Benn v Myles & Anor [2011] QCAT 567
CITATION: Benn v Myles & Anor [2011] QCAT 567
PARTIES: Mr Jason Benn
(Applicant)
v
Mr Anthony James Myles
AJ Myles & Co Pty Ltd ACN 111 244 823
(Respondents)
APPLICATION NUMBER: BD492-09
MATTER TYPE: Building matters
HEARING DATE: 19 and 20 July 2011
HEARD AT: Cairns
DECISION OF: Ms Joanne Browne, Member
DELIVERED ON: 18 November 2011
DELIVERED AT: Brisbane
ORDERS MADE: 1. The Respondent, Mr Anthony James Myles
pay the amount of $140,340.72 to the
Applicant, Mr Jason Benn by 4.00pm on
16 December 2011.
CATCHWORDS: Breach of contract – exclusion of liability – defective
and incomplete work
Section 77 Queensland Building Services Authority
Act 1991
APPEARANCES and REPRESENTATION (if any):
APPLICANT: Mr C J Ryall instructed by Robin Smith Solicitor
RESPONDENT: Mr J J Sheridan instructed by Williams Graham
Carmen Solicitors
REASONS FOR DECISION
Introduction
[1] Mr Benn had plans to relocate his family from city life to live on a family farm (in
El Arish).
-- 1 of 28 --
2
[2] Mr Benn and his wife (Suari Mason) were attracted to colonial style homes. In
particular Mr Benn liked the “tongue in groove style” and wooden floors, typical
features of colonial (Queenslander) style homes.
[3] Mr Benn and his wife inspected a colonial style Queenslander house (circa
1921) with a local builder (Mr Gary Kuhn) in early September 2008 at 2 Mill
Reserve, Mourilyan, prior to Mr Benn purchasing the house for $11,500.00.1
[4] It was Mr Benn‟s intention to relocate the house to the farm in El Arish. Mr Benn
planned to undertake some renovations to the house prior to living in it with his
family.
[5] Mr Myles is in the business of house relocation. Mr Benn saw Mr Myles‟
advertisement on the yellow pages website (on the internet) for “Complete
House Relocation Services” and contacted Mr Myles in early November 2008.
[6] Mr Benn and Mr Myles signed a contract on 6 January 2009 to relocate the
house from Mill Reserve, Mourilyan to 379 Granadilla Road, El Arish
(approximately 30 kilometres distance).
[7] The amount to be paid by Mr Benn to Mr Myles in consideration for the
relocation of the house was $48,000.00.
[8] The house was to be cut into two sections (halves) and transported in 2 stages –
one half of the house and then the other. There was some delay in transporting
the house due to heavy rainfall and a breakdown in the machinery used for
relocation.
[9] During completion of the works (relocation), a dispute arose between the parties.
Mr Benn claims that there was damage to the house as a result of the rainfall
prior to the contract being completed, and (amongst others) that Mr Myles failed
to undertake the contracted work and complete certain repairs and replacements
as agreed (and in accordance with the contract plans and the implied statutory
warranty).
[10] Mr Benn filed an application (and a further amended application) in the former
Commercial and Consumer Tribunal on 26 November 2009 seeking an order for
relief from payment in the amount of $4,800.00 plus an award for damages in
the amount of $60,000.00.
[11] Mr Myles filed a response and counter-application in the Queensland Civil and
Administrative Tribunal (QCAT) on 22 December 2009.
[12] Mr Benn claims (amongst others) the costs of repair, costs to complete works
and damages (including GST) as follows:2
1 Letter from Bundaberg Sugar to Mr Jason Benn dated 16 September 2008, “5”, Exhibit 15,
document 5. The house was also inspected by a builder (Mr Rob Wolf) in late September
2008.
2 Schedule of Amounts Claimed dated 11 March 2011, filed 15 March 2011, items numbered
1(a) and 1 to 26, including an amount for preliminaries. In accordance with a direction made at
-- 2 of 28 --
3
1) Costs to repair water damage $120,629.00
(b) Plus costs to remove damaged floors $ 96,860.00
2) Costs to complete works (“a to c”) $ 12,857.00
3) Extra rental expenses $ 6,460.00
4) Distress and inconvenience $ 10,000.00
The hearing
[13] Witnesses gave sworn evidence and were cross-examined at the hearing.
Documents were tendered including photographs of the house taken prior to and
after relocation.
[14] Prior to the hearing, a meeting of experts took place (experts conclave) between
Mr Gary Thompson (Quantity Surveyor and Builder), Mr Gavin Stewart (Quantity
Surveyor and Builder) and Mr Charles Michael Gianarakis (Civil Engineer) on
6 September 2010 and a joint experts report (with agreed costing) was prepared
and filed in the Tribunal (dated 21 September 2010).
[15] Mr Benn relies on his own statement and the statement of his wife (Ms Suari
Mason). Mr Benn also relies on the evidence (statements) of Mr Gary Kuhn
(Builder), Mr Graeme Arthur Coates (Electrical Contractor), Mr Charles
Gianarakis, Mr Gary Thompson and the joint expert report.
[16] Mr Myles relies on his own statements and the statements of Mr Robert Myles
(his nephew), Mr Callan Myles (his son), Mr Gavin Stewart, Mr Charles
Gianarakis and Mr David Fair (Drake Removal Homes).
Jurisdiction under the Queensland Civil and Administrative Tribunal Act 2009
[17] The proceedings were commenced in the former Commercial and Consumer
Tribunal (“the CCT”) which now falls under the jurisdiction of the Queensland
Civil and Administrative Tribunal (“QCAT”). QCAT has jurisdiction to determine
the application under section 256 of the Queensland Building Services Authority
Act 1991 (“the QBSAA”) which includes a dispute under the Act.
[18] For the purposes of section 77 of the QBSAA the tribunal is satisfied that this is
a “building dispute” which may be determined under the Queensland Civil and
Administrative Tribunal Act 2009 (“the QCAT Act”).
The issues to be determined
[19] The issues to be determined by the Tribunal are:
1) Who are the contracting parties;
2) What was the condition of the house prior to relocation;
the hearing, a revised assessment of damages was filed (applicant‟s supplementary
submissions dated 21 July 2011).
-- 3 of 28 --
4
3) Whether there is an exclusion of liability (under the contract) for water
damage;
4) Was Mr Myles in breach of the contract in failing to complete the works in
accordance with the warranty provisions under the Domestic Building
Contracts Act 2000 (the water damage to the house);
5) Was Mr Myles in breach of the contract in failing to install cyclone rods in
accordance with the contract (the plans);
6) The costs to complete the contracted works (as alleged);
7) The rectification costs for water damage to the house (as alleged);
8) Whether Mr Benn is entitled to rental expenses (as alleged);
9) Whether Mr Benn is entitled to a claim for distress and inconvenience;
10) Whether Mr Myles is entitled to payment of monies owing under the
contract (final progress claim).
The Contracting parties
[20] It is not disputed by the parties that discussions took place between Mr Benn
and Mr Myles personally in November 2008 prior to signing a contract on
6 January 2009. Mr Benn refers to discussions in November 2008 and January
2009.
[21] Mr Myles is a director of AJ Myles & Co Pty Ltd and contends that he was acting
as an agent of the corporate entity and the proper respondent liable for any
damages (which is denied by the respondents) is AJ Myles & Co Pty Ltd.
[22] On 6 January 2009, Mr Benn and Mr Myles signed a Minor Works Contract
together with General Conditions (the date for practical completion was 135
days). Mr Myles contends that he signed the contract on behalf of AJ Myles &
Co Pty Ltd. The terms of the Contract were partly oral and partly written.
[23] The BSA Minor Works Contract (dated 6 January 2009) provides “contractor”
details as “Anthony James Myles” together with Mr Myles‟ licence number and
address. The details for “ACN” have been completed under “contractor” details.
There is no reference in the contract to AJ Myles & Co. There is, however,
reference to AJ Myles & Co House Relocators in the General Conditions
attached to the contract.
[24] Prior to Mr Benn and Mr Myles signing the contract, an earlier contract had been
prepared by Mr Myles and was signed (only by Mr Myles) and dated
21 November 2008. The contract is in the same terms as the contract signed on
6 January 2009.
[25] The QBSA issued notification of insurance to Mr Benn (by letter dated
21 November 2008) in the name of Anthony James Myles (as contractor) for
“restumping &/or associated work as per contract” with a stipulated contract
value of $20,000.00 effective from 21 November 2008.
