Combined Building Services Pty Ltd v Springall and Anor [2011] QCAT 674
CITATION: Combined Building Services Pty Ltd v Springall
and Anor [2011] QCAT 674
PARTIES: Combined Building Services Pty Ltd
(Applicant)
v
Mr Kenneth Alexander Springall
Ms Janet Gwen Cornell
(Respondents)
APPLICATION NUMBER: BDL316-10
MATTER TYPE: Building matters
HEARING DATE: 9-10 June 2011 and 17-18 October 2011
HEARD AT: Townsville
DECISION OF: Ms Joanne Browne, Member
DELIVERED ON: 23 December 2011
DELIVERED AT: Brisbane
ORDERS MADE: 1. The Respondents, Mr Kenneth Alexander
Springall and Ms Janet Gwen Cornell pay the
amount of $15,891.67 to the Applicant,
Combined Building Services Pty Ltd by
4.00pm on 20 January 2012.
CATCHWORDS: Whether works had reached practical completion
– breach of contract – calculation of money
owing under the contract
Queensland Building Services Authority Act
1991, s 77
Bellgrove v Eldridge (1954) 90 CLR 613 cited
Wheeler & Anor v Ecroplot Pty Ltd [2010]
NSWCA 61 cited
APPEARANCES and REPRESENTATION (if any):
APPLICANT: Mr Kerry Anger representing Combined Building
Services Pty Ltd
RESPONDENT: Ms Janet Cornell representing the respondents
-- 1 of 16 --
2
REASONS FOR DECISION
Introduction
[1] Mr Springall and Ms Cornell (the respondents) engaged Combined Building
Services Pty Ltd to build a pergola and complete some renovation work to
their house at 11 Michelle Court, Alice River, Queensland.
[2] Mr Anger is a Director of Combined Building Services Pty Ltd and has been
a builder for some 22 years. Mr Anger was responsible for the contracted
building work at the respondents’ house.
[3] A Master Builders Residential Building Contract was signed by the parties
on 25 June 2009 and Combined Building Services Pty Ltd were contracted
to undertake the following works which commenced on or about 18 August
20091:
Close in garage and make 2 rooms
Close in patio
Add new room with bathroom and kitchenette
[4] During completion of the works a dispute arose between the parties. The
applicant claims that the final progress claim was not paid by the
respondents, practical completion having been reached on 22 March 2010.
The respondents argue that practical completion (as required under clause
17.1 of the contract) has not been reached and that the applicant is in
breach of the contract.
[5] The total contract amount for completion of the works was $147,197.00.
The respondents have made various payments to Mr Anger which total the
amount of $120,701.54.
[6] Mr Anger filed an application in QCAT on 1 October 2010 seeking an order
for payment of the final progress claim. The amount now claimed by the
applicant as the final progress claim (which is not disputed) is $23,534.52.
[7] The respondents filed a response and counter-application on 26 October
2010 and seek an order for relief of payment of the final progress claim and
that the applicant pay the amount of $32,519.48 as follows:
1) Liquidated damages (from 16/02/10 to 18/10/11) $30,450.00
2) Damages for breach of contract- $25,604.00
-pergola reconstruction $17,854.00
-replacement of the fascia $6,000.00
-cleaning $1,750.00
The hearing
1 Exhibit 1, attachment “ZF”.
-- 2 of 16 --
3
[8] The hearing was listed for 2 days commencing on 9 June 2011. On the
second day of the hearing (on 10 June 2011) it became apparent that the
hearing time allocated was inadequate and the proceedings (by consent)
were relisted for a further 2-day hearing (on a date to be advised by the
Tribunal). In an attempt to resolve the matter without a further delay, the
proceeding proceeded (with each party’s consent) to a compulsory
conference for the remainder of the day (on 10 June 2011). Unfortunately
the matter did not resolve (on 10 June 2011) and the matter proceeded to
hearing (part-heard) on 17 and 18 October 2011. The parties did, however,
make concessions during the hearing in relation to some of the issues in
dispute, in particular the amount claimed by the applicant for the ceramic
tiles (prime cost item) and variations to the contract (for tiling and the
bathroom). These items are relevant to the amount of the final progress
claim which the applicant alleges is owing under the contract.
[9] Mr Anger, Mr Springall and Ms Cornell gave sworn evidence and were
cross-examined at the hearing. Documents were tendered at the hearing
including photographs of the house taken during completion of the building
work. Written submissions were also filed by both parties.
[10] Mr Anger relies on his own affidavits (with attachments) and the affidavits of
Mr Sean Leslie Westwood (employee) and Mr Anthony Poole (Painter). Mr
Leslie and Mr Poole were not required for cross-examination and their
affidavits were tendered by Mr Anger without objection.
