Dunworth v Mirvac Qld Pty Ltd [2011] QCA 200 [2012] 1 Qd R 207
SUPREME COURT OF QUEENSLAND
CITATION: Dunworth v Mirvac Qld Pty Ltd [2011] QCA 200
PARTIES: MARIS ANNE DUNWORTH
(appellant/cross-respondent)
v
MIRVAC QUEENSLAND PTY LIMITED
ACN 060 411 207
(respondent/cross-appellant)
FILE NO/S: Appeal No 1363 of 2011
SC No 4514 of 2009
DIVISION: Court of Appeal
PROCEEDING: General Civil Appeal
ORIGINATING
COURT: Supreme Court at Brisbane
DELIVERED ON: 19 August 2011
DELIVERED AT: Brisbane
HEARING DATE: 25 July 2011
JUDGES: Chief Justice, McMurdo and Dalton JJ
Separate reasons for judgment of each member of the Court,
each concurring as to the orders made
ORDERS: 1. That the appeal be allowed, the orders and directions
made on 7 February 2011 be set aside, and the order
for specific performance made on 10 December 2010
also be set aside;
2. That there be a declaration that on or about 28
January 2011 the appellant validly rescinded her
contract with the respondent dated 25 June 2007;
3. That the respondent’s cross appeal be dismissed; and
4. That the respondent pay the appellant’s costs of the
appeal, and the hearing in the Trial Division, to be
assessed on the standard basis.
CATCHWORDS: CONVEYANCING – BREACH OF CONTRACT FOR
SALE AND REMEDIES – PURCHASER’S REMEDIES –
RESCISSION – OTHER CASES – where the appellant
agreed to purchase a residential apartment – where the
original completion date was 12 May 2009 – where the
appellant had contended she was induced to enter the contract
by false, misleading and deceptive representations and had
obtained an injunction on 11 May 2009 restraining the
respondent from terminating and the respondent had counter-
claimed for specific performance – where the appellant’s
-- 1 of 12 --
2
claim was dismissed on 10 December 2010 and an order for
specific performance was made with a completion date of
8 February 2011 – where the apartment was flooded and
damaged on 13 January 2011 so as to be unfit for occupation
as a dwelling – where on 24 January 2011 the respondent
made an offer to complete necessary restoration work and
delay completion by four months – where on 28 January 2011
the appellant purported to exercise her statutory right under
s 64 Property Law Act 1974 (Qld) to rescind the contract –
where on 3 February 2011 the appellant applied for
a declaration that the contract had been validly rescinded and
for dissolution of the order for specific performance – where
the trial judge extended the time for completion to 8 June
2011 and made orders to facilitate trial of the issues raised –
whether the trial judge erred in failing to determine certain
questions of law – whether the right of rescission under s 64
Property Law Act 1974 (Qld) could subsist beyond the
contractually appointed date for completion in circumstances
where there was a subsequent order for specific performance
– whether the apartment must have been uninhabitable as at
the date of rescission – whether the respondent’s capacity to
restore the apartment was relevant
EQUITY – EQUITABLE REMEDIES – SPECIFIC
PERFORMANCE – whether rescission of a contract after an
order for specific performance is made requires the leave of
the court – whether rescission of a contract after an order for
specific performance is made requires vacation of that order –
whether a declaration should be made that the contract was
validly rescinded
Trade Practices Act 1974 (Cth), s 87
Property Law Act 1974 (Qld), s 64
Sale of Land Act 1962 (Vic), s 34
Aarons v Advance Commercial Finance Ltd (1995) Aust
Contract R 90-056, considered
Fletcher v Manton (1940) 64 CLR 37; [1940] HCA 32, cited
JAG Investment Pty Ltd v Strati [1981] 2 NSWLR 600,
considered
Johnson v Agnew [1980] AC 367, cited
Lysaght v Edwards (1876) 2 Ch D 499, cited
Ogle v Comboyuro Investments Pty Ltd (1976) 136 CLR 444;
[1976] HCA 21, cited
Singh (Sudagar) v Nazeer [1979] Ch 474, cited
Stevter Holdings Ltd v Katra Constructions Pty Ltd [1975]
1 NSWLR 459, considered
Sunbird Plaza Pty Ltd v Maloney (1988) 166 CLR 245;
[1988] HCA 11, followed
Tropical Traders Ltd v Goonan (1964) 111 CLR 41; [1964]
HCA 20, cited
-- 2 of 12 --
3
COUNSEL: W Sofronoff QC SG, with R Myers, for the appellant
A J Myers QC AO, with L F Kelly SC, for the respondent
SOLICITORS: Hall Payne Lawyers for the appellant
Corrs Chambers Westgarth for the respondent
CHIEF JUSTICE:
Preliminary
[1] By a contract dated 25 July 2007, the appellant agreed to purchase from the
respondent a residential apartment in a proposed building at Tennyson, Brisbane.