[26] During cross-examination Mr Myles confirmed that he did hold a trade licence as
a carpenter and that relocation of a house was building work which he was able
to perform under his respective licence.
-- 4 of 28 --
5
[27] Mr Myles agreed, during cross-examination, that when lodging the documents
with the QBSA (for insurance) he told the QBSA that he would be the contractor,
however, he maintained that he had signed the contract for and on behalf of the
corporate entity (AJ Myles & Co).
[28] Ms Suari Mason (Mr Benn‟s wife), in her written statement dated 2 July 2010
(tendered at the hearing), states that Mr Benn did not sign the first contract
(dated 21 November 2008) as “it was taking time to get the plans through
council”.3 Ms Suari states that Mr Benn had “contacted Myles about relocating
the house” on the basis of “good advice” previously given to Mr Benn about
moving a house “around July 2008”.4
[29] The Tribunal accepts the non-contested evidence of Mr Benn that all
discussions in relation to the contract (prior to signing) were between himself
and Mr Myles.
[30] The certificate of insurance issued by the QBSA and the contract dated
6 January 2009 are in Mr Myles‟ name and not the corporate entity (AJ Myles &
Co). The Tribunal finds that Mr Myles in his personal capacity entered into and
signed the contract as the contractor responsible for the contracted works to be
performed.
The condition of the house
[31] There is conflicting evidence about the quality of the house prior to relocation.
[32] Mr Myles contends that the house prior to relocation was “in need of major
renovation works” and was “on the verge of demolition”.5 Mr Myles also states
that when he first inspected the house (prior to relocation) he “noticed that the
floor boards were splitting, floorboards coming loose in one part of the house”.6
[33] Mr Myles‟ evidence in relation to the condition of the house prior to relocation is
supported by Callan Myles (his son) and Robert Myles (his nephew).
[34] Callan (in his written statement dated 22 June 2010) states that the house was
in “poor condition” but structurally the house was in “reasonable condition”.
Callan states “aesthetically it was very run down with old painted floors around
the extremities of the house, faded carpet and stressed lino covering the older
style kitchen floor. This is not unusual with houses we’ve moved in the past”.7
[35] Mr Benn disputes Mr Myles‟ evidence. Mr Benn states that he did not see any
evidence of “severe wood rot”. However, the roof “was rusty and part of the
3 Statement of Suari Mason dated 2 July 2010, Exhibit 7, [10].
4 Exhibit 7, [4].
5 Exhibit 10, statement of Anthony James Myles dated 4 June 2010, [6].
6 Statement of Anthony James Myles dated 4 June 2010, Exhibit 10, [56].
7 Exhibit 14, [13].
-- 5 of 28 --
6
ceiling area was covered with black soot”.8 Mr Benn relies on a number of
photographs of the house taken by him prior to the house being relocated.
[36] Mr Benn states that prior to purchasing the house, it was occupied by tenants.
During oral evidence, Mr Benn stated that the tenants vacated the house in
August or September 2008.
[37] During cross-examination, Mr Benn was referred to a number of photographs of
the house taken by him prior to relocation. One of the photographs referred to
showed the flooring of the house and the linoleum. Mr Benn did not agree that
that the linoleum was of poor quality prior to relocation. Mr Benn did not agree,
however, that the photographs showed the house as being in “poor condition”
(prior to relocation) and stated that the photographs of the house show “poor
maintenance”. Mr Benn stated that he had plans to renovate the house after
relocation and did not agree that the house required “significant” renovations.
[38] Mr Benn was also referred, during cross-examination, to documentation relating
to the purchase of the house, obtained from Bundaberg Sugar. The documents
(dated 16 September 2008) confirm that Mr Benn paid $11,500.00 for the house.
The documentation states “payment must be received prior to commencement
of removal or demolition [of the house]”.9
[39] The Tribunal has carefully looked at the photographs tendered at the hearing by
Mr Benn, also included in the material tendered by Mr Myles on behalf of the
respondents. The photographs do not show any evidence of water damage to
the interior walls and floor. The photograph of the kitchen shows a tidy bench
with cupboards and an oven. The lounge room photograph clearly shows the
flooring (wooden floorboards) – the floorboards appear to be dry and there is a
“shiny” appearance to the floor depicted in the photograph.
[40] Mr Gary Kuhn (building contractor) inspected the house with Mr Benn in 2008
prior to its relocation. Mr Kuhn provided a written statement dated 29 April 2010
(tendered at the hearing) and gave evidence during cross-examination (by Mr
Sheridan) at the hearing.
[41] Mr Kuhn states (in his written statement) that the house appeared to be in “good
condition and structurally stable”. Mr Kuhn states that (in September 2008) he
saw “no obvious evidence of water damage to the ceiling”, he did not recall any
“defects” to the wall and the floor “felt solid” and he did not “detect any rotten
floor boards”.10 Mr Kuhn states that the exposed rafters and gutters showed
“signs of some rot” and were in “poor condition” and that this was “minor work
only”.11 Mr Kuhn refers (in his statement) to the quality of the floorboards. He
states that the flooring was in good condition and “would come up well with
8 Exhibit 4, [17].
9 Letter from Bundaberg Sugar to Mr Jason Benn dated 16 September 2008, attachment 5,
Exhibit 15.
10 Statement of Gary Kuhn, dated 29 April 2010, Exhibit 8, [6].
11 Exhibit 8, [7].
-- 6 of 28 --
7
sanding and polishing” and that only the central room floor showed signs of
polishing.12
[42] Mr Kuhn also inspected the house after its relocation. Mr Kuhn states that in
mid March 2010 the floors showed “signs that it had been wet. The nail heads
were rusty and a ring had formed around the top of the nails”.13 Mr Kuhn
provided a quote to Mr Benn for work to the floor of the house and this included
removal of the kitchen cupboards and bathroom fittings “so as to carry out the
job properly”.14
[43] During cross-examination Mr Kuhn conceded that he did not walk around every
square metre of the house. He stated, however, that you could look underneath
the house and if the floors were rotten you would feel movement in the boards.
Mr Kuhn stated that the condition of the house for its age was “quite good” and
that even in the bathroom there was “no rot”. Mr Kuhn stated that he did not
recall the condition of the carpet but did recall that the linoleum was “well aged”.
[44] Mr Kuhn refers to the rafters near the gutters as showing signs of “rot” and that
the gutters were in poor condition. Mr Kuhn does, however, corroborate the
evidence given by Mr Benn that the house appeared to be in good condition and
structurally stable. The Tribunal accepts the evidence of Mr Kuhn in relation to
the quality of the house prior to relocation and the observations made by him
after the house was relocated (in relation to water damage).
[45] Mr Graeme Arthur Coates (electrical contractor) also inspected the house with
Mr Benn (in March 2009) prior to relocation. Mr Coates prepared a statement
dated 29 April 2010 (tendered at the hearing) and gave evidence by telephone
(with leave) and was cross-examined at the hearing.
[46] Mr Coates states that when he inspected the house in March 2009 “the structure
looked generally dry and dusty”. Mr Coates inspected the house again on
10 May 2009 and provided a quotation to Mr Benn for the reconnection of the
power supply. Mr Coates states “due to the extensive water damage throughout
the house which was not evidenced during the initial inspection…” additional
work is required including rewiring and replacing light fittings.15 Mr Coates did
not inspect the roof battens and rafters, however, he states that the structure
looked “generally dry and dusty”.
[47] Mr Coates also states that on 10 May 2009 when he inspected the house that
the two halves (of the house) were not joined – “a tarpaulin was loosely attached
to the roof and [he] could see water damage down the walls, light fittings, ceiling
fans and power points”.16
[48] Mr Coates stated during oral evidence that the quotation provided to Mr Benn
included additional work (approximately 2 days) to rewire and replace light
12 Exhibit 8, [7].
13 Exhibit 8, [10].
14 Exhibit 8, [13].
15 Statement of Graeme Arthur Coates dated 29 April 2010, [9], Exhibit 16.
16 Exhibit 16, [10].
-- 7 of 28 --
8
fittings and that originally he was going to reconnect all circuits and this would
have happened had there been no water damage.
