis in a busy jurisdiction.3
[17] The reasons reveal that the learned Member was cognisant of the two
criteria. He referred specifically to each of them and to the contentions
made by the parties about them. His reference to the section is a little
confused, because he used different numbering, but he clearly enough
stated the relevant concepts and the arguments made by the parties.4
[18] The difficulty arises because the learned Member omitted to state a
conclusion on a critical question – whether there were exceptional
circumstances – before he moved on to consider whether there was
2 Attorney-General v Kehoe [2001] 2 Qd R 350 at 356; Tully v McIntyre [2001] 2 Qd R
338.
3 Spigelman CJ remarked in Commissioner of Taxation v Baffsky (2001) 122 A Crim R
568 at 578.
4 Transcript of reasons p 7-8.
-- 3 of 12 --
4
unfairness to the owner and whether Better Homes could demonstrate
unreasonable hardship.5
[19] He commenced his discussion by referring to the arguments made by
both parties. He considered the amount involved was significant, given
the benefit to the O’Reillys and the quality of the finished work. He noted
Mr O’Reilly was willing to pay the sum of $20,000 he says the builder
quoted in July 2008. He canvassed evidence about the cost of
construction and the way in which the deck was costed in the contract
and concluded it was not a provisional sum. He discussed and accepted
the evidence that the builder could have costed the work. At that point in
his reasons he introduced the question whether there would be
unfairness to the owner if the builder recovered the claim and then
commenced a discussion of the question of unreasonable hardship to the
builder.
[20] On one reading, the Appeal Tribunal might infer from his reasons that the
learned Member found there were no exceptional circumstances. Unless
he had done so, it would not have been necessary for him to consider the
other questions of unfairness to the owner and unreasonable hardship to
the builder.
[21] However, his failure to make an explicit finding on the point is significant,
given this was the primary ground advocated for the builder at the
hearing. Introducing the other criterion, in the way that he did, suggested
he had merged the concepts. In close proximity, he stated his conclusion
that the magnitude of the costs the builder could not recover did not
establish unreasonable hardship or an exceptional circumstance.6 He
made no express finding about the other circumstances relied upon to
establish exceptional circumstances.
[22] Reasons should state critical findings and the basis, however briefly
expressed, for making them. The failure to state a conclusion (and
reasons for it) on the criterion of exceptional circumstances makes it
impossible for the Appeal Tribunal to determine whether the learned
Member made an error of law in applying the law to the facts in this case.
That inadequacy in the reasons, itself, constitutes an error of law.
Unreasonable Hardship
[23] The other grounds of appeal relate to the way in which the learned
Member determined the alternative basis for the claim, that the builder
would suffer unreasonable hardship if it did not recover an amount for the
work.
[24] The specific errors alleged are that the learned Member:
(a) failed to exercise his statutory discretion because he wrongly
considered he was bound by the decision in Poiner v Quirk7; and
(b) that he undertook a subjective assessment of hardship when he
should have assessed the matter objectively.
5 Transcript of reasons p 9.
6 Transcript of reasons p 9.
7 Poiner v Quirk [2007] QDC 299.
-- 4 of 12 --
5
[25] In Poiner v Quirk, Judge McGill DCJ considered whether the former
Commercial and Consumer Tribunal had erred in rejecting a builder’s
claim to recover the costs of a non-compliant variation. He addressed
both criteria: exceptional circumstances and undue hardship. He noted
the builder did not assert exceptional circumstances at the original
hearing. He found no evidence to indicate there would be unreasonable
hardship to the builder in enforcing the requirements of the Domestic
Building Contracts Act 2000. In doing so he considered how the
requirement of unreasonable hardship should be interpreted:
There cannot be said to be unreasonable hardship just because he incurred
some additional cost which he cannot recover, one would expect that this is
precisely what the legislature intended in such circumstances.8
[26] That was not an observation confined to the facts of the case, but a
statement of how the section should be interpreted.
[27] At the time, the District Court was the appellate forum for decisions made
for the former Tribunal. QCAT now has the former Tribunal’s jurisdiction
as well as the Court’s former appellate function. It is true to say that the
decision by his Honour does not bind this Appeal Tribunal. However,
there can be no error in a member of the Tribunal, sitting at first instance,
in considering his Honour’s interpretation of the section was an
authoritative statement of how it should be applied.
[28] The Appeal Tribunal concurs in his Honour’s view that the fact that a
builder incurred, and cannot recover, the costs of a non-compliant
variation could not, alone, constitute unreasonable hardship. That
outcome is consistent with the evident purpose of providing an effective
incentive to comply with the requirements of the Act.
