Bell and Anor v Sambuc Pty Ltd [2011] QCAT 378
CITATION: Bell and Anor v Sambuc Pty Ltd [2011] QCAT
378
PARTIES: Mr Jonathan Bell
Mrs Kelsey Bell
v
Sambuc Pty Ltd
APPLICATION NUMBER: BDL232-10
MATTER TYPE: Building matters
HEARING DATE: 11 & 12 April 2011
HEARD AT: Brisbane
DECISION OF: Mr Andrew McLean Williams, Member
DELIVERED ON: 5 September 2011
DELIVERED AT: Brisbane
ORDERS MADE: [1] By consent, all issues relating to H3
treatment of timber are dismissed;
[2] The responsible officer at Master
Builders’ Queensland is to release from
trust the sum of $28,000 (QMBA File
Reference T-10-024) to Sambuc Pty Ltd
(Trading as Fine Edge Homes).
[3] The Applicants are to pay to the
Respondent the further sum of
$27,455.33 within 28 days of the date of
these orders in final satisfaction of the
Respondent’s claims for payment for the
costs of constructing the house at 33
Leila Place, at Pullenvale.
CATCHWORDS: Residential Building Dispute – whether works
had been conducted in accordance with contract
specification – whether project had attained
practical completion – meaning of “practical
completion”
Dispute as to costs of provisional sum and prime
cost items – whether escalation in sums charged
for provisional sum and prime cost items has the
effect of the builder breaching the standard
domestic building contract – statutory remedies
-- 1 of 27 --
2
for escalation in provisional sum costs
Entitlement to liquidated damages and interest
on late payment of progress claims
Domestic Building Contracts Act 2000, ss 59, 60
APPEARANCES and REPRESENTATION (if any):
APPLICANT: Mr Jonathan Bell & Mrs Kelsey Bell appeared in
person
RESPONDENT: Sambuc Pty Ltd appeared in person
REASONS FOR DECISION
[1] This is a domestic building dispute between homeowners, Mr Jonathon
Bell and Mrs Kelsey Bell (the applicants), against their builder Sambuc
Pty Ltd (ABN 2147 483 647), trading as „Fine Edge Construction and
Developments‟ (hereinafter „Fine Edge‟).
[2] The applicant‟s case was conducted by Mr and Mrs Bell, in person. Mr
David Manion is the authorised representative of Fine Edge, and he
conducted the builder‟s case before QCAT. The matter was conducted
over two days, being 11 and 12 April 2011. After the hearing, the parties
were given leave to file further written submissions, and the last of these
(a reply by the homeowners), was filed on 5 May 2011.
[3] The dispute relates to domestic building works undertaken pursuant to a
residential building contract for the construction of a new house of
substantial proportions on land situated at No 33 Leila Place, at
Pullenvale, in the Western suburbs of Brisbane.
[4] The homeowners and Fine Edge entered into a standard Master Builders
residential building contract on 11 May 2009. The original contract price
was $560,000.00 and the agreed construction period was 382.6 days,
with time commencing from when the concrete slab was down.
Subsequently, the contracting parties agreed that the date for final
completion would be extended for a further 14 days, until 14 September
2010.
[5] These proceedings were commenced by the applicants in July 2010,
even before the completion of building works, which Fine Edge contends
occurred on 13 September 2010. At this juncture, it bears observing that
the homeowners still dispute that the project has attained practical
completion.
[6] Unfortunately, and as became most conspicuous to me during these
proceedings, this is a case where the relationship between the
homeowners and the builder has broken down irretrievably. It is now a
relationship that is marked out by high levels of enmity and mutual
distrust.
-- 2 of 27 --
3
[7] By their originating Application, the homeowners were seeking orders
directing Fine Edge to expedite completion of the building project, in
accordance with the contract. In Part B of that Application, the
homeowners specify some 15 items of allegedly defective or otherwise
incomplete works. Because the applicants contend that the project has
not attained practical completion, they also claim that they are entitled to
liquidated damages from Fine Edge, at the agreed contract rate, which is
$75.00, per day.