[11] Ms Cornell relies on a joint statement of the respondents (with attachments)
and the affidavits of Mr Anthony Jacobs (witness) and Mr Bruce Dalton
(witness). Mr Jacobs and Mr Dalton were not required for cross-
examination and their affidavits were tendered by Ms Cornell without
objection.
[12] Some preliminary issues were raised by Ms Cornell at the commencement
of the hearing in relation to the production of documents (by the applicant)
as per the Direction of the Tribunal dated 9 March 2011 in response to the
respondents’ application for miscellaneous matters filed 3 December 2010.
Mr Anger referred the respondents to the Further and Better Particulars
dated 16 March 2011 (in response) and stated (during oral submissions)
that there was no defects list, as the parties could not agree to a list of
defects. In relation to the certificate of completion, Mr Anger tendered at the
hearing a Form 15 (compliance certificate) dated 30 April 2009 together with
amended plans (Exhibit 5). Ms Cornell on day three of the hearing tendered
(during evidence) a Form 61 (non-compliance notice) dated 26 March 2010
(Exhibit 16) which she states was obtained by her from Mr Ian Mills
(certifier).
The issues to be determined
[13] For the purposes of section 77 of the Queensland Building Services
Authority Act 1991 the Tribunal is satisfied that this is a “building dispute”
which may be determined under the Queensland Civil and Administrative
Tribunal Act 2009 (“the QCAT Act”).
-- 3 of 16 --
4
[14] The issues to be determined by the Tribunal are:
1) Whether the final progress claim is due and owing by the respondents
– was cleaning of the works completed and did the respondents take
early possession of the works?
2) Whether the applicant is in breach of the contract (regarding the
pergola and fascia)?
Entitlement to final progress claim (money owing to Mr Anger)
[15] Mr Anger argues that the works were completed by the applicant and
practical completion was reached on 22 March 2010. Mr Anger claims that
on 9 June 2010 he delivered to the respondents a final progress claim for
the Practical Completion Stage claiming an amount of $27,280.56 which
remains outstanding (adjusted at the hearing to an amount of $23,534.52).2
[16] Mr Anger contends that notwithstanding practical completion being reached
(as alleged) the respondents took possession of the works in late January
2010 by occupying the two front rooms of the renovation without first
obtaining the applicant’s consent. Mr Anger contends that under clause
17.9 of the contract if the owner takes occupancy then the works are
deemed to have reached practical completion under the terms of the
contract.
[17] The respondents argue (in written submissions) that the works never
reached practical completion on the basis that:
1) the applicant failed to make a final inspection, provide a defects list and
a certificate of completion as required under clause 17.1 of the
contract;
2) cleaning of the works was not completed by the applicant so as to
identify all defects in the works prior to a final inspection;
3) the applicant is in breach of the contract – the pergola is not
constructed in accordance with the approved plans (the contract) and
the fascia does not “match existing”.
[18] For the purposes of clause 17.1 of the contract, the respondents (in written
submissions) submit that only the contractual certificate (providing a date
and time for a final inspection) and not the compliance certificate
(certification by a registered certifier that the works comply with the certified
plans) is relevant.3
[19] Mr Anger claims in written submissions that despite the respondents taking
early possession of the works he still (on behalf of the applicant) made an
effort to fulfil his contractual obligations by nominating a date (30 March
2010) to inspect the works and complete a list of defects. Mr Anger, in his
statement and during oral submissions refers to various emails exchanged
between the parties, in particular an email dated 22 March 2010 to Mr
Springall which states:
2 See Exhibit 1, attachment “J”, Tax Invoice dated 9 June 2010 (final progress claim).
3 Amended written submissions dated 23 March 2011, [8].
-- 4 of 16 --
5
…I have booked a cleaner in for Wednesday this week to clean and after that
we should be at practical completion. I will then do a list of any defects and I
would ask you to do the same on the completion of all cleaning please…4
[20] The practical completion stage is defined under the contract (Part 1
Definitions) as:
means that stage of the works when the works are completed in accordance
with the contract and all relevant statutory requirements, apart from minor
omissions or minor defects, and the works are reasonably suitable for
habitation.
[21] In written submissions, Mr Anger contends that he has attempted on a
“number of occasions” by email to settle on a list of defects with the
respondents and that the respondents have either failed and/or refused to
agree on a list of defects.5 The respondents dispute this and contend (in
written submissions) that the applicant has failed to provide a contractual
certificate and a final defects list and complete cleaning prior to a final
inspection.
[22] If the respondents’ submissions are accepted and a finding is made by the
Tribunal that practical completion has not been reached, the respondents
seek an order for liquidated damages on the basis that the works have not
reached practical completion.
