Axtens and Anor v Brooks [2011] QCAT 517
CITATION: Axtens and Anor v Brooks [2011] QCAT 517
PARTIES: Jonathan Keith Axtens
Karen Axtens
v
Michael John Brooks
APPLICATION NUMBER: BD451-06
MATTER TYPE: Building matters
HEARING DATE: 4 October 2011
HEARD AT: Brisbane
DECISION OF: Sandra Deane, Member
DELIVERED ON: 3 November 2011
DELIVERED AT: Brisbane
ORDERS MADE: 1. Mr Brooks is to pay Mr and Mrs Axtens the
sum of $7,469.00 together with interest on
the sum of $7,469.00 calculated from the
date of the Application (1 September 2006)
to the date of this decision calculated at
the rate of 10% per annum on a simple
basis by 4:00pm on 6 December 2011.
2. The Application to Correct Order 1 of
17 November 2009 is allowed.
3. Order 1 of 17 November 2009 will be
corrected to provide “The rectification
orders (being Orders 1 and 2) made by the
Tribunal on 9 March 2009 will be vacated.”
4. Mr and Mrs Axtens’ application for costs
in relation to the assessment of damages
is dismissed.
5. Mr and Mrs Axtens’ application for costs
in relation to the Application for
Correction is dismissed.
CATCHWORDS: Building Contract – swimming pool depth not in
compliance with contract – contractor ordered to
rectify – problems implementing order because
homeowners sold property before rectification
performed – application to reopen allowed –
measure of damages – entitlement to costs of
rectification or other remedy
Commercial & Consumer Tribunal Act 2003,
-- 1 of 13 --
2
s 70, 71, 96
Queensland Civil and Administrative Act 2009, ss
100, 102, 260, 271
Queensland Building Services Authority Act
1991, s 77
Bellgrove v Eldridge (1954) 90 CLR 613
UI International Pty Ltd v Interworks Architects
Pty Ltd & Ors[2007]QCA 402
Westpoint Management Ltd v Chocolate Factory
Apartments Ltd [2007] NSWCA 253
Hallett & Ors v Queensland Building Services
Authority [2011] QCAT 355
Queensland Building Services Authority v
Johnston [2011] QCATA 265
Lyons v Dreamstarters [2011] QCATA 142
Oshlak v Richmond River Council (1998) 193
CLR 72
Latoudis v Casey (1990) 170 CLR 534 at 557
APPEARANCES and REPRESENTATION (if any):
APPLICANT: Jonathan Keith Axtens and Karen Axtens
represented by Mr C Ryall of Counsel instructed
by Robert P Palethorpe, Solicitor
RESPONDENT: Michael John Brooks represented by Mr HA
Mellick Jnr of Mellick Smith & Associates,
Solicitors
REASONS FOR DECISION
Background
[1] By direction of the Tribunal dated 11 April 2011 this matter was to be
determined on the papers in accordance with section 32 of the Queensland
Civil and Administrative Tribunal Act 2009 (QCAT Act). As a consequence
of the written submissions filed by Mr and Mrs Axtens a short oral hearing
was held and the parties supplemented the written submissions with oral
submissions.
[2] This dispute relates to the construction of a domestic swimming pool. The
original contract price was $31,120. As constructed the pool was slightly
shallower than specified in the contract.
[3] Mr and Mrs Axtens, the homeowners, commenced proceedings in the
Commercial and Consumer Tribunal (CCT) on 1 September 2006 and
originally claimed $93,764.50 for rectification costs for removing and
rebuilding the pool and re-landscaping.
-- 2 of 13 --
3
[4] From an early time Mr Brooks admitted non compliance with the contract
and offered to undertake rectification works but contended that this did not
require removing and rebuilding the pool.1
[5] An alternative rectification solution was proposed in the report of Mr
Colefax of Colefax Associated Consulting Engineers dated 9 March 2007.
Mr Brooks, the swimming pool contractor, gave evidence by way of quote
dated 15 July 2008 that the costs of this work would be $5,390.
[6] The CCT originally heard this matter on 31 July 2008. On 6 November
2008 the CCT made certain findings and made directions seeking further
evidence and submissions. These directions were to be carried out by
23 December 2008.
[7] Mr and Mrs Axtens gave evidence as to the cost of carrying out of the work
proposed by Mr Colefax by submitting a quote by Placid Pools Pty Ltd
dated 27 November 2008 that the costs would be $36,190 excluding any
rectification of the garden or fencing surrounding the pool if this was
damaged in the process. The quote was unsigned and was qualified as it
was stated to be “subject to site inspection”.