[49] Ms Suari Mason also states, in her statement dated 2 July 2010, that Mr Myles
informed her and Mr Benn in January 2009 that the house was “a little beauty”
and that the house would only need “[a] prep and repaint and the floor was
suitable to sand and polish”.17
[50] The Tribunal accepts the evidence given by Mr Coates about the quality of the
house prior to relocation and observations in relation to the “water damage”
during his inspection of the house on 10 May 2009. Mr Benn does not dispute
the fact that the house required some renovation work after relocation. The
evidence of Mr Benn in relation to the condition of the house is supported by the
evidence of Mr Coates and Mr Kuhn.
[51] The Tribunal is satisfied, based on the evidence of Mr Kuhn, Mr Coates and Mr
Benn, and its own observations made about the photographs (tendered at the
hearing), that the condition of the house prior to relocation was good with the
exception of some renovations to be undertaken by Mr Benn (not disputed) to
the house.
Evidence of Mr Myles (re water damage)
[52] On 17 or 18 March 2009 Mr Myles transported the first half of the house (to El
Arish). Mr Myles states that the stairs were inside the house – “the weather was
fine and so I did not cover the house with tarp at the time as I expected I would
be returning with the second part of the house that same day”.18
[53] Mr Myles was not, however, able to transport the second half of the house that
same day due to his trailer breaking down during the move – the hydraulic rams
required replacing/repair.
[54] Mr Myles attributes the failure of his machinery to the site being “very boggy
which put an additional strain on the truck”. Mr Myles states that it was the
responsibility of Mr Benn to provide access “on and off site” and Mr Benn was
therefore “partly responsible for the trailer breakdown and subsequent delays as
the site was in a very wet and boggy condition which put extra strain on [his]
truck”.19
[55] Mr Myles “determined” that it was not safe to remove the house (second half)
from the broken down trailer and for “safety and precautionary reasons” decided
to leave the house on the trailer.20
17 Exhibit 7, [17]. Mr Myles states (in his statement dated 4 June 2010, Exhibit 10) that the
reference to “little beauty” was in relation to the “ease” at which he could cut the house for
relocation (at [55]).
18 Exhibit 10, [28].
19 Exhibit 10, [29].
20 Exhibit 10, [30].
-- 8 of 28 --
9
[56] Mr Myles states that he went back to El Arish to place a tarpaulin over the first
half of the house shortly after the trailer broke down. Mr Myles states that he
used a “brand new tarp and tied it down with rope and nails at several places”.
Mr Myles did not use sheets of iron to hold it down because he states, “there
was no sheets of iron available”.21
[57] Mr Myles states that he also placed a “brand new tarp on the second half of the
house which was on the truck” and that it was only the “top part of the house that
needed tarps”.22
[58] The second half of the house remained on the trailer until 7 April 2010 when the
repairs to the trailer parts were completed. My Myles states that he did not tell
Mr Benn that it would take 2 to 3 weeks for the truck to be repaired as he did not
know how long the repairs would take – the parts had to come from Brisbane.23
[59] Mr Myles does not dispute that Mr Benn wanted the second half of the house to
be moved as soon as possible and states that he started to relocate the second
half of the house on 10 April 2010 (Good Friday). Mr Myles states that he does
not recall, “what the weather was like at the time”.24
[60] Mr Myles states that upon arriving at El Arish (on 10 April 2009) he “fully tarped
the roof and tied it down with at least 6 ropes” and “secured nails into each
eyelet”.25
[61] Mr Myles does not dispute that Mr Benn requested, “on a number of occasions”
to refit the tarpaulins due to rain and winds and that he, “complained that the
tarps were shredded”. Mr Myles states that he sent his workers (Callan and
Robert) to check the tarpaulins at the site and states that Callan told him that
“either Mr Benn had unfastened the tarp or a worker under the control of Mr
Benn’s had unfastened the tarp due to working on the extension”. Mr Benn
contends that Mr Myles did not take any steps to adjust the tarps and did not
take any steps to “lessen the water damage that he claims [Mr Myles] caused”.26
[62] Mr Myles stated during cross-examination that there were “lots of holes in the
roof” but admitted that the house had a “full ceiling”.
[63] Mr Myles also stated during cross-examination that he knew he would take time
off work (over the Easter break) when he relocated the second half of the house
on 10 April 2009. Mr Myles also had other work on during April 2009. Mr Myles
did not dispute that there was a period of time from early April to 9 June 2009
(on 9 June 2009 Mr Myles told Mr Benn he could put the roof on) that Mr Benn
“had to wait”.
21 Exhibit 10, [31].
22 Exhibit 10, [31].
23 Exhibit 10, [32].
24 Exhibit 10, [34].
25 Exhibit 10, [35].
26 Exhibit 10, [40].
-- 9 of 28 --
10
[64] Mr Myles also stated that one of the tarpaulins used to cover the roof of the
house was brand new. Mr Myles states that he sent his workers to look at the
tarpaulins when he received complaints from Mr Benn that there were holes in
the tarpaulins.
Evidence of Mr Benn (re water damage)
[65] Although the contract was signed on 6 January 2009, Mr Benn “did not mind”
that there was a delay to commence relocation (on 18 March 2009). Mr Benn
states that there was rainfall during that time and he had been advised by Mr
Myles and his workers that they were making the stumps for the relocated house.
[66] Mr Benn denies that the truck (on 18 March 2009) was “bogged down” during
the breakdown and states that he was “never informed of any access issues at
the Mourilyan site”.27
[67] On 19 March 2009 Mr Benn was informed by Mr Myles that it would take four
weeks for the rams to be fixed and Mr Benn states he requested Mr Myles get
another trailer. Enquiries were made (by Mr Benn and his wife) to use another
trailer (belonging to Mr Allan Damon). Mr Myles informed Mr Benn that a further
payment of $8,000.00 was required for the hire of Mr Damon‟s truck to move the
second half of the house. Mr Benn states that he offered to pay a company,
Coastal Fluid Power, to fix the rams to avoid any delay.28
[68] Mr Benn states that on 21 March 2009 he also requested that Mr Myles “do
something about the other side (the first half) of the house” as he was concerned
about the roof as there had been some rainfall.29
[69] Mr Benn does not dispute that Mr Myles used a tarpaulin to cover the roof of the
house (relocated) but states that the tarpaulins used were not of “industrial
quality”, were “poorly fitted”, tied down by ropes that would “continually let go
and the tarp came off several times”.30 Mr Benn states that Mr Myles did not use
the old sheets of iron to secure the tarpaulin (as requested).
[70] On 1 April 2009 the roof materials arrived and Mr Benn states that he stored the
materials in the farm shed – he could not refit the roof until relocation of the
other house and Mr Myles completed the cyclone upgrades.
[71] Mr Benn claims that he and his wife refitted the tarpaulin on many occasions.
Mr Benn states that Mr Myles nailed battens to the tarpaulin on the roof of the
house at El Arish on 9 May 2009. The tarpaulin on the roof of the house left on
the truck had “no such angled tarps to let out water”.31
[72] During the period 8, 9 and 10 April 2009 the surrounding area received 107mm
of rain. Mr Benn states that when the second half of the house arrived it was
27 Exhibit 4, [24].
28 Exhibit 4, [67].
29 Exhibit 4, [63].
30 Exhibit 4, [18], [27].
31 Exhibit 4, [18].
-- 10 of 28 --
11
covered with “a small tarp only”. The tarpaulin covered the two bedroom ceilings
only and “filled up with water and sat inside the ceiling cavity like a swimming
pool”.32
[73] Mr Benn states that during relocation of the second half of the house he had a
tractor and train ready to assist Mr Myles with transporting the house “on to the
pad” as the weather conditions had caused the truck to lose traction. Mr Benn
states that the second half of the house was left “as it was without trusses back
in place and without the open side being protected”.33
[74] On 10 April 2009 (Good Friday) the house arrived (according to Mr Benn) in “the
middle of a rain squall, water had already started pooling in the ceiling and was
dripping down the walls”.34 As the “small tarp was lying in the ceiling cavity and
full of water”, Mr Benn states that he had tried to lift the tarpaulin to enable the
water to “run off” rather than forming pools of water. Mr Benn states that the
house was left with trusses temporarily in place and a tarpaulin over them.