[23] The Tribunal has considered the emails exchanged between the parties
during the period of time it is alleged (by the applicant) that practical
completion was reached. The emails are attached to Mr Anger’s affidavit
(Exhibit 1) and the respondents’ statement (Exhibit 9):
1) On 7 March 2010 the respondents request that the applicant remove guttering and
fascia to match the existing “profile”.
2) On 22 March 2010 Mr Anger requested the respondents prepare a defects list “on
the completion of all cleaning” (Exhibit 1, attachment “Q”).
3) By reply on 22 March 2010, the respondents notified Mr Anger of various items (12)
that “need to be completed before practical completion [can] be achieved as these
items are not minor defects”. The respondents state that a list of defects will be
prepared once the cleaning is completed and practical completion has been
achieved.
4) On 23 March 2010 the respondents query why the cleaner “is coming” as there is
“still painting to be done inside and outside the house”.
5) By reply on 24 March 2010, Mr Anger states that the cleaner “needs to come in now
and clean the majority of marks that are on the walls” and that the painter can do
any touch ups once the cleaner has finished.
6) On 28 March 2010 the respondents request that Mr Anger give 24 hours notice of
who will be on site and details of work to be carried out. They also query when the
shade cloth will be installed on the pergola.
7) On 29 March 2010 Mr Anger notified the respondents that (amongst other things)
someone will clean the louvers and he “will attend [on 30 March 2010] in order to
complete a defects and omissions list”. Mr Anger also queries the colour of the
shade cloth chosen by the respondents.
8) By reply on 29 March 2010 the respondents informed Mr Anger that the inside of the
house needs to be cleaned “first” and that a “full list of defects cannot be completed
4 Exhibit 1, attachment “Q”.
5 Written submissions dated 8 March 2011, [37].
-- 5 of 16 --
6
until all of the house, inside and out has been cleaned and all works completed”.
The respondents also enquire about the guttering and the “quote for fitting of the
correct/matching fascia”.
9) On 30 March 2010 Mr Anger emailed the respondents stating that he is “cancelling
the cleaner” and will rebook the cleaner when all the painting is complete. Mr Anger
stated that the painter will be in contact to arrange a time to complete all “touch ups”
and will advise of the cost to replace the fascia.
10) On 10 April 2010 Mr Anger informed the respondents that the painter will be
attending next week and that he will be attending to the shade cloth on “Monday” (12
April 2010).
11) On 12 April 2010 the respondents state that the guttering will need to be painted
“along with the fascia” to “match existing”.
12) On 13 April 2010 Mr Anger notified the respondents about attending to the guttering
and fascia (painting), problems with the “A/C” unit, tiling for the splash back and the
mirror and that the “cleaner will be the last to be done as requested”.
13) On 28 April 2010 Mr Anger notified the respondents that he had completed “all
works up to practical completion” and requested that they put any “defects or
omissions” in writing to him.
14) On 4 May 2010 the respondents emailed Mr Anger a list of works “not yet
completed” and that they are unable to “make a final inspection” as the work “has
not been cleaned”.
15) On 10 May 2010 Mr Anger requested that the respondents provide a “letter for the
pergola as the Certifier will not issue a Final Certificate until he has the letter”. Mr
Anger also states that he requires access to the property with the engineer.
16) By reply on 10 May 2010 the respondents notified Mr Anger of the access times for
the engineer. They referred to the list and stated that the “areas highlighted in
yellow on the attached list are still not complete” and that they are “devoting all [their]
energies toward getting the attached list finished in full before addressing any other
matters”.
17) On 11 May 2010 the respondents queried when the engineer would be on site.
18) On 12 May 2010 Mr Anger by reply stated he is waiting for a reply from the engineer
and that he “will have men on site tomorrow to do some works outside also”.
19) On 13 May 2010 Mr Anger claims (in his affidavit) that an employee (Mr Westwood)
attended to cleaning at the house.
20) On 24 May 2010 Mr Anger requested the respondents contact G James (glass
manufacturer) or himself (Mr Anger) to arrange a site visit and requested access (on
25 May 2010) to “tidy up a couple of things such as the tiles”.
21) On 24 May 2010 the respondents by reply confirmed that G James (representative)
will visit Wednesday and stated that access is not possible tomorrow (Tuesday) –
stating “Wednesday fits with [us]”.
22) On 9 June 2010 Mr Anger issues a claim for payment for practical completion.
23) On 1 July 2010 Mr Anger receives a letter from the respondents’ solicitors (Wilson
Ryan Grose Lawyers) stating that (amongst other things) the applicant is in breach
of the contract because a certificate of practical completion has not been issued and
that the respondents “intend to terminate the Contract” unless the applicant rectifies
the breach within 10 days.
24) On 9 July 2010 the applicant’s solicitors (Ruddy Tomlins & Baxter) reply in writing to
Wilson Ryan & Grose Lawyers stating (amongst others) that the works have reached
practical completion.