[8] Neither of the quotes submitted set out calculations as to how the amounts
were derived.
[9] On 9 March 2009 the CCT found that rectification in accordance with Mr
Colefax’s report was a reasonable course. In view of the divergent
evidence of the costs of such rectification the CCT favoured a rectification
rather than a damages order and ordered:
a) Mr Brooks to rectify the defective pool depth in accordance with the
method described in the report of Mr Colefax of Colefax Associated
Consulting Engineers dated 9 March 2007 (including any rectification of
the garden or fencing if damaged in the process) by 4pm 30 June 2009.
b) That Mr and Mrs Axtens were relieved of any obligation to pay to Mr
Brooks the balance of the amounts owing under the building contract in
the sum of $1,933.75 to compensate them for their loss, including for
inconvenience, disappointment, loss of amenity or enjoyment.
c) Mr Brooks was to pay Mr and Mrs Axtens’ costs of the proceedings to
be assessed on the standard basis using the District Court scale
relating to applications of less than $50,000 to be assessed.
[10] In about March 2009 Mr and Mrs Axtens sold the property.
[11] Mr and Mrs Axtens did not inform the CCT or Mr Brooks of their intention or
decision to place the property on the market.
[12] On or about 17 March 2009 Mr Brooks became aware of a sale or
proposed sale.
1 Defence dated 25 September 2006 paragraphs 3 and 4.
-- 3 of 13 --
4
[13] On 18 March 2009 in response to an enquiry as to whether the house had
been sold Mr and Mrs Axtens’ legal representatives acknowledged to Mr
Brooks’ legal representatives that the property had been sold and the
contract was at that stage conditional.
[14] Mr Brooks was deprived of the opportunity to comply with the order within
the time allowed ie by 30 June 2009.
[15] In view of the time which elapsed from the CCT decision of 9 March 2009
until the confirmation of the conditional sale there cannot be any adverse
inference drawn against Mr Brooks for failure to comply with the
rectification order.
[16] Section 96 of the Commercial and Consumer Tribunal Act 2003 (Qld) (CCT
Act) provided that a party could apply to reopen an order if there were
problems with interpretation or implementation of an order.
[17] On 27 April 2009 Mr and Mrs Axtens applied to the CCT to reopen the
9 March 2009 decision seeking a monetary order as distinct from
rectification because the property was being sold with settlement to take
place on 1 May 2009.
[18] On 19 August 2009 Mr and Mrs Axtens sought an oral hearing to be
allowed to conduct cross examination. For reasons which are not readily
apparent from a review of the file the matter proceeded to be determined
on the papers without an oral hearing.
[19] On 17 November 2009 the CCT allowed the reopening and ordered that:
a) The rectification orders made on 31 July 2008 be vacated;
b) Mr Brooks pay Mr and Mrs Axtens the sum of $5,390 by 4pm
30 November 2009.
[20] The CCT also found that each party should bear their own costs and so no
order as to costs was made.
[21] From 1 December 2009 the Tribunal replaced the CCT on the
commencement of the QCAT Act.
[22] On 14 December 2009 Mr and Mrs Axtens filed a Notice of Appeal subject
to leave in the District Court seeking to appeal the order that Mr Brooks pay
Mr and Mrs Axtens the sum of $5,390 by 4pm 30 November 2009.
[23] On 18 December 2009 Mr and Mrs Axtens filed an application in this
Tribunal for correction of a decision because there were problems with
interpretation of the 17 November 2009 order.
[24] The issues were that:
a) there was no 31 July 2008 order;
-- 4 of 13 --
5
b) an order made on 9 March 2009 included an order requiring Mr Brooks
to carry out rectification work and a costs order;
c) Mr and Mrs Axtens contend that the “rectification orders” being vacated
did not extend to the costs order.
[25] On 18 August 2010 the District Court granted Mr and Mrs Axtens leave to
appeal (on the grounds of a denial of natural justice because they were not
allowed to test Mr Brooks’ evidence by cross examining him at an oral
hearing), allowed the appeal, allowed the application to reopen the 9 March
2009 decision and remitted the application to the Tribunal for determination
as to the measure of damages payable.