[8] By the builder‟s Response and Counter Application, Fine Edge seeks
orders dismissing the homeowners‟ Application, as well as orders
requiring the Bells to pay to Fine Edge outstanding amounts for various
progress claims. As at the date of filing its Counter Application, Fine
Edge claimed that $66,721.20 still remained outstanding. Fine Edge also
denied that there were any substantially defective or incomplete works;
and that the homeowners‟ claim before QCAT had been commenced
“vexatiously [so as] to delay payment of the Respondent’s progress
claims‖.
[9] Most recently, in the final submissions filed by Fine Edge at the
conclusion of the hearing (after leave for same was given by me), and
obviously after another opportunity to attempt to reconcile the various
payment schedules created by Mr Jon Bell against the invoices raised by
Fine Edge, the builder accepts the sum that the homeowners claim they
have already paid to the builder, yet says that it is still owed $62,390.89.
[10] By way of reply to the Response and Counter Application, Mr and Mrs
Bell deny that any monies are still owed by them, and they repeat and
rely on their previous contention that there are still numerous items of
defective and/or incomplete works. The Bells again say that the project
has not attained practical completion, and that they have a claim for
liquidated damages.
Framework for Analysis
[11] As the case was ultimately conducted before QCAT, the homeowners‟
Application was organised and presented under a number of discrete
heads of claim. These afford a useful framework for the further analysis
(and resolution) of the various competing claims by the homeowners and
the builder; such that I adopt that framework here, as part of my reasons:
(a) That QCAT should now determine the entitlement of the builder to
payments of interest in relation to late/overdue payments by the
homeowners in relation to progress claims numbered 2, 5, 6, 7, 9,
and 11; as well as the builder‟s entitlement to payment for various
provisional and prime cost items under the contract, pursuant to
sections 59 and 60 of the Domestic Building Contract Act 2000
(“the Commercial issues”).
(b) That QCAT should determine an appropriate adjustment to the
contract price for issues going to the claimed failure by the builder
-- 3 of 27 --
4
to use H-3 treated timber in the construction, as was required by
the contract (“the H-3 Timber issue”).
(c) That QCAT should determine an appropriate adjustment to the
contract price for issues going to the failure of the builder to use
„Durogal‟ treated SHS posts, as required by the contract
specification (“the SHS Post issue”).
(d) That QCAT should determine an appropriate adjustment to the
contract price for issues going to the completion of the internal
painting (“the internal painting issue”).
(e) That QCAT should determine an appropriate adjustment to the
contract price for issues going to the condition of the guttering
(“the guttering issue”).
(f) That QCAT should determine an appropriate adjustment to the
contract price for issues related to the construction of a retaining
wall (“the retaining wall issue”).
(g) That QCAT should determine an appropriate adjustment to the
contract price for issues going to the non-inclusion of floor wastes
in the laundry and powder room (“the floor wastes issue”).
(h) That QCAT should determine the defects listed in part 08 of the
homeowners filed documents, as well as a time-frame for
rectification of same (“practical completion”).
(i) That QCAT should determine an appropriate adjustment to the
contract price for liquidated damages (“the liquidated damages
claim”).
(j) That QCAT should determine appropriate orders pertaining to the
release of $28,000, (representing the quantum of the builder‟s final
progress claim), as has now been deposited by the homeowners
in the Queensland Master Builders‟ Association („QMBA‟) trust
account, pending resolution of this dispute (“the trust monies
entitlement”).
Matters No Longer in Dispute
[12] On the first day of this hearing Mr and Mrs Bell indicated that matters
relating to the retaining wall (item (f), from the list above), were no longer
in dispute.
[13] Next, after QCAT had heard considerable evidence and argument in
relation to H-3 timber treatment (including uncontested expert evidence
called by Fine Edge on the point), the homeowners indicated that they
were satisfied that those timber components within the construction
project that were required by the contract specification to be treated to H-
3 standard were, in fact, treated to that standard.
-- 4 of 27 --
5
[14] It is unfortunate that Mr and Mrs Bell did not give this concession much
earlier in this dispute. It is my assessment that disputation in relation to
H-3 timber treatment has greatly exacerbated the enmity, mistrust and
poor communication between the contracting parties throughout this
construction project, and its litigious aftermath. Considerable “shot and
powder” (that is: time, effort, and expense) has now been expended by
the parties in relation to this issue, in circumstances in which evidence
was made available by the builder to the Bells far earlier in the dispute,
that ought, reasonably, to have assuaged their concerns to ensure that
their home was constructed with H-3 timber.