25) On 16 July 2010 the respondents’ solicitors indicate (in writing) that they reserve
their right to terminate the Contract.
26) On 21 September 2010 the applicant’s solicitors request (in writing) that the
respondents pay the final progress claim.
[24] The Tribunal finds that the parties have demonstrated an intention to no
longer be bound by the terms of the contract as evidenced in the emails
exchanged between them (from 22 March 2010 to 12 May 2010) as set out
in paragraph [23] (above); and notwithstanding any alleged departure from
their contractual obligations neither party has exercised their respective
rights to terminate.
-- 6 of 16 --
7
[25] The Tribunal finds that the applicant did give notice to the respondents of a
date for final inspection of the works (by emails dated 29 March 2010 and
28 April 2010); however the inspection did not take place as the
respondents indicated (by emails dated 29 March 2010 and 4 May 2010
respectively) that there were incomplete works and the house had not been
cleaned.
[26] The Tribunal finds that the respondents’ conduct (as evidenced in the emails
exchanged) was at times contradictory by making requests for the
completion of certain works (which appear to be minor defects and
omissions) before cleaning can be done and then requesting that cleaning
be done before minor defects and omissions are attended to by the
applicant. The applicant has attempted to address the issues raised by the
respondents and this has led to a breakdown in communication and a
departure from the parties’ respective contractual obligations. For example,
on 23 March 2010 the respondents query why the cleaner is coming as
there is painting (works) to be done inside and outside and on 28 March
2010 the respondents request the applicant give 24 hours notice of who will
be on site and details of work to be carried out. However, in an email dated
30 March 2010 the respondents, in reply to Mr Anger’s email stating he will
be attending (on 30 March 2010) to inspect the works and to complete a
defect and omissions list, state that the house needs to be cleaned first and
all works completed before a list of defects can be prepared. Mr Anger (in
response) cancelled the cleaner and did not attend an inspection (email
dated 30 May 2010). The applicant did, however, state that he would
arrange for the painter to complete all touch ups (minor defects and
omissions).
[27] The respondents refer to various items that they claim “need to be
completed” before practical completion can be reached (emails dated
22 March 2010, 29 March 2010, 4 May 2010 and 10 May 2010). No
evidence was adduced (at the hearing) by the respondents to establish that
that the items (to be completed) were not minor omissions or defects. The
respondents did, however, indicate in an email dated 22 March 2010 that
the items were “not minor defects”. The reference to “touch ups” (on
30 March 2010) and to “tidy up” (on 24 May 2010) would appear to be (in
the absence of evidence to the contrary) references to minor omissions or
defects.
[28] Practical completion is reached as stated under the contract and as
provided under s 67 of the Domestic Building Contracts Act 2000 when all
works are completed in accordance with the contract and all statutory
requirements apart from minor defects and omissions. The respondents
have raised an issue (breach of contract) in respect of the pergola and the
fascia; however, during the time in which the applicant alleges practical
completion was reached (22 March 2010) the respondents have not raised
any issues in relation to the pergola and the fascia (in the various emails
exchanged); in fact quite the contrary. The respondents (email dated
28 March 2010) query when the shade cloth for the pergola will be installed
but did not raise any issues about the pergola construction – that it was not
square and that it does not extend from the roof. These are issues that
have been raised in the respondents’ response and counter-application.
-- 7 of 16 --
8
Furthermore, the respondents have instructed the applicant in writing (email
dated 12 April 2010) to arrange for painting of the guttering and fascia
notwithstanding issues being raised (in emails dated 9 December 2009,
7 March 2010 and 29 March 2010) about replacing the guttering and fascia
to “match existing”. The respondents did not raise any issues about the
applicant being in breach of contract during the time of practical completion
(22 March 2010) and again these issues (fascia not “matching existing”)
have been raised as part of the respondents’ response and counter-
application.
[29] The Tribunal finds that the works, as at 9 June 2010 when a claim was
made for final payment, had been completed by the applicant save for minor
defects and omissions. Notwithstanding the findings made by the Tribunal
about whether practical completion has been reached, the applicant is
entitled to recover any money owing for the works completed under the
contract on the basis that the respondents have had the benefit of the
works, less any claim for defective and incomplete work.6 It is therefore
necessary for the Tribunal to address the other issues raised by the
respondent: cleaning, early possession and breach of contract.
Cleaning
[30] The respondents (in their statement) refer to numerous photographs
(attachments KS79 and KS82 to 95, inclusive) which they submit show the
interior and exterior of the works as being left by the applicant without being
cleaned. The respondents further submit that cleaning was required to
enable a final inspection to take place.
