ACN 096 278 483 Pty Ltd v Vercorp Pty Ltd & Anor; Vercorp Pty Ltd v ACN 096 278 483 Pty Ltd [2011] QCA 189
SUPREME COURT OF QUEENSLAND
CITATION: ACN 096 278 483 Pty Ltd v Vercorp Pty Ltd & Anor;
Vercorp Pty Ltd v ACN 096 278 483 Pty Ltd [2011] QCA 189
PARTIES: In Appeal No 12847 of 2010:
ACN 096 278 483 PTY LTD as trustee of the WILLIAMS
FAMILY TRUST
(appellant)
v
VERCORP PTY LTD
ACN 010 198 268
(first respondent)
HEGIRA LIMITED
ACN 008 610 357
(second respondent)
In Appeal No 12868 of 2010:
VERCORP PTY LTD
ACN 010 198 268
(appellant)
v
ACN 096 278 483 PTY LTD as trustee of the WILLIAMS
FAMILY TRUST
(respondent)
FILE NO/S: Appeal No 12847 of 2010
Appeal No 12868 of 2010
SC No 6442 of 2004
DIVISION: Court of Appeal
PROCEEDING: General Civil Appeals
ORIGINATING
COURT: Supreme Court at Brisbane
DELIVERED ON: 9 August 2011
DELIVERED AT: Brisbane
HEARING DATE: 7 April 2011
JUDGES: Fraser and White JJA and Atkinson J
Separate reasons for judgment of each member of the Court,
each concurring as to the orders made
ORDERS: In Appeal No 12847 of 2010:
1. Dismiss the appeal.
2. Allow the cross appeal.
3. Declare that the contract between the first respondent
and the appellant for the purchase by the first
-- 1 of 33 --
2
respondent of Lot 413 on SP133280 should be
specifically performed and carried into effect.
4. Declare that the contract between the first respondent
and the appellant for the purchase by the first
respondent of Lot 414 on SP133280 should be
specifically performed and carried into effect.
5. The parties are at liberty to apply in the trial division
for any further or other orders relating to the specific
performance of those contracts.
6. Order that the appellant pay the respondents’ costs of
and incidental to the appeal.
7. Order that the first respondent pay the appellant’s
costs of the first respondent’s cross appeal.
In Appeal No 12868 of 2010:
1. Appeal dismissed with costs.
CATCHWORDS: CONTRACTS – GENERAL CONTRACTUAL
PRINCIPLES – PARTIES – GENERAL PRINCIPLES –
where Hegira and Barrier Developments “and or nominee”
entered into four contracts for the sale of land which
contained post settlement obligations – where Barrier
Developments nominated ACN as the purchaser under the
contracts – where ACN and Barrier Developments were
controlled by the same director – where during pre-
contractual negotiations Hegira made it clear that a nominee
would only be accepted if it agreed to comply with the post
settlement obligations – where ACN paid further deposits in
consideration of extensions of the finance approval dates and
the balance purchase price – whether, objectively viewed,
ACN intended to bind itself to the contracts, including the
post settlement obligations
CONVEYANCING – BREACH OF CONTRACT FOR
SALE AND REMEDIES – PURCHASER’S REMEDIES –
SPECIFIC PERFORMANCE – GENERAL PRINCIPLES –
where the contracts for sale included liquidated damages
clauses and options for Hegira to repurchase the land in the
event of breach of the post settlement obligations – where
Hegira (and Vercorp as Hegira’s assignee) commenced
proceedings in the District Court for damages pursuant to the
liquidated damages clauses – where Hegira and Vercorp later
commenced proceedings in the Supreme Court seeking
specific performance of the repurchase contracts – whether
the trial judge erred in finding that Vercorp had not waived
its rights to seek specific performance by instituting
proceedings for damages in the District Court
CONVEYANCING – BREACH OF CONTRACT FOR
SALE AND REMEDIES – PURCHASER’S REMEDIES –
SPECIFIC PERFORMANCE – GENERAL PRINCIPLES –
where the trial judge made a declaration that ACN was bound
-- 2 of 33 --
3
to complete two of the repurchase contracts but declined to
make a decree of specific performance because of allegations
of misconduct pursuant to the Trade Practices Act 1974 (Cth)
in ACN’s counterclaim which remained unlitigated – where a
number of the allegations of misconduct had previously been
struck out of the counterclaim – where it does not appear that
the misconduct will be pursued – whether the trial judge erred
in declining to make a decree of specific performance
CONVEYANCING – BREACH OF CONTRACT FOR
SALE AND REMEDIES – VENDOR’S REMEDIES –
RESCISSION OR TERMINATION – PURSUANT TO
CONDITION GIVING RIGHT TO RESCIND OR
TERMINATE – where in relation to two of the repurchase
contracts Vercorp provided the transfer documents and
valuation to ACN at about midday on the day of settlement –
where ACN pleaded that Vercorp failed to comply with its
obligation to provide the transfer documents “a reasonable
time before the Settlement Date” allowing ACN to terminate
the contract – whether the trial judge erred in finding that
Vercorp had not breached its obligation because the
determination of the price by valuation was a condition
precedent to the performance of the obligation, and that as a
result, ACN was not entitled to terminate the contracts
CONTRACTS – GENERAL CONTRACTUAL
PRINCIPLES – DISCHARGE, BREACH AND DEFENCES
TO ACTION FOR BREACH – CONDITIONS –
CONDITIONS PRECEDENT AND SUBSEQUENT – where
in relation to two of the repurchase contracts the valuations of
market value had not been received by the agreed date for
completion – where ACN purported to terminate the contracts
on the basis that Vercorp had failed to tender the balance
purchase price on the date for completion – whether the trial
judge erred in finding that the valuations were a condition
precedent to performance allowing either party to terminate
the contracts, and that as a result, ACN had validly
terminated the contracts
PROCEDURE – SUPREME COURT PROCEDURE –
QUEENSLAND – PROCEDURE UNDER UNIFORM
CIVIL PROCEDURE RULES AND PREDECESSORS –
PLEADING – GENERALLY – where ACN did not rely
upon the condition precedent as a basis for terminating the
contracts or specifically plead the condition precedent in its
defence and counterclaim – whether the trial judge erred in
finding that ACN had validly terminated the contracts
pursuant to the condition precedent
Land Title Act 1994 (Qld), s 184
Uniform Civil Procedure Rules 1999 (Qld), r 149(1)(c),
r 150(4)(a), r 150(4)(c), r 153(2)
-- 3 of 33 --
4
Banque Commerciale SA (In liq) v Akhil Holdings Ltd (1990)
169 CLR 279, cited
Codelfa Construction Pty Ltd v State Rail Authority (NSW)
(1982) 149 CLR 337; [1982] HCA 24, applied
Coulton v Holcombe (1986) 162 CLR 1; [1986] HCA 33,
cited
Godfrey Constructions Pty Ltd v Kanangra Park Pty Ltd
(1972) 128 CLR 529; [1972] HCA 36, cited
Harry v Fidelity Nominees Pty Ltd (1985) 41 SASR 458,
considered
Hill v Terry [1993] 2 Qd R 640, cited
International Air Transport Association v Ansett Australia
Holdings Ltd (2008) 234 CLR 151; [2008] HCA 3, cited
Minion v Graystone Pty Ltd [1990] 1 Qd R 157, cited
Overlook v Foxtel [2002] NSWSC 17, applied
Pacific Carriers Ltd v BNP Paribas (2004) 218 CLR 451;
[2004] HCA 35, cited
Parland Pty Ltd v Mariposa Pty Ltd (1995) 5 Tas R 121;
[1995] TASSC 91, applied
Re Ronim Pty Ltd [1999] 2 Qd R 172; [1998] QCA 444,
considered
Salter v Gilbertson (2003) 6 VR 466, considered
Sandra Investments Pty Ltd v Booth (1983) 153 CLR 153;
[1983] HCA 46, distinguished
Sargent v ASL Developments Ltd (1974) 131 CLR 634;
[1974] HCA 40, cited
Secured Income Real Estate (Australia) Ltd v St Martins
Investments Pty Ltd (1979) 144 CLR 596, cited
Shepherd v Felt & Textiles of Australia Ltd (1931) 45
CLR 359; [1931] HCA 21, cited
Vennard v Delorain P/L as Trustee for the Delorain Trust
[2010] QCA 309, cited
Vercorp Pty Ltd & Anor v ACN 096 278 483 Pty Ltd as
trustee of the Williams Family Trust (No 2) [2010] QSC 405,
considered
Whisprun Pty Ltd v Dixon (2003) 200 ALR 447; [2003]
HCA 48, applied
COUNSEL: A J H Morris QC, with L A Jurth, for the appellant in Appeal
No 12847 of 2010 and for the respondent in Appeal No
12868 of 2010
D R Cooper SC, with C L Francis, for the respondents in
Appeal No 12847 of 2010 and for the appellant in Appeal No
12868 of 2010
SOLICITORS: Londy Lawyers for the appellant in Appeal No 12847 of 2010
and for the respondent in Appeal No 12868 of 2010
Hynes Lawyers for the respondents in Appeal No 12847 of
2010 and for the appellant in Appeal No 12868 of 2010
-- 4 of 33 --
5
[1] FRASER JA: Hegira Ltd entered into four separate contracts to sell four lots of
vacant land at Pacific Harbour on Bribie Island to Barrier Developments Pty Ltd
“and or nominee”. Each contract conferred upon the seller an option to repurchase
the lot if the buyer did not complete construction of an approved dwelling house
within a specified period. Barrier Developments nominated ACN 096 278 483 Pty
Ltd as trustee of the Williams Family Trust and Hegira transferred the land to it
under each contract. ACN did not comply with the building covenants and Hegira
purported to exercise the options to repurchase the land from ACN. ACN denied
that it was obliged to sell the land.
[2] Hegira and Vercorp Pty Ltd (as assignee of Hegira’s rights under the contracts) sued
ACN in the trial division for, amongst other orders, specific performance of the
contracts for the repurchase by Vercorp of four lots of land from ACN. The trial
judge dismissed Vercorp’s claim for specific performance of the contracts for two of
the lots (Lots 411 and 412) but declared that on 7 June 2006 ACN was bound to
complete the contracts in relation to the other two lots (Lots 413 and 414).1
[3] ACN has appealed against that declaration. Vercorp has cross appealed, contending
that the declaration was insufficient and the trial judge should have ordered specific
performance of those contracts. Vercorp has also appealed against the trial judge’s
refusal of its claim for specific performance of the contracts for Lots 411 and 412.
[4] The issues in the appeals and cross appeal include the questions whether ACN
became contractually bound by the relevant provisions of the contracts and, if so,
whether it validly terminated the contracts resulting from Hegira’s exercise of the
options to purchase in the contracts. Before identifying the issues in more detail it is
useful to elaborate upon the factual background.
Factual background
[5] Each of the four contracts was made on 9 April 2001. The prices for the four lots
varied in a range between $500,000 and $650,000. The contracts included the REIQ
standard terms, special conditions 11 to 21 in Annexure A, “community
development covenants” in Annexure B, a “schedule of requirements” in Annexure
C, further special conditions 22 to 30 in Annexure D, and a disclosure statement and
plans in Annexure E.