[15] By consent of the parties I dismissed the H-3 component of the
applicant‟s claim (item (b) in paragraph 11, above) during the first day of
the hearing.
[16] For reasons of thematic convenience – and in manner following the rough
order of the evidence heard before the tribunal – I will deal next with
items (c) through (h) in the list of issues; before then dealing with items
(i), (j), and (a) as listed in paragraph 11 of these reasons for decision.
The SHS Posts issue
[17] The house at the centre of this dispute is an elevated timber frame
construction upon a sloping site (modified by means of cut and fill),
whereupon a large proportion of the home is set upon steel hollow
section („SHS‟) posts, above grade. The parties are in agreement that
the contract specification required that these SHS posts be finished in
“Duragal”, which is a galvanising treatment with high/very high corrosion
resistance properties.
[18] By reason of a mistake by the steel supplier, the SHS posts were
supplied to site finished in a red oxide primer, rather than Duragal. Had
the contracting parties waited for re-supply of the SHS posts, delays that
would hold up subsequent stages of the construction schedule would
have arisen, such that an election was made (apparently by agreement),
that construction would proceed utilising the red oxide-primed SHS posts.
[19] Although affording some protection against corrosion, it is agreed by the
parties that red oxide primer affords inferior protection against corrosion
to that afforded by Duragal. Sometime in either November or December
2009, Fine Edge offered to treat the SHS posts with an applied (in other
words, painted) finish, to improve their corrosion resistance. This was
again confirmed in an e-mail sent by Mr David Manion, on behalf of Fine
Edge, to Mr Jon Bell on 11 March 2010. By reply e-mail of that date Mr
Bell advised Mr Manion he was agreeable to the SHS posts being treated
by means of painting, yet also stated that the selected paint system still
needed to be agreed.
[20] The homeowners require that the selected paint system achieve an
equivalent standard of corrosion resistance to that which would have
been achieved had the SHS posts been supplied in Duragal, as originally
required. It is at this point where the dispute in relation to the SHS posts
-- 5 of 27 --
6
arises. The homeowners contend that protection equivalent to that
afforded by Duragal can only be achieved by means of an applied paint
system if the SHS posts are now powder-coated. The homeowners have
obtained a quotation to have the SHS posts powder-coated, and say that
this will cost $11,495.00. They are therefore willing to resolve this aspect
of their claim on the basis of a contract variation (in other words a price
reduction in their favour), of $11,495.00.
[21] Fine Edge hotly disputes that an equivalent corrosion resistance to that of
Duragal can only be achieved by means of powder-coating, and contends
that the application of an ordinary acrylic paint (over an appropriate metal
base-coat primer) will achieve an acceptable level of corrosion
resistance. Fine Edge has obtained and now put into evidence a report
from Dec Con Pty Ltd, dated 21 March 2010, given under the hand of Mr
George Englert. In that report, Mr Englert provides an opinion that the
coating system (i.e. paint) already applied to the posts at Pullenvale
accords with the requirements of Australian Standard 2311:2009 Guide to
Painting of Buildings and will provide the level of protection for the steel
posts situated under the residence that is mandated by that Australian
Standard.
[22] Mr Englert was also called to give oral evidence before the Tribunal,
whereupon he was cross-examined by Mr Bell, who is an engineer. Mr
Englert struck me as an impressive witness. Mr Englert was able to
explain why it is that AS2311:2009 Guide to Painting of Buildings was the
applicable standard, and why it was that the application of ordinary paint
could provide an adequate standard of corrosion resistance in conformity
with AS2311:2009. Mr Englert was also able to explain why it was
unnecessary to now treat the posts by means of powder coating in order
to obtain the same corrosion resistance as that afforded by Duragal (the
contract specification), which he states is a much higher level of corrosion
resistance than that conventionally required by AS2311:2009. I accept
Mr Englert‟s evidence in that regard.
