Donovan v Struber & Ors (No. 3) [2012] QLC 28
LAND COURT OF QUEENSLAND
CITATION: Donovan v Struber & Ors (No. 3) [2012] QLC 28
PARTIES: Gary Awarua Donovan
(applicant)
v.
Stephen Roy Struber and Dianne Rose Wilson-Struber
(respondents)
Chief Executive, Department of Environment and Heritage
Protection (formerly known as the Department of Environment
and Resource Management)
(Statutory Party)
FILE NO: MRA137-10, EPA209-10, MRA352-09, EPA351-09, MRA354-
09, EPA353-09, MRA356-09, EPA355-09, MRA342-11,
EPA352-11, MRA341-11, EPA353-11.
DIVISION: General Division
PROCEEDING: Applications for Mining Leases Environmental Authorities and
Objections thereto.
DELIVERED ON: 15 June 2012
DELIVERED AT: Brisbane
HEARD AT: Mareeba/Atherton/Brisbane.
MEMBER: Mr PA Smith
ORDERS: 1. Taking into consideration all of the evidence before me
and, in particular that evidence referred to above, and
noting in particular the terms of settlement agreed to as
between the miner and the landholders, I recommend to
the Honourable Minister for Natural Resources and Mines
that mining lease applications 20605, 20606, 20607, 20608,
20660 and 20670 each be granted over their entire
application area, for the terms set out in paragraph 20
hereto, for the purposes sought by the applicant, subject to
the inclusion of special conditions in the mining leases and
draft environmental authorities consistent with the details
as set out in paragraphs 30, 31 and 32 hereof.
CATCHWORDS: Mining – applications for mining leases and associated
environmental authorities – objections – Mineral Resources Act
1989 – Environmental Protection Act 1994
Jurisdiction of the Land Court – withdrawal of objections made
-- 1 of 11 --
2
under the Mineral Resources Act 1989 and the Environmental
Protection Act 1994 following a negotiated settlement – whether
the Court has jurisdiction to continue to make recommendations
Mining – recommendation under s.269 Mineral Resources Act
1989 – inclusion of special conditions agreed upon by the parties
– whether condition requiring the Mining Registrar to provide
the objectors with copies of the mining leases and environmental
authorities appropriate
Mining – compensation for grant of mining leases – agreement
reached between the parties – proceedings dismissed with no
order as to costs
APPEARANCES: Mr J Trevino of Counsel for the applicant;
Mr J Korn of Counsel for the respondent; and
Mr N Loos of Counsel for the Statutory Party.
SOLICITORS: Preston Law for the applicant;
Bottoms English for the respondent; and
Legal Services, Department of Environment and Heritage
Protection for the Statutory Party.
Background
[1] Gary Awarua Donovan (“the miner”) has lodged nine mining lease applications with the
Mining Registrar, Mareeba, seeking authority to undertake mining operations on land in the
Palmerville area of Queensland. Each application is either wholly, or partly, over pastoral
land owned by Stephen Roy Struber and Dianne Rose Wilson-Struber (“the landholders”).
The landholders1 lodged objections to the grant of each mining lease under the provisions of
the Mineral Resources Act 1989 (“the MRA”). The landholders have also lodged objections
under the Environmental Protection Act 1994 (“the EP Act”) relating to each of the nine
mining leases. The landholders` objections with respect to each mining lease relate to the
environmental authority application, and for some matters also relate to the draft
environmental authority for the application and the conditions included in the draft
environmental authority for the application. The Chief Executive, Department of
Environment and Heritage Protection (DEHP)2 is a Statutory Party with respect to each EP
Act matter.
[2] The hearing of four of the mining lease applications (MLA’s) and the objections thereto
commenced on 20 November 2009. The hearings relating to objections to another MLA’s
were adjourned, pending the outcome of the first four mining lease applications.
1 In some matters, Mr Struber is the only objector, whilst in others both landholders are objectors.
2 DEHP is the entity now responsible for the EP Act, replacing the Department of Environment and Resource Management.
-- 2 of 11 --
3
Subsequently, the miner lodged an additional two mining lease applications which were also
subject to objection by the landholders.
[3] There were significant issues between the landholders and the miner, as well as issues
involving the Statutory Party. In interlocutory proceedings, various declarations and other
orders were sought. These issues were resolved in part by the Court’s decision in Donovan v
Struber & Ors3. Ultimately, the hearing of all mining lease applications and objections
thereto, together with determinations of compensation with respect to each mining lease
application4 were listed for hearing commencing in Cairns on Monday, 4 June 2012. The
hearing was listed for one full sitting week, although there was some concern that the
hearing of all matters may have actually taken perhaps considerably longer. The affidavit
evidence filed was substantial and there were a number of expert witnesses to be called.
