Ceresola TLS AG v Thiess Pty Ltd & John Holland Pty Ltd [2011] QSC 115
1-1
SUPREME COURT OF QUEENSLAND
CITATION: Ceresola TLS AG v Thiess Pty Ltd & John Holland Pty Ltd
[2011] QSC 115
PARTIES: CERESOLA TLS AG
(applicant)
v
THIESS PTY LTD
(first respondent)
and
JOHN HOLLAND PTY LTD
(second respondent)
FILE NO/S: 3181 of 2011
DIVISION: Trial Division
PROCEEDING: Application
ORIGINATING
COURT: Supreme Court of Queensland
DELIVERED EX
TEMPORE ON:
14 April 2011
DELIVERED AT: Brisbane
HEARING DATE: 14 April 2011
JUDGE: Daubney J
ORDER: 1. The application is dismissed
2. The applicant will pay the respondents’ costs of
and incidental the application.
CATCHWORDS: CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – THE CONTRACT -
CONSTRUCTION OF PARTICULAR CONTRACTS AND
IMPLIED CONDITIONS – SECURITY AND RETENTION
FUNDS – where the applicant and the respondent entered
into a written agreement – where the contract provides for a
bank guarantee in favour of the respondent – where the
respondent contends it is entitled to liquidated damages from
the applicant and therefore intends to call on the bank
guarantee – where the applicant seeks an interim injunction to
restrain the respondent from calling on the bank guarantee.
Trade Practices Act 1974 (Cth)
Clough Engineering Limited v Oil and Natural Gas
Corporation Limited (2008) 249 ALR 458, considered
Fletcher Construction Australia Limited v Varnsdorf Pty Ltd
[1998] 3 VR 812, considered
-- 1 of 20 --
1-2 ORDER
1
10
20
30
40
50
60
Reed Construction Services v Kheng Seng (Australia) Pty Ltd
(1999) 15 BCL 158, cited
Wood Hall Limited v Pipeline Authority (1979) 141 CLR 443,
cited
COUNSEL: A P J Collins for the applicant
G A Thompson SC with D B Keane for the respondents
SOLICITORS: Mills Oakley Lawyers for the applicant
Thiess John Holland for the respondents
-- 2 of 20 --
1-3 ORDER
1
10
20
30
40
50
60
HIS HONOUR: On 3 April, 2009, the applicant and the
respondents (trading as “Thiess John Holland”) entered into a
written agreement under which the applicant agreed to provide
eight tunnel forming machines for use in a construction
project known as the Airport Link Project. For convenience, I
will refer simply to Thiess John Holland as the respondent.
Pursuant to that contract, in terms to which I shall refer in
some further detail shortly, the applicant procured provision
of a bank guarantee in favour of the respondent. The amount
presently secured under that bank guarantee is some
EUR 360,000.
The respondent has contended that it is entitled to liquidated
damages from the applicant as a consequence of late delivery
of the machinery under the agreement. The applicant contests
that the respondent has any such entitlement to claim
liquidated damages.
The respondent, however, has indicated its intention to call
on the bank guarantee and obtain payment of the approximately
EUR 360,000 thereunder, which it will apply to its claimed
liquidated damages.
The applicant now applies for an interim injunction to
restrain the respondent from calling on that bank guarantee.
The applicant seeks this injunction presently only on an
interim basis for a couple of weeks to enable material to be
-- 3 of 20 --
1-4 ORDER
1
10
20
30
40
50
60
put together for the purposes of a full interlocutory hearing
in respect of ongoing injunctive relief pending the
determination of the applicant's claim that the respondent is
not entitled to the liquidated damages to which it has
asserted a right.
The applicant has pointed to a number of issues which it says
give rise to good arguments as to why the respondent is not
entitled to the liquidated damages that it claims. It points,
for example, to clause 15.4 of the agreement, and contends
that the pre-conditions for the respondent to claim liquidated
damages in accordance with that clause have not been met.
A further argument mounted by the applicant is, in effect, in
reliance on the maxim “ex turpi causa non oritur actio", by
which the applicant contends that if there was any delay in
the delivery of this machinery under the agreement, such delay
was caused by fault or default on the part of the respondent,
and that in those circumstances the respondent cannot have the
benefit of a contractual provision which confers on it a
pecuniary benefit arising from its own default.
The applicant also argues that the calculation of the amount
of liquidated damages is incorrect and not in accordance with
the relevant contractual provisions. In particular, it points
to the calculation of liquidated damages in respect of a
number of items where the respondent has apparently taken
variations into account, but, so the applicant says,
-- 4 of 20 --
1-5 ORDER
1
10
20
30
40
50
60
contractual variations are not to be reckoned as part of the
calculation.