[23] The applicants did call some expert evidence of their own from a Mr
Roger Donald. Mr Donald is a carpenter by trade, but has now moved
into project management. I am sure Mr Donald has some understanding
of painting, but he is not trade qualified as a painter. Mr Donald‟s
testimony was hastily arranged overnight by Mr Bell, in an attempt to
rebut Mr Englert‟s evidence, which had been given on the previous day.
Mr Donald gave the clear impression to me that he conceived his task
before this tribunal to be one in which he was required to come along and
“swear the issue”, informing QCAT that powder coating was essential.
However, a more considered approach to the issue demonstrates that
this is not the case.
[24] I now express my clear preference for the opinion given by Mr Englert,
and note, in particular, that Mr Englert has a lengthy history teaching the
trade of house painting in the apprenticeship/TAFE system. I now accept
Mr Englert‟s explanation as regards the interpretation of the relevant
Australian Standards, and why it is that the alternate Australian Standard
-- 6 of 27 --
7
– that as espoused by the homeowners as being the applicable standard
– is not the applicable Australian standard.
[25] Mr Englert did however concede during his testimony that it may be
necessary to apply a further coat of gloss acrylic paint to the outer two
rows of posts (those closest to the perimeter of the building and thus
most exposed to the weather) to achieve the same level of corrosion
resistance as that afforded by Duragal. I accept that concession,
because it was readily given by Mr Englert, during his cross-examination.
I felt the frank concession to be a matter that galvanised the independent
nature of his evidence.
[26] I reject the need for powder coating as excessive and unnecessary. I find
that the dispute in relation to the SHS posts ought be determined on the
basis that the extant condition of the SHS posts can be brought up to
standard by means of an application of an additional coat of gloss acrylic
paint to the external two (2) rows of SHS posts, after these posts have
been appropriately prepared by means of light sanding in order for the
top-coat to key into the paint that is already on those posts.
[27] As a general proposition, I am ordinarily inclined to order that any defects
that have been identified in the course of proceedings before QCAT
should then be fixed by means of an order for rectification that is directed
towards the builder. However, in this instance, I have previously noted
that there is a high degree of enmity and mutual distrust between the
parties. In addition, this dispute has now been quite protracted. In light
of that, the interests of finality are, in my view, now better served by my
making a monetary compensation order in relation to the condition of the
SHS posts in lieu of a rectification order, thereby avoiding the risk of
further disputes between the parties, if an order were made requiring the
builder to return to site. By reference to the sum quoted as being the
likely costs for powder coating the SHS posts, I now order that the
contract price be varied in favour of Mr and Mrs Bell in the sum of $1,200
in order to provide a reasonably sufficient sum to put the applicants in a
position to then retain a painter to apply a further coat of gloss acrylic
paint to the outer two rows of SHS posts.
The Internal Painting Issue
[28] Next, the applicants contend that the house at No 33 Leila Place has
been painted in an incorrect colour scheme, on the inside.
[29] The applicants say that on 22 March 2010, Fine Edge had requested that
the homeowners advise the builder in relation to their selected internal
colour scheme. On 26 March 2010, by means of an e-mail sent at
8:57am, Mr Jon Bell advised Mr David Manion of the selected internal
colour scheme, and also indicated that this advice was given “further to
our discussions on Monday”.
[30] Later, in about late April 2010, Mrs Bell was on site dealing with issues to
do with tile selection, when she observed what appeared to be incorrect
-- 7 of 27 --
8
paint colours being applied to the internal walls. Mr Bell followed up on
this matter in another e-mail to Mr Manion, sent on 30 April 2010. That e-
mail expresses the position that the paint scheme was supposed to be in
conformity with Mr Bell„s earlier e-mail “JB087- Internal Paint”, as had
been sent on 26 March 2010.
[31] On the basis of the available evidence it seems satisfactorily clear
(particularly from a reply e-mail sent by Mr Manion to Mr Bell on 1 May
2010) that the internal colour scheme was being applied by the painter in
conformity with an earlier paint specification that had been forwarded by
Mr Bell to Mr Manion on 22 February 2010, as part of Mr Bell‟s e-mail
regarding the external colour scheme („JB067 – external colours/reply‟).