The purchase price was $2.155 million. Before any completion of the contract, the
by-then completed building was, on or about 13 January 2011, inundated by flood
water.
[2] The ground floor unit which is the subject of the contract was flooded. It was
necessary to remove the lower level of gyprock sheeting of the walls and to
disconnect the electrical wiring and appliances. A measure of the devastation of the
flood was that the respondent required four months to complete the necessary
restoration work, which it offered to carry out. The respondent made that offer on
24 January 2011.
[3] The appellant rejected the respondent’s offer to restore the unit, and on 28 January
purported to rescind the contract on the ground that the unit had been rendered
―unfit for occupation as a dwelling unit‖. The appellant thereby exercised
a statutory right of rescission said to arise from s 64 of the Property Law Act 1974
(Qld).
[4] That section provides:
―64 Right to rescind on destruction of or damage to dwelling
house
(1) In any contract for the sale of a dwelling house where,
before the date of completion or possession whichever
earlier occurs, the dwelling house is so destroyed or
damaged as to be unfit for occupation as a dwelling house,
the purchaser may, at the purchaser’s option, rescind the
contract by notice in writing given to the vendor or the
vendor’s solicitor not later than the date of completion or
possession whichever the earlier occurs.
(2) Upon rescission of a contract under this section, any money
paid by the purchaser shall be refunded to the purchaser and
any documents of title or transfer returned to the vendor
who alone shall be entitled to the benefit of any insurance
policy relating to such destruction or damage subject to the
rights of any person entitled to the insurance policy because
of an encumbrance over or in respect of the land.
(3) In this section—
sale of a dwelling house means the sale of improved land
the improvements on which consist wholly or substantially
of a dwelling house or the sale of a lot on a building units
plan within the meaning of the Building Units and Group
-- 3 of 12 --
4
Titles Act 1980 or the sale of a lot included in a community
titles scheme under the Body Corporate and Community
Management Act 1997 if the lot—
(a) wholly or substantially, consists of a dwelling; and
(b) is, under the Land Title Act 1994—
(i) a lot on a building format plan of
subdivision; or
(ii) a lot on a volumetric format plan of
subdivision, and wholly contained within a
building.
(4) This section applies only to contracts made after the
commencement of this Act and shall have effect despite any
stipulation to the contrary.‖
[5] The originally appointed completion date, following the establishment of the
applicable community title scheme, was 12 May 2009. The appellant contended she
had been induced to enter into the contract by false, misleading and deceptive
representations. On 11 May 2009, the day before the originally appointed date for
completion, the appellant obtained an injunction restraining the respondent from
terminating for default, in order to preserve her opportunity to have the court
declare the contract void under the Trade Practices Act 1974 should her contentions
be vindicated. In the resultant proceeding, the respondent counterclaimed for
specific performance.
[6] On 10 December 2010 the appellant’s claim was however dismissed, and an order
made for specific performance, with a completion date fixed for 8 February 2011. It
was on or about 13 January 2011 that the building was flooded and damaged, and
the appellant purported to exercise her statutory right to rescind on 28 January 2011.
[7] Because the sale contract was subject to the court order for specific performance,
the appellant needed the court’s leave to enforce her right. She therefore applied for
a declaration that the contract had been rescinded and the dissolution of the order
for specific performance. The learned primary Judge heard that application on
3 February 2011 and gave judgment on 7 February 2011 (completion was due under
the specific performance order on 8 February 2011). The instant appeal is brought
against that judgment.
The primary judgment
[8] The learned Judge extended the completion date to 8 June 2011, that is, by four
months, and made procedural orders to facilitate a trial of ―the issues raised in the
application‖, and entered the proceeding on the Commercial List. The extension of
time for completion was expressed to be made ―without prejudice to the
[appellant’s] right to maintain that the contract has been validly terminated pursuant
to section 64 of the Property Law Act 1974 (Qld)‖. Her Honour said there were
―questions of fact and law which cannot be determined in a summary fashion‖.