Further arguments advanced by the applicant go to the
construction of particular clauses of the agreement, and
amount to contentions that the claim for liquidated damages is
not available on a proper interpretation of the contract
between the parties.
I am prepared to accept for today's purposes that the matters
pointed to by the applicant are, if I may adopt somewhat old
fashioned language in this regard, triable issues or serious
questions to be tried with respect to the entitlement of the
respondent to claim liquidated damages for late delivery, and
with respect to the proper calculation of any such liquidated
damages.
The matter, however, does not rest there. This is not an
application to restrain the respondent from making a claim for
liquidated damages, if such a claim were able to be
maintained. This is an application to restrain the respondent
from calling on the unconditional bank guarantee that was
given as part of, and pursuant to, the contractual
arrangements entered into between the parties.
In that regard, the applicant's contention, and indeed the
applicant's only contention, is founded on clause 19.5 of the
contract, to which I will refer in some detail shortly.
-- 5 of 20 --
1-6 ORDER
1
10
20
30
40
50
60
The applicant's submission is that under clause 19.5 of the
contract the respondent's entitlement to make claim on the
security or bank guarantee is contingent on a number of
matters, the first of which being that there be monies due to
the applicant, which must then be utilised by way of deduction
and monies in priority to any call on the bank guarantee. It
was submitted that the call on the bank guarantee can and must
be made only after it is established that there are
insufficient monies to meet the claim, and then recourse can
be had to the bank guarantee for payment of any balance due.
The submission was that clause 19.5 is the only operative
clause in the contract by which effect or purpose is given to
the bank guarantee and that in the present case there is at
least a real issue as to whether the respondent has an
entitlement to make a claim on the bank guarantee, in
accordance with the provisions of clause 19.5.
The applicant says that, in view of that issue, the balance of
convenience favours the grant of an injunction on an interim
basis. It can be shortly stated that the applicant points to
public commercial embarrassment and possible detriment which
it might suffer if the bank guarantee is called on and it
becomes public knowledge that the bank guarantee has been
called on, as opposed to there being no prejudice that can be
suffered by the respondent if the injunction issues on an
interim basis and the status quo is preserved for a couple of
weeks.
-- 6 of 20 --
1-7
1
10
20
30
40
50
60
Counsel for the respondent, however, pointed to the
unconditional nature of the bank guarantee that has been given
and submitted that there is no such contractual restriction as
was contended for by the applicant such as gives rise to any
entitlement on the part of the applicant to seek injunctive
relief, whether on an interim or an interlocutory basis.
In order to understand the arguments advanced, it will be
necessary to refer to the relevant terms of the contract. The
starting point for present purposes is clause 23 of the
general conditions of the contract. Clause 23 provided:
Performance Security
Provision of Performance Security
23.1 The Supplier shall provide within 14 days of the date of
the execution of this Agreement, Performance Security to
TJH.
Failure to Provide Performance Security
23.2 Failure to provide Performance Security strictly in
accordance with Clause 23.1 shall be a substantial breach
of this Agreement within the meaning of Clauses 28.8 and
28.9.
Reduction of Performance Security
23.3 Upon issue of a notice referred to in Clause 18.1, TJH’s
entitlement to Performance Security shall be reduced to
-- 7 of 20 --
1-8
1
10
20
30
40
50
60
the percentage thereof stated in Schedule 2 or, if no
percentage is stated, by one-half.
Release of Performance Security
23.4 TJH shall release to the Supplier any remaining
Performance Security held in accordance with Clause 21.5.
"Performance security" was defined in clause 1.1 and Schedule
1 of the General Conditions of Agreement to mean: “1 or more
banker’s undertakings from an Australian bank in the form set
out in Annexure “A”, or other unconditional securities
acceptable to TJH and capable of being converted into money
through a bank in Brisbane, to secure the Supplier’s due and
property performance of this Agreement (including any
obligation under clause 24) in the amount(s) set out in
Schedule 2.
The contractual obligations relating to delivery appear in
clause 15. Clause 15.1 required that "[n]ot earlier than the
Earliest Date for Acceptance or later than the Date for
Delivery, the Supplier shall deliver the Plant to the Place
for Delivery."
I pause to note that one of the issues between the parties is
whether a date for delivery or dates for delivery was
nominated under the contract or subsequently reached as
between the parties. As with the other issues to which I
referred earlier, I am prepared to accept for today's purposes
that there are serious questions to be investigated in that
-- 8 of 20 --
1-9
1
10
20
30
40
50
60
regard but, again, the fact that those serious questions exist
is not determinative for present purposes.