[29] The test of unreasonable hardship requires an assessment of the impact
of that sanction on the builder in the circumstances in which the non-
compliance occurred. That is both a subjective and an objective enquiry:
subjective, in that evidence must be led to demonstrate hardship to the
builder; and objective, in that the nature and extent of the hardship must
be unreasonable in the circumstances in which it occurs.
[30] The magnitude of the sum that cannot be recovered is a relevant
consideration in both respects. Subjectively, the inability to recover an
amount may or may not cause hardship to the builder, depending on its
financial circumstances. A small sum for a sole operator whose margins
are slim might have a greater financial impact on that builder than a much
larger sum would have on an enterprise with a large turnover and good
profit margin.
[31] Objectively, the amount the builder is out of pocket will be one of many
possible factors to consider in determining whether the hardship would be
unreasonable. Other factors include the conduct of each of the builder
and the owner in explaining why the variation was not documented and
any discussions they had about the matter.
8 Poiner v Quirk [2007] QDC 299 at [74].
-- 5 of 12 --
6
[32] I am indebted to Mr Apel for his consideration of what evidence of
hardship was presented at the original hearing. He sets out the relevant
extracts in his reasons. I agree with his conclusion that there was
insufficient evidence to establish that Better Homes would suffer hardship
if it could not recover for the cost of the deck variation. All the learned
Member had before him was a bald assertion that this was so.
[33] In the absence of evidence of hardship, there can be no basis for
concluding there was unreasonable hardship. There was no error in the
learned Member’s finding that the builder had not established that
criterion.
Conclusion and orders
[34] The learned Member erred in one respect in failing to state his finding on
the criterion of exceptional circumstances. Not every error of law will
result in a decision being set aside on appeal. The error must be such as
to vitiate the decision.9
[35] For reasons given by Mr Apel, with whom I agree, the evidence led at the
original hearing was not sufficient to establish either that:
(a) there were exceptional circumstances sufficient to warrant the
builder recovering an amount for the variation; or
(b) the builder would suffer unreasonable hardship if he could not
recover an amount.
[36] The decision made by the learned Member was the correct decision on
the evidence before him. There would be no utility in allowing an appeal.
The appeal is dismissed.
MR PETER APEL
[37] I have had the benefit of reading the decision of her Honour Judge
Kingham in this appeal and I am in agreement that the Appellant has
established that the learned Member at the original hearing erred at law in
the reasons given for his decision.
[38] That then makes it necessary to review the evidence before the Tribunal
at the original hearing to consider whether the appeal should be allowed.
Relevant Background
[39] The Appellant is a building contractor who was engaged by the
Respondent in 2005 to construct a dwelling at 74 Harbour Drive,
Bluewater Estate, Trinity Park Cairns.
[40] A HIH new home contract was executed by the parties. It is not
contentious that the contract was for domestic building works and is
subject to the Domestic Building Contracts Act 2000 (“the Act”). The
contract price was $415,607.28.
9 Calin v Greater Union Organisation Pty Ltd (1991) 173 CLR 33 at 41; Stead v State
Government Insurance Commission (1986) 161 CLR 141 at 145.
-- 6 of 12 --
7
[41] The original specifications for works in the contract included (inter alia)
the requirement for the builder to construct a 20 square metre deck
between the pool and the canal frontage of the block.
[42] In 2007, shortly before handover of the dwelling to the owner, the owner
requested a variation to the contract with respect to the deck, now asking
for it to run the full width of the block, increasing its size to approximately
74 square metres.
[43] A document entitled “contract variations for job – O’Reilly” was prepared
dated 21st May 2007. It is accepted that this document did not meet the
requirements of the Act so as to constitute a properly documented
variation.
[44] Section 84(2) of the Act prevents the builder recovering an amount on
account of a variation if they have not complied with the requirements of
that Act to document the variation.
[45] Section 84 (4) of the Act provides:
“The Tribunal may approve the recovery of an amount by a Building
Contractor for a variation only if the Tribunal is satisfied that -
(a) either of the following applies:
(i) there are exceptional circumstances to warrant the
conferring of an entitlement on the Building Contractor
for the recovery o f an amount for the variation;
(ii) the Building Contractor would suffer unreasonable
hardship by the operation of sub section (2)(a) or (3) (a)
(b) It would not be unfair to the building owner for the Building
Contractor to recover an amount.”
[46] To determine the issues raised by section 84(4):
(a) Separate and distinct findings on each of the limbs of section
84(4)(a) should be given; and
(b) The determination of section 84(4)(a)(ii) requires subjective
evidence of the impact upon the builder which is then to be
objectively determined as reasonable or unreasonable.
Exceptional Circumstances
[47] The Appellant submits that the Member at first instance failed to consider
whether the circumstances put forward in the evidence (either alone or in
combination) constituted “exceptional circumstances” within the meaning
of section 84(4)(a)(i) but instead preoccupied himself with the question of
whether the quantum of the amount claimed of itself sufficient to
constitute “exceptional circumstances” to justify relief (Appellant’s
submissions page 8 paragraph 21). The submission is that this
represents a conflation of the two requisite enquiries (page 8 paragraph
22).
