Bergin v McLeod & Anor [2011] QSC 325
1-1
SUPREME COURT OF QUEENSLAND
CITATION: Bergin v McLeod & Anor [2011] QSC 325
PARTIES: PATRICK THOMAS BERGIN
(plainitff)
v
OKSANA GENNADIEVNA MCLEOD
(first defendant)
and
LINDSAY ROSS MCLEOD
(second defendant)
FILE NO: BS 7145 of 2011
DIVISION: Trial Division
PROCEEDING: Trial
ORIGINATING
COURT: Supreme Court of Queensland
DELIVERED EX
TEMPORE ON:
14 October 2011
DELIVERED AT: Brisbane
HEARING DATE: 12, 13, 14 October 2011
JUDGE: Daubney J
ORDERS: 1. Upon the defendants, each by their counsel giving the
undertaking set out in paragraphs 2 and 3 of Exhibit
3, it is ordered:
(1) The defendants and each of them, by themselves,
their employees, agents or otherwise howsoever,
be restrained from interfering with the
construction by the plaintiff of the driveway, in
accordance with the plan labelled SK02, annexed
to the statement of claim.
(2) The defendants pay compensation to the plaintiff
in the sum of $13,341.70.
2. The defendants pay the plaintiff’s costs including any
reserved costs of and incidental to the proceeding on
the standard basis.
CATCHWORDS: REAL PROPERTY – EASEMENTS – PARTICULAR
EASEMENTS AND RIGHTS – RIGHTS OF WAY –
OBSTRUCTION - where the plaintiff and first defendant are
-- 1 of 22 --
1-2 JUDGMENT
1
10
20
30
40
50
60
the registered properties of adjacent properties – where the
second defendant has the right to occupy the first defendant’s
property – where the plaintiff obtained a grant of easement
over the first defendant’s property – where a driveway was to
be constructed on the easement land - where the second
defendant undertook works which adversely impacted the
easement land – where the second defendant sought to
approve the works being undertaken by the plaintiff on the
easement land - where the second defendant obstructed works
on the driveway – where the plaintiff seeks injunctive orders
and damages – whether the second defendant has an
entitlement to approve the works on the easement land –
whether the defendants contravened s 179 of the Property
Law Act 1974 (Qld) – whether the plaintiff should be
awarded damages and injunctive relief.
PROCEDURE – COSTS – DEPARTING FROM THE
GENERAL RULE – CONDUCT OF PARTIES – OTHER
CONDUCT – where the plaintiff has enjoyed complete
success – where the plaintiff submits that the
unreasonableness of the second defendant’s conduct warrants
an award of costs on an indemnity basis - whether costs
should be on the standard or an indemnity basis.
Property Law Act 1974 (Qld), s 179, s 180
Colgate-Palmolive Company and Cussons Proprietary
Limited (1993) 46 FCR 225, cited
COUNSEL: J W Peden for the plaintiff
M Foley for the defendants
SOLICITORS: de Groots for the plaintiff
Redchip Lawyers for the defendants
-- 2 of 22 --
1-3 JUDGMENT
1
10
20
30
40
50
60
HIS HONOUR: The plaintiff is the registered proprietor of lot
76 on crown plan A1551, Parish of Albert, County of Ward ("lot
76"). The first defendant is the registered proprietor of lot
77 on crown plan A1551, Parish of Albert, County of Ward ("lot
77").
Even though lot 77 is registered in the first defendant's
name, it is occupied by her former husband, the second
defendant. He retained the right to occupy lot 77 under the
terms of the matrimonial settlement with the first defendant.
Although she does not live on the property, the first
defendant says that she fully supports and has always fully
supported decisions made by the second defendant about lot 77.
Lot 76 and lot 77 front the Logan River. They are adjoining
properties. They are also effectively landlocked. Lot 76 is
to the north of lot 77. Lot 77 is separated on its southern
side from a street called August Lane by another block of land
described as lot 78 on CP A1551, Parish of Albert, County of
Ward ("lot 78"). A parcel of Crown land lies to the east of
lots 78, 77 and 76.