[6] The community development covenants: obliged the buyer to construct the building
in accordance with specified “community development standards” and the schedule
of requirements; entitled the seller to remove structures which contravened the
covenants and to recover the costs of doing so from the buyer; obliged the buyer,
before selling, transferring or otherwise disposing of the land, to deliver to the seller
a deed of covenant by the purchaser in favour of the seller in the form of the
community development covenants; and obliged the buyer to pay liquidated
damages of $25,000 for any breach of the covenants.
[7] By cl 22 of the special conditions the buyer undertook to complete construction in
accordance with the covenants within a specified period of the date of the contract.
In the contract for the sale of Lot 411 the specified period was 30 months. For
Lot 412 the specified period was 18 months, for Lot 413 it was 54 months, and for
Lot 414 it was 42 months. Clause 25 of the special conditions provided:
1 [2010] QSC 405.
-- 5 of 33 --
6
“25.1 In consideration of the payment of the sum of One Dollar
($1.00) by the seller to the buyer (the receipt of which the
buyer acknowledges) the buyer grants to the seller an option
to purchase the land at the price hereinafter determined and
on the conditions specified herein.
25.2.1 This option is binding on the buyer and in the event of his
death on his estate
25.2.2 The benefit of this option may be assigned and may be
exercised by the seller or its duly appointed assignee.
25.3 This option may be exercised at any time after [the specified
period] from the date hereof in the event that the buyer has
not completed construction of an approved dwelling house
on the land in accordance with the terms of this contract.
25.4.1 Notice of exercise of option shall be given by written notice
to the buyer together with a bank cheque for $1,000 by way
of deposit on account of the purchase price.
25.4.2 On delivery of the Notice of Exercise of Option the buyer
and the seller become immediately bound as Vendor and as
Purchaser respectively under a Contract for sale of land in
accordance with the terms of the Contract currently
approved by the Real Estate Institute of Queensland for the
sale of land.
25.4.3 Settlement of the Contract shall take place within 30 days of
the date of delivery of the notice of exercise of option, or
such extended period as may be agreed.
25.5 The purchase price to be paid by the seller to the buyer
pursuant to this clause shall be the market value determined
by a Valuer or Land Economist appointed by the President
for the time being of the Australian Institute of Valuers and
Land Economists (Queensland Division).”
[8] ACN was incorporated on 21 March 2001. Mr Craig Williams was the sole director
of each of Barrier Developments and ACN at the time the contracts were entered
into. Mr Williams did not give evidence. The trial judge accepted the evidence of
a witness called by Hegira and Vercorp, Ms Mengel, about conversations she had
with Mr Williams during negotiations for the sales in about March 2001.
Mr Williams advised Ms Mengel that he required accounting advice on which entity
was to purchase the properties. He said that he was purchasing one of the properties
for himself to live in, one for his father, one for his family to use as a holiday home,
and the fourth property for his employees to use as a holiday home. Ms Mengel
discussed this with her superior, Mr Russell, who said that he would accept the
words “and/or nominee” in the contract but only on the condition that whichever
entity purchased the land must comply with the building requirements and otherwise
perform the contract. Ms Mengel passed that on to Mr Williams, telling him that
Mr Russell had insisted upon the requirement that whichever entity purchased the
land would have to comply with “the contract, the building covenant and especially
the building time frames.” Mr Williams replied that this was “not a problem at all”.
-- 6 of 33 --
7
[9] The concluded contracts identified “the buyer” as Barrier Developments Pty Ltd
“and or nominee” and the community development covenants defined “buyer” (in
cl 11.6 of Annexure B) as “the person why [sic] buys the allotment from the
developer”.
[10] A letter dated 23 April 2001 from Barrier Developments’ solicitor to Hegira’s
solicitor referred to ACN as the “intended purchaser” of the properties. Other
correspondence between the solicitors for ACN and Hegira continued to describe the
buyer of the properties as “Barrier Developments and/or nominee”, but payments
made in consideration of an extension of the finance approval dates were made by
ACN to Hegira on or about 2 August 2001, transfer documents were prepared
naming ACN as the transferee of each property, the balance purchase price was paid
by ACN on 2 November 2001, and the properties were transferred into ACN’s
name.
[11] Following settlement ACN failed to complete construction of the dwelling houses
by the times required by the contracts. Hegira purported to exercise the options to
repurchase Lots 411 and 412 by letters from its solicitor to ACN’s solicitor on 5 and
18 December 2003. By letter dated 24 February 2004, ACN’s solicitor replied in the
following terms:
“We now act on behalf of ACN 096 278 483 Pty Ltd as Trustee for
the Williams Family Trust. Our client has instructed us to write to
you in relation to your letter of 5 December 2003 to our client’s
former solicitors … and your letter of 18 December 2003 to our
client’s former solicitors … .
Under clause 25.4.3 of the respective contracts of sale, the settlement
of the contracts formed by the exercise of the options contained in
those contracts of sale was required to:
‘take place within 30 days of the date of delivery of
the Notice of Exercise of Option, or such extended
period as may be agreed’.
We further note that clause 25.4.2 of the respective contracts of sale
provides that:
‘On delivery of the Notice of Exercise of Option the
Buyer and the Seller become immediately bound as
Vendor and as Purchaser respectively under a
Contract for Sale of land in accordance with the
terms of the Contract currently approved by the Real
Estate Institute of Queensland for the sale of land.’
As you will be aware, the Real Estate Institute of Queensland
approved contract provides that if a buyer fails to comply with any
provision of the contract, the seller is entitled to terminate the
contract.
We note that in the case of each of the two contracts formed by the
exercise of the options, your client failed to tender the balance of the
purchase price on the due date for settlement. Our client regards this
failure as a serious breach of each of the contracts. In the
circumstances, our client elects to terminate both of those contracts.”
-- 7 of 33 --
8
ACN did not then deny that it had become bound as the buyer under the original
contracts of sale and as the seller under the repurchase contracts formed upon
exercise of the options.
[12] On 19 January 2004, Hegira commenced proceedings in the District Court against
ACN seeking $75,000 as liquidated damages. In that proceeding Hegira alleged that
ACN did not conduct any substantial building works on Lots 411, 412 and 413
between August 2003 and December 2003. That was alleged to constitute a breach
of a clause in the community development standards which provided that:
“No building shall be left without substantial work being carried out
for longer than one (1) month. Total construction time for erection of
a building shall not exceed nine (9) months…”.
[13] Hegira subsequently assigned all of its rights and interests in the contracts to
Vercorp. The District Court proceeding was not pursued, but it was not
discontinued.
[14] On 8 May 2006, Vercorp purported to exercise the options to repurchase Lots 413
and 414. ACN refused to reconvey the lots, but it did not then assert that it was not
bound by the options. Pursuant to cl 25.4.3 of the special conditions the due date for
settlement of the repurchase contract for Lots 413 and 414 was 7 June 2006. For
reasons to which it will be necessary to return, the valuation required by cl 25.5 was
not provided to ACN until the day of settlement. The transfer documents, which
could not be completed until the valuation had been received, were also not provided
until the day of settlement. Vercorp’s solicitors faxed the valuation and the transfer
documents to ACN’s solicitors at about 12.20 pm on 7 June 2006, together with
a copy of the bank cheques which would be provided at settlement. Vercorp
nominated 3.00 pm that day at the Titles Office as the time and place for settlement,
unless ACN notified to the contrary, and noted that if further time was required to
arrange releases of mortgages, a written request for an extension of the settlement
date should be forwarded.
[15] No representative of ACN attended at settlement. Vercorp’s solicitor sent a fax to
ACN’s solicitor stating that Vercorp remained ready, willing and able to settle at any
time up to 5.00 pm. In subsequent correspondence Vercorp affirmed the contracts.
On 13 June 2006, ACN, by it’s solicitor’s letter to Vercorp’s solicitor, purported to
terminate the repurchase contracts for Lots 413 and 414 on the ground (amongst
others) that Vercorp had “failed to give [ACN] reasonable time to consider the
valuation before the time for settlement expired.”
Proceedings in the trial division
[16] Vercorp and Hegira commenced proceedings against ACN in the trial division
seeking specific performance of the contracts to repurchase all of the properties,
damages for the cost of removing the partially erected dwellings, and liquidated
damages pursuant to the community development covenants. ACN defended the
proceedings. Amongst other defences, ACN contended that it was not bound by the
contracts but was a mere transferee of title to the properties, or it had validly
terminated the repurchase contracts, or that Hegira’s commencement and
maintenance of the District Court proceedings constituted an irrevocable election to
seek damages in lieu of a decree of specific performance in relation to Lots 411, 412
and 413.
-- 8 of 33 --
9
[17] The trial judge dismissed Vercorp’s claims for liquidated damages, and those claims
are no longer in issue. The trial judge rejected ACN’s “mere transferee” and
“irrevocable election” defences. The trial judge dismissed Vercorp’s claim for
specific performance of the repurchase contracts for Lots 411 and 412 on the
different ground that ACN had validly terminated those contracts. In relation to
Lots 413 and 414, the trial judge declared that on 7 June 2006 ACN was bound to
complete the repurchase contracts, holding that ACN had not validly terminated
those contracts. The trial judge made that limited declaration, rather than ordering
specific performance of the repurchase contracts for Lots 413 and 414, on the
footing that any order for specific performance should await the determination of
a counterclaim brought by ACN.
ACN’s appeal
[18] In ACN’s appeal, it contended that the trial judge erred in rejecting its arguments
that it was not bound by any of the contracts but was a “mere transferee” of Barrier
Developments or, in the alternative, that it had validly terminated the repurchase
contracts in relation to Lots 413 and 414, or Vercorp had made an irrevocable
election to seek damages in lieu of a decree of specific performance in relation to
Lots 411, 412 and 413.
The “mere transferee” ground
[19] In its appeal, ACN substantially repeated the argument rejected by the trial judge
that it had not become a party to any contract with Hegira (or Vercorp as Hegira’s
assignee).
[20] It is not contentious that a named purchaser’s nomination of a third party as the
transferee under a contract for the sale of land to the named purchaser “or nominee”
does not substitute the nominee for the originally named purchaser as a party to the
contract. Numerous decisions cited by the trial judge support that proposition.2
[21] The trial judge also referred to authority which supported ACN’s argument that clear
words would be needed to establish an agreement that, upon the original purchaser’s
nomination, the nominee would become a party to a contract with the vendor. In
Harry v Fidelity Nominees Pty Ltd3 King CJ observed that: he would be “most
unwilling to construe a contract as containing a provision of such unusual character
… unless the language of the contract was quite clear”; not only was the notion of
a vendor binding himself to accept an unknown nominee as the party to whom he
must look exclusively for performance of the contract an unusual one, it was “by no
means clear that such a provision could be made legally effective”; and “[t]he
substitution could only occur if the nominee subsequently agreed, for fresh
consideration or under seal, to perform the [original purchaser’s] obligations under
the contract.” The trial judge referred also to Phillips JA’s statement in Salter
v Gilbertson that:4
2 Tonelli v Komirra Pty Ltd [1972] VR 737; Jenkins v Smyth [1973] VR 441 at 447; Lambly v Silk
Pemberton Ltd [1976] 2 NZLR 427; Lord v Trippe (1977) 14 ALR 129 at 143; Hurrell v Townend
[1982] 1 NZLR 536; Harry v Fidelity Nominees Pty Ltd (1985) 41 SASR 458; Karangahape Road
International Village Ltd v Holloway [1989] 1 NZLR 83; Salter v Gilbertson (2003) 6 VR 466 at 473;
Commissioner of State Revenue v Politis [2004] VSC 126 at [16]; David Deane & Associates P/L
v Bonnyview P/L [2005] QCA 270 at [30]; Avzur Hotels Pty Ltd v Ivanhoe Entertainment Pty Ltd
(2009) 257 ALR 498 at 501; CPG01 Pty Ltd v Kourinos [2010] WASC 92.