[4] Shortly before the hearings were due to commence, Counsel for the Statutory Party
approached the Court at a review and directions hearing requesting that the parties be
ordered to attend a Preliminary Conference5 in an attempt to, at least, narrow the issues
between the parties. It was conceded that it would be very difficult to resolve all of the
issues between the parties. The Court subsequently ordered that a mediation be undertaken
for a period of one day, with the costs of an independent mediator being borne equally
between the three parties. The parties went on to engage Professor Robert Scott, a retired
Member of the Land Court, who commenced the mediation on Thursday, 31 May 2012.
[5] The mediation went exceptionally well. It continued for much longer than the anticipated
day. When the matters came on for the resumed hearing on Tuesday, 5 June 2012, Counsel
for each of the parties informed the Court that settlement had been reached in all respects in
relation to all 27 active cases before the Court, save for the question of costs as between the
miner, the landholder and the Statutory Party with respect to the objections to the mining
leases under both the MRA and the EP Act.
[6] In accordance with the terms of settlement, a copy of which was provided to the Court, the
miner has agreed to withdraw mining lease applications MLA20594, MLA20564 and
MLA20565. For their part, the landholders have agreed to withdraw their objections to
mining leases applications MLA20605, MLA20606 and MLA20607, MLA20608,
MLA20660 and MLA20670. It has further been agreed as between the miner, the
landholders and the Statutory Party that they consider it appropriate for agreed special
conditions to be incorporated into both the mining leases and environmental authorities. I
will deal with this nature of the matter later.
3 [2011] QLC0045.
4 In total, there were 27 active files as at 1 June 2012.
5 A Preliminary Conference having been conducted by the Judicial Registrar of the Court in December 2011.
-- 3 of 11 --
4
[7] Orders were made with respect to each compensation matter, dismissing each matter with no
order as to costs, as agreement had been reached between the miner and the landholders and
that agreement is in the process of being lodged with the Mining Registrar with respect to
the six remaining MLA’s.
[8] In normal circumstances, the remaining six mining lease applications would proceed with
the miner as the only party. However, as issues relating to costs with respect to the nine
mining lease applications remain outstanding, both the landowners and the Statutory Party
remain parties to the proceedings as regards final determination to costs.
Terms of Settlement
[9] As regards the six mining lease applications remaining for consideration, the following
terms of settlement are relevant6:
“3. General condition of Mining Leases (ML20605, ML 20606, ML20607, ML20608,
ML20660. ML20670):
3.1 The miner agrees to the following "before and after” compliance monitoring
regime:
The Miner will pay the costs of an annual environmental compliance
monitoring regime in relation to:
(a) Water quality including turbidity;
(b) Arsenic and mercury;
(c) Riparian vegetation;
(d) Bank stability;
(e) Stream stability including preservation of rock bars and deep
pools;
(f) The nature and extent of rehabilitation activities on mined areas;
(g) Compliance with the Standard Environmental Conditions of the
Code of Environmental Compliance for Mining Leases dated
January 2001.
The environmental compliance monitoring regime will be undertaken by an
independent expert (‘the expert’).
3.2 The expert shall be tasked to carry out a 'before and after' monitoring regime as
follows:
3.3 Prior to the commencement of mining, the expert will undertake a background
inspection in relation to the land to be mined in respect of the matters set out above
at 3.1(a) to 3.1(g) and prepare a background report;
3.4 Prior to the commencement of the wet season (i.e. not before 1 September and no
later than 30 November) the expert will undertake an inspection of land subject to
mining in respect of the matters set out above at 3.1(a) to 3.1(g) and prepare a
compliance report;
3.5 The expert will provide copies of the background report and compliance report
prepared in accordance with this paragraph to:
(a) the Miner;
(b) the Statutory Party; and
(c) the landholders.
6 Terms of Settlement between miner and landholder dated 1 June 2012.
-- 4 of 11 --
5
4. MLA 20605 - Additional conditions
4.1 Subject to Identification of the dams and their catchments:
(a) The miner will not access the dams within ML 20605 for water
supply purposes.
(b) The miner will not build any other dam wall or other obstacle so
as to affect by way of reduction the catchment for those dams.