[9] The question of fact the Judge identified was whether the premises had been
damaged so as to be unfit for occupation as a dwelling, and as to the ambit of
rectification. Counsel for the respondent had sought time to adduce evidence on
those aspects (a position no longer maintained on appeal).
-- 4 of 12 --
5
[10] As to questions of law, Her Honour considered ―moot‖ whether in referring to the
date of completion, section 64 is referring to ―the date set for completion [that is, by
the contract] or the date of actual completion‖. If the former, then Counsel for the
respondent now contend that no such rescission could have been effected after
12 May 2009. Her Honour also left open whether the exercise of a statutory right of
rescission after a specific performance order has been made entitles the party
exercising that right to the dissolution of the specific performance order.
[11] The extended completion date of 8 June 2011 has now passed. The parties have
however agreed to stay the operation of the orders made on 7 February 2011 until
the determination of the instant appeal.
The parties’ contentions
[12] Mr Sofronoff QC, who appeared for the appellant, submitted that the learned Judge
erred in failing to determine the following issues:
1. the effect of the subsistence of the specific performance order on the
exercise of the statutory right to rescind;
2. the date at which the premises must have been unfit for habitation for the
right under section 64 to have been available;
3. the date of completion contemplated by section 64, in circumstances where a
specific performance order was subsisting; and
4. any relevance in the respondent’s capacity to restore the damage.
He submitted that until those matters of law were resolved, Her Honour had no
basis upon which to determine ―whether to decide the issue or issues of fact herself
or send the matter for trial‖.
[13] Mr Sofronoff pointed to an unusual aspect of the order made by the Judge, in that
―the appellant will have to perform the contract by order of the court before the
court has even determined whether she was ever obliged to do so‖. He submitted
that Her Honour’s order should be set aside, and in lieu thereof, an order be made
that the order for specific performance be vacated, with a declaration made that the
contract was rescinded on 28 January 2011; or alternatively, in the event the
respondent may wish to pursue a factual issue about habitability of the premises on
28 January 2011, that a short adjournment be granted for that purpose so that the
respondent might gather and present material going to that issue. (The respondent
now concedes the premises were relevantly uninhabitable.)
[14] Mr Myers QC, who appeared for the respondent, submitted that the section 64 right
of rescission could only have been exercised prior to the contractually appointed
date for completion, and that the appellant’s case is based on ―an attempt to take
advantage of her own wrong‖ – being her failure to complete in accordance with the
contract. He submitted that while Her Honour erred in making orders numbers two
to four (the procedural orders facilitating a trial) and five (in relation to costs), she
correctly continued the operation of the specific performance order, and he sought
a further extension of the time for completion under that order. (The respondent has
filed a cross appeal.)
[15] As mentioned already, Mr Myers conceded that as at 28 January 2011 the premises
had been damaged so as to be unfit for occupation as a dwelling house, and that that
remained the position as of 8 February 2011.
-- 5 of 12 --
6
Discussion
The appropriateness of the approach taken at first instance
[16] If the questions of law should be determined favourably for the appellant, then there
would be no occasion for a trial.
[17] The position now taken for the respondent invites attention to a limited question of
construction, namely, whether a right of rescission under section 64 could subsist
beyond the contractually appointed completion date, in circumstances where, as
here, a specific performance order in effect took over. Had that issue been
determined favourably to the respondent, there likewise would have been no need
for a trial.
[18] It would therefore have been preferable had the Judge addressed those questions
definitively, because of the consequences if determined in a particular way.
[19] The orders in fact made amounted to a deferring of the determination of issues of
both law and fact, but with the unusual consequence, to which reference has already
been made, of obliging the appellant to complete the contract in circumstances
where a court may subsequently find that she was not in reality obliged to do so.
[20] In making the orders she made, the learned Judge was exercising a discretion.
While judges may in some circumstances decline to determine questions of law
summarily because of their complexity, as upon applications for summary
judgment, this was a situation where determinations should have been made so that
the scope of the parties’ respective obligations was clarified. In my respectful view,
the learned Judge erred in not determining those questions of law, and this court
should now do so. I therefore turn to those questions.