3 (1985) 41 SASR 458 at 460.
4 (2003) 6 VR 466 at 473.
-- 9 of 33 --
10
“As has been pointed out often enough, although it must be so if the
context so demands, it is a strong thing to regard the words ‘or
nominee’ as authorising B, unilaterally and in his or her own
absolute discretion, to nominate a purchaser to stand in the place of
B, with all the attendant consequences for A [the vendor]. For such
a construction ‘compelling language’ is required … .” (emphasis in
original)
[22] After considering those matters, the trial judge discussed a case in which a nominee
was found to be bound as purchaser. In Parland Pty Ltd v Mariposa Pty Ltd,
Green CJ, having referred to authorities and set out a passage from Harry v Fidelity
Nominees Pty Ltd, said:5
“Whilst accepting the above statements and also accepting that in
this particular case there was evidence of the conveyancing practice
referred to in those passages it must be kept in mind that every case
must be determined on the basis of the circumstances and terms of
the particular contract under consideration.
In my view the following circumstances militate in favour of a
conclusion that the first plaintiff was not merely the transferee of the
property but was a contracting party.
The contract was ‘between … the vendor of the one part and Andrew
Hamilton and Andrew McGregor or their nominee [hereinafter called
“the purchaser”] of the other part’. Prima facie the effect of those
words is that if Hamilton and McGregor did not nominate anyone the
contract was between the vendor of the one part and Hamilton and
McGregor [thereinafter called ‘the purchaser’] of the other part and
that if they did nominate someone then the contract was between the
vendor of the one part and the person nominated [thereinafter called
‘the purchaser’] of the other part. It follows that prima facie the
person nominated was a contracting party and that the word
‘purchaser’ refers to the person nominated wherever it appears in the
contract. Another internal indication supporting that construction is
provided by the fact that the only way in which the rezoning referred
to in cl15 could have been achieved was by an objection by the
owner or occupier of the property pursuant to the Local Government
Act 1962, s727(4). If the defendant’s contention is correct and for the
purposes of cl15 ‘the purchaser’ should be construed as referring to
the second and third plaintiffs notwithstanding that the first plaintiff
was nominated as the transferee, the clause would have been
unworkable from the beginning because the second and third
plaintiffs were not the owners and would not have had standing to
lodge the objection which was necessary to achieve the rezoning.”
[23] The trial judge considered that Ms Mengel’s evidence established that when Hegira
and Barrier Developments contracted, each knew that Barrier Developments
intended to nominate another entity which would also be controlled by Mr Williams,
but his Honour observed that the critical question involved the intention, objectively
viewed, of ACN. In finding that ACN was bound by the contract, the trial judge
reasoned as follows:6
5 (1995) 5 Tas R 121 at 128.
6 [2010] QSC 405 at [28]-[32].
-- 10 of 33 --
11
“… If a nominee were not to become bound by the provisions which
were to operate after settlement of the original sales by Hegira, how
was Hegira to have had the benefit of the contracts in those respects?
Moreover, if ‘the buyer’ referred to in Annexures B and D was to
remain Barrier Developments, the outcome would be that it, and not
the transferee, would have to construct houses upon land in which it
had no interest. The more likely intention to attribute to Barrier
Developments was that its exercise of its power of nomination
should result in the nominee being bound in its place. And that was
the likely intention to attribute also to Hegira, for otherwise the
benefit of these post settlement provisions would be substantially
denied to it.
In some of the authorities, it is said that the vendor would be unlikely
to have agreed to the substitution of an unknown person as the
purchaser. But in this case that consideration does not have the same
significance. The purpose of the contract, on the purchaser’s side of
the transaction, as known to both parties, was to permit an entity
controlled by Mr Williams to acquire the lands and to build upon
them. In any case, the post settlement provisions specifically
anticipated the substitution of a subsequent owner, although such a
person might be unknown to the vendor. As set out above, cl 4.1 of
Annexure B required ‘the buyer’ to obtain a deed of covenant from
its purchaser by which it agreed to be bound by these provisions. It is
not suggested that cl 4.1 was engaged here by the nomination of
[ACN] by Barrier Developments. But this provision indicates, upon
an objective view, an intention that the vendor should be able to
enforce these post settlement provisions against whoever was the
then owner of the land.
Accordingly, the term ‘the buyer’ within these post settlement
provisions should be construed as a reference to the entity which
became the transferee, whether Barrier Developments or, in the event
of its nomination of another transferee, that nominee. That is not
inconsistent with the identification of ‘the buyer’ on the first page of
each contract. Nor is it inconsistent with the definition of ‘buyer’ for
Annexure B within cl 11.6, where the term was defined as the person
who ‘buys the allotment from the developer’.
Ordinarily a vendor is taken to have agreed to transfer the land to the
purchaser or to the purchaser’s nominee, whether or not the contract
specifically provides for such a nomination: Lord v Trippe. In these
contracts, by necessary implication, Hegira agreed to transfer to the
nominee of Barrier Developments, but only upon the basis that the
nominee agreed to be bound by the post settlement provisions.
[Hegira and Vercorp] must not only demonstrate that it was Hegira’s
intention to have the transferee as the party against which it could
enforce the post settlement provisions. They must also prove that
[ACN] agreed to be so bound. [ACN], through Mr Williams, must be
regarded as a transferee which knew of the terms of the contracts of
sale. It was [ACN] which caused the contracts to be completed on
the buyer’s side. In particular, it was [ACN] which paid the price in
-- 11 of 33 --
12
each case upon settlement. In these circumstances, in taking the
transfer, by necessary implication [ACN] agreed with Hegira to be
bound as ‘the buyer’ under the post settlement provisions. The
consideration for [ACN’s] agreement was that transfer and Hegira’s
release of Barrier, neither of which Hegira had agreed to do absent
the nominee agreeing to be bound. In consequence, upon settlement
of each contract, [ACN] became bound to perform the post
settlement provisions … .” (citation omitted)
[24] ACN challenged the trial judge’s reasoning, arguing that the authorities required
“very clear language” or “compelling language” to justify departure from the
“ordinary” or “usual” position that in the case of a contract for the sale of land
between a vendor and a purchaser “or nominee” the nominee merely takes title to
the land but does not otherwise stand in the place of the purchaser. This was
submitted to be all the more so in a case, such as the present, where the relevant
contractual obligations sought to be enforced against the nominee were negative
covenants which could not bind the nominee in the absence of a contract between it
and Hegira.7
[25] ACN went so far as to contend that the requirement in the authorities that there be
“very clear language” ordinarily required express terms, but it did not cite any
authority which supported that proposition and it should not be accepted. As
Green CJ observed in the passage from Parland Pty Ltd v Mariposa Pty Ltd which
was quoted by the trial judge, every case must be determined on the basis of the
circumstances and terms of the particular contract under consideration. The clarity
of the contractual language required for a finding that a nominee is substituted for an
original contracting party may be influenced by the circumstances of the particular
case. So much follows from the basic principle, to which the trial judge adverted,
that the construction of a contract must be undertaken with a consideration of the
surrounding circumstances known to the parties and the purpose and object of the
transaction.8
[26] ACN argued that Green CJ’s statement in Parland Pty Ltd v Mariposa Pty Ltd that
“prima facie the person nominated was a contracting party and that the word
‘purchaser’ refers to the person nominated wherever it appears in the contract” was
not reconcilable with decisions such as Harry v Fidelity Nominees Pty Ltd and
Salter v Gilbertson. That argument treated Green CJ’s statement as a proposition of
law, but it was instead a conclusion derived from the distinctive facts of that case.
There, the identity of the purchaser’s nominee was known to the vendor. An
amended contract handed over at settlement added the words “or their nominee” to
the named purchasers, so that the contractual description of “the purchaser” became
the named purchasers or their nominee, and the contract also did not include any
mechanism to make the post settlement provisions enforceable against a purchaser’s
nominee.
[27] One of the circumstances upon which Vercorp relied in support of the trial judge’s
conclusion was that, following the discussions in March 2001 in which Ms Mengel
made it plain to Mr Williams that the reference to a nominee would only be
7 ACN cited Norton v Kilduff [1974] Qd R 47 at 54.
8 Codelfa Construction Pty Ltd v State Rail Authority (NSW) (1982) 149 CLR 337 at 350; Pacific
Carriers Ltd v BNP Paribas (2004) 218 CLR 451 at 462; and International Air Transport
Association v Ansett Australia Holdings Ltd (2008) 234 CLR 151 at 160.
-- 12 of 33 --
13
acceptable to Hegira on the condition that the entity which purchased the lots must
comply with the building requirements and perform the contracts in accordance with
the contractual building timeframes, the reference to a nominee was added to the
contracts and Mr Williams signed them on 27 March 2001. A comparison between
the original versions of Annexure D in each of the contracts and the revised versions
(sent to Hegira from one of Mr Williams’ companies on 27 March 2001)
demonstrated two additions: the words “or nominee” in the expression “Barrier
Developments/or nominee (As Buyer)” in the heading of Annexure D; and
Mr Williams’ initials and signature (in addition to the signature of the solicitor who
had originally signed Annexure D for Barrier Developments). ACN objected to the
use of that evidence for this purpose on the ground that Vercorp and Hegira’s reply
admitted the allegation in ACN’s defence that the contracts between Hegira and
Barrier Developments were executed by Barrier Developments, as buyer, on or
about 16 March 2001.
[28] The question whether ACN was bound by the contracts upon the lots being
transferred to it differed from the question of when Barrier Developments executed
the contracts. I accept Vercorp’s argument that the evidence that Mr Williams
added the words “or nominee” in Annexure D and his initials and signature after the
contracts had earlier been executed on behalf of Barrier Developments, and after the
conversation between Mr Williams and Ms Mengel, was relevant. Even if, which
I do not accept, that evidence went beyond the pleadings, Vercorp should be entitled
to rely upon it. The evidence was admitted at the trial without objection and ACN
did not argue that it might have conducted the trial differently had the evidence been
specifically pleaded.
[29] Although Vercorp did not allege that Barrier Developments made the contracts as
ACN’s agent, the treatment of ACN as a contracting party upon the transfer to it of
the land pursuant to Barrier Developments’ nomination was consistent with the
description of the buyer in each contract as comprehending Barrier Developments’
nominee. There are then the following additional circumstances: when the contracts
were concluded, Hegira and (by Mr Williams) Barrier Developments and ACN
understood that an aim of each contract was to regulate construction on the land
after settlement by the transferee of the land; the provisions to that effect would be
unworkable if they were unenforceable against Barrier Developments’ nominee;
both Barrier Developments and its nominee were controlled by Mr Williams; ACN
paid deposits in consideration of an extension of the finance approval dates, and
ACN paid the balance purchase prices in exchange for transfers of the properties to
it. Those circumstances provided a compelling justification for the conclusion that
ACN had contracted to be bound as purchaser upon taking a transfer of title as
Barrier Developments’ nominee.
