Advance Traders Pty Ltd v McNab Constructions Pty Ltd & Anor [2011] QSC 212
SUPREME COURT OF QUEENSLAND
CITATION: Advance Traders Pty Ltd v McNab Constructions Pty Ltd &
anor [2011] QSC 212
PARTIES: ADVANCE TRADERS PTY LTD
ACN 009 672 002
(Plaintiff)
v
McNAB CONSTRUCTIONS PTY LTD
ACN 073 311 681
(First Defendant)
and
McNAB CONSTRUCTIONS AUSTRALIA PTY LTD
ACN 102 840 906
(Second Defendant)
FILE NO/S: BS 9687 of 2009
DIVISION: Trial Division
PROCEEDING: Application
ORIGINATING
COURT:
Supreme Court of Queensland
DELIVERED ON: 4 August 2011
DELIVERED AT: Brisbane
HEARING DATE: 22 July 2011
JUDGE: Boddice J
ORDER: The application is dismissed
CATCHWORDS: PROCEDURE – SUPREME COURT PROCEDURE –
QUEENSLAND – PROCEDURE UNDER UNIFORM
CIVIL PROCEDURE RULES AND PREDECESSORS –
OTHER MATTERS – Where the defendants apply for an
order pursuant to r 483 Uniform Civil Procedure Rules 1999
(Qld) for the separate determination of questions in the
proceeding – Where the defendants submit that the separate
-- 1 of 8 --
2
determination of those questions will result in savings of time
and cost – Whether it is just and convenient for the order to
be made
Queensland Building Services Authority Act 1991 (Qld)
Uniform Civil Procedure Rules 1999 (Qld)
Body Corporate for Sun City Resort CTS 24674 v Sunland
Constructions Pty Ltd [2010] QSC 463
Arnold v Attorney-General (Vic) (unreported, Fed C of A,
Sundberg J, Nos VG629–37 of 1995, 8 September 1995,
BC9502745)
Evans Deakin Industries Ltd v Commonwealth [1983] 1 Qd R
40
Heery v Criminal Justice Commission [2001] 2 Qd R 610
Lee v Arisaig Pty Ltd & Ors [2005] QSC 265
McNab Constructions Pty Ltd v Queensland Building
Services Authority [2010] QCA 380
Puerto Galera Pty Ltd v J M Kelly (Project Builders) Pty Ltd
[2008] QSC 356
Pico Holdings Inc v Wave Vistas Pty Ltd [2003] QCA 204
Reading Australia Pty Ltd v Australian Mutual Provident
Society (1999) 217 ALR 495
Re Multiplex Constructions Pty Ltd [1999] 1 Qd R 287
Sherlex Pty Ltd v Thornton & Ors [2003] QCA 461
State of Queensland v Dale and Meyers Operations Pty Ltd
[2010] QSC 361
Watpac Civil Infrastructure Pty Ltd (formerly JMS Civil &
Mining (Aust) Pty Ltd) v Komatsu Pty Ltd [2009] QSC 281
COUNSEL: Doyle SC with Trim, M for the plaintiff/respondent
Fraser QC with Codd, B for the first and second
defendants/applicants
SOLICITORS: McInnes Wilson for the plaintiff/respondent
Lenz Moreton for the first and second defendants/applicants
[1] By application filed 31 May 2011 the first and second defendants (“the defendants”)
make application for an order pursuant to r 483 of the Uniform Civil Procedure
Rules 1999 (“UCPR”) for the separate determination of the following questions in
the proceeding:
(a) whether the contract entered into on 22 December 2004 was made between
the plaintiff, as principal, and the second defendant, as construction
manager;
-- 2 of 8 --
3
(b) whether the services agreed to be provided by the construction manager
under the contract were “building work” within the meaning of that term as
used in s 42 of the Queensland Building Services Authority Act 1991
(“QBSA Act”);
(c) whether any contractor‟s licence of an appropriate class for the services
existed under the QBSA Act:
(i) at the time when the services were provided, and
(ii) at least six months prior to the provision of the services.
[2] The defendants submit each of those questions is properly to be the subject of a
separate determination as they are discrete issues and although their determination
will not dispose of the litigation completely, their separate determination may result
in significant savings of time and cost in relation to the dispute the subject of the
proceeding, and assist in its ultimate compromise.
[3] The plaintiff opposes the separate determination of any of those questions. It
submits there is no truly separate question to be determined, that the questions are
not “ripe for determination”; that a separate determination of those questions is not
likely to save any meaningful time or expense; that the questions may instead lead
to a significant increase in time and expense, and that the separate determination of
those questions would unnecessarily fracture and delay the proceeding.