In any event, clause 15.4 provides, in effect, that if the
applicant failed to deliver the plant to the requisite place
by the due date for delivery, then the applicant was required
to pay the respondent "by way of liquidated damages the amount
per day stated in Schedule 2 for every day after but not
including the Date of Delivery up to and including the Date of
Delivery or the date that this Agreement is terminated,
whichever occurs first". That is the provision pursuant to
which the respondent has made claim against the applicant for
some €423,000 by way of liquidated damages.
Clause 19 of the agreement covers the contractual provisions
relating to payment claims, payment certificates and time for
payment and is in the following terms:
Payment
Payment Claims, Payment Certificates and Time for Payment
19.1 Upon the achievement of a Milestone, the Supplier may
deliver to TJH a claim for payment in respect of the
achievement of that Milestone, any variations implemented
in accordance with Clause 14 and any other amounts due to
the Supplier by TJH under this Agreement, together with
evidence in support of the total amount claimed for
payment by the Supplier and such other information as TJH
may reasonably require.
-- 9 of 20 --
1-10
1
10
20
30
40
50
60
19.2 Subject to Clause 19.3, TJH shall within the period
stated in Schedule 2, or if no period is stated in
Schedule 2 then within 28 days after receipt by TJH of
the Supplier’s claim for payment, pay to the Supplier the
amount it determines to be due to the Supplier in respect
of the claim for payment.
19.3 If property in or title to the Plant will not pass to TJH
immediately upon the payment of an amount to the Supplier
under Clause 192, it is a condition precedent to the
Supplier becoming entitled under Clause 192 to such
payment that the Supplier has first provided to TJH an
Advance Payment Security for an amount equal to the
amount claimed by the Supplier in its claim for payment.
19.4 Payment of moneys shall not be evidence of the value or
suitability of the Plant or an admission of liability but
shall be a payment on account only.
Set Offs by TJH
19.5 TJH may deduct from moneys otherwise due to the Supplier
any moneys due from the Supplier to TJH and if those
moneys are insufficient, TJH may have recourse to any
Performance Security or Advance Payment Security held by
TJH to obtain moneys due form the Supplier to TJH.
It is this last clause, 19.5, on which the applicant places
particular reliance for today's purposes. The applicant
contends that this is the only clause in the agreement in
which specific provision is made for the respondent to have
contractual recourse to the performance security.
-- 10 of 20 --
1-11
1
10
20
30
40
50
60
In the course of argument, counsel referred me to a number of
other provisions of the agreement and the schedules and the
annexures to the agreement, particularly with respect to the
disputes between the parties concerning the existence or
non-existence of dates for delivery. In view of my acceptance
for today's purposes of a genuine dispute on those issues
between the parties, it is unnecessary for me to recite those
terms at length. I should, however, record that the contract
sets out in annexure A the form of unconditional banker's
undertaking referred to in the definition of "performance
security" in clause 1.1.
The form of unconditional banker's undertaking provided for in
annexure A was as follows:
“In consideration of Thiess Pty Ltd and John Holland Pty Ltd
trading as Thiess John Holland ABN 17 438 477 668 of 1 Gympie
Road, Kedron, Queensland, 4101 accepting this undertaking in
satisfaction of the Thiess John Holland’s requirement for
[INSERT] (“Supplier”) to provide Thiess John Holland with
security for performance in relation to Agreement [insert
contract details] (“Agreement”) the [INSERT] bank of [INSERT]
(“Bank”) undertakes irrevocably and unconditionally to pay to
Thiess John Holland on demand in writing any sum or sums which
may from time to time be demanded by Thiess John Holland to an
amount now exceeding [INSERT] ($[INSERT]) (sum) in the
aggregate.
Such payment or payments will be made by the Bank to Thiess
John Holland without reference by the Bank to the Supplier and
notwithstanding any notice to the Bank by the Supplier not to
-- 11 of 20 --
1-12
1
10
20
30
40
50
60
pay to Thiess John Holland any moneys hereunder and
irrespective of the performance or non-performance by the
Supplier of the terms of the Agreement.
The Banks’ liability hereunder will not be impaired or
discharged by any alterations which may be made in the terms
of the Agreement or by any extension of time or other
forbearance on this part of either Thiess John Holland or the
Supplier to the other.
This undertaking will continue in force either until
notification in writing has been received by the Bank from
Thiess John Holland that this undertaking is no longer
required or until payment to Thiess John Holland by the Bank
of the whole of the sum or the balance thereof remaining after
any part payment or payments or until this Guarantee is
returned to the Bank.