Unfortunately, this colour scheme was later superseded by the e-mail of
26 March 2010, such that it would appear – at least to me on the balance
of probabilities – which the builder has, in this instance, mistakenly relied
on the superseded instruction. In his evidence Mr Manion explained that
he was being inundated by in-coming e-mails from Mr Jon Bell, and that it
was becoming a struggle to keep abreast of these. I find therefore on the
balance of probabilities that the revised instruction was a matter that got
lost in that volume of e-mail.
[32] The homeowners have now obtained a quotation from a painter of their
own, Trade Painters Pty Ltd (dated 20 October 2010: see attachment
04.13 in the applicant‟s bundle) indicating that the walls throughout the
internal of the house can now be re-painted for $4,500.00, plus GST. On
that basis the applicants now seek $4,950.00 as a variation by way of
reduction in their favour from the contract price in final resolution of the
internal painting issue.
[33] Although originally disputing that the incorrect paint scheme had been
applied inside the house, it would not seem that Fine Edge persists in
denying that the superseded colour scheme was on-forwarded to the
painter. Fine Edge has obtained a quotation of its own to rectify the
internal colour scheme and this quote (dated 18 March 2011), is more
recent than that obtained by the homeowners. It indicates that two coats
can be applied throughout the interior of the home for $2,000.00 inclusive
of GST.
[34] I prefer the evidence regarding the cost of this rectification work as
obtained by Fine Edge in preference to that obtained by Mr and Mrs Bell.
For reasons previously explained I will I order that there should be a
further variation of $2,000 in favour of the applicants, so as to put them in
a position to have the house repainted, internally.
The Guttering Issue
[35] In relation to this issue the homeowners indicate that the contract
provides (by means of drawing 06) that the facia/gutter should be “as
selected”.
[36] On Monday 1 February 2010 – again by means of an e-mail – Mr Manion
had requested that Mr Jon Bell provide his specification for the facia and
-- 8 of 27 --
9
gutter. By reply e-mail dated Wednesday 3 February 2010 Mr Bell
advised Mr Manion that the selected gutter was to be a “Lysaght Quad
175 Slotted”, coloured “Woodland Grey”. In addition, by means of that
same e-mail, Mr Bell also specified that the downpipes should be
“100mm round”.
[37] The homeowners contend that the gutter as installed does not comply
with this specification, and that it appears that a “150 Hi-front Quad”
gutter has been installed in lieu of the requested “Lysaght Quad 175
Slotted”. Further, the homeowners contend that the gutters – as installed
– do not comply with the requirements of AS3500.3.2 Stormwater
drainage – acceptable solutions, in that the gutters are inadequate to
discharge rainwater from the roof of the house at No 33 Leila Place. As
part of the applicants‟ materials, photographs have been included which
do show the gutters on the house overflowing, during a very heavy rainfall
event.
[38] The homeowners have also obtained two separate quotations from
independent guttering installers, one in the sum of $5,439.50; and one in
the sum of $7,579.00. Both of these do not include the price of
scaffolding, which will now be necessary if the gutters are to be replaced.
That – as yet unquantified expense – could be significant, given the
heights involved. Notwithstanding that the costs of scaffolding are not yet
quantified, the homeowners indicate that they are prepared to accept a
contract variation (again by way of a reduction in their favour) in the sum
of $8,000.00 in order to resolve the guttering issue.
[39] By way of reply on this issue, Fine Edge contends that during a meeting
held on 2 March 2010 the builder had explained to Mr Bell the reasons
why guttering different to that which had been specified had been
installed; explaining that the roofing plumber had flatly refused to warrant
his own workmanship if the selected gutter was installed, due to his
expressing a strongly held view that the gutter was too large for the
fascia, and therefore at risk of collapse under the weight of stormwater.
Fine Edge contends that around this time the homeowners agreed to
accept the installed gutter “as is”.