[31] Mr Anger argues that numerous attempts were made to arrange final
inspection and cleaning but the relationship had broken down between the
parties. Mr Anger contends (in his affidavit and during cross-examination at
the hearing) that notwithstanding the relationship breaking down, cleaning
was done and the photos tendered by the respondents are of the outside
areas so wind and dust would get in. The respondents dispute this and
argue that the photos show “builders residue” and the glass on the louvers
and tiles are not cleaned and it was therefore not possible to do a final
inspection. The respondents also rely on an email (and affidavit) from Mr
Dalton (Manager, G James Glass & Aluminium) in relation to the glass not
being cleaned and that Mr Dalton was of the opinion that the glass looked
like a construction site. The witness was not however called by the
respondents to give evidence.
[32] Mr Anger relies on the affidavit of Mr Westwood (employee) tendered at the
hearing in relation to the cleaning of the external areas (6.5 hours on
13 May 2010). Ms Cornell during oral submissions argues that the
respondents were not home at the time the cleaning was done and relies on
the affidavit of Mr Jacobs (witness) who states that the respondents were
6 See Nguyen v Luxury Design Homes Pty Ltd [2004] NSWCA 178, see Chesire and Fifoot,
Law of Contract (9th Aus Ed, 2008) p 1081.
-- 8 of 16 --
9
not home on 13 May 2010. Mr Jacobs was not required for cross-
examination.
[33] The evidence of Mr Dalton (uncontested) refers to the louvers as being in a
“condition consistent with a building under construction”. Mr Dalton’s
evidence is in the form of an email in response to the respondents’ request
for a statement “outlining the condition of the glass” during his visit of the
works on 26 May 2010. The evidence of Mr Dalton (email) and the
reference to a “building under construction” is ambiguous in that Mr Dalton
fails to address the issue of whether the louvers and the surrounding areas
had been cleaned. The Tribunal attaches no weight to Mr Dalton’s
evidence.
[34] The Tribunal does, however, accept the respondent’s evidence that the
applicant did not complete any cleaning to the interior areas. Mr Anger does
not dispute that the cleaning undertaken (by Mr Westwood) was not internal
but contends that the cleaning was to the external areas. The applicant has
not adduced any evidence to contradict the respondents’ contention that the
internal areas were not cleaned. During cross-examination at the hearing
Mr Anger stated that he could not recall if arrangements were made to have
the internal areas cleaned. The explanation provided by Mr Anger in
response to the photographs (which he says are of the outside areas so
wind and dust could get in) is not accepted by the Tribunal. The Tribunal
has viewed the photographs tendered by the respondents, the originals
were also produced at the hearing, and find that the photographs do show
debris on the floor (attachment KS87) and smudges to the louvers (viewed
from the inside – attachment KS79).
[35] Ms Cornell tendered two quotes for cleaning costs at the hearing. The
Tribunal finds that the amount of $1,000.00 is reasonable based on the
quotations tendered (Exhibits 14 and 15).
Early possession by the respondents (as alleged)
[36] There are factual issues in dispute and it is therefore necessary for the
Tribunal to make findings in relation to whether the respondents occupied
the two front rooms (took early possession) in early January 2010 and the
works are therefore deemed to have reached practical completion, as
alleged by the applicant.
[37] Mr Anger gave his consent in writing (by email dated 18 November 2009) to
the respondents to store their belongings in the front two rooms while the
tiling was being completed.7 During cross-examination at the hearing Mr
Anger gave evidence that he saw a bedroom set up and that he saw people
living in the two front rooms. Mr Anger referred to beds being slept in and
clothes and desk furniture in the rooms.
[38] Ms Cornell denies that the respondents were living in the two front rooms
and gave evidence at the hearing that they had simply moved their bedroom
furniture from two existing rooms (which were being tiled) to the two front
7 Exhibit 1, para 43 and attachment “T” (email dated 18 November 2010).
-- 9 of 16 --
10
rooms as they were instructed to do by the applicant. Mr Cornell states that
the furniture was only recently moved back and she denies that the
respondents or their family (children) had been sleeping there. Ms Cornell
tendered a photograph at the hearing (Exhibit 19) of a room which she says
her children have been sleeping in since November 2009 as evidence that
the two front rooms have not been occupied by the respondents (or their
family). The respondents also refer to the photographs taken (Exhibit 9) in
relation to the cleaning of the works (issue) which Ms Cornell submits clearly
shows they have not taken possession of the works.
[39] The Tribunal cannot be satisfied, based solely on the evidence of Mr Anger
that the respondents were sleeping in the two front rooms, as alleged.
There is no independent evidence before the Tribunal to corroborate Mr
Anger’s assertion that the respondents had taken up occupancy. There
were obviously other tradespersons (such as the tiler) completing work at
the house during the time when it is alleged the respondents took early
possession and yet no independent statements have been obtained in
relation to observations made about whether the respondents were sleeping
and living in the two front rooms. The Tribunal has also considered the
photographs taken by the respondents – the photographs (Exhibit 9) show
the works as being vacant (not occupied). The Tribunal does not accept the
applicant’s submission that the respondents took early possession of the
works by occupying the two front rooms.
