Ambience Designer Pools and Spas Pty Ltd v Curry and Anor [2011] QCAT 614
CITATION: Ambience Designer Pools and Spas Pty
Ltd v Curry and Anor [2011] QCAT 614
PARTIES: Ambience Designer Pools and Spas Pty
Ltd
v
Jason Curry
Yvonne Cochrane
APPLICATION NUMBER: BDL366-10
MATTER TYPE: Building matters
HEARING DATE: 16 August 2011
HEARD AT: Brisbane
DECISION OF: Mr Paul Favell, Member
DELIVERED ON: 9 December 2011
DELIVERED AT: Brisbane
ORDERS MADE: Mr Curry and Ms Cochrane pay
Ambience Designer Pools and Spas Pty
Ltd $4,920.68 by 4:00pm on 23 December
2011.
CATCHWORDS: Domestic swimming pool contract –
Variations – Progress claims – Non payment
– Valid termination – Counterclaim
APPEARANCES and REPRESENTATION (if any):
APPLICANT: Mr Victor Todorovic on behalf of Ambience
Designer Pools and Spas Pty Ltd – self
represented
RESPONDENT: Mr Jason Curry and Ms Yvonne Cochrane –
self represented
REASONS FOR DECISION
[1] On or about 6 July 2010 the applicant, Ambience Designer Pools and Spas
Pty Ltd (“Ambience”), and the respondents, Jason Curry and Yvonne
Cochrane, signed a SPASA Domestic Swimming Pool Contract pursuant to
which Ambience was required to construct a swimming pool at 19 Elkington
Circuit, North Lakes, the home of Mr Curry and Ms Cochrane.
-- 1 of 5 --
2
[2] The contract price was $41,130.00.
[3] The contract was made up of a Contract Schedule, General Specifications,
a list of pool/spa equipment, a Prime Cost Schedule, a list of additional
charges, a sketch of the proposed pool special conditions and general
conditions of contract. The contractor’s margin contract price and
provisional sums were included.
[4] Ambience contends that it performed the works required by the contract
between July and September 2010. It issued four invoices to a total of
$33,130.95. That amount included $2,295.95 for variations. Mr Curry and
Ms Cochrane paid Ambience $28,609.00. An amount of $4,521.95 of the
claimed sum was not paid and Ambience claims that amount and $7,325.00
as damages for breach of contract (loss of profits).
[5] It also claims interest and an order for the return of items supplied by
Ambience but not paid for by Mr Curry and Ms Cochrane.
[6] Ambience sent a Notice to Remedy Breach to Mr Curry and Ms Cochrane
on 13 October 2010, which also included a Notice of Suspension of Works
and a Notice of Intention to Terminate Contract.
[7] The basis of the Notice was an alleged breach of clause 10 of the contract
in that payment of two invoices had not been made in full within 5 days.
[8] Clause 10 of the contract required Mr Curry and Ms Cochrane to pay each
progress claim or other payment request immediately upon receiving the
claim or request. If Mr Curry and Ms Cochrane disputed the amount stated
in a progress claim they were obliged to pay that part of the claim not
disputed and give Ambience a written notice setting out the grounds of the
dispute on the balance within 5 days. Mr Curry and Ms Cochrane had no
right to deduct any amount from a progress payment due to Ambience.
[9] Clause 16 of the contract allowed Ambience to give Mr Curry and Ms
Cochrane a notice in writing, setting out the specific details of the failure or
default, and stating its intention to terminate the contract, if the failure or
default was not remedied within 5 days and when Mr Curry and Ms
Cochrane had failed to pay any progress or other amount due to Ambience
within the time allowed for by the contract and the default or failure was
capable of being remedied.
[10] If Mr Curry and Ms Cochrane did not remedy the failure or default within the
5 days, Ambience could terminate the contract immediately upon giving
them a further written notice.
[11] I am satisfied that Ambience, by invoice numbers 314 and 326, made
progress payment claims for Stages 2 and 3 respectively in accord with the
contract and I am satisfied that those claims were not paid in full within the
time allowed under the contract.
[12] I am satisfied that Ambience did give Mr Curry and Ms Cochrane a Notice to
Remedy Breach dated 13 October 2010. I am also satisfied that Mr Curry
and Ms Cochrane did not remedy the breach.
-- 2 of 5 --
3
[13] I am satisfied that Ambience was entitled under clause 15 of the contract to
suspend work, which it did and it was entitled to give the notices
contemplated by clause 16 of the contract.
[14] I am also satisfied that Ambience was entitled to terminate the contract
under clause 16(3) of the contract, which it did by an emailed letter dated
27 October 2010.
[15] Upon termination of the contract, Ambience was entitled to recover its
losses and expenses arising from the breach and the termination of the
contract.
[16] Invoice number 326 was a claim for Stage 4 under the contract relating to
the installation of filtration equipment. In Annexure “A” to the claim it was
described as a claim for the completion of Stage 3, the completion of
coping. That annexure was amended at the hearing of this matter to reflect
the actual claim made, and the claim partly the subject of the notices given.