[26] By directions dated 11 April 2011 and 23 June 2011 the parties were to
make written submissions as to the quantum of damages and on costs.
Discussion and Decision
[27] Mr and Mrs Axtens contend that:
a) the District Court accepted that the measure of loss was the cost of
rectifying the defective workmanship and found that it was an error of
law to consider the impact of the breach on the value of the home;
b) this Tribunal is limited to assessing the reasonable costs of rectifying
the pool in accordance with Mr Colefax’s report;
c) the quote by Placid Pools Pty Ltd dated 27 November 2008 in the sum
of $36,190 is to be preferred because it is an independent quote;
d) if the order of 17 November 2009 vacated the costs order of 9 March
2009, which is denied, they ought to be entitled to their costs of the
whole proceedings on the District Court Scale to be assessed or
alternatively on the Magistrates Court Scale applicable to the amount
awarded pursuant to sections 70 and 71 of the CCT Act;
e) if the order of 17 November 2009 did not vacate the costs order of
9 March 2009 they ought to be entitled to their costs since that time on
the District Court Scale to be assessed or alternatively on the
Magistrates Court Scale applicable to the amount awarded pursuant to
sections 70 and 71 of the CCT Act;
f) they ought to be awarded interest on any amount awarded as from the
filing date of 1 September 2006 pursuant to section 47 of the Supreme
Court Act 1995.
[28] Mr Brooks submits that the District Court did not go so far as to say that it
was an error of law to consider the impact of the breach on the value of the
home. I agree with this submission.
-- 5 of 13 --
6
[29] Everson DCJ stated at page 4: “In placing considerable weight on the
market value of the applicants’ property as a saleable commodity, the
tribunal has misdirected itself and erred in law.”
[30] In my view the error found by the District Court was not that the impact on
market value was considered but rather the weight given.
[31] The District Court remitted for determination the measure of damages. It
did not expressly limit this Tribunal to assessing the reasonable costs of
rectifying the pool in accordance with Mr Colefax’s report.
[32] Mr Brooks contends that:
a) the measure of Mr and Mrs Axtens’ loss is the diminution in value, if
any, of the house produced by the departure from the plans and
specification and any inconvenience and disappointment.
b) it has never been alleged that the difference in the depth of the pool led
to a diminution of the value of the property.
c) there was no evidence of any diminution in the value of the property.
d) there was no real evidence of substance that the difference in depth
caused any real loss of enjoyment.
e) the damages to which Mr and Mrs Axtens are entitled is nominal and in
any event does not exceed $2,000.
f) no order as to costs is appropriate.
[33] At the short hearing of this matter on 4 October 2011 Mr Brooks gave
evidence and was cross examined as to his quote dated 15 July 2008.
[34] Mr Brooks gave evidence that:
(a) he was an experienced pool builder;
(b) his quote of $5,390 did not include any allowance for his own labour;
(c) he had prepared the quote on the basis of performing much of the work
himself;
(d) the applicable day rate for his labour was $300-$350;
(e) he estimated that the work would take 4 days as against building a
whole pool in 7-8 days;
(f) he usually applies a 10% profit margin if he needs to get other
contractors in to perform work;
(g) his day rate does not include a separate profit margin;
-- 6 of 13 --
7
(h) Placid Pool’s profit margin may have been higher than 10%;
(i) he assumed that the disparity between the Placid Pool’s quote of
$36,190 and his own was because there must be a large profit margin
built in;
(j) the Placid Pool quote states that it was subject to site inspection which
usually means the contractor has not attended at site to inspect prior to
providing the quote;
(k) he is very familiar with the site;
(l) his original price for the pool of $31,120 included $9,104.20 in
equipment and equipment installation and a further $3,600 allowance
for solar heating, neither of which would need to be duplicated for the
rectification work;
(m)he disagreed with Mr Mosley’s estimate given in his letter dated
16 August 2007 that you could build four new concrete pool shells in the
time frame it would take to perform the rectification work and stated that
the rectification work was straight forward.
[35] In August 2007 Mr Mosley from Placid Pools, when approached to quote
for rectification work proposed by Colefax declined to do so.