Alleged Breaches of Contract
[40] The alleged breaches of contract include:
1) The pergola – the respondents allege it was not constructed in
accordance with the approved plans (in the contract) in that the pergola
does not come off the fascia and it does not extend the entire length of
the house and is a square (not with a rake). Furthermore, it was not
constructed for the purpose for which it was intended and that they
could not have known this until after it was finished. In particular the
sun heats up a part (or gap) of the wall – the pergola was finished in
winter and it was not until summer that the gap (difference from where
the shade cloth ends) that the sun heated up the exposed wall by
reason of the gap.
2) The fascia – it does not “match existing”.
[41] The issue of whether the applicant is in breach of contract (pergola and
fascia issues) is also relevant to the issue of whether or not the works had
reached practical completion – it is alleged by the respondents that the
pergola and fascia were not completed by the applicant in accordance with
the terms of the contract and that such works are not minor omissions or
defects.8
The pergola
8 Respondents’ Amended Written Submissions dated 23 March 2011.
-- 10 of 16 --
11
[42] It is not disputed that the pergola was not constructed according to the
approved plans which form part of the contract. A certificate of compliance
cannot issue until the respondents consent to the variation in the plans. The
respondents argue that they never saw the amended plans until December
2010.
[43] Mr Anger submits that it is not necessary to have a certificate of compliance
from the certifier for practical completion to be reached; however he
concedes (during oral submissions) that it is necessary to have a certificate
of compliance to be able to insure the works under the Queensland Building
Services Authority Act 1991.
[44] Mr Anger argues that the respondents consented to the variation in the
pergola plans. The respondents do not agree and contend that the variation
(which is disputed) was never put in writing by the applicant.
[45] Mr Anger admitted, during cross-examination at the hearing, that he had
failed to put in writing the alleged variation of the pergola, stating that it was
a “mistake on [his] behalf”.
[46] It is not disputed that Mr Anger built the pergola and that it was paid for by
the respondents. Furthermore, the applicant, once the pergola was
constructed, painted it and installed a shade cloth at the request of the
respondents. Mr Anger argues that he is therefore entitled to be paid for the
work completed by him.
[47] The respondents contend that they allowed Mr Anger to complete the
pergola because they were scared of him and they were told by other
builders to get the work done. Furthermore, the respondents contend that
the pergola was not constructed for the purpose for which it was intended –
to provide shade cover to the side of the house, and that this could not have
been known by them until summer when the sun heated up that part of the
wall which is not covered by the shade cloth.
[48] The relevant factual issue in dispute concerns a conversation which
allegedly took place on 6 October 2009 when Mr Anger says the
respondents agreed to amend the plan so that the pergola would extend
from the wall and not from the roof (fascia) because Mr Anger says the
integrity of the roof would be compromised – the roof could leak if the
pergola was constructed that way.
[49] Mr Anger also contends that the respondents agreed to the pergola being
constructed as a “square” and not with a “rake” as the approved plans show.
Mr Anger argues that the respondents agreed to the design (the “square”)
and the respondents dispute this and allege that Mr Anger constructed the
pergola that way because it was cheaper.
[50] Ms Cornell cross-examined Mr Anger at length at the hearing about the
issue of the pergola being constructed as a “square”. She referred to
various invoices (addressed to Mr Anger) which Ms Cornell argues is
evidence that Mr Anger ordered shorter planks of wood before the alleged
conversation in October 2009 (the date of alleged consent to the variation)
-- 11 of 16 --
12
and that the invoices are evidence that he always intended to build the
pergola in the “square” shape.
[51] Ms Cornell also gave evidence about holes being dug into the ground by Mr
Anger (in August 2009) before the October conversation and that the holes
(depicted in photographs tendered at the hearing) are evidence that Mr
Anger intended to build the pergola “short”. This is disputed by Mr Anger.
Mr Anger argues that the respondents agreed to put the posts to the left
hand side of the storm water drain (also depicted in the photograph) and this
is the reason why the shade cloth does not extend the entire length of the
building (house) and the length of the pergola is “short” as alleged by the
respondents. Mr Anger contends that the respondents agreed to the
position of the post and also states that the old and new plans show the
pergola finishing short of the fascia.
[52] At the hearing Ms Cornell referred to quotes from builders she says can vary
the design of the pergola – move the post and extend the shade cloth. Ms
Cornell also referred to an email to show that she requested the builder to
quote on the basis that the post was to be moved. Ms Cornell also
produced quotes on the basis of demolition and reconstruction of the
pergola in accordance with the approved plan.