[30] ACN argued that this case should be distinguished from Parland Pty Ltd v Mariposa
Pty Ltd. The cases are factually different of course, but there are the analogous
circumstances that the intended nominee of the named purchaser was identified in
discussions between the parties as being another company controlled by
Mr Williams, and the post settlement provisions expressed in the contract would be
ineffective unless ACN was bound by them. ACN argued that an important point of
distinction was that its substitution as a contracting party was inconsistent with
Hegira and Barrier Developments’ omission to utilise the contractual mechanism of
a novation under seal in cl 4.1 of the community development covenants. Clause
4.1 provided:
-- 13 of 33 --
14
“The buyer acknowledges that he will not sell, transfer or otherwise
dispose of the allotment without firstly delivering to the Developer a
Deed of Covenant duly executed by the Purchaser in favour of the
Developer containing covenants in the same terms (mutatis
mutandis) as are set forth in these covenants including an obligation
for each purchaser to obtain a further Deed of Covenant from any
subsequent purchaser.”
[31] The trial judge mentioned in [29] of his Honour’s reasons that it was not suggested
that cl 4.1 was engaged by the nomination of ACN by Barrier Developments, so this
seems to be a new point. Clause 4.1 was not designed to meet the situation which
arose in this case, because the contractual definition of the term “buyer” used in that
clause comprehended ACN as Barrier Developments’ nominee (see [9] of these
reasons) and the words “sell, transfer or otherwise dispose of the allotment” are
naturally understood as referring to post settlement dispositions by the buyer. It was
manifestly an aim of the contract that the community development covenants should
be enforceable by Hegira after settlement against whoever was the owner of the
land. In light of the express reference to that aim in the context of discussion about
intended nominees during pre-contractual negotiations, the parties’ failure to advert
to the possible use of a deed of covenant under cl 4.1 at that time tends, if anything,
to supply further objective support for the conclusion that ACN was intended to be
bound by the covenants as buyer.
[32] ACN argued that the transfer to it could not have occurred pursuant to a fresh
agreement under which it became bound as a party because Hegira gave no
consideration for any such agreement, Hegira being contractually obliged to Barrier
Developments to transfer title to ACN upon Barrier Developments’ nomination of
ACN as the transferee. That argument overlooked the trial judge’s finding, which
I would affirm, that the consideration for ACN’s agreement included Hegira’s
release of Barrier Developments.
[33] ACN argued that s 184 of the Land Title Act 1994 (Qld) militated against the trial
judge’s conclusion. Section 184(1) provides that the “registered proprietor of an
interest in a lot holds the interest subject to registered interests affecting the lot but
free from all other interests”, and s 184(2) provides that the registered proprietor “is
not affected by actual or constructive notice of an unregistered interest affecting the
lot”. It is uncontroversial, however, that those provisions provide no obstacle to
enforcing a contract against a registered proprietor who made that contract.
[34] Reference was made to evidence by Mr Russell to the effect that he did not believe it
was necessary for ACN to enter into the Deeds of Covenants and he assumed that
there was a “pre-dated agency agreement authorising Barrier to enter on behalf of
the Williams Family Trust.” Mr Russell’s subjective intentions and understanding
do not assist in answering the question whether ACN became bound as a party to
a contract with Hegira. That turns upon an objective analysis of what reasonable
parties in the position of Hegira, Barrier Developments, and ACN would have
understood to be the effect of their arrangements.9
[35] ACN argued that the trial judge’s finding was inconsistent with the evidence that as
late as October 2003 Hegira wrote to Barrier Developments complaining about
delays in construction of the lots and other breaches of contract. If that amounted to
9 See Pacific Carriers Ltd v BNP Paribas (2004) 218 CLR 451 at 461-462 [22].
-- 14 of 33 --
15
an admission, it was of little weight compared to the contemporaneous objective
circumstances which the trial judge analysed. Other correspondence was consistent
with the trial judge’s conclusion. In the 24 February 2004 letter from ACN’s
solicitor to Hegira’s solicitor, which was written in response to Hegira’s exercise of
the option to repurchase Lots 411 and 412, ACN’s solicitor acknowledged that
contracts had been formed between ACN and Hegira upon Hegira’s exercise of the
options under cl 25 of the contracts. As the trial judge pointed out, there was no
evidence which explained that inconsistency with ACN’s case at trial. Nor was
there any contention in the following months in the further correspondence about the
repurchase of Lots 411 and 412 that ACN had not been contractually bound to
reconvey those properties when the options to repurchase were exercised.
[36] I would affirm the trial judge’s conclusion that upon settlement of each contract
ACN became contractually bound to perform the post settlement provisions.
Termination of the repurchase contracts in respect of Lots 413 and 414
[37] Upon the assumption that it was bound to perform the post settlement provisions,
ACN argued that it had validly terminated the repurchase contracts for Lots 413 and
414 pursuant to cl 9.1 for breach of cl 5.2(1) of the REIQ standard terms which were
incorporated in those contracts. Those clauses provided:
“5.2 Transfer Documents
(1) The Transfer Documents must be prepared by the
Buyer’s Solicitor and delivered to the Seller a
reasonable time before the Settlement Date.
…
9.1 Seller May Affirm or Terminate
If the Buyer fails to comply with any provision of this
contract, the Seller may affirm or terminate this contract.”
[38] Vercorp’s solicitor did not deliver the transfer documents before the settlement date.
The trial judge referred to the reasons for the delay in the following passage:10
“The construction period for lot 414 expired on 9 October 2004 and
for lot 413 on 9 October 2005. On 4 November 2005, Hegira
assigned to Vercorp its rights in respect of these properties.
On 8 May 2006, Vercorp gave to [ACN] notice of that assignment
and notices exercising the options to repurchase lots 413 and 414.
Ultimately, there was no challenge to Vercorp’s claim to be entitled
to exercise those options (if the respondent had become bound by
them). The date for settlement was therefore 7 June 2006. Also on
8 May, Vercorp wrote to the President of the Australian Property
Institute asking for a valuer to be nominated. On the following day,
Mr McNamara for the Institute replied, advising that a certain valuer
had been nominated.
The valuer then contacted Mr Londy, who said that his client did not
then acknowledge that the options had been validly exercised and
said that it would not participate in the valuation process.
Correspondence then passed between the valuer, the Institute and
10 [2010] QSC 405 at [68]-[74].
-- 15 of 33 --
16
Vercorp’s solicitors. All of this must have caused some delay in the
completion of the valuation. The valuation was not provided until the
date of settlement, 7 June 2006. Lots 413 and 414 were valued at
$800,000 and $600,000 respectively.
By a facsimile transmission at about 12.20pm on 7 June, Vercorp’s
solicitors sent to Mr Londy a copy of the valuation and a transfer to
be executed by [ACN] and handed over at settlement. They attached
copies of bank cheques for $800,000 and $600,000 payable to
[ACN]. Their letter concluded as follows:
We note that there is a mortgage on each Lot to
NAB. We nominate settlement to take place at the
Titles Office at 3:00pm today unless you notify us of
the contrary in writing. However, if your client
requires additional time to have the transfers
executed and releases obtained from NAB then
please provide us with a written request for an
extension of the settlement date.
Our client is ready, willing and able to settle today.
At the appointed time of 3.00pm, Mr Murdoch of the solicitors for
Vercorp attended at the Titles Office to settle the contracts. No one
representing [ACN] attended. A little later, Vercorp’s solicitors sent
a fax to Mr Londy saying that Mr Murdoch had attended for the
settlement but had left at 3.20pm, and that Vercorp remained ready,
willing and able to settle at any time up to 5.00pm that day. They
added that if [ACN] wanted an extension of time then Mr Londy
should fax a request so that they could take Vercorp’s instructions.
There was no response that day from Mr Londy.
On 8 June 2006, Vercorp’s solicitors wrote to Mr Londy, purporting
to affirm the contract and advising that if Mr Londy contended that
the 30 days ran from some other time, they expected that Vercorp
would be ‘agreeable to settling on whatever date is the appropriate
date’.
On 13 June 2006, Mr Londy replied that if Vercorp proved that the
options were validly exercised by it (which Mr Londy said, [ACN]
did not admit), Vercorp was not entitled to an order for specific
performance for two reasons. One was that the amount of the
valuations was ‘much too low’ and that ultimately the valuation
report was ‘unreliable and invalid for the purposes of the present
exercise’. That contention was struck out of the Defence by an order
on 16 December 2008. The other ground was an alleged estoppel,
apparently based upon something which had occurred at an
unsuccessful mediation held in July 2005. The details of that ground
need not be considered here because it is not pleaded. In that letter,
there was also some complaint that the valuation had been given only
two hours prior to the time for settlement, which was said to have
given ‘insufficient time to properly consider our client’s position’.
But [ACN’s] pleaded point, which was that an unreasonably short
time was allowed for settlement of the repurchase contracts, was not
raised.”
-- 16 of 33 --
17
[39] The trial judge accepted that cl 9.1 “is in terms by which it is engaged by any breach
of the contract by the buyer, no matter how serious.”11 The trial judge found,
however, that Vercorp had not “failed to comply” with cl 5.2(1) because, by
necessary implication, the determination of the price under cl 25.5 of Annexure D
was a condition precedent to the performance of the obligation expressed in
cl 5.2(1). The trial judge held that this implication satisfied the prerequisites for an
implied term expressed in Codelfa Construction Pty Ltd v State Rail Authority
(NSW)12 and that the implication was necessary in the same way as a similar term
was implied in Re Ronim Pty Ltd13 (where the Court implied a term that where,
through no fault of the parties, they could not carry out the necessary checks to
verify title on the day for completion, the obligation to complete should be
suspended until that could be done). The trial judge reasoned as follows:14
“In the present case, by the unavailability of the valuation, which
was not the fault of Vercorp, it became impossible for Vercorp to
comply strictly with cl 5.2(1). It cannot be thought that the parties
intended that in this circumstance, Hegira or its successor should find
itself in breach of the repurchase contract, such that the unwilling
vendor of the land might have all of the rights and remedies for
breach of contract, including a right of termination. Clause 9.1 is
engaged only where there is a failure to comply with the provision of
the contract. As other parts of cl 9 confirm, it is only a breach of
contract which will engage cl 9. Because Vercorp was under no
obligation to deliver the transfer documents until they could be
prepared, as long as the impediment to their preparation was not
through its default, the obligation under cl 5.2(1) was suspended and
was not breached. Accordingly, cl 9 was not engaged.
The evident purpose of cl 5.2(1) is to ensure that a seller has
sufficient time to execute the transfer documents to be delivered at
settlement. In the present case, if it was impossible for that to occur
because the transfer documents were delivered only on the day for
settlement, then [ACN] would have been excused from the obligation
to settle on that day. This would have been because either
performance of the contract would have become impossible, thereby
discharging the contract, or because by a further implication, the
contract would have remained on foot but with the settlement date
extended to allow [ACN] whatever time was required. However, it is
unnecessary to discuss that question, because there is no evidence
that it was impossible for [ACN] to settle on 7 June. More precisely,
there is no evidence that it was impossible for [ACN] to execute the
transfer documents and to bring them to a settlement on that
afternoon. Notably, at the time there was no complaint made by or
for [ACN] that this was impossible.”