5. MLA 20608 - Additional Conditions Plan of Operations and the Dam Wall
5.1 In respect of the discrete areas described as Dawson’s Hill and the breached dam
adjacent to Dawson's Hill, the Miner will submit a proposal, in written form in
respect of each area to the expert that deals with:
(a) The environmental values (as if the pre-existing mine
contaminants did not exist)
(b) Potential adverse and beneficial impacts on the environmental
values.
(c) Any code of environmental compliance and standard conditions
that are to apply.
(d) The extent of the environmental commitment the applicant
proposes for mining activities to protect or enhance the
environmental values in the event the code does not apply or
address an impact.
(e) Contain enough other information to allow the independent
expert to decide whether mining should proceed and if so the
conditions to apply.
(f) A copy of the miner's proposal is to be provided to the land
holder who may comment on it.
(g) The expert will consider and if appropriate approve the mining in
respect of each area. Mining will not take place on either of
those areas unless the expert approves the proposal.
(h) The approval or otherwise of the expert shall be communicated to
the miner, the landholder and the Statutory Party.
5.2 Should the Miner mine the dam area referred to in paragraph 5.1 above, the Miner
will rehabilitate the dam wall at the conclusion of mining and will, in accordance
with Condition 36 of the Standard Environmental Conditions of the Code of
Environmental Compliance for Mining Lease Projects 2001, consult with the
Landholder about obtaining written agreement that the Landholder will take
responsibility for the dam at the surrender of the lease.
6. Independent Expert Appointment
6.1 The Parties agree to appoint an expert in relation to matters covered by conditions 3
and 5.
6.2 The process for appointing an expert will be as follows:-
(a) The Miner will give the Landholder a notice requesting that they
nominate a list of experts for the purpose this Agreement;
(b) The Miner and the Landholder will exchange a list of experts
being a maximum of 4 persons together with copies of each
-- 5 of 11 --
6
proposed experts CV for appointment to a panel within 10
Business Days of the notice in 6.2(a) above.
(c) The Miner will provide a consolidated list of experts together
with a nomination of one expert from the list to be the
independent expert to the Landholder within10 business days.
(d) Where the nominated expert is agreed by the Landholder they
will give notice to the Miner within 28 days of receipt of the
consolidated list in 6.2(c) above.
(e) In the absence of agreement of the nominated expert by the
Landholder, or such other expert by the Parties within 28 days
from 6.2(c) the Miner will provide the consolidated panel of
experts, together with any CVs and any written submissions (the
submissions need not be exchanged), to Professor Robert Scott
who will decide the expert to be engaged for the purposes of this
Agreement.
(f) In the event that Professor Scott is unable to appoint an expert
then within 28 days the Miner will make a request to the
President of the Bar Association for a member of the association
in Cairns to nominate an expert from the panel.
6.3 An Expert appointed under this clause will continue for such period as the expert is
prepared to accept the position or the parties agree in writing to the substitution of a
further expert.
6.4 All documents and notices required to be given under this Agreement to each of the
Parties will be given by registered post to the Party's solicitors being Mrs Anne
English or Mr Andrew Kerr unless otherwise advised.
7. Variation of Access (ML20605, 20606, 20607, 20608, 20660, 20670)
7.1 The Miner agrees to amend the access to the above MLAs in terms of the attached
map initialed by the parties. The amendment will be effected by way of an
application to vary access made to the Mining Registrar at Mareeba.
8 Property Tracks
8.1 The Miner acknowledges the existence of property tracks within ML20605,
ML20606 and ML20607, ML20608. The Miner agrees that if he undertakes
mining which affects these property management tracks he will ensure that an
equivalent tracks is constructed so as to allow for continuing use of the tracks.”
[10] On Wednesday, 6 June 2012, the solicitor for the Statutory Party informed the Court that the
Statutory Party had no issue with respect to the proposed special conditions of the relevant
environmental authorities with respect to the six remaining mining lease applications.
Jurisdiction of the Land Court
[11] Following amendments to the MRA in 20107 amendments were made to s.265 of the MRA to
the extent that the Land Court no longer has jurisdiction to deal with mining lease
applications to which no objection is duly made. However, in the matters currently under
consideration, due to the lodgement of objections the Land Court was seized of jurisdiction,
7 See Act No. 17 of 2010.
-- 6 of 11 --
7
both under the MRA and the EP Act. As I said in the matter of Genesis Resources Ltd8 at
paragraph 5:
“[5] In my view, it is necessary for the Court to make a recommendation to the Minister
in this matter under the ‘new’ s.265 even though there are no longer any properly
made objections. Having been seized of jurisdiction by the referral from the Mining
Registrar, and in the absence of any clear legislative intent for that jurisdiction to
end on the withdrawal of the objections, the Court must exercise its jurisdiction in
accordance with the Act and make its recommendation to the Minister pursuant to
s.269.”