[53] The Tribunal has some difficulty with the respondents’ evidence that they
did not consent to the variation in the plans as to the construction of the
pergola. On 28 March 2010 the respondents emailed Mr Anger requesting
that he notify them as to when the shade cloth will be fitted to the pergola.
There were several emails exchanged between the parties during the
construction of the works; particularly emails sent by the respondents
referring to various issues but no mention of any issues with the pergola
design – the square shape, the gap in the extension and that it does not
extend from the roof. On 2 February 2010 the respondents emailed the
applicant stating, “we want to finish painting the pergola. When will the paint
be dropped off?” In the same email the respondents refer to other issues
with the works such as (amongst others) the doors and bathroom.
[54] The Tribunal attaches no weight to the evidence adduced by the
respondents (invoice regarding material purchased) which they submit show
the applicant had plans to construct the pergola (not in accordance with the
plans) prior to the October 2010 conversation. Mr Anger, during cross-
examination at the hearing, presented as a reliable witness and responded
to Ms Cornell’s questions about the materials ordered (in the invoices) to
construct the pergola. For example, Mr Anger stated (in relation to the
timber ordered) that the same size timber could be used had the pergola
been constructed from the fascia.
[55] The Tribunal attaches no weight to the evidence adduced by the
respondents in relation to the Form 61 (Exhibit 16). Mr Anger, during cross-
examination at the hearing, gave evidence that the items referred to in the
Form 61 were examined by the engineer (Pat Murray) on site with the
respondents and the only issue outstanding is that the respondents need to
“sign off’ on the amended plans to so that a final compliance certificate can
be issued for the pergola (construction).
-- 12 of 16 --
13
[56] The Tribunal attaches no weight to the evidence adduced by the
respondents in relation to the Queensland Building Services Authority
(QBSA) licence search (Exhibit 17) which Ms Cornell contends is evidence
that Mr Anger has no regard “for the rules”. The QBSA licence search
shows that the applicant’s licence was suspended from 17 November 2009
to 3 December 2009 and Ms Cornell submits that Mr Anger continued work
on the house during this time. The evidence (QBSA licence search and
letter dated 26 November 2009) was obtained after the commencement of
the hearing (tendered by Ms Cornell on 17 October 2011). Ms Cornell
admits, however, that she received notification of the suspension of the
applicant’s licence in correspondence received from the QBSA in November
2009 (letter dated 26 November 2009) and had “forgotten” about the QBSA
letter – she had the letter in a “pile of papers”. Mr Anger, during cross-
examination, stated that the reason for the suspension of the licence was in
relation to providing financial documentation (to be provided by his
Accountant) to the QBSA and Mr Anger stated that he continued working
during the period of suspension to “keep the job moving”.
[57] The Tribunal does not accept the respondents’ contention that the applicant
was claiming progress claims before the works were completed. Mr Anger
addressed the issues raised (for example) by Ms Cornell during cross-
examination in relation to the Tax Invoice dated 27 November 2009 (claim
for sheeting and plastering, Exhibit 1 attachment KS27). Mr Anger stated
that there were some changes to the works (plastering) as requested by the
respondents and this explained why a progress claim was issued before
plastering work was completed.
[58] The Tribunal does not accept the evidence of the respondents that they did
not raise any issues about the construction of the pergola with Mr Anger
because when they raised objections with him he became aggressive and
intimidatory. Mr Anger gave oral evidence at the hearing that he has never
been aggressive and denied that he has raised his voice as alleged by Ms
Cornell. Ms Cornell, during cross examination at the hearing, gave
contradictory evidence about this issue (intimidatory conduct) – she referred
to Mr Anger’s aggressive behaviour but also stated that the respondents did
not raise any objections about the pergola as they did not believe they could
get another builder on site so while they explored their options they went
ahead with the pergola. Notwithstanding the contradictory evidence given
by the respondents about the intimidatory conduct of Mr Anger, they did not
raise any objection (with Mr Anger) in their emails to the applicant during
construction of the pergola.
[59] The Tribunal prefers the evidence of Mr Anger in relation to the October
2010 conversation about the changes to the construction of the pergola. Mr
Anger presented as a reliable witness and was able to recall the
conversations with the respondents about the change in the plans – pergola
coming off the wall (and not the roof) and the footing holes (length of
pergola). For example, Mr Anger recalled where the respondents were
standing during the October 2010 conversation – at the rear of the property
near the septic tank. Mr Anger also conceded during cross-examination that
the plans (existing and amended) show a slope in the pergola design (the
-- 13 of 16 --
14
pergola has been constructed as a square). Mr Anger stated that the plans
do not, however, specify an angle the pergola should be placed at (the
rake). The Tribunal also accepts Mr Anger’s evidence in relation to the
position of the posts and that the old and new plans show the pergola
finishing short of the fascia.