The proceeding
[4] The plaintiff was the developer of an apartment complex built in the redevelopment
of a wool store at Teneriffe. As part of that redevelopment, a written contract for
construction management services (“the contract”) was entered into on 22
December 2004. The contract was executed by the plaintiff and the second
defendant. The first defendant‟s name appeared in the heading of that contract.
[5] The plaintiff seeks a declaration that the contract entered into between the plaintiff
and the second defendant was in truth a contract between the plaintiff and the first
defendant. It seeks a repayment of over $10 million from the defendants on the
basis that the first defendant did not have a building licence and was thereby
precluded from receiving monetary consideration pursuant to s 42 of the QBSA Act.
It also seeks repayment of moneys paid to the second defendant pursuant to void
adjudications. In the alternative, the plaintiff pleads that if the contract was between
the plaintiff and the second defendant, the second defendant has been overpaid its
contractual entitlements by over $6 million.
[6] The pleadings are voluminous. They have been amended over the course of the
proceeding, which was commenced in 2009. Relevantly, for the purposes of the
present application, the plaintiff alleges:
(a) the first defendant was the contracting party;
(b) the first defendant, as the contracting party, was required to hold a licence
pursuant to the QBSA Act;
(c) the first defendant did not hold a licence pursuant to the QBSA Act at the
relevant time;
(d) accordingly, the only entitlement of the first or second defendant to receive
money from the plaintiff arose under s 42(4) of the QBSA Act.
-- 3 of 8 --
4
[7] The defendants allege that:
(a) the second defendant was the contracting party;
(b) the services provided by the construction manager under the contract was
not “building work” within the meaning of s 42 of the QBSA Act at the
relevant time;
(c) there was no licence of an appropriate class for the provision of services
under the contract by the construction manager at the relevant time;
(d) by reason of (c), s 42 does not apply to the activities of the construction
manager under the contract.
[8] The defendants estimate a hearing of the preliminary issues would take three to four
days. The plaintiff estimates a hearing of the preliminary issues would take five to
six weeks.
Rule 483
[9] Relevantly, r 483 of the UCPR provides:
“The Court may make an order for the decision by the court of a
question separately from another question, whether before, at, or
after the trial or continuation of the trial of the proceeding.”
[10] The rule is intended to provide for the determination of an issue or issues the
resolution of which is likely to lead to substantial savings and expense.1 Whether
an order is made is subject to the exercise of the discretion of the Court.2 In
exercising that discretion, a relevant consideration is whether it would be
convenient to determine first the issues raised, and, in particular, whether the
successful determination of the separate issues would:
(a) relieve the parties and the Court of the need to otherwise consider a
significant volume of documents;
(b) avoid the need for the Court at trial to consider expert evidence,
(c) avoid, or at the very least reduce, the necessity for a lengthy trial.3
[11] In Reading Australia Pty Ltd v Australian Mutual Provident Society & anor,4
Branson J said, in respect of a provision in the Federal Court Rules, which is
materially in identical terms to r 483:
“(a) …
(b) a question can be the subject of an order for a separate
decision under 0 29 r 2 even though a decision on such a
question will not determine any of the parties‟ rights
(Landsal Pty Ltd (in liq) v REI Building Society at FCR 425;
ALR 647);
(c) however, the judicial determination of a question under 0 29
r 2 must involve a conclusive or final decision based on
1 Evans Deakin Industries Ltd v Commonwealth [1983] 1 Qd R 40 at 45-46.
2 Body Corporate for Sun City Resort CTS v Sunland Constructions Pty Ltd [2010] QSC 463 at [19].
3 State of Queensland v Dale and Meyers Operations Pty Ltd [2010] QSC 361 at [19], [20].
4 (1999) 217 ALR 495 at [8].