[12] General issues relating to MLA20605, MLA20606, MLA20607, MLA20608, MLA20660,
and MLA20670 leaving to one side the special conditions agreed between the parties as set
out above, I will first consider the relevant criteria as set out in s.269(4) of the MRA. It
should be noted that the Court has a considerable amount of filed material before it with
respect to each of these mining lease applications, and has already had a number of days of
sworn evidence provided with respect to some of these applications. The Court also
undertook a detailed inspection of the land in the vicinity of the MLA’s and also inspected
mining operations currently undertaken by the miner.
[13] Clearly, in light of the detailed evidence filed by the landholders, significant comment could
be made with respect to a number of criteria under s.269(4) of the MRA. However, I
consider it unnecessary to go into any great detail whatsoever with respect to each criteria in
light of the mediated agreement entered into between the parties which has seen the miner
abandon three mining lease applications and the landholders withdraw their objections to six
mining lease applications and the environmental authorities thereto.
[14] In considering the provisions of s.269(4) of the MRA, I have also taken into account the
significant material lodged with the Court by the Mining Registrar with respect to each
MLA.
[15] I now turn to consider each of the provisions of s.269(4) of the MRA. My comments
regarding each provision relate to all six mining lease applications.
Section 269(4)(a) – Have the provisions of the Act been complied with?
[16] The Mining Registrar issued Certificates of Application with respect to all six applications.
The Mining Registrar can only issue a Certificate if satisfied that the applicant is eligible to
apply for the mining lease and has complied with the requirements of the MRA with respect
to the application.9 In my opinion, there is sufficient evidence of compliance with the
provisions of the Act in respect to this application.
8 [2011] QLC 0022.
9 See s.252 of the MRA.
-- 7 of 11 --
8
Section 269(4)(b) – Is the land applied for mineralised or are the other purposes for which the lease
is sought appropriate?
[17] I am satisfied from the applicant’s evidence that the land applied for is mineralised. The
leases are located within a known mining area.
Section 269(4)(c) – If the land applied for is mineralised, will there be an acceptable level of
development and utilisation of the mineral resources within the area applied for?
[18] The material before me reveals the applicant’s proposed mining operations and program for
each lease, and shows appropriate development and utilisation of the mineral resources
within each area applied for.
Section 269(4)(d) – Is the land and the surface area of that land in respect of which the mining
lease is sought of an appropriate size and shape?
[19] The material before me appears to indicate mining lease applications of an appropriate size
and shape in light of the proposed mining operations.
Section 269(4)(e) – Is the term sought appropriate?
[20] The term sought for each MLA is as follows:
(a) MLA 20605 – 25 years
(b) MLA 20606 – 25 years
(c) MLA20607 – 15 years
(d) MLA20608 – 15 years
(e) MLA20660 – 15 years
(f) MLA20670 – 15 years.
[21] I consider the term of each lease application appropriate.
Section 269(4)(f) – Has the applicant the necessary financial and technical capabilities to carry on
mining operations under the proposed mining lease?
[22] The material indicates that the applicant has the financial and technical capabilities to carry
on the mining operations. The applicant has detailed his considerable mining experience. I
am satisfied that the requirements of this criterion are met.
Section 269(4)(g) – Has the past performance of the applicant been satisfactory?
[23] In light of the terms of settlement, and taking into account the special conditions in
particular, I am satisfied that, so long as those special conditions are made, there are no
concerns with regards to the applicant’s past performance.
Section 269(4)(h) – Will any disadvantage result to the holders of existing exploration permits or
mineral development licences or existing applicants for exploration permits or mineral development
licences?
[24] There is nothing in the material to indicate any disadvantage to any other person.
-- 8 of 11 --
9
Section 269(4)(i) – Do the operations to be carried on under the authority of the mining lease
conform with sound land use management?
[25] There is no evidence before me to suggest that the proposed operations do not conform with
sound land use management.
Section 269(4)(j) – Will there be any adverse environmental impacts, and if so, the extent thereof:
[26] Draft environmental authorities were publicly advertised. Although there were objections
lodged, they were withdrawn following negotiations. There is no evidence to suggest that the
environmental impacts will not be adequately dealt with by compliance with the conditions
of the authorities and the special conditions thereto.