When the plaintiff purchased lot 76 in 2003, both lots 76 and
77 enjoyed the benefit of an access easement over lot 78.
That easement extended to a point at the south-eastern edge of
lot 77 and provided access to and from August Lane. Further
access to lot 76 was not, however, formalised at that time.
The plaintiff's practical access to his property was over a
-- 3 of 22 --
1-4 JUDGMENT
1
10
20
30
40
50
60
dirt track which meandered from the end of August Lane and
traversed both lot 77 and the Crown land.
In 2004, the plaintiff commenced negotiations with the second
defendant with a view to formalising access to lot 76 by means
of an easement along the eastern edge of lot 77. This
easement was proposed to join up with the existing easement
over lot 78, run along the eastern boundary of lot 77 and
provide access to the south-eastern corner of lot 76.
Negotiations were unsuccessful over a period of years. In the
meantime the second defendant undertook a number of works on
lot 77 including enlarging what had been a small pond into a
significant dam on the eastern side of lot 77, fencing the
eastern boundary of lot 77 such as to prevent use of the dirt
track access to lot 76, across lot 77 and the Crown land, and
planting a line of saplings in the eastern part of lot 77.
Between the dam and the eastern boundary there remained a
sufficient strip of land running along the eastern boundary to
be used for access to lot 76. The saplings were planted along
this strip of land.
With negotiations for an easement having failed, the plaintiff
instituted proceedings in this Court with a view to obtaining
a grant of easement. That proceeding came on for trial in
November 2009 but settled on the first day of trial.
On 17 November 2009 the plaintiff and the first defendant
-- 4 of 22 --
1-5 JUDGMENT
1
10
20
30
40
50
60
executed a deed of settlement by which the first defendant
agreed to grant the plaintiff a registered easement over lot
77 in accordance with the draft easement document annexed to
the settlement agreement. I observe in passing that this
agreement was actually signed by the second defendant as
"authorised agent" of the first defendant.
Moreover, on 17 November 2009 the parties consented to the
following orders being made by the Court:
"By consent, the order of the Court is that:
(1) pursuant to section 180 subsection (1) of the Property Law
Act 1974 (Qld), there be imposed upon the land described as
lot 77 on CP A1551, Parish of Albert, County of Ward, in the
State of Queensland a statutory right of user in the form of
an easement in favour of the land described as Lot 76 on CP
A1551, Parish of Albert, County of Ward, in the State of
Queensland; (2) Such easement is to be in terms of the draft
easement marked Annexure A to this order;
(3) The Applicant pay to the Respondent the sum of $82,500 by
way of compensation for the imposition of the easement;
(4) There be no order as to costs."
It was further declared that the right of user in order 1 was
exercisable in perpetuity. The form of draft easement annexed
to the order was the same as the easement annexed to the terms
of settlement.
The easement was ultimately registered in the Queensland Land
Registry on 22 July 2010. The land, which is the subject of
-- 5 of 22 --
1-6 JUDGMENT
1
10
20
30
40
50
60
the easement, is a four metre wide strip of land along the
eastern boundary of lot 77. The terms of the easement include
the imposition on the plaintiff of an obligation to construct
a driveway along the easement.
By clause 4.1 of the easement the plaintiff:
"must construct a Driveway and Improvements on the Burdened
Land at the Grantee’s cost, including conducting all
earthworks and obtaining all Local Government approvals and
environmental approvals (if applicable) necessary to construct
the Driveway and Improvements; and
4.1.1. the Driveway must be sealed in a manner similar to the
easement over Lot 24A, also known as Lot 78 on Crown Plan
A1551; and
4.1.2. The easement must have a maximum width of four (4)
metres at any point and the sealed section of the Driveway
must be no wider than is reasonably necessary to provide the
Access and must be constructed in a way which, as far as is
reasonably possibly[sic] will avoid damage to the existing
trees; and
4.1.3. the Grantee will plant a line of trees or similar
screening plants along the driveway to act as a privacy
screen."