Notwithstanding anything contained herein the Bank reserves
the right to terminate this undertaking at any time upon
payment to Thiess John Holland of the sum or the balance
thereof remaining after any part payment or payments or such
lesser amount as Thiess John Holland may require.
On expiry or when no longer required please return this
document for cancellation to the Manager”. (emphasis added)
For reasons that I will elaborate on shortly, counsel for the
respondents emphasised the passage in the form of undertaking
that I have highlighted, noting that the parties agreed that
the form of undertaking to be given by the bank was
unconditional in terms and, in particular, required the
bank to make payment "irrespective of the performance or
-- 12 of 20 --
1-13
1
10
20
30
40
50
60
non-performance by the supplier of the terms of the
agreement".
The preliminary question raised by the respondent is to the
effect that the applicant is simply not entitled to seek an
injunction to restrain the respondent from calling on that
unconditional bank guarantee.
The principles governing the construction and application of
bank guarantees have been considered in a number of cases of
high authority over the last 30 years or so, commencing with
what has been described as the seminal judgment of the High
Court in Wood Hall Limited v. Pipeline Authority (1979) 141
CLR 443.
In the relatively recent judgment of the Full Federal Court in
Clough Engineering Limited v. Oil and Natural Gas Corporation
Limited (2008) 249 ALR 458, French, Jacobson and Graham JJ in
a joint judgment set out a convenient summary of the
constructional principles relating to the performance of bank
guarantees. In the course of that judgment, their Honours
drew particularly on the judgment of the Victorian Court of
Appeal in Fletcher Construction Australia Limited v. Varnsdorf
Pty Ltd [1998] 3 VR 812.
On the basis of those authorities, it is sufficient for
present purposes to note that the general rule is that a Court
will not enjoin the issuer of a performance guarantee from
performing its unconditional obligation to make payment. A
-- 13 of 20 --
1-14
1
10
20
30
40
50
60
number of exceptions to that general rule have been
identified. They are identified in Clough Engineering at [77]
as:
(1) An injunction will issue to prevent a party in whose
favour the performance guarantee has been given from acting
fraudulently.
(2) An injunction will issue to prevent a party in whose
favour the performance guarantee has been given from acting
unconscionably in contravention of the Trade Practices Act
1974 (Cth).
(3) While the Court will not restrain the issuer of a
performance guarantee from acting on an unqualified promise to
pay if the party in whose favour the guarantee has been given
has made a contract promising not to call upon the bond,
breach of that contractual promise may be enjoined on normal
principles relating to the enforcement by injunction of
negative stipulations in contracts. Their Honours drew in
that regard from the judgment of Austin J in Reed Construction
Services v Kheng Seng (Australia) Pty Ltd (1999) 15 BCL 158 at
164.
Their Honours in the Full Federal Court said in relation to
that last mentioned principle that: “it may be preferable not
to describe this as an exception but rather as an over riding
rule because it emphasises that the 'primary focus' will
always be the proper construction of the contract".
-- 14 of 20 --
1-15
1
10
20
30
40
50
60
Their Honours in Clough Engineering went further to refer to
the judgment of the Full Court in Victoria in the Fletcher
Construction case, noting particularly the purposes identified
in the Fletcher Construction case for which a beneficiary of a
bank guarantee may have stipulated for same in a contract.
In the Fletcher Construction case, Callaway JA identified
those reason in brief at 826: "One is to provide security. If
[the beneficiary] has a valid claim and there are difficulties
about recovering from the party in default, it has recourse
against the bank. The second reason, which is additional to
the first, is to allocate the risk as to who shall be out of
pocket pending resolution of the dispute. The beneficiary is
then able to call upon the guarantee even if it turns out, in
the end, that the other party was not in default".
The exercise then becomes one of looking at the contract in
question to determine whether the provision of the bank
guarantee was one merely for provision of security or was an
exercise as between the parties in risk allocation pending
resolution of the dispute.
The Full Federal Court in Clough Engineering noted the
importance of examining a contract carefully for the purposes
of undertaking such an exercise. At [80] their Honours
said,(citing Fletcher Construction at 827): "Thus, subject to
the exceptions of fraud and unconscionability, the beneficiary
of a performance guarantee granted in its favour as a risk
-- 15 of 20 --
1-16
1
10
20
30
40
50
60
allocation device, will be entitled to call upon the guarantee
even if it turns out, ultimately, that the other party was not
in default".
Their Honours followed that statement of principle immediately
with an observation that: “in determining whether the
underlying contract confers an unfettered right to call upon
the performance guarantee, the performance of such instruments
in the construction industry, both nationally and
internationally, is a factor which bears upon the question of
construction of the contract”.