[40] Fine Edge also arranged for evidence to be given before the tribunal by
Mr Scott Ellis-Butler, who is a hydraulic consultant in the employ of DEB
& Associates. Mr Ellis-Butler has provided a report dated 14 March 2011,
which was presented in evidence before me. In that report, Mr Ellis-
Butler indicates that all gutter and downpipe sizes were reviewed by him
and in his assessment all of the eaves and gutters at No 33 Leila Place
are of sufficient size (assuming here that the gutters are 150mm), other
than perhaps for those in the area of the roof described in that report as
“Area A”.
[41] Mr Ellis-Butler says that, with respect to Area A, the position of the
downpipe at the internal corner in the gutter (and immediately below a
valley gutter higher on the roof), introduces additional volumes of water
and turbulence in this area, so as to prevent the gutter and downpipe
from performing at capacity. This is the same area of gutter that is
-- 9 of 27 --
10
portrayed in the photographs put into evidence by the homeowners
showing the gutter overflowing during a significant rainfall event. Mr Ellis-
Butler indicates that it is his opinion that any difficulties caused by water
overflow will not be solved by means of a simple replacement of the
gutters, but could be ameliorated by means of a larger rain head, at the
internal corner of the gutter as indicated in “Area A” in his report dated
14 March 2011.
[42] There is a further wrinkle in this tranche of the dispute. As part of its case
before the Tribunal the homeowners also contend that the gutters, as
installed, are not 150mm Hi front quad as had been agreed could be left
in-situ, notwithstanding that the homeowners had previously specified
that their selected guttering style was to be “Lysaght Quad 175”. The
photographs provided by the applicants show a tape measure across the
base of the gutter, which appears to indicate that the guttering profile is
only 130mm wide. Prima facie, this certainly gives rise to the suggestion
that the guttering is not 150mm wide, and is in fact undersized. Certainly,
Mr Ellis-Butler conceded that much, under questioning from me. This
issue has however since been satisfactorily addressed by the builder as
part of the additional materials, as were filed by the builder by leave, on
21 April 2011. As part of those additional materials, Fine Edge has
adduced some trade literature that shows that the correct means by
which to assess the size of the installed gutter is not by means of a
measurement across the base of the gutter profile, but rather to measure
across the gutter profile diagonally. The trade literature certainly goes to
show that the base profile of 150 Hi-front Quad gutter is 129.58mm (say,
130mm) yet this is still marketed as “Hi-front quad gutter – 150mm”.
I accept therefore that it is erroneous to measure gutter supplied by this
particular manufacturer in the manner (quite innocently) attempted by the
Homeowners.
[43] Included as part of the additional materials adduced by Fine Edge by
leave is also a copy of an e-mail from Mr Bell dated 2 March providing
minutes of a meeting of that date in which Mr Bell indicates (Item 5 of the
e-mail) that “JB agreed to accept the gutter as is”. On the basis of that e-
mail I find that the gutter should not be removed and replaced with
Lysaght Quad 175, as the original contract specification has since been
varied, by subsequent agreement between the contracting parties.
[44] Mr Manion has also obtained an additional (supplemental) report from Mr
Scott Ellis-Butler who had taken the opportunity (at my suggestion) to re-
visit his calculations regarding stormwater discharge rates, given the
nature of the roof in question. The revised report Mr Ellis-Butler has
produced now advises that there are three (3) areas on the roof that will
likely require modification to comply with AS/NZS3500.3. These areas
are described by Mr Ellis-Butler as Areas A, B and C. Mr Ellis-Butler
advises that Area A requires the installation of a rain head and 100mm
downpipe “as detailed in the previously issued sketch HSK-04”. This is a
reference to the report provided by Mr Ellis-Butler that was referred to in
his evidence before the Tribunal, being his original report dated 14 March
2011. In addition, Mr Ellis-Butler says that a similar rain head is also
required at Area B, and that Area C requires replacement over its entire
-- 10 of 27 --
11
length of the installed gutter with a “true” 150mm quad gutter. For
reasons that relate to the proper means for understanding the way to
measure this type of gutter (diagonally), I find that there is not any need
to replace the gutter along Area C, as advised in the supplementary
report obtained from Mr Ellis-Butler dated 19 April 2011. In all other
respects I accept the expert evidence of Mr Ellis-Butler.