The question of construction
[21] The effect of the specific performance order was to subject the future exercise of the
parties’ contractual rights and obligations to court control (Singh (Sugadar)
v Nazeer [1979] Ch 474, 480-2). The contract remained in force and did not merge
in the judgment for specific performance (Johnson v Agnew [1980] AC 367, 393,
Ogle v Comboyuro Investments Pty Ltd (1976) 136 CLR 444, 460).
[22] Mr Myers submitted that ―[t]he only agreed date of completion was that for which
the contract provided and which, in accordance with its terms, was 12 May 2009‖,
and that that is the date relevant for the purposes of section 64, rather than ―a date
fixed of necessity by a court because one party breached the contract‖.
[23] On the other hand, Mr Sofronoff primarily submitted that section 64 refers to the
―actual date for completion which is current at the date of termination‖, including
a date set by the court, although he advanced a less restrictive construction in his
reply, to which I will come.
[24] Mr Myers responded that the appellant thereby asked the court to interpret section
64 to ―enable her to take advantage of her own wrong‖, and referred to well-
established authority that ―a statute should not be interpreted to enable a person to
gain an advantage or profit from his or her own wrong‖ (for example, Bennion on
Statutory Interpretation, 5th ed, p 1141).
-- 6 of 12 --
7
[25] The statutory provision accords a right of rescission where premises are rendered
uninhabitable ―before the date of completion or possession‖.
[26] Subject to the terms of the particular contract (compare cl 15.2 of this contract), a
purchaser would at common law have to suffer the consequence of that loss
(Fletcher v Manton (1940) 64 CLR 37, 45, 49; Lysaght v Edwards (1876) 2 Ch D
499, 507). This statutory provision ameliorates that position. (Victoria has
a broadly comparable provision: s 34 Sale of Land Act 1962 (Vic).)
[27] Naturally read, those words in section 64 could refer to one or other of the
following.
[28] First, they could refer to the currently applicable date for completion or possession
as at the time the premises suffered the requisite damage. If the damage occurs
prior to that date, the right of rescission arises. In that regard, it may be noted the
provision does not refer to the date of completion ―appointed under the contract‖,
suggesting a date ordered by the court could fall within the ambit of the provision.
[29] Second, the words could refer to the earlier of the date of actual completion or
possession, a possibility which engaged Counsel towards the end of their oral
argument. Supporting that construction is the reference in section 64 to a date ―of‖,
rather than ―for‖, completion or possession, as if referring to a date of actual
completion, or the actual taking of possession.
[30] The apparent objective of this beneficial provision is to accord relief to a purchaser
where, without fault on his or her own part, the subject matter of an uncompleted
contract is rendered unfit for the purpose. Consistently, the second of those
constructions is textually preferable: if prior to actual completion or possession the
premises are rendered unfit in that way, the purchaser gains a right of rescission.
[31] As has been seen, the written submissions focused on the significance of the court’s
imposition of the date for completion by means of the order for specific
performance, in the context of the contractually agreed date for completion. It is not
necessary to analyse those competing contentions in detail because of what
I consider to be the natural construction of the provision. But in deference to the
arguments of Counsel, the following points may briefly be made, and they support
the view that if the actual date ―of‖ completion should yield to the current date ―for‖
completion, the latter concept nevertheless embraces a date set by the court under an
order for specific performance and is not limited to the contractual prescription.
[32] First, Mr Myers submitted that the decree for specific performance need not have
specified a date for completion, reinforcing his contention as to the irrelevance of
the date in fact appointed here by the court. The submission would be sufficiently
answered by the fact that the court did appoint the date which thereby became the
currently applicable date for the purpose of section 64. Had no date been set by the
court, one party could have given notice to complete, or the parties may have agreed
on a date, or the court could itself subsequently have set a date. Had no date been
nominated, agreed or set in that way prior to 28 January 2011, the section would
nevertheless have been engaged, because ―the date of completion or possession‖
would, although not yet prescribed, have remained in the future.
[33] Second, the opening words of section 64(1), ―[i]n any contract for the sale…‖, upon
which Counsel for the respondent relied, would not require or suggest that the
-- 7 of 12 --
8
subsequent reference to ―the date of completion or possession‖ be limited to that
contractually agreed. The opening reference to ―the contract‖ is intended simply to
signal that the availability of this right of rescission is limited to agreements for the
purchase of dwellings.