-- 4 of 8 --
5
concrete and established or agreed facts for the purpose of
quelling a controversy between the parties (Bass v
Permanent Trustee Co Ltd (1999) 198 CLR 334; 161 ALR
399; [1999] HCA 9 at [45]);
(d) where the preliminary question is one of mixed fact and law,
it is necessary that the question can be precisely formulated
and that aft of the facts that are on any fairly arguable view
relevant to the determination of the question are
ascertainable either as facts assumed to be correct for the
purposes of the preliminary determination, or as agreed facts
or as facts to be judicially determined (Jacobson v Ross
[1995] 1 VR 337 at 341, referring to Nissan v Attorney-
General [1970] AC 179 at 242-3; [1969] 1 All ER 629 at
663-4 per Lord Pearson; Bass v Perpetual Trustee at [53]);
(e) care must be taken in utilising the procedure provided for in
0 29 r 1 to avoid the determination of issues not „ripe‟ for
separate and preliminary determination. An issue may not be
„ripe‟ for separate and preliminary determination in this
sense where it is simply one of two or more alternative ways
in which an applicant frames its case and determination of
the issue would leave significant other issues unresolved
(CBS Productions Pty Ltd v O’Neill (1985) 1 NSWLR 601
per Kirby P at 606);
(f) factors which tend to support the making of an order under
0 29 r 2 include that the separate determination of the
question may:
(i) contribute to the saving of time and cost by
substantially narrowing the issues for trial, or even
lead to disposal of the action; or
(ii) contribute to the settlement of the litigation (CBS
Productions Pty Ltd v O'Neill per Kirby P at 607);
(g) factors which tell against the making of an order under 0 29
r 2 include that the separate determination of the question
may:
(i) give rise to significant contested factual issues both
at the time of the hearing of the preliminary
question and at the time of trial (GMB Research &
Development Pty Ltd v Commonwealth [1997] FCA
934);
(ii) result in significant overlap between the evidence
adduced on the hearing of the separate question and
at trial – possibly involving the calling of the same
witnesses at both stages of the hearing of the
proceeding: (GMB Research & Development Pry
Ltd v The Commonwealth; Arnold v Attorney-
General (Vic) (unreported, Fed C of A, Sundberg J,
Nos VG629-37 of 1995, 8 September 1995,
-- 5 of 8 --
6
BC9502745). This factor will be of particular
significance if the Court may be required to form a
view as to the credibility of witnesses who may
give evidence at both stages of the hearing of the
proceeding; or
(iii) prolong rather than shorten the litigation (GMB
Research & Development Pty Ltd v
Commonwealth).”
These factors have been identified as being relevant in considering the operation of
r 483.5 Ultimately, the issue for the Court, in determining whether to exercise the
discretion and make an order for separate determination, is whether it is “just and
convenient” for the order to be made.6
The application
First question
[12] There is no doubt that a material fact in issue is the identity of the party contracting
as construction manager. The plaintiff contends that whilst the contract was
executed by a director of the second defendant, the first defendant was specifically
named in the contract and the second defendant executed the contract as agent for
the first defendant. The defendants contend the second defendant made the offer to
contract and was intended by the parties to be the contracting party.
[13] The defendants submit that the prior determination of this question is “ripe for
determination”. Further, it is a discrete issue and its determination will impact on
the issues to be determined in respect of s 42 of the QBSA Act. The plaintiff
submits that the question of who was the contracting party is not “ripe for
determination”. It will require a substantial hearing itself as it requires a
determination of the objective intention of the parties in all the circumstances.7 Its
early resolution will not resolve the proceedings, or save any meaningful time or
cost. Instead, it may lead to an increase in time and costs.
[14] In support of the contention that the issue of the correct identity of the contracting
party cannot be resolved by a confined body of evidence, the plaintiff asserts that
the defendants‟ own pleading demonstrates that resolution of the issue will require
consideration of the extrinsic events pleaded by the defendants, including oral and
written communications, an alleged previous history of dealings, and events after
the contract was signed. It will also require a consideration of numerous
discussions pleaded by the plaintiff by way of reply, and consideration of
documentation.
[15] Whilst courts are now more liberal in their consideration of whether to order the
separate determination of preliminary questions,8 caution must be exercised before
making such an order having regard to the risk of being too readily tempted by the
5 Body Corporate for Sun City Resort CTS v Sunland Constructions Pty Ltd [2010] QSC 463 per
Applegarth J at [19].
6 Arnold v Attorney-General (Vic) (unreported, Fed C of A, Sundberg J, Nos VG629-37 of 1995, 8
September 1995, BC9502745), followed in Reading Australia Pty Ltd v Australian Mutual Provident
Society (supra) at [9].
7 Pico Holdings Inc v Wave Vistas Pty Ltd [2003] QCA 204 at [3]-[6], [44], [51] and [63].
8 See Re Multiplex Constructions Pty Ltd [1999] 1 Qd R 287; Heery v Criminal Justice Commission
[2001] 2 Qd R 610.
-- 6 of 8 --
7
promise of a saving of time and costs whereas the outcome results in time wasting
and an increase in costs whilst also fragmenting and delaying the outcome.9
[16] Having considered the competing claims, and the detailed pleadings in respect of
this issue, I am not satisfied this question is an appropriate question for a separate
determination prior to the hearing of the proceeding. The question is a central issue,
and the subject of extensive pleading. Its resolution will require consideration of
voluminous evidence and documentation. Its determination is likely to take much
more than three to four days. It will involve extensive preparation. Its
determination will not obviate the need for an extensive trial in any event.