[75] Mr Benn alleges that he telephoned Mr Myles (on 12 April 2009) and requested
that he “tip the truck slightly so the water could run out”. Mr Benn states that Mr
Myles was unable to do this as “all staff were off on leave”. Mr Myles stated that
“she‟ll be right, these old houses can take a lot of water”.35
[76] Mr Benn and his wife removed the floor coverings out of the house to stop water
from soaking into the timber floor in an attempt to minimise water damage. Mr
Benn also took photographs of the inside of the house.
[77] The surrounding area received further rain – Mr Benn states that between 12
and 14 April 2009 there was approximately 150mm of rain. Mr Benn states the
house was drenched with 370mm of rainfall from the time it was on site.36
[78] Mr Benn states that he attempted to “tie” down the tarpaulin (again) on 12 April
2009 and Tuesday, 14 April 2009.
[79] On 24 April 2009 the two halves of the house were put in place (“chocked”) but
not joined and a tarpaulin was again placed over the roof. Mr Benn states that
there was no iron to help “prop up the tarp and help prevent rain entering the
building”.37
[80] Mr Myles did not return to complete the works (re-joining and cyclone upgrading)
on 29 April 2009 (Mr Benn states “as promised”).
[81] On 2 May 2009, Mr Benn states that the tarpaulin was “off the house twice”. He
states that “large holes were ripped in the tarp and there was water still all
32 Exhibit 4, [74].
33 Exhibit 4, [77].
34 Exhibit 4, [79]
35 Exhibit 4, [82].
36 Exhibit 4, [85].
37 Exhibit 4, [88].
-- 11 of 28 --
12
through the house”.38 Mr Benn states that Mr Myles told him he would send his
workers (to fix the tarpaulin).
[82] During the period from 5 May 2009 to 12 May 2009, Mr Benn states that he had
discussions with Mr Myles (on 5 May 2009) in relation to the water penetration.
Mr Benn states that Mr Myles informed him “that‟s what ya get in the tropics, it‟s
a tropical climate”.39
[83] Mr Benn states that on 7 May 2009 the water damage continued (there was
further rainfall) to the internal parts of the house and he again attempted to
contact Mr Myles.
Exclusion of liability for water damage (the exclusion clause)
[84] There is an exclusion clause in the general conditions of the contract. It
provides that “any water damage to house whilst roof is off” is “not included in
contract price”.
[85] The Tribunal has considered the written submissions filed and oral submissions
made by counsel (at the hearing) in relation to whether the contract provides Mr
Myles with an exclusion of liability for any water damage to the house (as
alleged).
[86] In the decision of Darlington Futures Ltd v Delco Australia Pty Ltd40 the High
Court of Australia held that:
interpretation of an exclusion clause is to be determined by construing the clause
according to its natural and ordinary meaning, read in the light of the contract as
a whole, thereby giving due weight to the context in which the clause appears
including the nature and object of the contract, and, where appropriate,
construing the clause contra proferentem in case of ambiguity.41
[87] That is, in “interpreting” the exclusion clause, the Tribunal must consider the
contract (in writing) and the context in which it was prepared including the nature
of the works to be performed by Mr Myles, to determine its objective purpose
with respect to the contract.
[88] Mr Sheridan of counsel, on behalf of the respondents, argues that the exclusion
clause brings to the attention of Mr Benn that there is no liability for any water
damage.
[89] Mr Ryall of counsel, on behalf of Mr Benn, argues that in determining the terms
of the contract it is necessary to consider the relevant facts and objective
purpose of the contract.42 Furthermore it is argued that the exclusion from
liability in relation to water damage would only have effect to the extent that such
38 Exhibit 4, [91].
39 Exhibit 4, [98].
40 (1986) 161 CLR 500.
41 (1986) 161 CLR 500, p 8.
42 Applicant‟s Outline of Argument, [8]. See Darlington Futures Ltd v Delco Australia Pty Ltd
(1986) 161 CLR 500.
-- 12 of 28 --
13
water damage did not arise from a breach of the statutory warranty as provided
under s 44 of the Domestic Building Contracts Act 2000 (DBCA).43
[90] Mr Ryall submits that the exclusion clause ought not apply to any damage
because: 44
1) the majority of the damage occurred after the time the need to have the
roof removed for transport had passed;
2) the tarpaulins were not fixed in an appropriate way or were not of the right
size or quality;
3) the tarpaulins once damaged with holes were not replaced and this was a
breach of the implied obligation to use good quality materials;
4) the work was poorly scheduled delaying the time during which the roof
could be replaced.
[91] The contract dated 6 January 2009 provides that the following items are
included in the contract price:
House prepared for relocation
House relocated
Sited/levelled
Restumped
Cyclone upgraded
All costs of police, pilot and ergon escorts arranged by AJ Myles & Co
BSA insurance
Transit insurance
[92] The Tribunal has considered the wording of the exclusion clause in the context
of “items” to be included in the contract and the representations made by Mr
Myles to Mr Benn in relation to the work to be carried out by him (relocation).
[93] Mr Myles, on his own admission, agreed to “put tarps” on the roof once the roof
was removed. Mr Myles states (in his written statement) that he told Mr Benn on
site prior to relocation of the house that “we will endeavour to limit the amount of
rain or water that gets into the house by putting tarps on the roof once it is
removed, but it is not possible to stop this entirely”.45
[94] Mr Benn states that he “wanted [Mr Myles] to quote on a complete house
relocation with the only difference to the existing building to lower the height
from highest to 800mm off the ground, refit the stairs and realign the rear roof”.46
[95] Mr Benn states that in January 2009 he asked Mr Myles about what he had to
do once he had “finished [the work]” and Mr Myles replied, “nothing, when we
are finished you don‟t need to do anything, you put on the new roof”.47
43 Applicant‟s Outline of Argument, [9].
44 Applicant‟s Outline of Argument, [15].
45 Exhibit 10, [12].
46 Exhibit 4, [5].
47 Exhibit 4, [19].
-- 13 of 28 --
14
[96] Mr Benn does not dispute that tarpaulins were placed on the roof (on the two
halves of the house) but contends that the tarpaulins used were inadequate and
(amongst others) not fitted properly to prevent water penetrating the interior of
the house during completion of the works.
[97] Mr Benn states that representations were made by Mr Myles, his son (Callan
Myles) and nephew (Robert Myles) that it would take “two weeks” to move the
house and that Mr Myles stated that “it would not take long” to move the
house.48 During cross-examination, Mr Myles did not dispute that it would be
reasonable to expect that the roof would be off the house for 3 to 5 days.
[98] The Tribunal accepts the submission made by Mr Ryall of counsel on behalf of
Mr Benn that the reference to the “roof being off” in the exclusion clause is a
reference to the roof of the house having to be removed to lower its height to
enable transport on a trailer. It is reasonable for Mr Benn to expect (at the time
of signing the contract) that Mr Myles would take care of the house and take all
reasonable steps to schedule the works to minimise the time the roof is off and
to use good quality materials (tarpaulins) during completion of the works.
[99] The Tribunal accepts the submission made by Mr Ryall that the exclusion clause
(in the contract) should not apply to any damage caused by Mr Myles‟ failure to
schedule the works so as to minimise the time the house remains unroofed, to
use good quality materials and to carry out the works as required under the
implied warranty in s 44 of the DBCA.
Alleged Breaches of Contract (water damage)
[100] The alleged breaches of contract by Mr Myles include:49
1) The delay caused by the breakdown of the trailer rams resulting in the
house being left in two parts for long periods;
2) The decision to move the second part of the house in the rain and then left
without a roof over the Easter period;
3) The failure of the contractor to replace the iron on the roof prior to leaving
to complete other work;
4) A failure to replace the roof and or provide effective cover for the house
during the rain period (when work could not be completed);
5) A failure to replace torn and damaged tarpaulins (with holes); and to
properly fix the tarpaulins.
[101] There is an implied warranty under sections 43 and 44 of the DBCA that the
work carried out by the contractor (Mr Myles) will be in accordance with “all
relevant laws and legal requirements, including, for example, the Building Act
1975” and that the work will be “carried out” in an “appropriate and skilful way”
and with “reasonable care and skill”.
48 Exhibit 4, [27].
49 Applicant‟s Outline of Argument, [14].
-- 14 of 28 --
15
[102] The Tribunal must determine whether the works completed by Mr Myles were
carried out in an appropriate and skilful way and with reasonable care and skill.