[34] Third, Counsel for the appellant pointed out that the respondent could have avoided
the risk of this situation arising by terminating the contract for the appellant’s
failure to complete, rather than enforcing the contract following the dismissal of the
appellant’s claim on 10 December 2010. While the respondent would thereby have
avoided this risk, with the inundation occurring later, I do not consider it necessary
or especially helpful to have regard to that sort of consideration in determining the
natural construction of section 64: the words are clear and speak for themselves.
[35] Fourth, Counsel for the respondent provided an example of what was said to be the
―capricious‖ operation of section 64 if the construction primarily urged by the
appellant were adopted. Counsel submitted that ―a purchaser who had no grounds
for rescinding a contract and who was due to complete it under the contract, and
who had an expectation from weather predictions that a severe flood could occur in
the foreseeable future (or a damaging storm), could deliberately and wilfully breach
the contract, fail to complete, and act on the chance that a court-ordered date for
specific performance would post-date a flood or damaging weather event that might
occur‖, and under that scenario derive a right of rescission. What I believe is the
natural construction of section 64 should not yield to such an extreme possibility.
[36] Fifth, I would in any case accept the responding submission for the appellant, that
when the court specified a new date for completion, that became in all respects the
applicable date under the contract which subsisted subject to court control.
[37] But as I have said, it is compelling to conclude, and I do, that the provision should
naturally be read as contemplating the actual date ―of‖ completion or possession: if
that has not arrived, in that neither completion has occurred nor possession been
taken, and the requirement of the provision is satisfied (destruction or damage
leading to unfitness for occupation), a right of rescission is available to the
purchaser.
Conclusion
[38] It follows that because, as conceded, the unit was rendered uninhabitable by the date
of the purported rescission, the appellant gained a right to rescind at any time up to
the date of actual completion or possession (whichever be the earlier date).
[39] Addressing the other points left open by Her Honour, I would accept the submission
that the unit must have been uninhabitable as at the date of the rescission which was
effected. Also, noting that the provision gives no right to a vendor to maintain the
contract in order to attempt to repair the damage, the possibility of restoration does
not preclude rescission where the premise of the provision has been met, that is, the
dwelling has been destroyed or damaged so as to be unfit for occupation as
a dwelling.
[40] The submission that this construction rewards a wrong-doing purchaser is
unfounded. The appellant had at an anterior stage suffered the consequence of her
breach of contract: she was subjected to court orders adverse to her, including an
-- 8 of 12 --
9
order for specific performance, the respondent having decided to enforce rather than
terminate the contract. The subsequent damaging of the property was obviously
entirely without fault on her part. Any benefit she gained from the exercise of her
right of rescission was not consequent upon any ―wrong-doing‖ on her part, the
consequences of which had earlier been spent; it was the consequence of the
operation of remedial legislation.
Appropriate relief
[41] The orders made by the learned Judge should be set aside, and the order for specific
performance originally made on 10 December 2010 and varied by Her Honour on
7 February 2011 set aside.
[42] In Sunbird Plaza Pty Ltd v Maloney (1988) 166 CLR 245, 260 Mason CJ observed
that ―rescission after an order for specific performance requires the leave of the
court or, more appropriately, the vacation of the order‖. Neither was sought in this
case in advance of the purported rescission. In Stevter Holdings Ltd v Katra
Constructions Pty Ltd [1975] 1 NSWLR 459, 469-470, Helsham J dealt with such a
situation by discharging the contract. See also the approach of the New South
Wales Court of Appeal in JAG Investment Pty Ltd v Strati [1981] 2 NSWLR 600,
603. In Stevter, Helsham J observed that where a rescission had otherwise been
duly effected, there would ordinarily be an entitlement to the discharge of the
contract.
[43] We were informed that whether the contract is discharged now, or the rescission on
28 January 2011 retrospectively authorized, has no commercial consequence.
Which course is now followed is a formality.
[44] However, following the approach suggested by Mason CJ in Sunbird Plaza, the
preferable approach in this case is probably simply to order that the order for
specific performance made on 10 December 2010 and varied on 7 February 2011 be
vacated. That would fall within the court’s power in regulating performance by the
parties under the contract, and would operate to remove, retrospectively, the fetter
upon the appellant’s power to exercise her statutory right of rescission when she
did.