[48] The determination of this aspect of the Appellant’s argument requires
consideration of:
(1) The evidence before the Tribunal at hearing; and
(2) The Appellant’s submissions on that evidence.
-- 7 of 12 --
8
Evidence at the hearing
[49] The hearing at first instance was conducted over four days, being 4 and
5 March 2010 and 23 and 24 September 2010. The relevant evidence
was given on the first hearing day, 4 March.
[50] What may be gleaned from Mr Cavallaro’s evidence at pages 14, 15, 17,
20, 23 and 25 of the transcript of 4 March 2010 hearing day is:
(a) That Mr Cavallaro considered the construction of the revised
deck would be complex;
(b) He had never built a structure like that before and that there
were complicating factors such as tides, and the possible
presence of crocodiles in the water, which created difficulty;
(c) He at no time had any intention of building the structure himself;
(d) He was aware that the owner wanted to have a costing, and that
the owner had questioned whether the rate of $275.00 per
square meter would be usable;
(e) That he told the owner it was “extremely difficult and I cannot
work the price out”.
I did not find any other useful references in Mr Cavallaro’s evidence on
the other hearing days or in the Affidavit material of Mr Cavallaro put into
evidence at the commencement of the hearing.
[51] Mr Eden in his evidence on 5 March confirmed the difficulty of the deck
construction job (“the hardest deck I’ve ever built”). Mr Eden also
significantly commented at page 13 of the day’s transcript that he was
never asked to quote the job.
[52] The evidence of the owner, Mr O’Reilly is that he:
(a) Requested the change to the deck specification;
(b) Asked for a price on the revised specification on numerous
occasions but did not receive a price; and
(c) That ultimately the deck was built to his satisfaction.
Appellant’s Submissions
[53] The Appellant’s Counsel put forward a number of issues which were
submitted were exceptional circumstances which may warrant the
conferring of the entitlement on the building contractor to recover an
amount for the variation. These issues were identified as:
1. The work was done at the owner’s request;
2. It was a considerable departure from the original plan;
3. The work was done;
4. The work was done to the owner’s satisfaction;
5. The builder is not profiting from the deck construction;
6. The variation was documented, only poorly;
7. The construction of the deck proceeded as a consensual
arrangement;
-- 8 of 12 --
9
8. The cost to which the owner was exposed was not open ended
– it was able to be ascertained; and
9. Issues relating to the loss of control of the site.
[54] Looking at these issues in turn, I make the following observations:
(a) Items 1, 3 and 4 do not of themselves constitute any
exceptional circumstance and are what any owner ought to
expect from a job. Counsel for the Appellant conceded that
these items were put forward as what might be considered to
be a “double negative” i.e. to counter any allegation that may
be raised by the owner that either the works were unknown
to, or a surprise to the owner, that they were either not
performed or were unsatisfactorily performed. None of those
arguments are raised by the owner, so these issues do not
assist in the consideration of exceptional circumstances.
(b) Item 2 – Whilst it is clear that the revised deck specification
was a significant departure from the original deck plan, in the
context of the total building contract (of which the deck
formed part) the total variation to the deck at its highest cost
would amount to less than 10% of the contract value. I do
not therefore accept that the change in the scope of the deck
works is such as to constitute such a significant departure
from the original plan as to be able to be considered an
exceptional circumstance.
(c) Item 5 – Whilst it is reasonable to expect that a builder, as a
business operator, would factor in a profit on work that they
perform, does the absence of a request for profit contribution
on part of a job constitute an exceptional circumstance? In
this case the builder did not attempt to cost the job, and for
his own commercial reasons elected to do the job “at cost”
(though there was some debate as to what that term was
intended to mean).
The Builder is in the position of control in this situation as to
whether he seeks to profit on his work or not. That he has
chosen not to in this case does not logically equate to an
exceptional circumstance for the purposes of section
84(4)(a)(i) of the Act. This is an exercise of commercial
judgement on the part of the building contractor, and I do not
see it as an exceptional circumstance.
(d) Items 6 and 7 – The attempt at documenting the variation is
not sufficient to meet the requirements of the Act, and
therefore insufficient at law.
The Act imposes requirements on the documentation of
variations, for good reason and to avoid disputes precisely of
this nature. That the parties proceeded on the basis of a
defective document, all be it consensually, is not evidence of
an exceptional circumstance, only of non compliance.
-- 9 of 12 --
10
(e) Item 8 – I have difficulty accepting this assertion, in
circumstances where the builder himself, with access to the
costing information, had to make several attempts at
calculation of his final claim.