Furthermore, did Mr Benn give Mr Myles a sufficient or reasonable opportunity to
complete or rectify any defective work (as alleged).50
[103] It is not disputed that:
1) The roof of the house had to be removed prior to transportation – it was
necessary to lower the height of the house to facilitate transport on a trailer.
2) Mr Benn was responsible for reroofing the house.
3) The first half of the house was moved on 17 or 18 March 2009 (the
weather was fine).
4) The second half was moved on 10 April 2009 and was left on Mr Myles‟
truck due to concerns about possible fractures to the “footing holes”.
5) Mr Myles commenced joining the 2 external sides of the house on 19 May
2009, and installation of the roof was completed (by Mr Myles) on 19 June
2009.
6) On 22 May 2009, Mr Benn referred certain issues he had in relation to the
work to be performed by Mr Myles to the Queensland Building Services
Authority (QBSA).
7) There was rainfall during the completion of the works in Mourilyan and El
Arish – in early February 2009, early/mid March 2009, early to mid April
2009 and in May 2009.51
[104] The Tribunal does not accept Mr Myles‟ argument that Mr Benn is responsible
for the breakdown in the machinery on 18 March 2009 which caused the delay in
transporting the second half of the house.
[105] The Tribunal prefers the evidence of Mr Benn that he was not informed about
any “access” issues at the time of relocation (on 17 March 2009). Mr Benn gave
evidence that he assisted Mr Myles with transporting the second half of the
house on 10 April 2009. Mr Benn states “I had to tow the truck with the house
on it into place with a farm tractor as the rain caused the truck to lose traction.
The truck was never bogged down, just unable to move effectively due to loss of
traction on hard slippery clay surface”.52
[106] Mr Myles does not dispute that Mr Benn wanted the second half of the house
relocated as soon as possible and he was able to successfully transport the first
half of the house (on 18 March 2009) without any “access” issues (to the site).
50 See Scott Building Pty Ltd v Minogue & Coal Basin Equipment Pty Ltd [2010] QCAT 420.
51 Australian Government Bureau of Meteorology, Daily Rainfall for 2009 (South Johnstone),
attachment C6, Exhibit 4. There are also rainfall statistics for the Mourilyan and El Arish areas
attached Exhibit 14.
52 Exhibit 4, [24].
-- 15 of 28 --
16
[107] The Tribunal has also considered the photographs taken by Mr Benn of the
house (at the Mourilyan site) on 16 March 2009 prior to the first half of the house
being transported. The site appears to be dry and there is green grass
surrounding the house.53
[108] The Tribunal finds that the breakdown of the trailer delayed relocation and
extended the time during which the house was left unroofed and exposed to
possible water damage from the rainfall. Mr Myles does not dispute that he had
time off and other work over Easter (April 2009). The Tribunal finds that this
again delayed relocation and completion of the contracted works (i.e. re-joining
of the house).
[109] Mr Benn alleges the house was damaged by water (rainfall) in March 2009,
during the Easter break (mid April 2009) and on 5 May 2009, as a result of the
tarpaulins blowing off. The tarpaulins were, however, replaced according to the
evidence of Mr Callan Myles.
[110] There is conflicting evidence about the quality of the tarpaulins used to cover the
house (the two halves) and whether the tarpaulins were properly and securely
fixed as to the prevent water penetration and damage to the house.
[111] Callan (Mr Myles‟ son) corroborates the evidence given by Mr Myles that the
tarpaulins used were of good quality and were large enough to cover the roof of
the house. Callan states “we placed and secured tarps on this house like every
other, however with the heavy rain and squalls it is almost impossible to stop
everything that ‘mother nature threw at it’. I used the best of my ability to keep
the tarps tied down”.54
[112] Callan states that he attended the site (El Arish) on at least 3 occasions after
relocation to “adjust the tarps which had moved due to heavy rain and wind…on
each occasion the tarps were intact and I only needed [to] refasten small
sections of the tarp that had come loose”.55 Callan also refers to attendances at
the site when he noticed the ropes used to tie down the tarpaulin had been
untied and that work had commenced on the house (construction of an
extension) and that rain could enter the unprotected area.56
[113] During cross-examination Callan did not dispute that one of the photographs
taken by Mr Benn of the tarpaulin showed a hole. When questioned about
whether he knew the tarpaulin was ineffective and that water was getting
through the tarpaulin, he stated that during the months of April and May 2009
they “did their best”.
[114] Robert (Mr Myles‟ nephew) also gave evidence about the quality of the
tarpaulins used to cover the house. Robert states that after relocation of the first
half of the house to El Arish the old roofing materials were removed to perform
53 Exhibit 5, p 9.
54 Exhibit 14, [31].
55 Exhibit 14, [32].
56 Exhibit 14, [33].
-- 16 of 28 --
17
cyclone upgrades and two-thirds of the iron was left on the house. A new
tarpaulin was purchased (from a local store and placed over the roof). Robert
states “[Mr Myles] appeared later that day or the following morning and gave to
me the industrial tarps that was then used to replace the other tarping. It
covered the entire area and securely tied down and secured into place”.57
[115] Robert, during cross-examination, agreed that the roof could not be fitted until he
had finished the cyclone upgrades. Robert did not deny that the tarpaulin had
holes and stated that this was “mainly from ripping off the roof”. Robert stated
that they tied the tarpaulins back down.
[116] Mr Coates also gave evidence about the tarpaulin on the house, during his
inspection on 10 May 2009 (at El Arish) and states that the tarpaulin was
“loosely attached” to the roof.
[117] The Tribunal prefers the evidence of Mr Benn about the quality of the tarpaulin
used to cover the first half of the house after relocation (to El Arish), that the
tarpaulin was too small, was not fitted properly and was damaged (ripped). Mr
Benn refers to several occasions when he says he attended to refitting and re-
tying the tarpaulin and dates of when he says he informed Mr Myles about his
concerns – on 21 March 2009 (concerns raised with Mr Myles), on 12 April 2009
(tie down of tarpaulins by Mr Benn), 14 April 2009 (tie down of tarpaulins by Mr
Benn), 2 May 2009 (tarpaulins off house), 5 May 2009 and 12 May 2009
(discussions with Mr Myles about the tarpaulins).
[118] Mr Benn gave evidence at the hearing that he used his own rope to tie down the
tarpaulin to prevent lifting, as the tarpaulin was “short” on one side. A
photograph taken by Mr Benn on 9 May 2009 (tendered at the hearing58) shows
the tarpaulin tied down by green rope. Mr Benn referred to other photographs
taken by him in early and mid May 2009 which show the tarpaulin (on the first
half of the house) ripped with holes and the tarpaulin left on the second half of
the house which Mr Benn was also inadequate as water pooled in the centre of
the tarpaulin as a result of the rainfall.59
Cyclone Upgrades (alleged breach of contract)
[119] The contract included “cyclone upgrading” and was therefore was contracted
work to be performed by Mr Myles.
[120] In November 2008 plans were prepared for certification to enable Mr Benn and
his family to live in the house once relocated. The building designer provided in
the plans for the installation of cyclone rods – a method of cyclone upgrading.
[121] Mr Benn states that Mr Myles recommended an alternative tie down method –
because of the “tongue and groove timber” the cyclone rods method would look
57 Statement of Robert William Myles dated 22 June 2010, Exhibit 13, [20].
58 Exhibit 5, p 12.
59 Exhibit 5, pp 12, 13.
-- 17 of 28 --
18
“ugly”. Mr Benn states that Mr Myles indicated he would speak to “the engineer”
about the tie down method and would “get back to [him]”.60
[122] Mr Myles agreed, during cross-examination, that it was his job to ensure that the
roof and the rest of the house was upgraded according to the plan (details in the
drawings). However, Mr Myles contends that there was a variation to the
contract with the approval of Mr Gianarakis which provided for an alternative
method of tie down instead of cyclone rods.61
[123] Mr Benn argues that he did not receive any contract variation documents in
relation to an alternative tie down method and that Mr Myles delayed in carrying
out the cyclone upgrading and that the works carried out were defective and
incomplete.62
[124] The incomplete and defective works included (as alleged) – split rafter blocks
under batten joints, poorly fitted cyclone straps, ceiling rafters that had been cut
during the relocation process and not re-joined, and the installation of batten
joints without rafter blocks. Mr Benn claims rectification expenses in the amount
of $4,757.00 (inc GST).63
[125] Furthermore, Mr Benn argues that the plans which formed part of the contract
required Mr Myles to install 24 cyclone rods and Mr Myles has failed to give
credit or to make an adjustment of the contract price in Mr Benn‟s favour on the
basis that the alternative method of tie down (as opposed to installation of
cyclone rods as required under the contract) attracted a saving of $2,860.00.