[36] In November 2008 Mr Mosley from Placid Pools provided a quote for the
rectification work, subject to site inspection, which did not provide any
detailed pricing breakdown. Mr Mosley was not cross examined.
[37] Mr and Mrs Axtens submit that the Placid Pools quote represents the
market price of the cost of rectification and should be accepted in
preference to Mr Brooks’ evidence.
[38] Whilst the Placid Pools quote is an independent quote it must be viewed in
the context that Mr Mosley had previously indicated that Placid Pools did
not wish to undertake the work and more likely than not has not attended at
site to form an informed view of the work required.
[39] In forming a view about the reasonable costs of rectification I have
considered that this quote is for considerably more than the original
contract price to build the whole pool which included a significant quantity
of equipment and solar heating. These items represented approximately
40% of the original contract price. If these items are excluded from the
comparison then the Placid Pool’s quote is almost twice that of the original
pool construction price.
[40] Both parties referred to the decision in Bellgrove v Eldridge2 as did the CCT
Member as authority for the proposition that the general rule regarding the
measure of damages is the difference between the contract price the work
was contracted for and the cost of making the work conform to the contract
2 (1954) 90 CLR 613.
-- 7 of 13 --
8
with the addition of appropriate consequential damages provided that
undertaking the work to produce conformity is a reasonable course to
adopt. If this general rule does not apply then the measure is diminution in
value. The Court of Appeal endorsed this approach in UI International Pty
Ltd v Interworks Architects Pty Ltd & Ors3 and also confirmed that sale of
the property does not necessarily displace the entitlement to the costs of
rectification.4
[41] The CCT Member5 noted that “Both the manner of rectification and the
costs of performing it must be reasonable”.
[42] Mr Brooks submits that:
a) the Placid Pool quote is disproportional to the original contract price and
therefore does not satisfy the test;
b) the appropriate measure is therefore diminution in value of which there
is no evidence;
c) there was minimal inconvenience and therefore nominal damages
should be awarded;
d) regard should be had to the fact that the property has been sold.
[43] Having regard to the matters in [39]-[42] I prefer the evidence of Mr Brooks,
who is an experienced pool builder and is familiar with the site, as to the
reasonable cost of performing the rectification work.
[44] I find that the reasonable cost of performing the rectification work is $7,469:
(a) $5,390 per quote dated 15 July 2008;
(b) $1,400 (4 days labour @ $350);
(c) $679 (10% profit margin).
[45] I assess damages payable by Mr Brooks to Mr and Mrs Axtens in the sum
of $7,469.
[46] I also award interest on the sum of $7,469 calculated from the date of the
Application (1 September 2006) to the date of this decision calculated at
the rate of 10% per annum on a simple basis.
Application to Correct
[47] In relation to the Application to Correct a decision filed 18 December 2009 I
have reviewed the orders and the various reasons for decision made in this
matter.
3 [2007]QCA 402.
4 Westpoint Management Ltd v Chocolate Factory Apartments Ltd [2007] NSWCA 253.
5 [2008] CCT BD451-06 at [26].
-- 8 of 13 --
9
[48] The CCT Order of 9 March 2009 contained 5 separate orders.
[49] Orders 1 and 2 specifically referred to rectification.
[50] Order 3 was in the nature of a damages order in that it relieved Mr and Mrs
Axtens from paying the balance of the contract sum to Mr Brooks “having
regard to the significant consequential loss …. including inconvenience …..
loss of amenity or enjoyment.”6
[51] Orders 4 and 5 related to costs.
[52] The order of 17 November 2009 contained 2 separate orders.
[53] Order 1 provided “The rectification orders made by the Tribunal on 31 July
2008 will be vacated.”
[54] Order 2 provided for payment of damages in lieu of rectification. This order
was subsequently successfully appealed.
[55] It is clear that Order 1 erroneously referred to 31 July 2008 and ought to
have referred to 9 March 2009.
[56] The application before the CCT was in relation to varying the orders
requiring rectification be undertaken.
[57] The CCT considered the issue of costs7 and considered it appropriate to
make no order as to costs. In my view this solely related to the application
to vary the orders and not to the proceedings as a whole.
[58] I am not satisfied that the CCT intended to vacate all of the orders. If it had
intended to do so then it could have done so in express language.
[59] In these circumstances I find that “rectification orders” referred to Orders 1
and 2 of the Order of 9 March 2009 and therefore the costs orders in
Orders 4 and 5 were not vacated.