[17] I decline, in the exercise of my discretion, to order that the first question be
determined separately.
Second and third questions
[18] The defendants submit the second and third questions involve matters of
construction in respect of a legislative provision which has itself been the subject of
consideration by this Court.10 Further, their determination as separate questions will
result in a considerable saving of time and money in respect of the determination of
the remaining issues in dispute in the proceeding.
[19] In support of that contention, the defendants submit that depending on the outcome
of those separate determinations, the defendants will not be obliged to lead evidence
to prove an entitlement under s 42(4) of the QBSA Act to retain any of the monies
paid by the plaintiff. This will result in a substantial reduction in the length of the
trial and the number of expert witnesses required to be called at any trial. It will
also reduce the number of expert witnesses required to provide reports.
[20] The defendants further submit that the determination of those questions will impact
on which party has the burden of proving an entitlement to amounts in dispute, and
that the determination of who has the burden of proof will significantly assist in the
preparation of the evidence for the proceeding itself, and perhaps, in its resolution
without a trial.
[21] The plaintiffs submit that a preliminary determination of the second and third
questions would not resolve the proceedings, would likely require a duplication of
evidence, and will necessitate an assessment of the credibility of witnesses on more
than one occasion. It would also not save any meaningful time or expense.
[22] In support of this contention, the plaintiff submits that the question of whether the
“services” were “building work” within the meaning of the legislation, cannot be
resolved merely by a consideration of the contract itself. Its determination must be
considered in context, and by having regard to the services set out in part B of the
contract. The plaintiff submits a consideration of part B indicates that the words
contained therein are ambiguous and will require the Court to consider evidence of
the surrounding circumstances in order to construe the words in part B. This will
result in a substantial hearing, and the likely duplication of evidence at a later
hearing with the potential for inconsistent findings as to credit as well as a
9 Sherlex Pty Ltd v Thornton [2003] QCA 461 at [16]-[20]; Lee v Arisaig Pty Ltd & Ors [2005] QSC
265 at [12], [21]-[22]; Watpac Civil Infrastructure Pty Ltd v Komatsu Pty Ltd [2009] QSC 281 at [4]-
[8].
10 See Puerto Galera Pty Ltd v J M Kelly (Project Builders) Pty Ltd [2008] QSC 356. See also McNab
Constructions Pty Ltd v Queensland Building Services Authority [2010] QCA 380.
-- 7 of 8 --
8
lengthening of the trial process. The plaintiff submits that the construction of an
ambiguous, or potentially ambiguous, contract is not appropriate for determination
as a preliminary issue in the absence of evidence as to surrounding circumstances.11
[23] Further, the plaintiff submits that even if the second and third questions were
ordered to be determined separately, and prior to the trial itself, their determination
would not resolve the central issue in the proceedings. The separate questions are
directed to whether the services the first defendant agreed to perform pursuant to the
contract required a licence, and whether there was a licence for those services that
were agreed. This would not resolve the question of who actually performed the
work of the construction manager, whether the work actually performed by the
construction manager required a licence, and whether there was an available licence
for the work actually performed. The defendants do not merely dispute that the
work required under the contract was building work within the legislative provision.
They also dispute that the first defendant performed either building work or the
services required under the contract12 and separately plead the second defendant
performed various kinds of work described as “trade works”13 and procured various
items for use by the plaintiff or trade contractors. The defendants plead that these
kinds of work were outside the scope of services under the contract or were, in the
alternative, a variation to it. Evidence will be required to identify the trade works
and items procured by the defendants.
[24] Whilst there is merit in the defendants‟ submission that a separate determination of
the second and third questions could be useful in resolving which party has the onus
of proof, I am not satisfied that a separate determination of those questions would
result in any significant saving of time or expense in respect of the ultimate hearing
of the proceeding. The defendants contend that the second and third questions
could be determined in one day. Having regard to the pleaded issues, this is likely
to be an under estimate. In any event, it is apparent from a consideration of the
issues that even if that be so, there would remain substantial issues for
determination. Accordingly, a separate determination of these questions will not
obviate the need for a lengthy trial. It also will not save any significant time or
expense. Indeed, there is a significant risk that the determination of the summary
issue would be delayed by an appeal from the determination of this issue.
[25] I decline, in the exercise of my discretion, to order that the second and third
questions be determined separately.
Orders
[26] The application is dismissed. I shall hear the parties as to costs.
11 Sherlex Pty Ltd v Thornton & Ors [2003] QCA 461 at [16]-[20].
12 See para 22, sub (a) of the defence.
13 See para 16A of the defence.
-- 8 of 8 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2011/212