[126] The following evidence is relevant to this issue:
1) There was an inspection by Mr Crawford on 5 June 2009. Mr Benn and
Callan attended the inspection. A compliance inspection report was
issued on 5 June 2009 (No. 01114) listing further work required to comply
with the development permit.64
2) On 10 June 2009 Mr Benn (as owner builder) and Mr Dave Bevan (Unique
Roofing) fitted fascia and gutters to the house prior to reroofing.
3) On 15 June 2009 Mr Myles completed further works (cyclone upgrading).
Mr Bevan was present during the works when an issue arose about the
quality of the battens – Mr Bevan dropped one of the battens to the ground
to demonstrate its poor condition. Robert (Mr Myles‟ nephew) gave
evidence that he cannot dispute that some of the battens broke apart
60 Exhibit 4, [35].
61 Mr Gianarakis in his report dated 23 August 2010 (Exhibit 2) states that Rob Wolf Designs
amended the plans for the “tie down” method and approved the plans on 20 May 2009 (at
[4.2]). The report of Mr Gianarakis provides that Mr Myles used the tie-down method with
additional nailing of Vee-J wall boards also referred to in the report of Mr Gary Thompson,
Exhibit 9, [28].
62 Applicant‟s Submissions dated 17 May 2010, [24].
63 The amount claimed is based on the agreed costing (joint expert report), Exhibit 10 and
Exhibit 4, [48].
64 Attachment C3, statement of Jason Benn dated 4 May 2010, Exhibit 4.
-- 18 of 28 --
19
when they were thrown onto the ground to reveal that they were rotting on
the inside.65
4) On 16 June 2009, Mr Benn completed a number of repairs to the house
frame – battens and rafter ends and cyclone straps. 66 Mr Crawford
inspected the site.
5) On 19 June 2009 a new roof was fitted to the house by Mr Benn (as owner
builder) with Mr Bevan.
6) On 22 July 2009, the QBSA (Billy Courtney) inspected the site.
7) On 25 June 2009, Mr Benn wrote to Mr Myles (AJ Myles & Co) requesting
that he attend to outstanding floor upgrades to enable the building to
comply with cyclone upgrades.67
8) On 7 August Mr Gianarakis (CMG Consulting Engineers) inspected the
site and provided a handwritten report on work to be completed. Mr Myles
completed the work on 20 August 2009 and on 1 and 2 September 2009,
the wall bracing was completed. 68 Mr Gianarakis in his report dated
23 August 2010 states that his inspection on 7 August 2009 identified “a
number of items requiring completion and or rectification. This work has
been carried out and is structurally adequate”.
9) On 20 August 2009 Mr Myles completed work required by CMG (except
for wall bracing).
10) On 1 September 2009 the tie down and bracing was completed.
11) On 16 September 2009 Mr Gianarakis issued an inspection certificate
(Form 16) in relation to the sub-floor framing, roof upgrade framing and
bracing.
[127] There is conflicting evidence about what was agreed between the parties.
Callan (Mr Myles‟ son) gave evidence that they were waiting for Mr Benn to
indicate when the roof was to be refitted before they “upgraded” the roof. The
reason for this was so as to minimise the exposure to water – it was necessary
to remove the remaining iron on the roof. Callan states that the cyclone upgrade
involved “battening and screwing, the installation of cyclone strapping as well as
the tailing out of the rafters that had rotted away on the outside”.69 Robert
conceded during cross-examination that the roof could not be put on until he had
finished doing the cyclone upgrades.
65 Exhibit 13, [18].
66 Exhibit 4, [115].
67 Exhibit 4, Attachment B1.
68 Exhibit 4, [152].
69 Exhibit 14, [22].
-- 19 of 28 --
20
[128] Mr Myles states that in January 2009 Mr Benn “represented” to him that he (Mr
Benn) would attend to all rafter repairs, batten replacement and cyclone
strapping.
[129] The contract refers to cyclone upgrade items included in the contracted works.
Mr Myles, during cross-examination at the hearing, stated that the bracing was
not included in the contract but he “did it”.
[130] Mr Gianarakis gave evidence at the hearing in relation to the work performed by
Mr Myles. His report dated 23 August 2010 refers to the nailing of the vertical
wall lining to the bearer and states that the work “demonstrates poor
workmanship” but the nails are structurally sufficient.
[131] Mr Gianarakis states that the installation of cyclone rods would be more cost
effective for the house and the use of “vertical lining for tie-down requires all
boards to be double nailed top and bottom” and is therefore “labour intensive”.
Mr Gianarakis states that the cyclone rods would provide a “more structurally
effective tie-down”, however, each method (cyclone rods and alternative tie-
down method) is with respect to “structural adequacy” of equal preference.
[132] Mr Benn states that he completed the works (on 16 June 2009) in accordance
with Mr Matthew Crawford‟s inspection report. Mr Benn states “for this reason I
concluded extra work had to be carried out by me before the roof frame could
comply with the Council approval allowing for the roof to be fitted”.70
[133] Mr Myles argues that the repairs completed by Mr Benn were extra work and in
any event were not necessary for Council approval. Mr Myles states that he
recalls Mr Crawford saying to Mr Benn that “those repairs to the house frame
[were] not necessary for Council approval purposes, but if it were my house I
would do it”.71
[134] Unfortunately Mr Crawford was not available to give evidence at the hearing. It
is not contested, however, that Mr Benn together with Mr Bevan fitted a new roof
to the house (completed on 19 June 2009). Mr Gianarakis, in his report dated
23 August 2010 does not refer to any completed work as being unnecessary for
the purposes of certification as suggested by Mr Benn. However the Tribunal
notes that this question was not specifically put to Mr Gianarakis during cross-
examination.
[135] The Tribunal prefers the evidence of Mr Benn that Mr Crawford inspected the
work on 16 June 2009 and indicated that the roof frame was compliant and that
the extra work performed by him was necessary prior to re-roofing. The Tribunal
finds that cyclone upgrades included all necessary work to enable certification
and was work to be performed by Mr Myles and this included the installation of
cyclone rods as per the contract plans. The amount claimed by Mr Benn in
relation to the extra work performed is therefore allowed in the amount of
$4,757.00 (inc GST).
70 Exhibit 4, [46].
71 Exhibit 10, [52].
-- 20 of 28 --
21
[136] The Tribunal is not satisfied, however, that Mr Benn is entitled to a deduction or
saving for the alternative tie-down method used (in lieu of cyclone rods). Mr
Gianarakis states (in his report dated 23 August 2010) that the installation of
cyclone rods would be more cost effective and the tie-down method is more
labour intensive. Mr Benn has claimed an amount for the incomplete work and
his claim has been allowed (in full).
Costs to complete works
[137] On 19 May 2009 Mr Myles commenced work on joining the external sides of the
house but not the internal sections. Mr Myles (in his statement dated 4 June
2010) states that he joined the external sides of the house and the internal
ceilings.
[138] There is reference to the “bracing” including the re-joining of internal and
external walls where they have been cut for the house to be relocated in the
report of Mr Gianarakis (date 23 August 2010). Mr Gianarakis states that he has
viewed photographs supplied by Mr Benn which show “misalignment and gaps
in the join of the internal wall. These have subsequently been covered with a
timber quad section and filler to rectify the aesthetics”.72
[139] Mr Benn contends that it was an implied term of the contract that Mr Myles
would relocate and reinstate the house and that Mr Myles would “adequately”
join (the house) both externally and internally.
[140] Mr Benn states that Mr Myles told him during contract negotiations that he would
“re-join the house and place strips on all cuts, make a join in the floor boards
that would be hardly noticeable”.73
[141] Robert (Mr Myles‟ nephew) refers to a conversation that he says took place
between Mr Myles and Mr Benn, prior to relocation – Mr Benn stated (allegedly)
that he would replace the ceiling sheeting with VJ to match the rest of the
veranda. Mr Benn disputes this.