[45] There should also however be a declaration that the appellant validly rescinded the
contract on 28 January 2011. With the vacating of the order for specific
performance, such a declaration is strictly not necessary, but should be made lest
there be any residual doubt as to the validity of the rescission. So far as necessary,
the court would thereby be seen to be lending its authority to that course
retrospectively.
Orders
[46] The following orders should be made:
1. that the appeal be allowed, the orders and directions made on 7 February
2011 be set aside, and the order for specific performance made on 10
December 2010 also be set aside;
2. that there be a declaration that on or about 28 January 2011 the appellant
validly rescinded her contract with the respondent dated 25 June 2007;
3. that the respondent’s cross appeal be dismissed; and
4. that the respondent pay the appellant’s costs of the appeal and cross-appeal,
and the hearing in the Trial Division, to be assessed on the standard basis.
-- 9 of 12 --
10
[47] McMURDO J: I agree with the orders proposed by the Chief Justice and
I substantially agree with his reasons.
[48] The application to the primary judge involved no factual issue of any consequence.
Clearly the property was unfit for occupation when the appellant purported to
terminate the contract and was to remain so for some months. But the respondent
suggested to the primary judge that there was a factual question, which was whether
the unfitness for occupation came from the flooding itself as distinct from what the
respondent had done afterwards, such as removing all sheeting and disconnecting
electrical wiring. As I read the transcript of that argument, this was the factual issue
which the respondent suggested required a trial. Not surprisingly, that was not
a submission repeated in this appeal. The respondent could hardly have avoided the
operation of s 64 by proving that the critical damage was that which it had inflicted.
[49] The real question raised by the application concerned the proper interpretation of
s 64 and, in particular, the meaning of the expression ―date of completion‖. The
appellant’s principal argument is that this was the date fixed by the Court in
ordering specific performance of the contract. The respondent’s case is that it was
the agreed date for completion, which had long passed. And ultimately the
appellant further argued that it means the date of actual completion. In my view, it
is that third argument which should be accepted.
[50] A difficulty in this interpretation is that s 64 does not simply refer to completion,
but to the date of completion. Against that, the term is date of completion rather
than date for completion. And the respondent conceded that the alternative of
―possession‖ means actual possession, rather than an agreed date on which the
purchaser would take possession, which provides some support for the
interpretation which I accept.
[51] The evident policy underlying this provision is the protection of purchasers of
dwelling houses from the burden of having to complete a contract where the house
becomes uninhabitable by destruction or damage after the contract is made. Absent
a term to the contrary, the common law position would be that the property would
be at the purchaser’s risk pending completion.1 The apparent purpose of this
provision is to shift that risk to vendors.
[52] The respondent argues that the legislative purpose could not have been to assist a
purchaser who had failed to complete as agreed, which was the position here.
However, the respondent’s argument, if accepted, would also affect the position of
an innocent purchaser. Upon its argument, if the agreed date for completion passed
because of the default of the vendor, after which the house was destroyed but before
completion, nevertheless the purchaser would be without the protection of s 64(1).
That unattractive result, it is argued, would be the consequence of the purchaser’s
election to affirm the contract. This is difficult to reconcile with the apparent
purpose of the provision. Moreover, an innocent purchaser would not be obliged to
elect immediately upon the vendor’s failure to complete on the agreed date,2 so that
upon the respondent’s argument, a purchaser could lose the benefit of s 64 where
the house is destroyed prior to an election to affirm.
[53] The most likely intention, which is consistent with the words used, is that this
alteration of the risk in favour of purchasers should remain in place notwithstanding
1 Fletcher v Manton (1940) 64 CLR 37 at 45.
2 Tropical Traders Ltd v Goonan (1964) 111 CLR 41.
-- 10 of 12 --
11
the passage of the agreed date for completion. The burden of this risk upon the
vendor is made an element of the contractual relationship for as long as the contract
remains on foot. Where an innocent vendor affirms the contract after a purchaser’s
failure to complete, the contract which is affirmed retains that element. In this
particular case, the innocent vendor was restrained by an interlocutory injunction
from terminating the contract for the purchaser’s failure to complete, although the
purchaser’s claim for ultimate relief, under s 87 of the Trade Practices Act 1974
(Cth), was for the termination of the contract. On one view, the operation for s 64
in these circumstances could appear harsh. But the particular circumstances could
not have been considered to be so likely to occur that they should affect the
interpretation of s 64.