[17] Part of the claim of Ambience is “$7,325 being for damages suffered as a
result of loss of profit”. During the hearing I was told that that claim included
$3,000-$4,000 for damages, legal costs and a sum for the items admitted as
being provided to Mr Curry and Ms Cochrane as set out in paragraph 10 of
Annexure “A”.
[18] The response of Mr Curry and Ms Cochrane prior to the hearing was to
deny that Stage 3 had been completed. That is no longer part of
Ambience’s claim in that the Stage 3 claim is not pursued and Stage 4 is
claimed.
[19] I was informed by Mr Todorovic that Stage 4 was complete. Photographs of
the installed filtration systems are exhibit VT7 to exhibit 1.
[20] I accept that the stages claimed had been completed and the claims were
appropriately made. Mr Curry and Ms Cochrane have not claimed
otherwise. The claims complied with clause 10 or clause 26 of the contract.
[21] Mr Curry and Ms Cochrane claim that Ambience terminated the contract
without sufficient reason based on an unpaid progress claim for incomplete
works. I do not accept that claim for the reasons I have given above.
[22] Mr Curry and Ms Cochrane claim $24,821.00 from Ambience made up of
$6,074.00 for out of pocket for costs to complete works including the unpaid
progress claim works in question; $8,843.00 for rectification of defective
work and damage caused by the applicant; $9,904.00 for “award for
damages and legal fees”.
[23] The last mentioned claim above was said to be particularised in
Annexure “B” to the response to the claim. Annexure “B” is a record of a
time line. The contents of Annexure “B” do not form a basis for this claim.
There is no entitlement under the contract. There is no particularisation of
the claim and no basis for quantifying the claim.
[24] The rectification claim primarily concerns the cost of rectifying a damaged
deck over which machinery passed during construction of the pool.
Ambience had admitted liability for the replacement or rectification of the
deck. During the hearing I was informed that the insurance company CBE
-- 3 of 5 --
4
agreed to pay for the deck and that Mr Todorovic undertook to remit the
payment for the deck in full to Mr Curry and Ms Cochrane and pay the
$500.00 excess. I was told that such a proposal was acceptable and the
Tribunal need not be further concerned with that part of the claim.
[25] Mr Curry and Ms Cochrane claimed that some items which should have
been supplied under the contract were not provided. One such item was
three underwater spa electronics niche lights with a quoted price of $990.00.
During evidence, Mr Todorovic agreed to reimburse $400.00 for one light
which was provided for in the contract but was not on the plan which he
says accompanied the contract.
[26] Mr Curry and Ms Cochrane say that the following items were included in the
contract but not supplied by Ambience:
a) Skimmer box lid $118.00
b) 3-way valve $ 36.00
c) Eyeball white parts $ 22.00
d) Suction 50mm parts for pool pipes $ 26.00
e) Backwash trenches, pipes and hookup $500.00
f) Completed install of pipes / valves / fit pump /
backwash / test pipes
$305.00
Total $1,007.00
[27] I was not supplied with evidence of the cost of those items. Mr Todorovic
admitted that the backwash connection was not begun. He said he supplied
the backwash line but could not connect them because he was waiting for a
licensed plumber to carry out the work. He said a 3-way valve was not
supplied because it was not part of the filtration system but was part of a
water feature.
[28] Mr Curry and Ms Cochrane make their claims primarily based on the
presumption that the contract was not validly terminated. For the reasons I
have already given, the contract was validly terminated.
[29] Ambience is entitled to its claim of $411.95 (balance of invoice number 314)
and $4,110.00 (balance of invoice number 326).
[30] Ambience is also entitled to its loss of profit on the remainder of the work,
which on the contract price is $10,295.00. There is no evidence of what the
profit would be and in those circumstances the Tribunal is unable to
determine the quantum of the loss of profit.
[31] Under the contract, Ambience is entitled to interest on overdue payments at
the rate of 10 per cent. At that rate, the interest award should be $452.20
per annum. I award interest for 13.5 months, namely, $508.73.
[32] Mr Curry and Ms Cochrane are not entitled to the cost of completion of the
pool because the contract was validly terminated. They are entitled to the
-- 4 of 5 --
5
cost of remedying any proven defect. I have not been provided with
evidence of defects. I do not accept any order should be made for defects.
[33] Both parties represented themselves. Both apparently had incurred legal
costs but neither proved those costs. I am not satisfied that the interests of
justice require a departure from the usual order for costs under section 100
of the Queensland Civil and Administrative Act 2009, namely, that each
party bear their own costs.
[34] During the hearing, Mr Curry and Ms Cochrane conceded that they should
pay $290.00 with respect to part of the claim in paragraph 18 of the
Annexure to the claim. The respondents have the items listed in paragraph
10 of that Annexure for which Ambience has paid but not proved the cost.
The items are not able to be returned and in the circumstances I am unable
to determined any compensation order or cost of supply.
[35] Further, Mr Todorovic conceded that he should pay $400.00 because of one
fewer light.
[36] Accordingly, the order of the Tribunal is that Mr Curry and Ms Cochrane pay
Ambience Designer Pools and Spas Pty Ltd $4,920.68 by 4:00pm on
23 December 2011.
-- 5 of 5 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2011/614