Section 269(4)(k) – Will the public right and interest be prejudiced?
[27] There is nothing in the material to indicate any prejudice to the public right and interest.
Section 269(4)(l) – Has any good reason been shown for a refusal to grant the mining lease?
[28] There was no evidence before me that indicated any good reason why these applications
should be refused.
Section 269(4)(m) – Is the proposed mining operation an appropriate land use taking into
consideration the current and prospective uses of the land?
[29] The materials show that the projects are for the extraction of potentially valuable resources
in accordance with the environmental processes. Significantly, all objections have been
withdrawn following negotiations between the parties, for which all are to be congratulated.
I am satisfied that the proposed mining operations are an appropriate land use.
Special Conditions
[30] Mr Korn of Counsel for the landholders submitted that the various special conditions set out
in the terms of settlement should be selectively applied to the various MLA’s and
environmental authorities relating to the six existing mining lease applications. Mr Korn’s
submissions have been accepted by both the miner and the Statutory Party. Accordingly, the
special conditions from the terms of settlement should, in my view, be applied to the mining
lease applications and environmental authorities as follows:
(a) as regards the mining leases under the MRA relating to ML20605, ML20606,
ML20607, ML20608, ML20660 and ML20670 special conditions in accordance with
conditions 7 and 8 of the terms of settlement;
(b) as regards the draft environmental authority pursuant to s.222(b) of the EP Act with
respect to:
(i) MIC 200837408 for MLA20605, conditions 3, 4 and 6 of the terms of
settlement.
-- 9 of 11 --
10
(ii) MIC 200837408 for MLA20606, conditions 3 and 6 of the terms of
settlement.
(iii) MIC 200837408 for MLA20607, conditions 3 and 6 of the terms of
settlement.
(iv) MIC 200837408 for MLA20608, conditions 3, 5 and 6 of the terms of
settlement.
(v) MIC 201211710 for MLA20660, conditions 3 and 6 of the terms of
settlement.
(vi) MIC 201211710 for MLA20670, conditions 3 and 6 of the terms of
settlement.
Provision of Granted ML’s and EA’s to the Landholders
[31] The landholders have sought to have special conditions inserted into each mining lease
granted with respect to the six MLA’s that, upon grant of the mining leases, the Mining
Registrar provide a copy of each lease to the landholder. I consider such a special condition
given the rather unique circumstances of these matters, appropriate. I consider it sufficient
for the Mining Registrar to provide a copy of each mining lease to the landholder’s solicitor,
Messrs Bottoms English.
[32] Likewise, the landholders have also suggested that the environmental authorities with
respect to each of the MLA’s also be provided by the Mining Registrar, as agent/delegate for
the Statutory Party, to the landholder upon grant of each environmental authority. I consider
this also appropriate given the circumstances of this matter, and again consider it appropriate
that copies of the granted environmental authorities be provided to the landholders via their
solicitor, Messrs Bottoms English.
Environmental Objections
[33] It should be noted that I have not made any recommendation to the Minister responsible for
the EP Act. This is because of the operation of the EP Act Chapter 5, Part 6, Subdivision 2,
and in particular ss. 227 and 228. In my view, the EP Act operates differently to the MRA
in circumstances where objections are withdrawn after the land Court is seized of
jurisdiction. It is a matter for the Administering Authority to ensure that the terms agreed to
by the miner and landholder, to which it has indicated its support, are incorporated into the
relevant Environmental authorities.
[34] As I accept that there is a possibility for confusion, I have included reference to all special
conditions, including those best suited to the Environmental Authorities, in this
recommendation which, because of the operation of the relevant statutes, must be only to the
Minister responsible for the MRA.
-- 10 of 11 --
11
Recommendations
1. Taking into consideration all of the evidence before me and, in particular that evidence
referred to above, and noting in particular the terms of settlement agreed to as between the
miner and the landholders, I recommend to the Honourable Minister for Natural Resources
and Mines that mining lease applications 20605, 20606, 20607, 20608, 20660 and 20670
each be granted over their entire application area, for the terms set out in paragraph 20
hereto, for the purposes sought by the applicant, subject to the inclusion of special
conditions in the mining leases and draft environmental authorities consistent with the
details as set out in paragraphs 30, 31 and 32 hereof.
PA SMITH
MEMBER OF THE LAND COURT
-- 11 of 11 --