[60] The Tribunal finds that the applicant is not in breach of the contract in
respect of the pergola construction and that the respondents either
expressly or implied by their actions consented to the variations in the
pergola design.
[61] The Tribunal does, however, accept the respondents’ evidence that when
meeting with Mr Anger (prior to construction of the pergola) they indicated
that they “wanted a pergola to shade the western side of the house to make
it cooler” and that the pergola constructed provides inadequate shade cover
to the side of the house and that this was not something which could have
been known by the parties at the time of construction – it became apparent
in summer that part of the wall heats up and therefore the pergola does not
fulfil the purpose for which it was constructed.
[62] The respondents rely on various quotations obtained for the costs
associated with demolishing and rebuilding the pergola and the costs to
move the existing footings and extend the shade cloth to rectify the issue of
the sun heating up the side of the wall. The Tribunal has considered the
decision in Bellgrove v Eldridge9 where the rectification work to be
performed must be both necessary and reasonable10 and the decision in
Wheeler & Anor v Ecroplot Pty Ltd11 in determining the reasonableness of
rectification costs.
[63] The Tribunal finds that the quotation obtained by the respondents (Exhibit
13) from Tropical Lifestyle Builders in relation to moving the existing footings
and fitting a new shade cloth in the amount of $6,642.85 is reasonable and
should be deducted from any money owing by the respondents to the
applicant for completion of the works.
The fascia
[64] The respondents allege that the fascia was not installed in accordance with
the terms of the contract – “like to match like”. Mr Anger (on behalf of the
applicant) argues that it was not possible to match the existing fascia.
[65] Ms Cornell relies on various emails from suppliers as evidence that it was
possible to get materials to match the existing fascia which was installed
some two months before any issue was raised by the respondents about it
"matching existing".
[66] The Tribunal does not attach any weight to the evidence adduced by the
respondents in relation to the availability of materials to “match existing”
9 (1954) 90 CLR 613 referred to in Pulitano v Mikescapes Pty Ltd [2010] QCAT 248 and
Franklin v A&S Bricklaying Service [2010] QCAT 69.
10 See Tabcorp Holdings Limited v Bowen Investments Pty Ltd [2009] HCA 8.
11 [2010] NSWCA 61.
-- 14 of 16 --
15
which they say could have been obtained by the applicant. Mr Anger gave
evidence at the hearing (during cross-examination) that he had contacted
several suppliers and used a material which was only “slightly different”. Mr
Anger states that he removed (on 13 April 2010) guttering already installed
at no expense to the respondents on the basis that they were not satisfied
with the product that had been used. Mr Anger states in his affidavit that he
removed the guttering in the “interests of customer relations”.12
[67] Notwithstanding the emails which Ms Cornell says support the respondents’
submission in relation to the fascia, the fact remains that the respondents
told Mr Anger to arrange for the fascia (installed by the applicant) to be
painted (by Mr Tony Poole) on 12 April 2010. The applicant relies on the
affidavit of Mr Tony Poole who was responsible for painting the fascia at the
respondents’ house.
[68] Ms Cornell admits that the respondents asked the applicant to arrange for
the painting of the fascia but once painted, it did not match the existing
fascia. The respondents (in their statement) state that they requested the
fascia be painted, as they wanted to see if it would match as the applicant
refused to replace it without payment of additional money.
[69] Ms Cornell relies on quotes obtained to remove the existing fascia and
replace it with fascia to match the style of the house. The quote is in the
amount of $6,000.00. The issue of the fascia was raised by the
respondents in emails dated 9 December 2009, 29 March 2010, and
30 March 2010. On 30 May 2010 Mr Anger advised the respondents that
the cost to replace the fascia would be $2,800 (before painting). The
Tribunal prefers the evidence of Mr Anger that the fascia had been installed
several weeks prior to the issues being raised by the respondents and that
they have accepted the installation of the fascia and elected to continue with
the contract by instructing Mr Anger (on 12 April 2010) to arrange for
painting of the fascia. The respondents’ claim for the costs of replacing the
existing fascia is not accepted.
Calculation of money payable
[70] The Tribunal has assessed damages (based on the findings made) as
follows:
Money owing under the contract - $23,534.52
LESS cleaning costs - $1,000.00
LESS pergola costs - $6,642.85
Balance owing $15,891.67
[71] The Tribunal orders that the respondents Mr Springall and Ms Cornell pay
the amount of $15,891.67 to the applicant, Combined Building Services Pty
Ltd by 4.00pm on 20 January 2012. Upon payment of the money owing
under the contract ($15,891.67) by the respondents, the applicant is to
12 Exhibit 1, [72].
-- 15 of 16 --
16
deliver to the respondents the keys and all documents (including manuals
and certificates) relating to the works completed.
-- 16 of 16 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2011/674