Armenores v The Body Corporate for the Peninsula Community Titles Scheme 9865 [2011] QCAT 537
CITATION: Armenores v The Body Corporate for the
Peninsula Community Titles Scheme 9865
[2011] QCAT 537
PARTIES: Mr David Armenores
v
The Body Corporate for the Peninsula
Community Titles Scheme 9865
APPLICATION NUMBER: OCL097-11
MATTER TYPE: Other civil dispute matters
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Peta Stilgoe, Member
DELIVERED ON: 3 November 2011
DELIVERED AT: Brisbane
ORDERS MADE: The time for lodging a request to record a
new community management statement
pursuant to s 385(6) of the Body
Corporate and Community Management
Act 1997 is extended to three months
after the date on which the tribunal
makes final orders in the proceeding.
CATCHWORDS: BODY CORPORATE – where decision to
return to pre-adjustment contribution
schedule – where lot owner made
application to change entitlements – where
body corporate did not lodge request within
3 months – where applicant wanted to
prevent the body corporate lodging request
within time
Body Corporate and Community
Management Act 1997, ss 279, 385(6),
385(7), 358(8), 385(9), 388(8), 388(9),
389(4), 390
Queensland Civil and Administrative
Tribunal Act 2009, ss 58, 61
-- 1 of 5 --
2
APPEARANCES and REPRESENTATION (if any):
This matter was heard on the papers in accordance with section 32 of the
Queensland Civil and Administrative Tribunal Act 2009.
REASONS FOR DECISION
[1] On 20 July 2009, a member of the Commercial and Consumer Tribunal,
Mr Dorney QC (as he then was), ordered that the contribution schedule for
the Body Corporate for the Peninsula Community Titles Scheme 9865 be
adjusted.
[2] At a meeting on 18 June 2011, the body corporate committee resolved to
adjust the contribution schedule to reflect the scheme immediately prior to
the tribunal‟s decision.1
[3] Section 385(6) of the Body Corporate and Community Management Act
1997 requires the committee lodge a request to record a new community
management statement within 3 months of that decision. In the meantime,
Mr Armenores brought an application under s 385(8)(b) for an adjustment
to the pre-adjustment contribution schedule.
[4] At Mr Armenores‟ request, the committee gave an undertaking not to
request a new community management statement until after a committee
meeting scheduled for 6 August 2011.
[5] As a preliminary question, I am asked to decide “the section 385 issue”.
Mr Armenores submits that, in determining the question, I should make the
following orders:
a) That the body corporate be restrained from taking any action (to record
a community management statement that reflects the pre-adjustment
entitlements) until the determination of final orders.
b) That the body corporate be required to lodge a request to record a new
community management statement within three months of the final
order.
c) That the body corporate may rely on these orders as a bar to any
proceeding brought by lot owners under s 389(4) of the Body Corporate
and Community Management Act 1997.
[6] The reasons for the parties‟ interest in this question is the significant costs
involved in recording a new community management statement, which
may be duplicated if Mr Armenores‟ application is successful.
[7] Mr Armenores submits, with some justification, that the 6-month period in
s 385(6) is prohibitively restrictive once the tribunal becomes involved.
[8] The body corporate submits that, once an application is filed, the
committee is no longer bound to lodge a new community management
statement within 3 months.
1 Pursuant to s 385(4) Body Corporate and Community Management Act 1997.
-- 2 of 5 --
3
[9] Section 385(7) provides that s 385(6) will not apply (and the body
corporate will not have to request a new community management
statement within 3 months of the decision) if:
a) the tribunal makes an order for an adjustment of the contribution
schedule before the end of the 3-month period; and
b) the order provides for a change to the contribution schedule lot
entitlements.
[10] Section 388(8) provides that, if the tribunal makes an order adjusting the
contribution scheme, the body corporate must lodge a request to record a
new community management statement within 3 months after the order is
made. Section 388(8) does not apply, and a body corporate will not have
to lodge a request, if the tribunal‟s order is the same as the contribution
entitlement contemplated by the body corporate under s 385(6).2
[11] Section 385(7) makes sense. There is no point in recording a new
community management statement if it will be replaced by another
community management statement within a short period of time.
[12] I consider that the body corporate‟s submission is misconceived. The Act
does not release it from the obligation to lodge a request for a new
community management statement except in limited circumstances.
Those limited circumstances do not apply here.
[13] The business of a body corporate must go on. While it is reasonable to
assume that the business of a body corporate can continue for three
months while there is some doubt about which contribution schedule
operates, any longer period must start to cause difficulties. The committee
must send notices to lot owners requiring payment of the contribution
schedule, prepare financial reports for the current financial year and
budgets for the next financial year. A lot owner‟s attitude to the financial
records and budget will be coloured by that owner‟s individual liability to
contribute.