[142] The Tribunal prefers the evidence of Mr Benn that it was an implied term of the
contract that Mr Myles would re-join the house both internally and externally. Mr
Benn has been consistent in his evidence as to the representations made by My
Myles prior to relocation that all he was required to do (after relocation) was to
re-roof the house.
[143] The Tribunal finds that the amount claimed by Mr Benn for completion of the re-
joining of interior walls in the amount of $825.00 (inc GST) is therefore allowed.
[144] Mr Benn also claims an amount for incomplete work relating to re-fitting the
stairs, re-aligning the roof and fitting of piers to the pantry on the basis that this
72 Report of Charles Gianarakis dated 23 August 2010, Exhibit 2.
73 Exhibit 4, [153].
-- 21 of 28 --
22
was work that formed part of the contract. Mr Myles disputes this and argues
that he has complied with his contractual and statutory obligations.
[145] The Tribunal has made findings of fact about Mr Benn‟s evidence in relation to
the contracted works to be performed by Mr Myles. Notwithstanding those
findings and a preference for Mr Benn‟s evidence in relation to discussions that
took place prior to relocation of the house (in March 2009), there are some
unresolved issues in relation to the re-fitting of the stairs and what was agreed.
[146] Mr Benn states that it was an implied term of the contract that the stairs would
be relocated and installed. The front stairs were allegedly stolen from the
Mourilyan site – only the rear stairs were transported by Mr Myles (on 18 March
2009). Mr Myles states that Mr Benn took the front stairs to the new site (El
Arish).
[147] There was no evidence adduced by Mr Benn during cross-examination at the
hearing in relation to whether he had transported the front stairs, as alleged by
Mr Myles.
[148] Callan (Mr Myles‟ son) refers to the inspection with Mr Crawford on 5 June 2009
(in his statement dated 22 June 2010) and that Mr Crawford stated, “the stairs
must be taken down as they did not comply with Council regulations”. Mr Benn
does not dispute that he re-fitted the stairs – he removed the stairs he
“temporarily affixed and later refitted them with a landing to comply with Council
requirements”.74
[149] The Tribunal can not be satisfied based on the evidence (unchallenged) before it,
that it was an implied term of the contract that Mr Myles would fit the front stairs
and that Mr Myles was responsible for transporting the front stairs to the site (El
Arish).
[150] The Tribunal is, however, satisfied as to the remaining amounts claimed by Mr
Benn in relation to incomplete work for realignment of the rear roof and fitting
piers to pantry, and that this was work that formed part of the contract. Mr
Gianarakis (in his report dated 23 August 2010) states that re-aligning of the roof
and fitting piers to the pantry section of the house is “generally accepted practice
or standard applied to the building industry”.
[151] The amount claimed by Mr Benn based on the agreed costing (in the joint expert
report) is therefore allowed.
Rectification costs (water damage to house)
[152] The Tribunal has made findings about the condition of the house at the time of
purchase (by Mr Benn prior to relocation). The Tribunal did not accept Mr Myles‟
evidence that the house was in very poor condition.
74 Exhibit 4, [39].
-- 22 of 28 --
23
[153] The Tribunal is satisfied that the house sustained water damage as alleged by
Mr Benn during relocation (between 18 March 2009 to 10 May 2009). The
Tribunal has considered the evidence of Mr Benn and the various photographs
tendered at the hearing which clearly show water damage to the ceiling, walls
and floor.
[154] The Tribunal has also considered the evidence of Mr Coates who states (in his
report dated 29 April 2010) that he could see water damage during his
inspection of the house on 10 May 2009 to the walls, light fittings, ceiling fans
and power points.
[155] There is also evidence (reports) included in the statement of Mr Benn (dated
4 May 2010), from Mr Wayne Parfitt (ACCS) and Mr Bill Courtney (QBSA) who
make observations (in their reports) about water damage to the house during
inspections on 13 June 2009 and 22 July 2009 (respectively).
[156] The relevant authority in determining the quantum payable by a builder for
completing and rectifying the building works in accordance with the contract is
the decision in Bellgrove v Eldridge 75 where the rectification work to be
performed must be both necessary and reasonable.76
[157] The Tribunal was referred to the decision in Wheeler & Anor v Ecroplot Pty Ltd77
which held in determining the reasonableness of rectification costs that:78
In the case of a building contract such as the present the prima facie measure of
damages is the „amount required to rectify the defects complained of and so give to
[the plaintiff] the equivalent of a building on [his or her] land which is substantially in
accordance with the contract
[158] It was further held in applying the principle in Bellgrove that the work undertaken
must be necessary and reasonable where “the test of „unreasonableness‟ is [as
held in the decision of Tabcorp Holdings 79 ] only to be satisfied by fairly
exceptional circumstances”.80
[159] Mr Sheridan (of counsel) submits that it is necessary for the Tribunal to
determine whether the cost of repairs (as claimed) are reasonable having regard
to the principle in Bellgrove or whether it would be reasonable to award the cost
of replacement of a house (of equal value).
[160] Mr David Fair gave evidence about the cost of transporting a house from
Brisbane to far north Queensland. Mr Fair stated that the cost of relocation (for
a colonial style house) is $53 per kilometre distance. However, in his
experience houses are not relocated beyond a 3 to 4 kilometre, as it is very
75 (1954) 90 CLR 613 referred to in Pulitano v Mikescapes Pty Ltd [2010] QCAT 248 and
Franklin v A&S Bricklaying Service [2010] QCAT 69.
76 See Tabcorp Holdings Limited v Bowen Investments Pty Ltd [2009] HCA 8.
77 [2010] NSWCA 61.
78 Wheeler & Anor v Ecroplot Pty Ltd [2010] NSWCA 61, [80].
79 See Tabcorp Holdings Limited v Bowen Investments Pty Ltd [2009] HCA 8.
80 Wheeler & Anor v Ecroplot Pty Ltd [2010] NSWCA 61, [80], [81].
-- 23 of 28 --
24
expensive to relocate. Mr Fair also stated that colonial style houses sell very
quickly if they are in good condition and these houses are not always available.
[161] The Tribunal prefers the submissions of Mr Ryall in relation to whether it would
be reasonable to award the replacement value of the house or the reasonable
costs of repairs. Mr Ryall submits that Mr Benn and his wife wanted “this
particular house” notwithstanding that it might have been unattractive from the
outside. The Tribunal accepts the submissions made that a replacement house
would attract further delay (waiting for a suitable replacement) and costs of
relocation, cyclone upgrading and demolition and removal of the existing
(current house).
[162] The Tribunal must determine the amount of damages (rectification costs) as
claimed having regard to the agreed costing and damages claimed by Mr Benn.
[163] The agreed costing (joint expert report) includes a claim for preliminaries – an
allowance made by a builder to cover costs for such items as (amongst others)
insurance, statutory fees and charges and scaffolding. The preliminaries are
calculated using a percentage or calculated on preliminary items individually. It
is agreed between the parties that a suitable percentage for preliminaries is 16%.
[164] Mr Gavin Stewart and Mr Gary Thompson gave evidence at the hearing that an
owner builder would incur costs associated with the renovation work (i.e.
preliminaries). The Tribunal is satisfied that Mr Benn is entitled to a claim for
preliminaries at the rate of 16% as agreed.
[165] There are two proposed methods of rectification in relation to the wooden
floorboards – replacement of the wooden floors and the alternative floating floor
system method (a cheaper method).
[166] Mr Benn also claims an alterative amount of $96,860.00 (inc GST) being the
costs of removing the damaged floors in accordance with the report of Mr Gary
Kuhn (builder) dated 30 April 2010.
[167] It is not disputed that both floor systems are suitable.
[168] Mr Sheridan submits that the Tribunal should, however, prefer the least
expensive option in relation to the proposed flooring (item 20 on the agreed
costing) on the basis that there is no evidence before the tribunal as to why the
more expensive option (proposed by My Kuhn) should be preferred.
[169] Mr Ryall argues that had the contract been performed properly Mr Benn would
have had a timber floor with floorboards. It is therefore reasonable to claim for
the cost of a replacement floor system as quoted by Mr Kuhn.
[170] The Tribunal prefers the submissions made by Mr Sheridan in relation to the
reasonableness of the amount claimed for the preferred floor system.