The term "Driveway" was defined in clause 1 of the easement to
mean "a sealed driveway sealed in a manner similar to the
driveway over Lot 24A, also known as Lot 78 on Crown Plan
A1551, constructed of any material for the carriage of
vehicles, trucks, natural persons or animals located upon the
-- 6 of 22 --
1-7 JUDGMENT
1
10
20
30
40
50
60
Burdened Land."
By clause 2 the first defendant granted the plaintiff an
easement over the burdened land for what was described as the
"Purpose". Clause 3 defined "Purpose" as including access
which meant "allowing access (including carriageway or
footway) or right of way over the Burdened Land, to persons
and to vehicles".
By clause 4.10 of the easement the plaintiff acknowledged that
if the plaintiff breached the easement then "the grantor may
do anything the Grantor thinks is reasonably necessary to
correct the breach (such as removing a structure erected on
the Burdened Land in breach of this easement) at the
[plaintiff's] cost."
Despite having signed the settlement agreement and consented
to the Court making the order it did in November 2009, the
second defendant thereafter undertook works which adversely
impacted on the easement land. Those works can generally be
described as falling into two categories:
(a) He enlarged the eastern edge of the dam in such a way as
to cause the dam to encroach on the southern third of the
easement land - this is depicted in Exhibit 10;
(b) He removed topsoil from the easement such as to camber the
surface of the easement land down to the level of the dam
surface - this is depicted in Exhibit 26.
I have already mentioned that the second defendant had
-- 7 of 22 --
1-8 JUDGMENT
1
10
20
30
40
50
60
previously undertaken works to enlarge the dam. I should also
mention that he only retrospectively obtained the necessary
local authority approvals to undertake those works. The local
authority did, however, give approval but subject to extensive
conditions concerning inter alia the permitted height of water
in the dam.
The second defendant claimed that the further works undertaken
after the signing of the settlement agreement and the making
of the consent order and which impacted on the easement land
was done in early January 2010. He made this claim by
reference to a cheque stub and bank statement which he claimed
evidenced payment to an earthworks contractor for work done
prior to 22 January 2010. No evidence was led from the
earthworks contractor.
On the other hand, Mr Nolan, a surveyor, expressed the opinion
by reference to aerial or satellite photos of the property
that the earthworks were probably carried out between
23 January 2010 and 25 April 2010. Another surveyor, Mr
Fussell, said that when he surveyed the easement on 4 February
2010 he was able to drive along its length and he did not
notice anything untoward about its width.
The combined independent evidence of the surveyors and the
lack of corroborating evidence for the second defendant lead
me to conclude that the works which impacted on the easement
land were performed at some time between 4 February 2010 and
25 April 2010.
-- 8 of 22 --
1-9 JUDGMENT
1
10
20
30
40
50
60
In making that finding I also note that even on the second
defendant's version he caused these works to be undertaken at
a time after the parties had agreed to the grant of the
easement and the Court had made the order by consent to effect
the grant of easement.
In late 2010 the local authority confirmed to the plaintiff
that no further operational works approval was required for
the construction of the driveway.
Between December 2010 and mid-2011 the plaintiff and the
second defendant exchanged e-mail correspondence which became
increasingly belligerent. The plaintiff was wanting to get on
with the construction of the driveway. The second defendant
was insisting on being present and in effect insisting on
approving the works undertaken. Apart from some general
assertion that he had the right to do so because it was his
land, the second defendant could point to no lawful
entitlement to impose his approval as a condition of the works
on the driveway. His misplaced belief in this "entitlement"
led him to obstructing works on the driveway. He caused a
bulldozer and a trailer to be parked in positions which
prevented access to the easement land in late 2010/early 2011.
The extreme rainfall of early 2011 led to an effective but
temporary moratorium. In May 2011 the plaintiff gave the
second defendant notice of the plaintiff's intention to
commence construction on the driveway. That construction
commenced on the 2nd of June 2011 with preliminary earthworks.