[45] Although the parties have agreed by means of a subsequent variation
made on or about 2 March 2010 to leave the gutters installed by Fine
Edge in-situ, I find that the installation of the additional rain heads as
described in the reports provided by Mr Scott Ellis-Butler dated 14 March
2011 in Areas “A” and “B” (only), as were described by Mr Ellis-Butler in
his supplemental report dated 19 April 2011 should also be implied as a
necessary corollary to that agreement, in order to ensure that the gutters
can still comply with the relevant Australian Standard, AS/NZS3500.3.
Having regard to the available evidence going to the costs of replacing
the gutter, a fair and reasonable allowance by means of a further
variation in favour of the homeowners for the cost of supplying and
installing two rain heads as have been recommended would be in the
order of about $500. I therefore order that sum as a further variation in
favour of the homeowners.
The Floor Wastes Issue
[46] The homeowners contend that the building contract required for the
installation of floor wastes to the laundry and the powder room. Initially,
these were not installed. This would appear to have been an oversight
on the part of the builder. This oversight was advised by the
homeowners to Fine Edge in an e-mail from Mr Jon Bell sent on 24 June
2010.
[47] Sometime shortly after this Fine Edge did arrange for the installation of a
floor waste to both the laundry and the powder room, by means of the
removal and replacement of a single floor tile. However, the homeowners
contend that this still does not conform to the applicable Australian
Standard, which they say is AS3740 Waterproofing of Domestic Wet
Areas. Herein, the difficulty is that although each of the laundry and the
powder room now has a floor waste, there is no fall across the surface of
the floor towards the floor waste.
[48] Photographs provided to the Tribunal by the applicants (see attachment
07.04 at page 2) do show what appears to be a four-foot spirit level on
the floor. That photographic evidence tends to suggest that the floor is
level. I accept that evidence and find that the floor is, on the balance of
probabilities, level.
[49] The applicants rely upon AS3740 – 2010 (Waterproofing of Domestic Wet
Areas) and in particular where it provides at paragraph 3.11:
―Where a floor waste is required, the floor finish shall be
constructed so that water flows to the waste without water being
-- 11 of 27 --
12
retained on the finished surface with the exception of residual
water remaining due to surface tension.‖
[50] By way of reply Fine Edge contends that the owners sent an e-mail
amending the plans for the laundry that do not show a floor waste, and
that in all events, “good building practice” requires fall for laundry floors to
go to the nearest exit, for flood-control. Although the builder has provided
what appears to be some “screen shots” of a portion of a building plan for
the laundry, the accompanying e-mail, by which the builder contends that
the homeowner amended the plans for the laundry so as to exclude a
floor waste from that room have not been included as part of Folio 13 in
the respondent‟s bundle of materials. I cannot infer from this evidence
that there was any agreement to exclude a floor waste (which in all
events appears contrary to the applicable Australian Standard). Equally,
it is the case that the homeowners deny ever having made such an
amendment.
[51] Although Mr Manion also contends that good building practice requires
that the fall across the laundry floor be directed towards the nearest exit
for flood-control, I find this assertion to be inconsistent with what is
specified by plain words in paragraph 3.11 of AS3740-2010. I do not
accept Mr Manion‟s evidence on this particular point. Even if there is fall
to the nearest exit, photographs of a four-foot spirit level across the tiled
floor which have been included as part of the homeowners bundle (which
evidence I have already said I have accepted), does tend to suggest that
the floors in each of the powder room and the laundry are level; such that
it is now very difficult to accept that that there is any fall across the floor,
towards the nearest exit.
[52] On the basis of the evidence before me – and here relying in particular on
AS3740-2010 – I find that each of the laundry and powder room qualify
as “wet areas” (paragraph 1.4.28 in AS3740-2010 refers), such that the
floor finish in each of these rooms ought to have been constructed so that
water flows to the floor waste. Although it was commendable for the
builder to install floor wastes after the omission had been identified, the
difficulty is that the retrofit cannot achieve the necessary fall in the floor,
so as to comply with the Australian Standard. The tiled floors in each of
the powder room and the laundry will need to be lifted, in order that the
finished tiled floor can be re-installed, once an appropriate tile bedding
with fall-to-waste has been constructed. This is an unfortunate state of
affairs, given that an apparently good quality tiling job (together with any
preliminary waterproofing), must now be destroyed in order to fix the
problem, but there would appear to be no way around it.