[14] The Act specifically allows the body corporate to “hold off” if, within the 3-
month period, the tribunal determines that another contribution schedule
should apply. The omission of any mechanism to deal with a longer period
does not seem to me to be an omission or oversight. Rather, the
interaction between ss 385(7) and 388(9) leads me to the conclusion that
the Legislature did intend that the body corporate would request the pre-
adjustment contribution schedule be recorded while it was waiting for a
decision by the tribunal.
[15] My view of the interaction between ss 385(7) and 385(9) is confirmed by
s 390. The body corporate is responsible for the costs of dealing with a
motion to revert to the pre-adjustment contribution schedule and the costs
of preparing and recording the new community management statement.3
That obligation does not extend to the costs associated with an application
such as Mr Armenores has made. It is conceivable, although not
2 Section 388(9).
3 Section 390(1).
-- 3 of 5 --
4
inevitable, that “the costs associated with an application” would include the
costs of a further new community management statement.
[16] Mr Armenores has referred the tribunal to the decision of Shaftson
Towers4. In that case, the debate was, as here, whether the adjustment
was a decision of a court, tribunal or adjudicator or whether it was simply
an order giving effect to an agreement. The adjudicator ordered that,
pending a final determination, the body corporate was not to lodge a new
community management statement to re-adjust the lot entitlements. The
order remained in effect for two months only. The decision was made on
the basis that:
a) Significant cost and inconvenience would flow if the body corporate
actually lodged the community management statement, adjusted levies
accordingly and then had to lodge a new community management
statement and readjust owners‟ levies.
b) The issue in dispute appeared to be “so simple”.
c) If the parties were unable to resolve the dispute, a final order could be
made “in the near future.”
[17] The adjudicator in Shaftson Towers relied on the power to make interim
orders contained in s 279. Section 279 allows an Adjudicator to make an
interim order if the Adjudicator is:
satisfied, on reasonable grounds, that an interim order is necessary because
of the nature or urgency of the circumstances to which the application relates.
[18] No such power is granted to the tribunal by the BCCM Act. However, the
President, Justice A Wilson SC has clearly articulated the approach in
situations such as this5:
“QCAT can exercise the original jurisdiction conferred by an enabling Act if an
application is brought to it: s 15. In exercising that jurisdiction QCAT may
perform the functions upon it by the QCAT Act or the enabling Act: s 16.
Under s 9(4) the Tribunal also has jurisdiction to „…do all things necessary or
convenient for exercising its jurisdiction‟. The Tribunal‟s powers relevantly
include, under s 60, the traditional equitable powers of courts to make
declarations and, under ss 58 and 59, to make interim orders or grant
injunctions.”
[19] The tribunal‟s powers to grant an interim order are contained in s 58(1) of
the Queensland Civil and Administrative Tribunal Act 2009. The power
can be exercised if the tribunal considers that an order is in the interests of
justice including, for example:
a) to protect a party‟s position for the duration of the proceeding; or
b) to require or permit something to be done to secure the effectiveness of
the exercise of the tribunal‟s jurisdiction for the proceeding.
[20] The tribunal has power to grant injunctions6 and make declarations7 but
they are powers that can only be exercised by a judicial member of the
tribunal.
4 [2011] QBCCMCmr 320
5 McDonald’s Australia Ltd v Emaaas Pty Ltd [2011] QCAT 293 at [24], [25]
-- 4 of 5 --
5
[21] The tribunal also has the power to extend a time limit fixed by an enabling
Act.8 An extension may be given even if the relevant time for complying
with the relevant requirement has passed.9 The tribunal cannot extend or
shorten a time limit or waive compliance with another procedural
requirement if to do so would cause prejudice or detriment, not able to be
remedied by an appropriate order for costs or damages, to a party or
potential party to a proceeding.10
[22] I am not persuaded that the parties view the issues in the present
application is “so simple” but, logically, there are good reasons to make
orders which do not require the body corporate to lodge a request for a
new community management statement until final orders have been made:
a) The final hearing is set down for hearing on 1 February 2012.
b) No lot owner has applied for an order under s 389(4) requiring the body
corporate to lodge the request.
c) Neither the body corporate nor Mr Armenores want the body corporate
to incur the expense of lodging the request for the new community
management statement until final orders have been made.
d) There is no suggestion that any party will suffer prejudice by delaying
the request for a community management statement.
[23] As the body corporate has shown no inclination to apply to record the new
community management statement, I do not consider it necessary to grant
an injunction. Given the powers available under s 61 of the QCAT Act, the
appropriate solution is simply to extend the time for lodging a request to
record a new community management statement pursuant to s 385(6) of
the BCCM Act to three months after the date on which the tribunal makes
final orders in the proceeding.
6 Section 59 QCAT Act.
7 Section 60 QCAT Act.
8 Section 61(1)(b) QCAT Act.
9 Section 61(2) QCAT Act.
10 Section 61(3) QCAT Act.
-- 5 of 5 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2011/537