-- 9 of 22 --
1-10 JUDGMENT
1
10
20
30
40
50
60
The second defendant, however, took great exception to how
those works were being undertaken. In particular he resented
the fact that saplings along the easement were removed and,
together with fence posts which he had inexplicably left piled
on the easement land, were being used, so he perceived it, as
part of the base of the driveway being constructed. He was
mistaken about that. I accept the explanation given by
Mr Rolton, the plaintiff's earthworks contractor, that these
items were being used temporarily to assist in stabilising the
earthmoving equipment and were not to be used permanently as
part of the driveway base.
In any event, the second defendant took matters into his own
hands. He drove a small bulldozer along the easement in such
as way as to prevent the plaintiff's contractors from
continuing their work. Construction work ceased.
The plaintiff's response to this conduct by the second
defendant was to invoke his lawful remedies by instituting
proceedings in this Court. On 16 August 2011 the plaintiff
filed a claim and statement of claim seeking a range of
injunctive orders and also claiming damages.
On 25 August 2011 the plaintiff filed an application for an
interim injunction to restrain the second defendant from
blocking or obstructing the easement. That application came
before the Court on 26 August 2011. The hearing was resolved
on the basis of undertakings in the following terms:
"Upon the undertaking of the plaintiff by his Counsel giving
-- 10 of 22 --
1-11 JUDGMENT
1
10
20
30
40
50
60
the usual undertaking as to damages (sic).
And upon the undertaking of the defendants, by themselves,
their servants, agents or otherwise, howsoever, not to block
or obstruct or permit the blocking up of or obstructing of the
Easement Number 713366693 at Lot 77, CP A1551, County of Ward,
Parish of Albert, title reference 50156699, being the land
located at 24B August Lane, Alberton in the state of
Queensland (“Easement land”) until further Order.
And upon the undertaking of the defendants by their Counsel
giving the usual undertaking as to damages.
And upon the undertaking of the plaintiff, by himself, his
servants, agents or otherwise, howsoever not to construct a
driveway on the Easement land until further Order."
The Court also made directions to bring the matter on for an
expedited trial.
The relief claimed by the plaintiff in this proceeding was
articulated in the prayer for relief as follows:
"1. Damages.
2. Interest on such damages under 47 of the Supreme Court Act
1995.
3. An injunction restraining the defendants, by themselves,
their servants, agents or otherwise howsoever, from
interfering with the construction by the plaintiff of the
driveway in accordance with the plan labelled SKO2 annexed to
this statement of claim.
4. An injunction restraining the defendants, by themselves,
their servants, agents or otherwise howsoever, from blocking
-- 11 of 22 --
1-12 JUDGMENT
1
10
20
30
40
50
60
or obstructing or permitting the blocking up of or obstructing
of the Easement land.
5. An injunction requiring the defendants to construct and
maintain the Dam in accordance with the dimensions and
infrastructure set out in the Development Approval dated
6 March 2009 and for so long as either of them is the legal
owner or occupier of the First defendant's Land to maintain
that infrastructure such as to ensure the water level of the
Dam is no higher than 1.2 metres AHD."
When the matter was called for trial before me counsel for the
defendants offered a number of undertakings on behalf of his
clients. Following some useful and productive discussion
between the Bench and the Bar table counsel for the defendants
obtained instructions to expand the scope of the undertakings
offered. Those undertakings are set out in Exhibit 2.
It seems to me that several of those undertakings are
sufficient to meet a number of the claims advanced by the
plaintiff. The defendants have offered an undertaking that
they by themselves, their servants or agents will not block or
prevent blocking up of or obstruction of the easement land.
That undertaking answers paragraph 4 of the plaintiff's prayer
for relief.