[60] I allow the Application to Correct Order 1 of 17 November 2009.
[61] I order that Order 1 of 17 November 2009 will provide “The rectification
orders (being Orders 1 and 2) made by the Tribunal on 9 March 2009 will
be vacated.”
Costs
[62] Mr and Mrs Axtens contend that they should receive the benefit of a costs
order pursuant to the now repealed Commercial and Consumer Tribunal
Act 2003 (CCT Act) for the proceedings since 9 March 2009.
6 Axtens v Brooks [2009] QCCTB 43 at [11].
7 Axtens v Brooks [2009] QCCTB 276 at [23]-[26].
-- 9 of 13 --
10
[63] As set out above the CCT dealt with costs of the application to vary up to
17 November 2009 by making no order as to costs.
[64] On the material before the Tribunal this costs decision was not appealed.
Any costs order, if ordered, would relate to the Tribunal’s proceedings as to
the assessment of damages remitted from the District Court and to the
Application to Correct filed 18 December 2009.
[65] It is necessary to have regard to the transitional provisions in the QCAT
Act.
[66] Prior to commencement of the QCAT Act Mr and Mrs Axtens had the right
to appeal the CCT decision of 17 November 2009 upon obtaining leave of
the District Court. An appeal was filed and subsequently allowed.
[67] Section 260 of the QCAT Act applies if the appeal was not commenced
prior to 1 December 2009 but commenced within the appeal period or
having been commenced was not finally dealt with prior to 1 December
2009.
[68] In either of these circumstances where the District Court’s decision was to
remit the matter, the Tribunal must deal with the matter under the CCT Act
as if it were still in force and only has the functions of the CCT and can only
make a decision the CCT could have made in relation to the matter under
the CCT Act. The CCT Act and other relevant laws continue to have effect
as if they were still in force for these purposes.8
[69] The Tribunal has recently determined that the relevant provisions when
considering whether to make an order for costs in existing tribunal
proceedings9 are sections 100 and 102 of the QCAT Act.10
[70] In the Hallett decision it was accepted that:
a) section 271 of the QCAT Act requires the Tribunal to deal with the
matter under the QCAT Act;
b) the Tribunal only had the powers that the CCT had, which included the
power to award costs;
c) the awarding of costs ought to be determined by application of the
QCAT Act provisions i.e. section 102.
[71] This reasoning was recently accepted by the Appeal Tribunal11.
[72] However section 271 of the QCAT Act does not contain the equivalent of
section 260(5) of the QCAT Act which provides that “the former Act, and
other relevant laws, continue to have effect as if they were still in force”.
8 Section 260(3), (4) and (5) QCAT Act.
9 Section 271 QCAT Act.
10 Hallett & Ors v Queensland Building Services Authority [2011] QCAT 355.
11 Queensland Building Services Authority v Johnston [2011] QCATA 265.
-- 10 of 13 --
11
[73] I accept that the preferred construction of section 260 of the QCAT Act is
that the costs application relating to the matter remitted by the District Court
continues to be governed by the laws in force prior to 1 December 2009
including the now repealed CCT.
[74] Section 77 of the Queensland Building Services Authority Act 1991 (QBSA
Act) conferred jurisdiction on the CCT and now on the Tribunal to
determine building disputes such as the one brought by Mr and Mrs Axtens.
Section 77(1)(h) of the QBSA Act provides that the tribunal may award
costs. Prior to 1 December 2009 the “tribunal” was defined as the CCT.
[75] This section has recently been considered by the Appeal Tribunal in Lyons
v Dreamstarters.12 The Appeal Tribunal noted at [33]-[34] that “A
jurisdiction given in general terms allows the Tribunal to make an order as
to costs that is justified in the circumstances.13 It is a broad general
discretion which must be exercised judicially, not upon irrelevant or
extraneous considerations but upon facts connected with or leading up to
the litigation.”14
[76] As noted by the Appeal Tribunal above whilst the discretion in section
77(1)(h) of the QBSA Act is broad it must be exercised having regard to
relevant facts.
[77] Mr and Mrs Axtens have been awarded damages, however they have
received an award for a small fraction of the amount originally claimed and
did not succeed in the amount contended for in their most recent
submissions. This is a factor which militates against exercising a discretion
to award costs.