If the builder with that information at his finger tips
experienced that difficulty, what hope would the owner have
had of knowing what the extent of his liability may be for the
job? It is clear on the evidence that the builder had no
intention of doing the work himself, and that at all times it was
his intention to engage a subcontractor to do the job. He did
so, but did not request of that subcontractor a quote for the
job. The builder therefore made no attempt to cost the job
himself (noting his earlier comments as to why that may have
been a difficult task, but none the less it was not attempted)
and the builder did not attempt to obtain a cost estimate or
quote from the subcontractor who had the responsibility of
performing the job.
The Owner has their contractual relationship with the builder,
not the subcontractor. The home owner was not in a position
of being able to request a costing from the subcontractor, and
neither should the home owner have been put in the position
of having to pursue that. It is clear that the builder’s intention
was that whatever the subcontractor delivered as their final
bill for the deck was passed on to the owner. Without any
prior quotation or estimate of what those costs might be, that
cost could only be considered open ended. I do not see that
this assertion is borne out on the evidence and it therefore
cannot be taken to be an issue which may constitute an
exceptional circumstance.
(f) Item 9 – There is no evidence to suggest the builder’s ability
to cost, or construct the deck were complicated by access
issues. There had been handover of the site to the owners
but there is no evidence of any actual restriction of access.
I do not see from the evidence that this an exceptional
circumstance to warrant the conferring of an entitlement upon
the builder for recovery of an amount for the variation.
[55] I am not satisfied that the evidence, or the Appellant’s submissions have
established exceptional circumstances as required by section 84(4)(a)(i)
of the Act.
Hardship
[56] Looking at the hearing transcript, the issue of hardship is covered only
briefly by the evidence of Mr Cavallaro, at page 34 of the transcript of the
hearing of 4 March 2010. The highest the Appellant’s position is put is:
“…so is it hardship? How would you go with 50 grand out of your pocket,
anybody here with 50 grand out of their pocket; it’s going to hurt”.
-- 10 of 12 --
11
[57] I observe from reading the transcript of the hearing conducted on 23
September 2010, that the Principal of the Appellant company, Mr
Cavallaro was recalled, and at that time again gave evidence in relation to
the hardship aspect. That evidence is seen at pages 31 and 32 of the
transcript of that day’s hearing. The substance of Mr Cavallaro’s
evidence was that missing out on $50,000.00 worth of income is certainly
felt by a business, though there was no suggestion by Mr Cavallaro (he
specifically denied the suggestion) that his company was insolvent.
[58] The Appellant submits that the member at first instance sought to assess
hardship in a subjective manner in the context of the Appellant’s
circumstances, rather than in an objective impartial way.
[59] Section 84(4)(a)(ii) contains both subjective and objective tests – firstly it
must be shown subjectively that hardship has been suffered as a result of
the builder’s inability to recover an amount for the variation. That
hardship must then be judged objectively as to whether it is an
unreasonable hardship.
[60] To argue for hardship, evidence must be put before the Tribunal of what
hardship has been experienced by the building contractor through their
inability to recover the value of the variation.
[61] No evidence was put forward to demonstrate that the company was in
hardship, save for the statement made by Mr Cavallaro in his evidence,
as quoted above.
[62] The Tribunal cannot be satisfied on the minimal evidence before it that
hardship to the building contractor has been established through the
absence of the funds to have been generated by the variation. Even if
“50 grand is going to hurt” was accepted as evidence of hardship, then
the Tribunal has no evidence upon which to objectively determine
whether that hardship is unreasonable.
[63] The legislation in this circumstance is clear: hardship of itself is not
sufficient, but that hardship must be unreasonable for the builder to
qualify for the protection of section 84(4) of the Act.
[64] The Tribunal had scant evidence to consider whether hardship had been
caused, and no evidence addressing the issue of whether that hardship (if
found) was unreasonable.
[65] The Tribunal at first instance, and this Tribunal now, cannot determine the
test as satisfied in the absence of that evidence.
[66] I find that the requirements of the test imposed by section 84(4)(a)(ii) of
the Act have not been satisfied on the evidence of the Appellant.
[67] As neither of the tests imposed by section 84(4)(a)(i) and (ii) have been
satisfied, then there arises no need to consider the fairness test imposed
by section 84(4)(b).
[68] The Appellant has not satisfied me that either:
(i) Exceptional circumstances existed to warrant the conferring of
an entitlement on the building contractor for the recovery of an
amount for the variation; or
-- 11 of 12 --
12
(ii) The Appellant will suffer unreasonable hardship by their inability
to recover an amount for the variation.
[69] I therefore dismiss the Appeal.
ORDER
[1] The Appeal is dismissed.
-- 12 of 12 --
Official source: https://www.sclqld.org.au/caselaw/QCATA/2012/037