The defendants also offer an undertaking that they “will not
do anything to increase height or cause blocking of the
existing drain or do anything that will un-naturally increase
the water level of the dam above approximately 1.2 metre AHD
-- 12 of 22 --
1-13 JUDGMENT
1
10
20
30
40
50
60
as per Project Number 08351 Drawing Number C03 of the Gold
Coast City Council.”
The injunction sought by the plaintiff was, as is apparent
from paragraph 5 of the prayer for relief, much more extensive
in its ambit. I accept the submission of counsel for the
defendants that it amounted to a request for an injunction to
compel complete compliance with all the terms of the local
authority's approval. Even if such an injunction were
available it would clearly go beyond what is required to
protect the plaintiff's legitimate interest in the easement
land in the present case.
If the second defendant is foolish enough to breach the
conditions of the local authority approval that is a matter
which can be taken up with the local authority. What the
second defendant has demonstrated, however, is a propensity to
cause impact to the easement land by adjustment of the dam
levels or dam walls and that is the appropriate subject of
relief in the present case. That issue, it seems to me, is
adequately addressed by the terms of undertaking number 3
contained in Exhibit 2.
The issues left for determination then are the plaintiff's
claim for an injunction to enable construction of a driveway
and a claim for damages.
In respect of the injunction the undertaking originally
offered by the defendants at the commencement of the trial was
-- 13 of 22 --
1-14 JUDGMENT
1
10
20
30
40
50
60
in the following terms:
"The First and Second defendant, by themselves, their servants
or agents will not interfere with the construction by the
Plaintiff of the driveway on the following condition:
a. That the Plaintiff builds the driveway in accordance with
the 'PROPOSED DRIVEWAY DETAILS 5763-110804-SK01" attached to
the HCE Engineers report dated 7 July 2011."
The "condition" stated in that undertaking was subsequently
expanded to purport to permit a 3.3 metre wide driveway with
one edge 300 millimetres from the eastern boundary and the
other edge 300 millimetres from the western alignment of the
easement. Regardless of the width of the driveway offered
under this undertaking however, the form of the undertaking
betrays the same error of thinking which has pervaded much of
the second defendant's approach to this matter. Once again,
he seeks to impose a condition of his own satisfaction on the
plaintiff's construction of the driveway in circumstances
where, by the terms of the easement, he has no entitlement to
do so. What the easement requires is that the plaintiff
construct a driveway, the sealed section of which "must be no
wider than is reasonably necessary to provide the Access and
must be constructed in a way which is far as is reasonably
possibly (sic) will avoid damage to the existing trees". That
is the obligation on the plaintiff.
By executing the settlement agreement, consenting to the Court
order and executing the easement, which was subsequently
registered, the defendants implicitly agreed to permit the
-- 14 of 22 --
15 JUDGMENT
1
10
20
30
40
50
60
plaintiff to perform the works necessary to fulfil his
obligations under the easement. The facts of this case show
that the second defendant clearly impeded the plaintiff in
fulfilling those obligations. That manifested itself in:
(a) the second defendant's physical obstruction of the works;
and
(b) the excavation work undertaken by the second defendant
which adversely impacted on the easement land (as described
above).
The debate before me then descended into the detail of what
width of driveway should be constructed and what works are
required for that. That debate was relevant to both the terms
of the injunction sought and the claim for damages. The
debate on both sides was a little artificial in several
respects. First, the debate turned on engineering plans for
the driveway showing different widths of sub-base work
required to achieve different widths of driveway on the
surface. These plans did not exist, however, when the
plaintiff's contractors commenced work in June 2011. Indeed,
Mr Rolton confirmed in evidence that he did not have any plans
or diagrams of the nature of the work he was about to perform
when he started work on 2 June 2011.
The debate was also quite artificial from the defendants'
perspective. The defendants, by their counsel, were adamant
that they wanted a driveway constructed properly and safely to
ensure, as counsel put it, that the defendants' duty of care
to people using the driveway would be satisfied. I have
-- 15 of 22 --
16 JUDGMENT
1
10
20
30
40
50
60
already noted the second defendant's misconception about his
entitlement to "approve" the construction of the driveway.