11 [2010] QSC 405 at [77]. The trial judge referred to Honner v Ashton [1980] ANZ ConvR 343, to its
overruling in Hewitt v Debus (2004) 59 NSWLR 617, to matters which might distinguish the latter
decision from the usual position in Queensland, and to the potential for cl 9.1 to have harsh
consequences in a rising market as identified by Robin DCJ in Le v Qureshi [2003] QDC 442.
12 (1982) 149 CLR 337 at 347.
13 [1999] 2 Qd R 172.
14 [2010] QSC 405 at [79]-[80].
-- 17 of 33 --
18
[40] ACN argued that the trial judge erred in finding that the determination of the
purchase price under cl 25.5 of Annexure D was a condition precedent to the
performance of the obligations in cl 5.2(1). ACN also argued that the trial judge
erred in finding that: the unavailability of the valuation was not the fault of Vercorp
and it was thereby impossible for Vercorp to comply strictly with cl 5.2(1); the
obligations in cl 5.2(1) were suspended and not breached; and Vercorp was therefore
not in breach and ACN was not entitled to terminate the repurchase contracts. ACN
submitted that the error was demonstrated by the trial judge’s findings, made in the
course of concluding that ACN had duly terminated the contracts for the repurchase
of Lots 411 and 412, that: there was no requirement for ACN to be involved in the
process of appointing a valuer pursuant to cl 25.5; it was possible for Hegira (or
Vercorp) to ensure that the valuation machinery was working before it was
employed by obtaining the valuation under cl 25.5 prior to giving the notice of
exercise of option under cl 25.4.1; and the parties had agreed (in cl 25.4.3) upon
settlement of the repurchase contracts within 30 days of delivery of the notice of
exercise of option rather than according to when the purchase price was determined
by the valuation.
[41] I would affirm the trial judge’s conclusions on these points. There could be no
settlement prior to the determination of the market value, which was the purchase
price of the lots. As Hegira and Vercorp pointed out, in the course of finding that
ACN had duly terminated the contracts for the repurchase of Lots 411 and 412, the
trial judge found that it was a condition precedent to performance of the repurchase
contracts that a valuer acting under cl 25.5 determined the market value of the
relevant lot by the agreed date for performance. I will explain why I reject
Vercorp’s challenge to the finding when I discuss its appeal. It logically follows
from that finding that the determination of the purchase price was also a condition
precedent to the purchaser’s obligations to deliver the transfer documents to the
seller at a reasonable time before the settlement date under cl 5.2(1). Otherwise it
does not seem necessary to attempt to expand upon the trial judge’s persuasive
reasons for the conclusion that the contracts were subject to the condition precedent.
[42] ACN has also failed to demonstrate any error in the trial judge’s finding that the
unavailability of the valuation was not the fault of Vercorp. The fact that the
contract permitted Vercorp to seek the appointment of a valuer before giving the
notice of exercise of option did not mean that it was obliged to do so or that it was at
fault in omitting to do so. Vercorp sought the appointment of a valuer on the same
day that it exercised the option. There seems to be no basis for concluding that
Vercorp should have anticipated that the valuation might not be provided until the
very last day of the 30 day settlement period.
[43] ACN challenged the trial judge’s conclusion that it was not entitled to terminate the
contracts for the repurchase of Lots 413 and 414 on the further ground that the trial
judge should have found that settlement of the repurchase contracts was to occur
only upon “reasonable notice by either party” or “within a reasonable time after
a date and time stipulated by either party”. ACN argued that Vercorp’s facsimile
transmission at about 12.20 pm on 7 June 2006, which nominated settlement to take
place at the Titles Office at 3.00 pm that day, did not comply with that implied term.
[44] The trial judge was not persuaded that the alleged term should be implied or that, in
the unusual circumstances of the case in which Vercorp did not receive the
valuations until the day for settlement, the steps required to be taken by ACN to
settle could not have been taken before 5.00 pm on that day.
-- 18 of 33 --
19
[45] The trial judge explained the conclusion that the alleged terms should not be implied
in the following passage:15
“In any event, I am not persuaded that a term should be implied as
[ACN] has pleaded. Such a term does not satisfy the prerequisites
that it is necessary to give the repurchase contracts business efficacy.
Nor is it so obvious as to go without saying. No authority was cited
by [ACN] for the implication of such a term, although these contracts
adopt the REIQ terms. Clause 5.1(1) of the REIQ terms provided that
settlement was to occur between 9.00am and 5.00pm on the
settlement date. Clause 5.1(2) provided that the place of settlement
was to be the Titles Office, failing a nomination of another place by
[ACN]. According to the express terms then, the parties were obliged
to settle on the settlement date without any notice by one to the other
of a date, time or place. There is no basis then for implying a term
that any such notice was required and that it be reasonable notice or
for settlement ‘a reasonable time after a date and time stipulated by
either party’. Instead, each party was obliged to settle on the due date
as long as that had not become impossible and by circumstances
beyond that party’s control.” (footnote omitted)
[46] ACN argued that the necessity for implying the alleged term arose because cl 25.4.3
of Annexure D required settlement of the repurchase contracts to take place at any
time within 30 days of the date of delivery of the notice of exercise of option and
that 30 day period was “at large”. No such implication was necessary. Clause
25.4.3 did not permit the buyer under the repurchase contract to require the seller to
settle at any time before the last day of the 30 day period. In the absence of any
nomination of an earlier time, settlement was due by 5.00 pm on the final day of the
period. It was not necessary for the buyer under the repurchase contract to give any
notice to that effect since it was provided for by the terms of the contract.
[47] Furthermore, ACN’s contention that Vercorp gave ACN just two and a half hours
notice of settlement is not accurate. ACN must be taken to have anticipated from
the outset that it might be required to settle by 5.00 pm on the final day of the
settlement period (7 June 2006). Vercorp did not purport to require ACN to settle
before 5.00 pm: the nomination of 3.00 pm as the time for settlement in the notice
given by Vercorp’s solicitor at 12.20 pm on 7 June 2006 was qualified by the words
“unless you notify us of the contrary in writing”. That reflected the provisions in
cl 5.1(1) and cl 6.1 of the REIQ standard terms that settlement “must occur between
9am and 5pm on the Settlement Date” and that the time of day is not of the essence.
ACN was entitled to settle at any time during the four and a half hours before
5.00 pm after Vercorp’s solicitors sent to ACN’s solicitors a copy of the valuation
and a transfer to be executed by the trust company. The trial judge accepted
evidence that after no one representing ACN attended at the Titles Office to settle
the contracts at 3.00 pm, Vercorp’s solicitors sent a facsimile to ACN’s solicitors
stating that Vercorp remained ready, willing and able to settle at any time up to
5.00 pm that day. ACN referred to expert evidence to the effect that two and a half
hours notice where no prior arrangements had been made to effect settlement was
unreasonable, but that evidence was not inconsistent with the trial judge’s
conclusion that ACN failed to establish that it could not have taken the steps
required on its part to effect settlement before 5.00 pm.
15 [2010] QSC 405 at [87].
-- 19 of 33 --
20
Abandonment of specific performance of Lots 413 and 414 by claiming
damages in the District Court
[48] The trial judge rejected ACN’s contention that Hegira had abandoned a claim for
specific performance of the repurchase contracts for Lots 413 and 414 by
commencing proceedings against ACN in the District Court claiming liquidated
damages of $75,000. (ACN’s contention that Hegira had made such an election was
not limited to the contracts for Lots 413 and 414, but it was unnecessary for the trial
judge to consider the contention in relation to Lots 411 and 412 because his Honour
concluded that ACN had in any event duly terminated the repurchase contracts for
those lots.) The trial judge considered this argument in the following passage:16
“On 19 January 2004, Hegira brought proceedings against [ACN] in
the District Court claiming $75,000. The pleaded case was for
$25,000 under each of the contracts for the sale of lots 411, 412 and
413, pursuant to cl 5.1 of Annexure B to the contracts, as Hegira’s
solicitors had demanded on the previous day. That provision, set out
above at [7], provided that in the event of any breach of any of those
covenants, the Buyer was to pay to Hegira $25,000 by way of
liquidated damages ‘or such greater sum as may represent the actual
loss or damage suffered by Pacific Harbour by reason of such
breach’. The breach complained of was that between August 2003
and December 2003, [ACN] had conducted no substantial building
works on any of lots 411, 412 and 413. That was pleaded as a breach
of a term within that attachment described as Community
Development Standards. The relevant term was as follows:
No building shall be left without substantial work
being carried out for longer than one (1) month.
Total construction time for erection of a building
shall not exceed nine (9) months. …
The alleged breach, in essence, was halting the progress of
construction. This was not the basis for the exercise of an option to
repurchase according to Annexure D, because the option could be
exercised only in the event that construction had not been completed
in accordance with the contract. The date for completion of lot 414
was 9 October 2004, and the date for lot 413 was a year later. The
District Court proceedings were thereby commenced before the
option to repurchase either of those properties was exercisable.
Accordingly, the option was not exercisable for the breach which
was pleaded in the District Court proceedings and nor had the
options for lots 413 and 414 become exercisable at the time that
those proceedings were issued. At least for those reasons, [ACN’s]
argument that the commencement of the District Court proceedings
involved an election not to exercise the options to repurchase cannot
be accepted. By their written submissions, counsel for [ACN] argue
that ‘the right to claim damages and the option to repurchase are
inconsistent rights because each would result in the Applicants being
compensated for the same breach’. But there is no inconsistency.
16 [2010] QSC 405 at [90]-[91].
-- 20 of 33 --
21
And a further problem with the submission is that the option to
repurchase is not compensatory.” (emphasis in original)
[49] ACN contended in its appeal that “[i]n respect of Lots 411, 412 and 413, [Hegira
and Vercorp] conclusively elected to seek damages in the District Court
proceedings” and “[b]y their election, … abandoned any claim to specific
performance in respect of those Lots”. The argument assumed that Hegira’s right to
damages under cl 5.1 of the community development covenants and its right to
exercise the option for repurchase under cl 25.3 of Annexure D were “inconsistent
the one with the other and … because they are inconsistent neither one may be
enjoyed without the extinction of the other”.17 For the reasons given by the trial
judge there was no such inconsistency. The commencement and maintenance of the
District Court proceedings involved no election by Hegira or Vercorp not to
maintain the right to claim specific performance of any of the repurchase contracts.
[50] ACN also argued that Hegira and Vercorp’s conduct in continuing two sets of
proceedings which involved overlapping issues and relief was an abuse of process
which was relevant to the consideration of whether to grant equitable relief. The
trial judge’s reasons for rejecting that argument were that the breaches complained
of in the two sets of proceedings were different and the District Court proceedings
had not been prosecuted.18 ACN did not point to any particular error in that
reasoning. There was no error.
Other issues in ACN’s appeal
[51] It is unnecessary to consider ground 4 of ACN’s appeal. It related only to Lots 411
and 412, in relation to which ACN succeeded. ACN abandoned ground 9 of its
appeal, which challenged a decision by the trial judge to refuse leave to rely upon
a proposed amended defence.
