Auscoast Builders Pty Ltd v All State Waterproofing [2011] QCAT 491
CITATION: Auscoast Builders Pty Ltd v All State
Waterproofing [2011] QCAT 491
PARTIES: Auscoast Builders Pty Ltd
v
All State Waterproofing
APPLICATION NUMBER: BDL052-10
MATTER TYPE: Building matters
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Ms Kate Buxton, Member
DELIVERED ON: 14 October 2011
DELIVERED AT: Brisbane
ORDERS MADE: That the sum of $2,761 be paid by the
Respondent All State Waterproofing to the
Applicant, Auscoast Builders Pty Ltd within
30 days of this order.
CATCHWORDS: Summary determination and assessment of
damages for rectification – water proofing
APPEARANCES and REPRESENTATION (if any):
This matter was heard and determined on the papers pursuant to s 32 of
Queensland Civil and Administrative Tribunal Act 2009 (QCAT Act).
REASONS FOR DECISION
[1] Auscoast Builders Pty Ltd („Auscoast‟), the applicant in these proceedings,
engaged All State Waterproofing („All State‟), the respondent, in about July
2007, to perform waterproofing works at a Townsville unit development.
[2] On 2 March 2010, at a point where the parties had been unable to resolve
their dispute in relation to those waterproofing works, Auscoast filed an
application to QCAT. Auscoast sought rectification of those works and
associated costs.
[3] On 29 March 2010, All State filed a response indicating a preparedness to
rectify. These proceedings have been managed through a serious of
directions hearings and compulsory conferences. To date, certain
rectification works have been carried out to the roof. The planter boxes at
-- 1 of 4 --
2
the development have not been rectified and remain the only outstanding
issue between the parties. On 21 February 2011, during a compulsory
conference, the parties agreed that this remaining issue of the planter boxes
be resolved by agreement in the following terms:
“The Applicant and the Respondent agree to meet on site at a time between
14 March and 2 April 2011 at which time:
a) The Applicant will remove soil 150 mm either side of the expansion joint
in the planter boxes subject of this dispute and test for leaks with water.
b) The Respondent will inspect the waterproof membrane and sealant to the
expansion joint and if damaged will:
i) Repair and rectify same in a proper and tradesmen like manner;
ii) Shall bear the cost of such rectification.
c) Upon compliance with direction (a) hereof the application shall be
dismissed.
d) Should there be any dispute as to as to compliance with direction (a)
hereof the Building Services Authority shall be appointed by the Tribunal
to undertake an inspection of the planter box and a report by the BSA
shall be final and binding on the parties.”
[4] However, this matter was not resolved in accordance with that agreement.
The meeting did not take place on site between the agreed dates and, as a
result of the meeting not having taken place, the rest of the agreement has
been unable to be carried out. Directions have since been given for the
parties to make submissions to the Tribunal and for the Tribunal to make a
decision on the papers on a summary basis in relation to the outstanding of
liability for and assessment of costs of rectification of the planter box.
[5] The agreement clearly contemplated that, at the time it was made, there was
an issue remaining between the parties as to who was responsible for the
ongoing waterproofing issue. The material filed by the parties deals
substantively with only the issue of assessment of costs. It is clear from the
application that the Applicant holds the Respondent, who has carried out the
waterproofing services, responsible for this issue. The Respondent has not
filed any substantive material in response to those allegations and has, in
relation to certain aspects of the assessment issues dealt with below,
indicated a preparedness to pay those costs. On the state of the evidence
available to be taken into account in determining this matter on the papers,
there is sufficient evidence to form a concluded view that the issue of liability
in relation to the waterproofing is not seriously in dispute by the Respondent.
[6] I do not regard the task with which the Tribunal is now charged to be
affected or influenced by the agreement reached on 21 February 2011. That
agreement was not carried out and the Tribunal is left to adjudicate between
the parties as to the liability for the re-waterproofing. I have indicated that
-- 2 of 4 --
3
this liability rests with the Respondent. In those circumstances I will turn the
evidence in relation to the assessment of damages.
[7] By letter to QCAT dated 27 July 2011, Auscoast has submitted what it has
described as a “detailed estimate of costs for rectification of leaking planter
box”. The sum of those costs is $4,589.88.
[8] On 1 August 2011 All State responded by indicating that many of the items
on Auscoast‟s “estimate” should be at its own cost. All State have also
referred to the agreement of 21 February 2011 to determine who should pay
what. The items of the costs which All State‟s admitted it should bear total
$1,144 plus GST (the Applicant‟s items 5 and 6 only).
[9] Despite being given the opportunity to file any relevant material, it is
surprising that neither party has offered any independent evidence as to the
likely cost of rectification. The Applicant‟s “estimate” appears to have been
created by the Applicant to assist the Applicant and must be weighed
accordingly. Having said that, All State does not make any submissions as
to the reasonableness of the calculations made by Auscoast, but rather
submits that it ought to be reasonable for only some, but not all, of those
costs. Subsequently, in a more detailed response filed in QCAT on
6 September 2011, All State have provided alternative calculations for sums
totalling $1,006 in rectification costs, again asserting that All State would be
undertaking that work. The difficulty in forming a concluded view as to the
cost of rectification of the planter boxes in the absence of any independent
quotes, estimates or expert evidence on the topic is further hampered by the
parties‟ reference to the agreement which has not been, and now cannot be,
carried out and which is not applicable in the Tribunal‟s determination of this
assessment.
[10] In making that assessment, Auscoast claim $4,589.88 and All State submit
that $1,006 is sufficient. Turning to Auscoast‟s material (filed 27 July 2011)
first, I do not consider that Auscoast is entitled to any site establishment
fees. They have not demonstrated why the rectification works cannot be
undertaken by sufficiently local company to obviate this need.
[11] As the agreement is not applicable the Respondent‟s admission that the
removal soil, plants, water systems etc. should rest with the Applicant is now
irrelevant. Items 2, 3 and 4 totalling $715 appear to have been arrived at
using a reasonable estimate of time and hourly rate and will be allowed.
Items 5 and 6 are the items totalling $1,006 referred to above which All State
seems to accept are reasonable. Both these sums should be paid by the
Respondent.
[12] The remaining sum of $1,040 for 16 hours in labour in repairing and re-
waterproofing also appears reasonable. I have already indicated that liability
for the rectification costs rests with All State. The material in the Applicant‟s
application, together with certain admissions made by All State, are
consistent with this conclusion. Finally, I do not accept that the Applicant
has proven the need for accommodation for workers or site disestablishment
fees for the same reasons expressed above in relation to site establishment
fees.
-- 3 of 4 --
4
[13] The allowable cost for rectification works is therefore the sum of the allowed
amounts of $715, $1,006 and $1,040 totalling $2,761. I order that the sum
of $2,761 be paid by All State to Auscoast within 30 days of this order.