This misconception was evident even in his conduct after he
blocked access to the easement land in June 2010 when he, as
he deposed in his affidavit sworn 26 August 2011, called on
the plaintiff to provide "evidence of the Plaintiff's
compliance with the Easement, namely:
(a) A copy of any permits relating to building of the
driveway;
(b) A complete copy of plans and engineering details of the
Driveway;
(c) Undertaking that the Plaintiff would replace the trees
that the Plaintiff unnecessarily removed from the Property and
in the process of preparation of building of the driveway."
The second defendant had no entitlement to (a) or (b)
Requirement (c) was already covered under the express terms of
the easement. This false sense or claim of entitlement
contributed to the artificiality of the defendants' position,
the truth of which was probably best expressed by the first
defendant who when asked about the width of the driveway said
in evidence, "I believe that 3.5 metres would be enough, but
four metres is fine for me." There is also a sense of
artificiality in seeking to determine what driveway can be
constructed by reference to the easement land as it was in
November 2009 when the parties agreed to the grant of the
easement. The reality is that the second defendant, by his
subsequent works, both partly encroached on and generally
adversely affected the easement land and this in turn has an
impact on what should now happen to enable the plaintiff to
-- 16 of 22 --
17 JUDGMENT
1
10
20
30
40
50
60
fulfil his obligation under the easement to construct a
driveway.
It is possible that works could now be conducted wholly within
the four metre width of the easement land which would yield a
driveway (some three metres wide) which runs hard up against
the eastern boundary of lot 77. This is what is depicted in
the engineer's drawing marked SKO1. The fact that this is
possible does not make it reasonable. The easement expressly
contemplates that the purpose of the easement includes
allowing access to person and vehicles. The width and
placement of the driveway on the easement land is to be such
as is "reasonably necessary" to provide the access. That
clearly allows for something more than the bare minimum. It
seems to me that the driveway proposed in drawing SKO2
satisfies the requirement of reasonable necessity.
Construction of a driveway in accordance with SKO2 will
require however the placement of sub-base material beyond the
four metre width of the easement land. That has been
necessitated in no small part by the second defendant's
conduct in excavating the dam in a way which has encroached on
the easement and in removing the surface from the easement
land to create a camber or "bench" towards the dam. In so
doing the defendants contravened section 179 of the Property
Law Act 1974. Counsel for the defendants faintly advanced an
argument that the fact that the easement was not registered
until June 2010 meant that conduct by the defendants prior to
that date could not be considered as constituting
contravention of section 179. That section however expressly
-- 17 of 22 --
18 JUDGMENT
1
10
20
30
40
50
60
operates for the benefit of "all interests" in the subject
land and that clearly extends to the equitable interest the
plaintiff held in the easement land from 17 November 2009.
The second defendant's excavations in 2010 had the effect of
removing support from the easement land. The works
contemplated in SKO2 are necessary to restore that support,
notwithstanding that they involve the placement of sub-base on
the dam side of the easement land.
Before departing from this aspect I should note that the
second defendant also sought to justify his "self-help" on the
basis of clause 4.10 of the easement. Again, his reliance in
that regard is misplaced. That clause allows him to correct a
breach, not to take the law into his own hands by preventing
the plaintiff from fulfilling his obligations under the
easement.
I am satisfied that the plaintiff should have an injunction
which will enable him to undertake works on the easement land
to build a driveway in accordance with plan SKO2. The history
of obstruction by the second defendant makes it clear that
such an injunction is necessary.
There remains then the question of damages, or, more
appropriately titled, compensation. As I found above, the
defendants, by the actions of the second defendant, breached
the obligation of support imposed by section 179 of the
Property Law Act. The plaintiff will undoubtedly be put to
extra expense in constructing the driveway as a consequence.
-- 18 of 22 --
19 JUDGMENT
1
10
20
30
40
50
60
The plaintiff claimed the sum of $26,683.80 (including GST)
being for hire of machinery and for materials. This was based
on a quote from Mr Rolton for performing the "additional work"
involved in implementing plan SK02.