Their Honours went on, however, to note that whilst the
commercial background informs the construction of a contract,
the Court ought not too readily favour a construction which is
inconsistent with an agreed allocation of risk as to who is to
be out of pocket pending resolution of the dispute about
breach.
Their Honours said at [83]: "It follows that clear words will
be required to support a construction which inhibits a
beneficiary from calling on a performance guarantee where a
breach is alleged in good faith, that is, non-fraudulently".
Their Honours said further at [85] that: “The question of
construction as to whether the underlying contract contains a
qualification on the right to call upon the security must be
determined in light of the contract and the form of the
performance guarantee as contained in the contract”. They
-- 16 of 20 --
1-17
1
10
20
30
40
50
60
said that: “This accords with the basic principle of
construction that the terms of an instrument must be read as a
whole”.
Turning then to the contract with which we are concerned in
the present case, the immediate question is whether the
provision of the bank guarantee was an exercise in allocating
risk. It also involves a consideration as to whether, as is
contended by the applicant, the only work to be done by the
undertaking is pursuant to clause 19.5.
I have already referred to clause 23.1 which is an express
requirement on the part of the applicant to provide the
performance security. The requirement for it to provide the
security was not hedged about in any way. It was an absolute
condition and, indeed, by clause 23.2, was made a fundamental
condition of the contract between the parties.
There was also no issue about the form of the bank guarantee
which was to be provided. It was agreed by the parties
expressly to be one which was unconditional in terms and,
again, not hedged about in any way by conditions or
pre-conditions. The terms of the unconditional banker's
undertaking contained in annexure A have been set out above
and really speak for themselves.
I do not accept the applicant's submission that the only work
to be done by the performance guarantee under the contact is
that provided for by clause 19.5. Clause 19.5 represents a
-- 17 of 20 --
1-18
1
10
20
30
40
50
60
particular circumstance within which the parties have agreed
that recourse might be had by the respondent to the bank
guarantee but it is by no means the only circumstance within
which the bank guarantee has efficacy under the terms of the
agreement.
The performance security which the applicant was required to
put up by the terms of clause 23 of the agreement was one
which, according to the definition of "performance security",
was "to secure [the applicant's] due and proper performance of
this Agreement". That had application across the agreement
generally and, indeed, the definition of performance security
gives a further example of the application or availability of
the performance guarantee, namely, by way of securing
obligations under clause 24 of the agreement.
Clause 24 of the agreement, the terms of which I will not set
out in full here, effectively contained a put option by which
the respondent could compel the applicant to buy back the
plant on specified terms and conditions and it specified
prices nominated. The performance security was expressly
contemplated to extend to securing the performance by the
applicant of its obligations under that buy-back scenario.
Moreover, the entitlement of the respondent to make claim for
liquidated damages under clause 15 is not linked to or
necessarily interconnected with the payment regime and setoff
regime set out under clause 19 of the agreement. The
-- 18 of 20 --
1-19
1
10
20
30
40
50
60
respondent's claim for liquidated damages is, in effect,
freestanding and is able to be pursued by it as such.
It seems to me, therefore, that it cannot be said that the
only work available to be performed by the bank undertaking is
for the purposes of acting, in effect, as backup security for
moneys which may be claimed under setoff by the respondent
pursuant to clause 19.5.
Having reviewed the contract, it seems to be much more likely
that the provision of the performance security constituted an
exercise in risk allocation under the terms of the contract
and, in particular, I am fortified in that view by having
regard to the unconditional nature of the bank undertaking in
the unconditional form agreed to by the parties as set out in
annexure A.
There is, so far as I can see, no allegation that the
respondent proposes to make its claim on the bank guarantee in
circumstances infected by either fraud or unconscionability.
I should make one concluding observation and that is this: I
have already referred to the observation by the Full Court in
Clough Engineering that clear words will be required to
support a construction which inhibits the respondent in this
case from calling on the performance security. For the
reasons that I have given, it seems to me that clause 19.5
does not have the general application which is contended for
by the applicant and, in any case, does not constitute clear
-- 19 of 20 --
1-20
1
10
20
30
40
50
60
words which would inhibit the respondent from making claim on
the unconditional bank guarantee.
In the absence of any operative fraud or unconscionability,
therefore, it seems to me that there is no reason on a proper
construction of the contract why the respondent ought be
deprived of the opportunity to call on the unconditional bank
guarantee of which it has the benefit.
In view of those findings, therefore, there is no proper basis
for the grant of the injunction, even on an interim basis, and
the application is therefore dismissed.
...
HIS HONOUR: The applicant will pay the respondent's costs of
and incidental to the application.
-----
-- 20 of 20 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2011/115