Vercorp’s cross appeal
[52] In Vercorp’s cross appeal it sought an immediate decree of specific performance of
the repurchase contracts for Lots 413 and 414. Grounds 1 to 6 of Vercorp’s notice
of cross appeal were repeated in Vercorp’s appeal and it is appropriate to consider
them in that context. As will appear, none of those grounds has merit. That leaves
for consideration ground 7, in which Vercorp contended that the trial judge erred in
finding that ACN’s counterclaim should be litigated before any decree of specific
performance of the repurchase contracts for Lots 413 and 414 might be considered.
[53] The trial judge declined to grant specific performance of the repurchase contracts for
Lots 413 and 414 because part of ACN’s counterclaim sought relief under the Trade
Practices Act 1974 (Cth) for misleading and deceptive conduct, said to have been
engaged in by Hegira and Vercorp in obtaining the valuations for the repurchases.
His Honour reasoned that those allegations might, if established, lead to a grant of
relief under s 87 of the Trade Practices Act in a way which would affect the
performance of the repurchase contracts. For that reason, the trial judge’s order in
favour of Vercorp was limited to a declaration that on 7 June 2006 ACN was bound
to complete contracts for the sale to Vercorp of Lots 413 and 414.
[54] The counterclaim sought a declaration that the “[v]aluations referred to in the
Defence” (which included reference to the valuations in respect of Lots 413 and 414
17 Sargent v ASL Developments Ltd (1974) 131 CLR 634 at 641 per Stephen J.
18 [2010] QSC 405 at [94].
-- 21 of 33 --
22
pleaded in paragraph 64(b) of the defence) were “invalid and of no effect by reason
of the breach by [Vercorp] (and further, or alternatively, [Hegira]) of section 52 of
the TPA as pleaded therein”, and consequential relief pursuant to ss 80, 82 and 87 of
the Trade Practices Act. Vercorp contended in its written outline of submissions in
support of its cross appeal that: the alleged misleading and deceptive conduct (which
was pleaded in paragraph 144 of the counterclaim) was the failure to inform the
valuers “of the Valuation Issues pleaded above in response to paragraph 64 of the
current Statement of Claim”; paragraph 64 did not plead any “Valuation Issues” in
relation to Lots 413 and 414; and the parts of the previous pleading which did relate
to Lots 413 and 414 were struck out by an order made by the trial judge on
16 December 2008. Those contentions were consistent with the form of paragraph
64 as it appears in the record, in which subparagraphs (d)-(g) (including the only
reference to “Valuation Issues” in subparagraph (f)) are struck through.
[55] Because ACN’s counterclaim was stayed pending resolution of the issues
determined by the trial judge, there remains the prospect that the counterclaim might
be amended. It seems, however, that ACN does not wish to pursue this aspect of its
counterclaim. ACN did not dispute Vercorp’s analysis. In ACN’s written outline of
submissions it conceded that if its appeal was dismissed and Vercorp’s appeal was
allowed, Hegira or Vercorp was entitled to specific performance of the repurchase
contracts for Lots 413 and 414. That was not directly responsive to Vercorp’s
argument but it suggested that there was no issue under the Trade Practices Act in
relation to those lots. Vercorp made those points in its written outline of
submissions in reply. It submitted that if ACN’s appeal was dismissed Vercorp was
entitled to specific performance of the repurchase contracts for Lots 413 and 414
irrespective of the fate of Vercorp’s appeal. ACN did not make any submissions in
response, either in writing or orally. I conclude accordingly that there is no issue on
this point.
[56] For these reasons I accept Vercorp’s contention that specific performance of the
repurchase contracts for Lots 413 and 414 should now be ordered. It is appropriate
to make only a general decree. If more specific orders are required they can be
sought in the trial division in the usual way.
[57] I do not regard Vercorp’s success on this point as justifying any adjustment to the
costs order which is otherwise appropriate in light of the fate of grounds 1 to 6 of
Vercorp’s cross appeal. ACN did not contest the order sought by Vercorp and that
order could have been sought before the trial judge at a directions hearing.
Vercorp’s appeal
[58] In Vercorp’s appeal it contended that the trial judge erred in finding that ACN had
validly terminated the repurchase contracts for Lots 411 and 412.
[59] The trial judge summarised the relevant evidence in the following passage:19
“[ACN] was obliged to complete the construction of a dwelling on
lot 411 within 30 months from the date of the contract of sale, ie by
9 October 2003. It was obliged to complete the construction of a
house on lot 412 within 18 months, ie on 9 April 2002. It failed to do
so in each case. In the second half of 2003 Mr Williams and Mr Dal
19 [2010] QSC 405 at [35]-[49].
-- 22 of 33 --
23
Bon for [ACN] gave frequent assurances that the buildings would be
completed but these were not fulfilled. Accordingly, Hegira became
entitled to exercise the options to repurchase lots 411 and 412.
On 5 December 2003, Hegira’s solicitors wrote to Coyne Coyne &
Towers, exercising the options in respect of lots 411 and 412 on
behalf of ‘Hegira Pty Ltd’ rather than Hegira Limited. On
18 December, Corrs Chambers Westgarth for [ACN] replied,
contending that the notices were ineffective because of that
misnomer. On the same day, Hegira’s solicitors wrote back
confirming that they acted on behalf of Hegira Limited and that their
earlier notice had contained a typographical error. They asserted that
the previous notices were valid. Alternatively, they said that this
letter of 18 December should be taken as an exercise of the options.
Bank cheques totalling $2,000 had been posted with the previous
notices, consistently with cl 25.4.1 of Annexure D. They wrote, as
they had earlier written on 5 December, that the purchase price was
to be the market value determined by a valuer appointed according to
cl 25.5 and that they would forward a form of contract in the terms
then approved by the REIQ in accordance with cl 25.4.2. At the end
of each of their letters of 5 and 18 December, they wrote:
We note settlement is due within thirty (30) days or
such further time as may be agreed. Obviously the
purchase price will need to be organised beforehand
but we will attempt to expedite that matter.
On 18 December, Hegira’s solicitors wrote a further letter to Corrs
Chambers Westgarth, demanding the payment of $25,000 in respect
of each of lots 411, 412 and 413, in consequence of [ACN’s] failure
to conduct substantial building work on each lot for a period of in
excess of one month. That amount was claimed under cl 5.1 of the
covenants in Annexure B.
On 19 December 2003, Hegira’s solicitors wrote to the President of
the Australian Property Institute (Queensland Division), which was
the body previously known as the Australian Institute of Valuers and
Land Economists. They asked for the appointment by the President
of a valuer or land economist to fix the market value of each of lots
411 and 412, pursuant to cl 25.5 of Annexure D. Their letter was
copied to Corrs Chambers Westgarth.
On 22 December 2003, Corrs Chambers Westgarth wrote to request
an extension, under the (2001) contracts of sale, of the date for
completion of construction to 15 September 2005. That was rejected
by a letter from Hegira’s solicitors of 29 December 2003.
On 15 January 2004, an officer of the Australian Institute of Property
Valuers telephoned Hegira’s solicitors to advise that the appointment
would be made by the Vice President because ‘the President is with
the NAB [National Australia Bank] and a bit close to the matter’.
The President was Mr Ide who, as an employee of that bank,
perceived a potential conflict of duties because Hegira was a wholly-
owned subsidiary of the bank. In fact, on settlement of the (2001)
-- 23 of 33 --
24
contracts of sale, on Hegira’s behalf he had executed the transfers to
the respondent. After some further discussions between the
Institute’s Executive Officer, Mr McNamara, and Hegira’s solicitors,
they wrote to Corrs Chambers Westgarth on 19 January 2004,
advising of the problem with Mr Ide and of his preference for the
Vice President to make the nomination of the valuer. They asked for
advice by 21 January of whether [ACN] had any objection to the
President making that nomination. There was apparently no reply
before 2 February 2004, when Hegira’s solicitors wrote to
Mr McNamara requesting that the Vice President make the
nomination. On 17 February 2004, Mr McNamara wrote to Hegira’s
solicitors, with a copy to Corrs Chambers Westgarth, advising that
‘the Institute’ had nominated a valuer, Mr Harvey. Mr McNamara
wrote that the nomination had been undertaken by the Vice President
‘on the basis that such will be acceptable to both parties’.
On 19 February 2004, Hegira’s solicitors wrote to Mr Harvey to give
him instructions. On 23 February, Mr Harvey replied, giving
a quotation of his fees. At the same time he wrote to Londy Lawyers,
who by then were acting for [ACN].
On 24 February, Mr Londy wrote the letter referred to above at
[19].20 No point was there taken about the appointment of a valuer
by the Vice President, rather than by the President. [ACN’s] position
there stated was that Hegira had wrongly failed to tender the balance
of the purchase price on the due date for settlement, which was
30 days from either 5 or 18 December 2003, and in consequence
[ACN] purported to elect to terminate each contract of repurchase.
On the following day, Hegira’s solicitors wrote to dispute that
contention and to argue that by an implied term, the date for
settlement was to be extended to a reasonable time after receipt of
the valuation.
On 27 February 2004, Hegira’s solicitors corresponded further with
Mr Harvey, enclosing copies of quotations for demolition of the
houses which had been partially constructed for the purposes of his
valuation. On 3 March, they wrote to Mr Londy proposing that the
valuer’s fees be shared equally between the parties. Mr Londy
replied on 5 March saying that in view of [ACN’s] termination of the
contracts, ‘the valuation exercise in which you are belatedly
engaging, is entirely pointless’. Undeterred, Hegira’s solicitors wrote
to Mr Harvey on 7 April 2004, confirming his engagement and
offering to pay all of his fees in the event that [ACN] did not
contribute to them.
After some further correspondence between the solicitors as to
whether the contracts had been validly terminated, Hegira’s solicitors
wrote on 19 April contending that the parties had impliedly agreed to
extend time to the extent necessary in order for the prices to be fixed.
They also suggested another view of the events, which was that the
contracts of repurchase had been ‘terminated by frustration for the
20 That letter is quoted in [11] of these reasons.
-- 24 of 33 --
25
failure of the anticipated event that the independent valuer would fix
a purchase price’, in which case, they contended, the options could
be exercised afresh given that the houses remained uncompleted. All
of that was rejected by Mr Londy in a letter of 27 April.
On 30 April 2004, Mr Harvey sent his valuation of lots 411 and 412
to Hegira’s solicitors. It appears that he did not send it also to
Mr Londy. Mr Harvey valued lots 411 and 412 at $750,000 and
$800,000 respectively.
On 7 June 2004,21 Hegira and Vercorp executed a document entitled
‘Assignment of Contract’ in relation to each of lots 411 and 412
whereby Hegira assigned to Vercorp all of its rights and interests in
the repurchase contracts which were said to have resulted from the
exercise of the options on 5 December 2003.
On 8 June 2004, Hegira’s solicitors again wrote to Mr Londy. Their
letter made no reference to the assignment to Vercorp. But they
enclosed transfer documents for lots 411 and 412 in which Vercorp
was shown as the transferee. They wrote that ‘[o]ur client is now in a
position to settle the purchase of the above lots’ and they nominated
16 June 2004 at 2.30pm at the Titles Office as the time and place for
settlement. The consideration shown on the transfers corresponded
with Mr Harvey’s valuations.