[171] There is evidence before the Tribunal being the joint experts report dated
21 September 2010 and the report of Mr Gavin Stewart dated 18 October 2010
-- 24 of 28 --
25
which addresses the issue of preferred floor system. The experts (Mr
Thompson, Mr Stewart and Mr Gianarakis) state “CG (Mr Gianarakis) advised
that both [floor] systems were suitable for the intended application”.
Furthermore, Mr Thompson in his report dated 15 March 2010 states that he, Mr
Thompson and Mr Gianarakis “investigated some alternative products that could
be laid on top of the existing floor that was reported to be structurally sound”.
[172] The Tribunal finds that the alternative floor system (item 19 referred to in the
joint expert report) should be allowed in the amount of $34,609.00 (plus GST).
[173] In relation to the claim for electrical expenses, Mr Coates gave evidence at the
hearing about the quote provided in the amount of $4,235.00. Mr Coates stated
that the amount included replacing wires in the roof, rewiring of lights and
switches and replacing lights, fans and power points. Mr Coates stated that had
there been no water damage to the house he would have reconnected all the
circuits.
[174] The Tribunal accepts the evidence of Mr Coates in relation to electrical
expenses necessary to replace wires, rewiring and replacing of lights and that
such costs are reasonable in the amount of $4,235.00 (plus GST).
[175] The Tribunal accepts the evidence of the joint experts in relation to the
remaining items listed in the agreed costing having found that there was water
damage to all areas of the house (walls, ceilings and floors) and finds that the
amounts claimed in relation to items numbered 7, 8, 10, 11, 14, 21, 22, 23, 24,
25 and 26 are reasonable:81
Additional rental expenses
[176] Mr Benn seeks leave to amend his claim to include additional expenses incurred
while he waited for the house to become habitable. Mr Benn claims the amount
of $6,460.00 for 34 weeks at the rate of $190.00 per week. Mr Benn relies on
his own evidence in support of the claim.
[177] The Tribunal is not satisfied on the evidence that Mr Benn has incurred
additional expense (rent) for reasons attributed solely to Mr Myles.
[178] There is evidence before the Tribunal to indicate that during completion of the
contracted works Mr Benn was also undertaking additional works (as owner
builder) to the house – installation of a large septic system and trenches,
construction of a large carport shed. 82
[179] The Tribunal is not satisfied that the delays in reaching practical completion
were solely attributable to Mr Myles or whether it was in fact necessary for Mr
Benn to complete the additional works prior to occupation and whether it was
81 Agreed costing, Exhibit 3. Items are exclusive of GST. The Tribunal refers to the report of Mr
Gavin Stewart dated 18 October 2010, Exhibit 18, which provides further clarification as to the
findings made in relation to the water damage to the house (at [2]). Item 9 of the schedule
refers to “sanding” which is included in item 19.
82 Memorandum of Billy Courtney (QBSA) undated, attachment C1, Exhibit 4.
-- 25 of 28 --
26
therefore necessary to make alternative arrangements for living (rental
expenses) while the owner builder works were being completed.
[180] Notwithstanding the finding that Mr Benn was completing additional works, there
is no evidence before the Tribunal evidencing expenditure of the rental
expenses. The claim for rental expenses is not allowed.
Claim for distress and inconvenience
[181] Mr Benn claims an amount of $10,000.00 for distress and inconvenience as a
result of Mr Myles‟ breach of contracts and the warranties, inconvenience and
distress and anxiety.
[182] Mr Ryall, in written submissions, refers to the decision in Pearce t/a Freestyle
Projects v Caswell.83
[183] In the decision of Pearce an award of $2,000.00 for compensation was allowed
to represent the “distress” that arose as “a direct result of the situation with the
[builder] in terms of the defective work, the need to involve the BSA, the need for
extensive rectification, and the significant delay in the completion of their dream
home”.84
[184] Mr Myles and his wife (Suari) have given evidence about the distress and
inconvenience caused by the delay in relation to the relocation of the house, the
damage to the house caused by water penetration and the need to undertake
work not completed by Mr Myles including completion of cyclone upgrades and
re-joining of the house.
[185] The Tribunal finds that it is appropriate that Mr Benn receive some nominal
compensation for his distress, inconvenience and loss. The Tribunal will allow
the amount of $2,000.00.
Entitlement to final progress claim (money owing to Mr Myles)
[186] The commencement date of the contract is disputed. Mr Myles argues the start
date of the contract was 18 March 2009 and Mr Benn argues it was 6 January
2009. The issue is relevant as to the date for practical completion (135 days
from the date of commencement).
[187] Mr Myles contends that the works were practically completed on 20 August 2009
and Mr Benn argues that Mr Myles is yet to bring the works to practical
completion.
[188] Mr Myles, during cross-examination at the hearing, stated that during the period
from 6 January 2009 to 18 March 2009, there was preparation of the house prior
to its relocation on 18 March 2009 (first half of the house). Mr Myles also states
83 [2009] QCCTB 192. Also see Paans v Phil Martyn Constructions Pty Ltd & Tamawood
Homes Pty Ltd [2004] QCCTB 111.
84 [2009] QCCTB 192, [93].
-- 26 of 28 --
27
(in his statement dated 4 June 2010), that he started some “preparatory work on
site prior to 16 January 2009”.85
[189] Mr Benn states that on 15 January 2009 he paid $14,400 to AJ Myles & Co as
required under Item 10 of the contract (commence works). Mr Benn states that
he did not receive all the necessary contract documents from Mr Myles as
required under the QBSA Minor Works Contract.
[190] The Tribunal accepts the evidence of Mr Myles that prior to the house (first half)
being relocated Mr Myles was undertaking preparations for the relocation. This
is consistent with the evidence of Mr Benn in that he states, “nothing much
happened with the relocation” during January and February 2009 as he had
been informed (by Mr Myles) that the stumps were being prepared for the house
relocation and there was rainfall during this time.86
[191] The Tribunal finds that the date of commencement of the contract was 6 January
2009 as provided in the contract and the date for practical completion (135 days)
was 21 May 2009.
[192] Mr Myles contends that he completed the works on 20 August 2009 and that Mr
Myles has failed to pay the final progress claim in the amount of $4,800.00.
[193] The final progress payment is due under the contract upon completion of the
works. Practical completion for a regulated contract is defined under the DBCA
as the stage when the works are completed in accordance with the contract and
relevant statutory authority without any “omissions or defects” or apart from
“minor omissions or minor defects” and the home is “reasonably suitable for
habitation”.
[194] The Tribunal does not accept Mr Myles‟ submission that the contracted works
were completed (by him) on 20 August 2009. The Tribunal has made findings
about the non-completion of contracted works and has allowed amounts (as
claimed) to complete the work. Mr Myles is, however, entitled to recover the
money owing for the works completed (by him) on the basis that Mr Benn has
had the benefit of the works, less any claim for defective and incomplete work.87
The Tribunal will allow the amount of $4,800.00 to be offset against any award of
damages payable by Mr Myles.
Calculation of damages
[195] The Tribunal has assessed damages (based on the findings made) as follows:
Preliminaries at 16%88 $17,948.68
7. Level & re-hang ceiling $ 5,190.00
8. Replace floor coverings $ 2,550.00
10. Interior walls $26,663.00
85 Exhibit 10, [23].
86 Exhibit 4.
87 See Nguyen v Luxury Design Homes Pty Ltd [2004] NSWCA 178.
88 Based on the total of the items listed below.
-- 27 of 28 --
28
11. Interior painting $10,774.00
14. Kitchen cabinets $ 7,436.25
21. French doors $ 1,608.50
22. Internal doors $ 1,608.50
23. Exterior door $ 407.50
24. External door $ 407.50
25. Casement windows $ 6,983.00
26. 5 hopper windows $ 1,018.00
13. Electricals $ 4,235.00
19. Replace damaged floors $ 34,609.00
18. Re-join interior walls $ 750.00
3. Realign rear roof $ 2,014.00
4. Fit piers (pantry) $ 1,600.00
5. Rafter end repairs $ 900.00
6. Replace battens $ 3,425.00
$130,127.93
PLUS GST $ 13,012.79
PLUS claim for inconvenience & loss $ 2,000.00
Total $145,140.72
LESS money owing to Mr Myles $ 4,800.00
$140,340.72
[196] The Tribunal orders that Mr Myles pay the amount of $140,340.72 to Mr Benn by
4.00pm on 16 December 2011.
-- 28 of 28 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2011/567