There are, however, a number of difficulties in simply
accepting those figures. The first is, as I have said, that
SK02 did not exist when Mr Rolton first went to perform works
on the driveway on 2 June 2011.
It was not suggested that he was not going to construct an
appropriate driveway if he had been permitted to proceed on
that date. The extent of the difference between what he was
originally going to build and the works required under SK02
were never made clear in evidence.
Secondly, his evidence was, to say the least, confused, as to
whether there was overlap between the so-called "additional
work" and work which he would have performed in any event.
Doing the best I can in the circumstances, I consider it
appropriate to allow 50 per cent of the claimed additional
costs as representative of the extra work required to re-
instate the support for the easement land. That yields an
award of $13,341.70. That cost has not yet been incurred by
the plaintiff, so no interest is payable.
The following outcome then ensues: Upon the defendants, each
by their counsel giving the undertaking set out in paragraphs
-- 19 of 22 --
1-20
1
10
20
30
40
50
60
2 and 3 of Exhibit 3, it is ordered:
(1) The defendants and each of them, by themselves, their
employees, agents or otherwise howsoever, be restrained from
interfering with the construction by the plaintiff of the
driveway, in accordance with the plan labelled SK02, annexed
to the statement of claim.
(2) The defendants pay compensation to the plaintiff in the
sum of $13,341.70.
...
HIS HONOUR: The plaintiff has enjoyed substantive success in
this proceeding in respect of two of the injunctions sought.
The necessity for me to rule in respect of those was obviated
only by the fact that the defendants offered sufficient
undertakings at the commencement of the trial.
In respect of the balance of the relief sought, for the
reasons that I gave earlier, the plaintiff has enjoyed
complete success. There is, in the circumstances, no reason
why costs should not follow the event.
The only real question is whether I should accede to the
plaintiff's request that he have his costs, not on the
standard basis, but on the indemnity basis. Reliance was
placed on the well-known articulation of principles by Justice
Sheppard in Colgate-Palmolive Company and Cussons Proprietary
Limited (1993) 46 FCR 225.
-- 20 of 22 --
1-21
1
10
20
30
40
50
60
The submissions by the plaintiff in that regard focussed on
the unreasonableness, if not irrationality, of the second
defendant's conduct in blocking construction and a perverse
attitude to his entitlement to have control over the works
being performed for construction of the driveway.
All those matters were canvassed by me in my reasons for
Judgment and contributed to my conclusion that the plaintiff
should enjoy the relatively rare phenomenon of the form of
injunctive relief which I, ultimately, ordered. Those matters
do not, however, amount, in my view, to sufficient cause to
advance beyond the usual order as to costs to what the
authorities repeatedly described as an exceptional award, that
is, to award costs on the indemnity basis.
The one matter which was highlighted by counsel for the
plaintiff in his submissions was, in effect, the deterrent
factor which would flow from making an award of costs on an
indemnity basis. It was submitted that an award of indemnity
costs would possibly, and hopefully, have the effect of
causing all parties to consider, carefully, in the future any
conduct in breach of their lawful obligations.
It is not properly within the province of an award of costs to
be penal or to prevent people from either exercising their
rights or seeking to vindicate any defences they might have.
I am not aware of any authority which would justify an award
of indemnity costs for the purposes of deterring conduct in
the future and I do not think that this is an appropriate case
-- 21 of 22 --
1-22
1
10
20
30
40
50
60
for such a precedent to be set.
The order will therefore be that the defendants pay the
plaintiff's costs including any reserved costs of and
incidental to the proceeding on the standard basis.
In pronouncing that order I express the fervent hope that the
parties are now quit of the Supreme Court of Queensland and,
indeed, every other Court in this State and that they can get
on in neighbourly fashion and enjoy the amenities that they,
undoubtedly, have worked hard for on the banks of the Logan
River.
-----
-- 22 of 22 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2011/325