On 16 June 2004, someone from Hegira’s solicitors attended at
settlement. No-one attended for [ACN]. On that day Hegira’s
solicitors sent a letter to Mr Londy saying that they were ready,
willing and able to settle throughout the remainder of the day and
they enclosed copies of the bank cheques which they held for
settlement. That afternoon, Mr Londy replied saying that he had not
received copies of the valuations. He maintained that the contracts
had been terminated by [ACN]. Alternatively, he contended that
Hegira was in breach by failing to provide the valuations to [ACN]
within a reasonable time or by failing to complete within
a reasonable time after receipt of the valuations. On 25 June,
Mr Londy wrote again, putting forward further reasons why [ACN]
had not been obliged to settle on 16 June. It is unnecessary to
consider these points which by a previous order, I struck out of the
Defence.”
[60] The trial judge found that: each repurchase contract was subject to a condition
precedent that a valuer acting under cl 25.5 of Annexure D determine the market
value for the lot by the agreed date for performance in cl 25.4.3; because that
condition was not fulfilled the contracts for Lots 411 and 412 were able to be
terminated by either party; and ACN terminated those contracts on 24 February
2004. The trial judge reasoned as follows:22
“The real question here is whether the fact that the price had not been
fixed within the 30 day period had the result that the contract was
able to be terminated by [ACN], not for a breach or repudiation by
21 The trial judge noted that “[t]he assignment for Lot 411 is dated 7 June 2004; the assignment for
Lot 412 is undated but apparently was signed on the same day.”
22 [2010] QSC 405 at [53], [60]-[65].
-- 25 of 33 --
26
Hegira, but for non-fulfilment of a condition precedent to
performance. The contracts which came into existence upon the
exercise of the options were not uncertain because the price in each
case had not been fixed. They were contracts the performance of
which was subject to the prices being fixed. If that was a condition
which had to be satisfied within the period of 30 days, then it was
open to either party to terminate the contract upon the failure of that
condition and [ACN’s] termination on 24 February 2004 was valid,
although its basis was misstated.
…
In the present case, the parties adopted an objective standard by
which the price was to be fixed, which was the then market value of
the land. That strengthens the argument for [Hegira and Vercorp]
that a failure of the agreed machinery for determining that market
value did not put paid to their agreement. A court could determine
the then market value. Nevertheless, the question of construction
remains: did the parties agree that the price must be determined by,
and only by, the valuer appointed under cl 25.5?
In my conclusion, that last question must be answered “yes”, mainly
because the parties agreed that settlement should take place within
30 days of the exercise of the option. It may be accepted that the
parties could have reasonably anticipated some failure of the agreed
machinery which would have left the price undetermined at the end
of that period. But notwithstanding the difficulties which were
experienced in this case in the appointment of a valuer, the risks of
the machinery failing were relatively small. After all, Hegira was
under no express time limit to exercise the option. And it was not
precluded from asking the President of the Institute to appoint
a valuer and from obtaining that valuation prior to exercising its
option. There was no requirement for [ACN] to be involved in the
appointment process. It was possible then to ensure that the
machinery was working before it was to be employed. On the other
hand, it could not have been anticipated that there would be any
prospect of a determination of the market value of the land by a court
within the period of 30 days.
Young J saw the same problem in GPI Leisure Corporation Ltd
v Herdsman Investment Pty Ltd (No 1). In that case, the fact that the
property there would have to be valued and traded “in a relatively
short period of time” was in his view relevant in considering whether
a clause should be construed as requiring a sale of certain property at
a fair market price.
The time limit of 30 days is important in this way, regardless of
whether it was a term of the repurchase contracts that time should be
of the essence. Clause 25.4.2 of Annexure D incorporated into the
repurchase contracts the terms of the then REIQ form of contract
(which were also those which the parties had employed in the 2001
contracts of sale). By cl 6.1 of those terms, time was of the essence
of the contract (except regarding any agreement between the parties
-- 26 of 33 --
27
on a time of day for settlement). [Hegira and Vercorp] argue that
such a term was so inconsistent with the purpose of the options to
repurchase that by necessary implication, that standard term should
be excluded. I do not accept that submission. If anything, the purpose
of the option to repurchase would be promoted by a term making
time of the essence, for it would tend to expedite the repurchase of
the land so that Hegira could put paid to the impact of the
purchaser’s default in complying with the building covenants. But
regardless of whether time was made of the essence, it is clear that
the parties agreed upon a settlement of the repurchase contract within
30 days. They did not agree, for example, upon a settlement which
was to occur according to when the price was determined. Nor did
they simply agree that a settlement should occur within a reasonable
time. They agreed upon a settlement at the end of a period, within
which there was no real prospect that the price could be determined
other than by the machinery of a valuation expressed within cl 25.5.
It follows that the relevant condition precedent to performance was
the determination of that market value by a valuer acting under
cl 25.5 and that this condition had to be satisfied by the agreed date
for performance. Because that condition was not fulfilled, the
contract of repurchase was able to be terminated by either party.
That is not an unlikely intention to attribute to the parties. It broadly
accords with the position in contracts for the sale of goods, for which
s 12 of the Sale of Goods Act 1896 (Qld) (and its equivalents in other
jurisdictions) provides that where there is an agreement to sell on
terms that the price is to be fixed by the valuation of a third party,
and the third party cannot or does not make the valuation, the
agreement is avoided. In cases such as the present, the contract
would be voidable by either party for failure of the condition, it
being a condition precedent to performance and not to the existence
of the contract itself. But that difference is of no practical
consequence here, where [ACN] unequivocally terminated the
contracts on 24 February 2004.”
[61] I accept ACN’s argument that this analysis was correct.
[62] Vercorp objected that this argument was not open to ACN because the condition
precedent found by the trial judge was not within ACN’s pleaded defence that ACN
terminated the contracts because of Hegira’s alleged breach in failing to complete
the contracts within 30 days of its exercise of the options. The trial judge rejected
that defence on the ground that there was no obligation on either party to complete
the contracts unless and until the price was fixed and Hegira had not promised that
the land would be valued within the 30 day period.23 Vercorp cited the requirement
in r 153(2) of the Uniform Civil Procedure Rules 1999 (Qld) (“UCPR”) that a party
who denies the occurrence of a condition precedent must specifically plead that
denial, and the general rules of pleading in the UCPR rr 149(1)(c), 150(4)(a), and
150(4)(c). Vercorp also argued that a passage in the judgment of Mason CJ and
Gaudron J in Banque Commerciale SA (In liq) v Akhil Holdings Ltd24 established
23 [2010] QSC 405 at [50]-[52].
24 (1990) 169 CLR 279 at 286-287.
-- 27 of 33 --
28
that it was not open to the trial judge to decide the case on the basis of the condition
precedent because ACN had not pleaded such a condition precedent.
[63] I accept ACN’s argument that the question whether the repurchase contracts
included the condition precedent found by the trial judge was an aspect of the
contractual construction issue raised by the pleadings. ACN pleaded that: the
repurchase contracts provided that settlement was to take place within 30 days of
exercise of the option, with time of the essence; Hegira did not effect settlement by
that time; and ACN terminated the contracts on or about 24 February 2004 by its
solicitor’s letter of that date.25 The pleading attributed the termination of the
contracts to Hegira’s failure to complete rather than to the absence of the valuation
required by the contract, but the significance of that distinction is reduced by the fact
that the failure to complete was itself plainly attributable to the absence of the
valuations fixing the prices. Furthermore, Vercorp’s own statement of claim dealt
with the proper construction of the contract. It pleaded the facts upon which the trial
judge’s analysis depended, including that the prices had not been fixed by valuations
within the 30 day period specified by the express terms of the contracts. Vercorp
sought to overcome that apparent obstacle to its claim by alleging that, by a process
of construction or implication, “the parties agreed that settlement [of the contracts
for the repurchase of Lots 411 and 412] would be extended by agreement for
a period necessary to allow the purchase price to be determined in accordance with
clause 25.5 of Annexure D if for any reason it could not be determined within
30 days of delivery of the notice of exercise of the option.”26 That necessarily
comprehended a case that upon the proper construction of the contracts, or by
a process of implication, performance of the contracts was not conditional upon the
prices being fixed by valuations before the specified time for settlement. ACN
specifically denied the allegation. For these reasons, the trial judge’s findings that
the contracts were subject to the condition precedent and that it was not fulfilled
were not outside the pleadings.
[64] There was no question that ACN purported to terminate the contract, but Vercorp
made the point that ACN did not specifically plead that its purported termination
was justified by non-fulfilment of the condition precedent. That is so, but ACN did
plead that it had terminated the contracts, and the question whether ACN’s
purported termination was effective despite its invocation of breach of contract
rather than non-fulfilment of a condition precedent involves only a question of law.
On this point the facts are uncontroversial and the parties have had a full opportunity
to argue the point. It is therefore permissible for this Court to deal with it,27 and
I consider that it is just to do so.
[65] Vercorp argued that the trial judge erred in finding that ACN’s purported
termination of the repurchase contracts by its solicitor’s letter dated 24 February
2004 letter was valid. The argument was that the letter (which is set out in [11] of
these reasons) was ineffective because it relied upon a breach of contract rather than
non-fulfilment of a condition precedent. ACN invoked Shepherd v Felt & Textiles
of Australia Ltd28 for the proposition that a purported termination of a contract is
valid although it relies upon a ground for termination which is not available and
does not express a ground which is available. Vercorp argued that the principle did
25 Defence, paragraph 41(d)(iii), 46(a), (aa), (ac)(i), (b).
26 Fifth further amended statement of claim, paragraph 47.
27 See Coulton v Holcombe (1986) 162 CLR 1 at 7-8.
28 (1931) 45 CLR 359.
-- 28 of 33 --
29
not apply to termination for non-fulfilment of a condition precedent to performance.
No authority was cited for that proposition and I do not accept it. In Minion
v Graystone Pty Ltd,29 McPherson J held that the authorities supported the broad
principle that an “action taken must be capable of being justified at law, but that the
grounds of justification, although they must have existed, need not have been known
or relied upon at the time the action was taken.” Whether or not that is applicable
where a contract is purportedly terminated under or for breach of a statutory
provision may depend upon the effect of the statute,30 and there may be other
limitations upon the breadth of the principle, but there seems no reason to doubt that
it applies where a purported termination for breach of contract is justifiable by
a different available ground of non-fulfilment of a condition precedent expressed or
implied in the contract.
[66] It remains necessary to consider whether there was a real possibility that further
evidence might have been adduced or the case might have been run differently in
any other respect if ACN had specifically pleaded that it had terminated the
repurchase contracts for non-fulfilment of the condition precedent.31 As to that,
Vercorp argued that if termination for non-fulfilment of the condition precedent had
been specifically pleaded it would have had “the opportunity” to adduce additional
evidence and argue a different case, but it did not submit that there was any real
possibility that it would have done so. This is not simply a matter of semantics. It is
to be expected that if any of the additional arguments to which Vercorp referred
were thought to be meritorious, it would have pleaded them in its own statement of
claim, just as it pleaded a particular construction or implication by way of explaining
why it could insist upon settlement despite the expiry of the time for settlement
specified in the express terms of the contracts.