[54] Central to the respondent’s argument is the proposition that the contract remained
unaffected by the terms of the order for specific performance. I would accept that
proposition which, although not affecting the interpretation of the section, is
relevant to the terms of the relief which should be granted to the appellant. The
appellant applied for a declaration that she had duly terminated the contract on
28 January 2011. She also applied for an order that ―the decree of specific
performance and the ancillary and incidental orders made herein on 10 December
2010 be dissolved‖. This was consistent with the longstanding view that an order
for specific performance should not be left in place if the contract had been or was
to be terminated. In Sunbird Plaza Pty Ltd v Maloney, Mason CJ (with whom
Deane, Dawson and Toohey JJ agreed) said that ―…rescission after an order for
specific performance requires the leave of the court or, more appropriately, the
vacation of the order‖.3
[55] But according to some authority, a contract could not be terminated after a decree of
specific performance without first obtaining the permission of the Court, so that it
would be by the Court’s order that the termination occurred. For example, in JAG
Investment Pty Ltd v Strati, Hope JA, citing Johnson v Agnew,4 said that in this
context ―…it is clear that the contract cannot be determined until the approval or
order of the court has been obtained, and that it is the order, or something done by
authority of the order, that operates to terminate the contract‖.5 At the same time,
Hope JA said of this jurisdiction (to set aside the order for specific performance)
that its ―precise nature … is not entirely clear‖.6
[56] In Sunbird Plaza Pty Ltd v Maloney, Mason CJ noted that a line of English
authority, for the proposition that a plaintiff who has obtained an uncompleted order
for specific performance cannot terminate for the defendant’s subsequent
repudiation, had been strongly criticised7 and his Honour referred in particular to
Meagher, Gummow & Lehane, Equity: Doctrines & Remedies (2nd ed 1984) [2053],
pp 504-507 (a criticism maintained in the current edition).8 Meagher JA repeated
that criticism in Aarons v Advance Commercial Finance Ltd9 where, after a
purchaser failed to perform according to an order for specific performance, the
vendor went back to Court to seek to terminate the contract. His Honour said: ―…
3 (1988) 166 CLR 245 at 260.
4 [1980] AC 367 at 394.
5 [1981] 2 NSWLR 600 at 603.
6 Ibid.
7 (1988) 166 CLR 245 at 259.
8 Meagher, Gummow & Lehane, Equity: Doctrines & Remedies (4th ed, 2002) [20-265].
9 (1995) Aust Contract R 90-056.
-- 11 of 12 --
12
[at] that point, in my view, the vendor could have terminated the contract without
further ado. However, a doctrine seems to be prevalent that a contract cannot be
terminated by the innocent party if a decree for specific performance has been made
by the court. I can see no justification for any such doctrine. Once it is conceded –
and all authorities do concede it – that an order for the specific performance of
a contract does not cause the contract to merge in the order, no rational justification
of the doctrine can be formulated: sed dis aliter visum: Johnson v Agnew [1980]
AC 827, JAG Investments Pty Ltd v Strati [1981] 2 NSWLR 600‖.10
[57] That criticism has particular force, but it remains necessary to proceed according to
Sunbird Plaza Pty Ltd v Maloney, from which it is clear that in this context, there
must be some order which puts paid to the order for specific performance.
Mason CJ was careful to point out that this was appropriately described as
a vacation of the order for specific performance rather than the grant of the Court’s
permission for the termination of the contract. Here, although specific performance
had been ordered, the contract retained in all respects its effect according to its
terms. An order of the Court was unnecessary for the appellant to terminate this
contract, as she did on 28 January. But the order for specific performance could not
be left unattended, and the Court’s record had to be amended to correspond with
what had become the contractual position. Accordingly, the appropriate orders are
those proposed by the Chief Justice.
[58] DALTON J: I agree with the orders proposed by the Chief Justice, and his reasons
for them. I also agree with the reasons of Philip McMurdo J and the views he
expresses as to vacation of an order for specific performance being the preferable
course after a contract is properly terminated during the currency of such an order.
10 Ibid at 90,285.
-- 12 of 12 --