[78] Under the CCT Act “the main purpose of this division is to have parties pay
their own costs unless the interests of justice require otherwise”.15 The
next consideration is whether, having regard to the interests of justice, in
reliance on the factors set out in section 71(4) and the provisions of section
71(5) of the CCT Act, another order is warranted.
Outcome of the proceeding
[79] The proceedings were commenced by Mr and Mrs Axtens seeking
damages in the order of $94,000.
[80] Whilst they have ultimately been successful the measure of damages
awarded to them has been a small fraction of the damages initially sought.
Conduct of the parties before and during the proceeding
[81] Mr Brooks conceded liability at an early time.
Nature and complexity of the proceeding
12 [2011] QCATA 142.
13 Oshlak v Richmond River Council (1998) 193 CLR 72 at 88.
14 Latoudis v Casey (1990) 170 CLR 534 at 557.
15 Section 70 CCT Act.
-- 11 of 13 --
12
[82] The application did not involve overly complex issues.
Relative strengths of the claims made
[83] The issue for determination was what damages were applicable. Mr and
Mrs Axtens were ultimately successful but for a small fraction of the amount
originally claimed and did not succeed in the amount contended for in their
most recent submissions.
Any contravention of an Act
[84] This is not a relevant factor in this proceeding.
For a proceeding to which a State agency is a party, whether the other
party to the proceeding was afforded natural justice by the State agency
[85] This is not a relevant factor in this proceeding.
Anything else the tribunal considers relevant
[86] A party to a proceeding is not entitled to costs merely because the party is
the beneficiary of an order of the tribunal or the party was legally
represented at the proceeding.16
[87] Mr and Mrs Axtens are the beneficiaries of an order for costs made by the
CCT on 9 March 2009.
[88] Having regard to the above factors some of which are in favour of an award
of costs but most which are not, the interests of justice do not point to a
costs award to overcome the starting position that each party pay their own
costs.
[89] It is therefore appropriate that there be no order for costs in relation to the
assessment of damages being the matter remitted from the District Court.
[90] If I am wrong that the decision of 17 November 2009 to award no costs
remains on foot then having regard to the criteria in the CCT Act I find that
it is appropriate that there be no order for costs in relation to the application
to reopen.
[91] In relation to the Application to Correct filed 18 December 2009 that was an
application commenced in this Tribunal and the awarding of costs ought to
be determined by application of the QCAT Act provisions.
[92] Having regard to the conduct of this matter the Application to Correct was
very much secondary to the assessment of damages and the parties made
limited submissions in relation to it.
16 Section 71(5) CCT Act.
-- 12 of 13 --
13
[93] The QCAT Act provides “Other than as provided under this Act or an
enabling Act, each party to a proceeding must bear the party’s own costs
for the proceedings.”17
[94] Section 102(1) states “The tribunal may make an order requiring a party to
a proceeding to pay all or a stated part of the costs of another party to the
proceeding if the tribunal considers the interests of justice require it to make
the order.”
[95] Section 102(3) sets out criteria to which the Tribunal may have regard.
[96] Having regard to the criteria the interests of justice do not point so
compellingly to a costs award to overcome the starting position that each
party bear their own costs.
[97] It is appropriate that there be no order as to costs in respect of the
Application to Correct.
[98] If I am wrong that the awarding of costs in relation to the Application to
Correct is governed by the QCAT Act then having regard to the criteria
under the CCT Act I find that it is appropriate that there be no order for
costs.
Orders
[99] Mr Brooks is to pay Mr and Mrs Axtens the sum of $7,469.00 together with
interest on the sum of $7,469.00 calculated from the date of the Application
(1 September 2006) to the date of this decision calculated at the rate of
10% per annum on a simple basis by 4:00pm on 6 December 2011.
[100] The Application to Correct Order 1 of 17 November 2009 is allowed.
[101] Order 1 of 17 November 2009 will be corrected to provide “The rectification
orders (being Orders 1 and 2) made by the Tribunal on 9 March 2009 will
be vacated.”
[102] Mr and Mrs Axtens’ application for costs in relation to the assessment of
damages is dismissed.
[103] Mr and Mrs Axtens’ application for costs in relation to the Application for
Correction is dismissed.
17 Section 100 QCAT Act.
-- 13 of 13 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2011/517