[67] Vercorp’s strongest argument on the pleading point was that, if termination for non-
fulfilment of the condition precedent had been specifically pleaded, it could have
sought relief against forfeiture.32 Vercorp did not argue, however, that if relief from
forfeiture was realistic it could not have maintained such a claim in its own
statement of claim or upon the basis of the pleaded defence. Nor did Vercorp
identify any possible evidence or argument which might have justified relief from
forfeiture. In these circumstances, and again bearing in mind that Vercorp’s own
pleading alleged a ground for overcoming the obstacle to ordering specific
performance that the valuations had not been obtained in accordance with the
express terms of the contract, I am not persuaded that there is any realistic
possibility that the trial might have been run differently if ACN had specifically
pleaded that it terminated the contracts for non-fulfilment of the conditions
precedent.
[68] Accordingly I do not accept Vercorp’s argument that ACN was not entitled to rely
upon the trial judge’s analysis to resist Vercorp’s appeal. In the course of explaining
why I do not accept Vercorp’s challenges to the trial judge’s reasoning, I will deal
both with the arguments agitated before his Honour and with additional arguments
29 [1990] 1 Qd R 157 at 164.
30 See Vennard v Delorain P/L as Trustee for the Delorain Trust [2010] QCA 309 at [52]-[54].
31 See Whisprun Pty Ltd v Dixon (2003) 200 ALR 447 at 461 [51].
32 Hill v Terry [1993] 2 Qd R 640 per Ryan J at 657 (Byrne J agreeing). McPherson SPJ, who was in
dissent on this point, observed at 649 that where “nothing in the nature of a breach has been
committed, it is, to say the least, doubtful whether equity has power to relieve against loss of the
interest of the purchaser in consequence of the exercise of a power to determine the contract”.
-- 29 of 33 --
30
which Vercorp contended it would have advanced if ACN had specifically pleaded
that it terminated the contracts for non-fulfilment of the condition precedent.
[69] Vercorp argued that the trial judge erred in finding that the purchase price under the
repurchase contracts must be determined only by the valuer appointed under cl 25.5.
That was related to its argument that time was not of the essence of the parties’
obligations to complete the repurchase contracts: it was not reasonable to expect that
the valuation exercise would have been performed by a court within the specified
time after it appeared that the valuation contemplated by the contracts could not be
completed in that time. I do not accept the argument. Clause 6.1 of the REIQ
standard terms made time of the essence. Clause 25.4.2 of Annexure D provided
that on delivery of the notice of exercise of option, “the buyer and the seller become
immediately bound as Vendor and as Purchaser respectively under a Contract for
sale of land in accordance [with] the terms of the Contract currently approved by the
Real Estate Institute of Queensland for the sale of land.” That was plainly apt to
incorporate cl 6.1 of the REIQ standard terms. Nor was there any inconsistency
between cl 6.1 and the apparent aim of the special conditions. As the trial judge
observed, the parties did not agree upon a settlement which was to occur according
to when the price was determined or within a reasonable time, and the purpose of the
option to repurchase would be promoted by a term making time of the essence as
that would “tend to expedite the repurchase of the land so that Hegira could put paid
to the impact of the purchaser’s default in complying with the building covenants.”33
[70] Vercorp argued that, as a matter of construction of cl 25.4.3, ACN did not have a
right to terminate where settlement did not occur within the 30 day period because
the valuer acting under cl 25.5 had not determined the market value. It contended
that the parties did not contemplate that either party could withdraw from the
contracts in that circumstance, and that their intention, objectively ascertained, was
that both would cooperate to achieve performance outside the 30 day period if
required. That construction would conflict with the express term in cl 25.4.3. Nor
do I accept Vercorp’s argument that the reasoning in Re Ronim Pty Ltd34 justified an
implied term to the effect that the date for settlement should be extended until the
time when the valuation could be obtained. Such an implied term would conflict
with cl 25.4.3 and it was not necessary in view of Hegira’s ability to obtain the
valuation before exercising the option.
[71] Vercorp argued that the view that Hegira could have requested the President to
appoint a valuer and obtained a valuation before exercising the option was
commercially unrealistic or contrary to the construction of cl 25 as a whole.
Because of the possibility of movements in the market prices of the lots, it may be
arguable that a notice of exercise of option under cl 25.4.1 should be given no later
than upon the date of or within a reasonable time after the valuation under cl 25.5,
but there is no sufficient basis for implying a term that the valuation may be
obtained only after the exercise of the option under cl 25.3. Vercorp referred to
ACN’s pleaded allegation that the option could only be exercised within
a reasonable time after the occurrence of a breach of cl 22, but that allegation, which
Vercorp denied, was not inconsistent with the view that the valuation might be
obtained before exercise of the option.
[72] Vercorp contended that an implied term in the repurchase contracts obliged ACN to
agree to extend the period for settlement and that such an agreement was expressly
33 [2010] QSC 405 at [61]-[63].
34 [1999] 2 Qd R 172 at 180 [18], 181 [21].
-- 30 of 33 --
31
contemplated by cl 25.4.3. The admitted implied term was that ACN was obliged to
do everything within its power to confer upon Vercorp the full benefit of the
repurchase contracts. The question whether the repurchase contracts imposed the
duty which Vercorp postulated depends upon the intention of the parties manifested
by the contracts.35 The commercial object of the contracts did not extend to
permitting Hegira to purchase Lots 411 and 412 in all circumstances where ACN
defaulted under cl 22. It is necessary to have regard also to the time limit specified
in cl 25.4.3. The expression in cl 25.4.3, “or such extended period as may be
agreed” conveyed that agreement was not mandatory; it was a matter for each party
whether or not to make any such agreement. To imply that the parties were obliged
to extend the period for settlement if it could not occur within 30 days would be to
impose an agreement to agree. That would be inconsistent with the word “may” in
cl 25.4.3 and with the absence of any express link in the contract between the time
for settlement and the time of receipt of the valuation. Vercorp pointed out that the
parties would have been at liberty to agree to defer the time for settlement in the
absence of the words “as may be agreed”, but that does not justify departure from
the ordinary meaning of those words. The parties were at liberty to agree or not to
agree upon any extension of time.
[73] Vercorp advanced the similar contention that the right to terminate could only be
exercised in good faith, reasonably, and in accordance with an implied obligation
that the parties would reasonably cooperate towards performance and would “take
all reasonable steps to render the contract efficacious in accordance with the
presumed intention of the parties”.36 Assuming, without deciding, that any such
obligations might be implied, the reasons I have already given explain why I reject
Vercorp’s argument that ACN was in breach of them. The terms of the repurchase
contracts expressly required any repurchase to be completed within the specified
period, but in the events that occurred those contracts were incapable of being
completed at that time. In Overlook v Foxtel37 Barrett J observed that the duty of
good faith is “a duty to recognise and to have due regard to the legitimate interests
of both the parties in the enjoyment of the fruits of the contract as delineated by its
terms.” The terms of the contracts did not confer any interest upon the parties in
having the contracts performed beyond the specified times.
[74] Vercorp argued that the trial judge’s analysis was inconsistent with the High Court’s
decision in Sandra Investments Pty Ltd v Booth,38 but in that case Gibbs CJ made it
clear that every case depends upon the particular provisions of the contract. The
decision in Sandra Investments Pty Ltd v Booth that the vendor had no right to treat
the contract as being at an end turned upon the facts that the contract conferred upon
the purchaser the option to cancel the contract if the relevant condition precedent to
performance (a local government approval to a plan of subdivision and engineering
plans) was not obtained within a specified time, and the purchaser did not exercise
that right. There was no analogous provision or similar conduct in this case.
[75] Vercorp contended that ACN was not entitled to terminate the repurchase contracts
for non-fulfilment of the condition precedent because ACN had by its conduct
35 Secured Income Real Estate (Australia) Ltd v St Martins Investments Pty Ltd (1979) 144 CLR 596 at
607-608 per Mason J (Gibbs, Steven and Aickin JJ agreeing).
36 See Seddon and Ellinghaus, Cheshire and Fifoot’s Law of Contract, 9 th ed, 2008, LexisNexis
Butterworths, Sydney, 2008, at paras 10.41, 10.42, 20.16, 20.18 and 21.33 citing Godfrey
Constructions Pty Ltd v Kanangra Park Pty Ltd (1972) 128 CLR 529 at 538, 544, and 551-552.
37 [2002] NSWSC 17 at [67]. I have added the emphasis.
38 (1983) 153 CLR 153 at 157, 161-162.
-- 31 of 33 --
32
evinced an intention not to perform the repurchase contracts and thereby repudiated
them. However, Vercorp did not identify any conduct by ACN before the due date
for settlement in January 2004 which evinced any such intention. If there were any
substance in this point, Vercorp presumably would have pleaded it in response to
ACN’s allegation that it had terminated the repurchase contracts for breach, but the
point was not pleaded.
[76] Vercorp also argued that the trial judge erred in finding that the appointment of
Mr Harvey as valuer by the Vice President of the Australian Institute of Valuers and
Land Economists (Queensland Division) was not in accordance with cl 25.5 of
Annexure D, and in failing to consider whether, and in failing to find that, there was
an implied term that the appointment could be made by the Vice President or next
senior office bearer where the President would not make the appointment. The trial
judge considered that it was not necessary to determine this issue, but found that the
valuation which was ultimately produced was not made under cl 25.5 because
Mr Harvey’s firm was appointed by the Vice President of the Institute rather than by
the President of the Institute. I respectfully consider that there is substance in
Vercorp’s submission that, where the President appropriately refrained from making
the appointment because of a potential conflict of duties, it should be implied that an
appointment of a valuer by the next most senior officer fulfilled the requirement that
the appointment be “by the President for the time being” of the Institute. However,
it is not necessary to decide the point because I have concluded that ACN validly
avoided the repurchase contracts before Mr Harvey sent his valuation of Lots 411
and 412 on 30 April 2004.
[77] Vercorp’s appeal should be dismissed.
Proposed orders
[78] In my opinion the appropriate orders are:
(a) In Appeal No 12847 of 2010:
(i) Dismiss the appeal.
(ii) Allow the cross appeal.
(iii) Declare that the contract between the first respondent and the
appellant for the purchase by the first respondent of Lot 413
on SP133280 should be specifically performed and carried
into effect.
(iv) Declare that the contract between the first respondent and the
appellant for the purchase by the first respondent of Lot 414
on SP133280 should be specifically performed and carried
into effect.
(v) The parties are at liberty to apply in the trial division for any
further or other orders relating to the specific performance of
those contracts.
(vi) Order that the appellant pay the respondents’ costs of and
incidental to the appeal.
(vii) Order that the first respondent pay the appellant’s costs of the
first respondent’s cross appeal.
(b) In Appeal No 12868 of 2010, dismiss the appeal with costs.
-- 32 of 33 --
33
[79] WHITE JA: I have had the benefit of reading the reasons for judgment of
Fraser JA. I agree with those reasons and there is nothing which I can usefully add.
I agree with the orders proposed by his Honour.
[80] ATKINSON J: I agree with the orders proposed by Fraser JA and with his
Honour’s reasons.
-- 33 of 33 --
Official source: https://www.sclqld.org.au/caselaw/QCA/2011/189