[53] The homeowners have obtained quotations (now Exhibit 5) from two tilers
and two plumbers in relation to the necessary works to redo the laundry
and powder room in order to obtain the necessary fall-to-waste in the
floors. The lowest of these is that for $2,095.50 in accordance with the
quotation obtained from “David Head Wall and Floor Tiling”, dated
15 March 2011. To this figure must still be added a further estimated
$468.00 for tiles and about $500.00 for associated plumbing works.
-- 12 of 27 --
13
I accept these estimates as reasonable and now order that there be a
further variation in favour of the homeowners in the sum of $3,063.50.
Practical Completion
[54] The applicants contend that as at the time of this application to QCAT the
domestic building construction project at No 33 Leila Place at Pullenvale
had not reached practical completion, by reason of the matters listed in
folios 02 to 07 of the materials that were filed in this tribunal by the
homeowners in accordance with a tribunal direction given to them on
9 February 2011. These matters are, of course, those matters previously
addressed in these reasons.
[55] Matter 02 relates to the H-3 treatment of timber. This issue was
dismissed from this claim (with the consent of the parties) and it is
certainly apparent to me that all timbers within the construction project at
33 Leila Place that were required to be treated to H-3 standard had been
treated to that standard, such that it cannot be said that this aspect of the
construction project had not ever reached practical completion. In
addition, dispute item 06 (being the retaining wall issues) was also not
pursued by the homeowners as part of these proceedings. In short
therefore the applicants now contend that the dispute referable to the
condition of the SHS posts; matters going to the internal painting; matters
going to the condition of the guttering; and the absence of proper fall-to-
waste in the tiled floor of the laundry and powder room are matters that
have the further result that the project has also not attained practical
completion. For reasons that I shall now elaborate, I cannot agree with
that contention.
[56] “Practical completion” is a matter that is defined in the general conditions
of the Standard Master Builders‟ Residential Building Contract:
Practical completion stage means that stage of the works when
the works are completed in accordance with the contract and all
relevant statutory requirements, apart from minor omissions or
minor defects, and the works are reasonably suitable for
habitation.
[57] Whether the project has attained practical completion is now a question
for this Tribunal to determine. In relation to the allegation that Fine Edge
did not attain practical completion, the homeowners assert:
a. the project cannot be said to have reached practical completion
because of the omissions and defects previously raised by the
homeowners;
b. upon achieving practical completion pursuant to the contract a
defects document is required to be submitted by the builder to the
homeowners pursuant to Clause 17.5;
c. The defects document provided to them by Fine Edge is non-
compliant for reasons stated by them in Mr Bell‟s e-mail
-- 13 of 27 --
14
correspondence to Mr David Manion of 14 September 2010. As
part of Mr Bell‟s e-mail correspondence of that date he contends
that on Monday 13 September 2010 there had been a meeting on
site at No 33 Leila Place at which the builder had spoken to
Handovers.com Pty Ltd, whom Mr and Mrs Bell had been intent on
using as their accompanying agent during the practical completion
inspection, yet Mr Manion refused to let the representative from
Handovers.com participate in the inspection. Mr Bell further
records that Mr Manion did produce a practical completion stage
notice and advised him that this stage had been reached the
previous Friday, 10 September 2010. Mr Bell further records that
the builder and the owners conducted an inspection to identify
omissions and defects and that the builder completed a defects
document. Yet, the owners allege that the builder refused to
include in the defects document certain matters identified by them.
On 22 September 2010, Handovers.com did conduct a further
inspection of the house at 33 Leila Place. That inspection report
(now attachment 08.04 in the applicants‟ bundle of materials) does
record that the project had attained practical completion.
[58] As might be expected, the version of events going to the meeting on
13 September 2010 as has been given to this tribunal given by the builder
is slightly different to that given by the homeowners. According to Mr
Manion, the project had reached practical completion on 13 September
2010, albeit with some minor defects and omissions. Fine Edge says that
in accordance with Clause 17 of the Residential Building Contract it is
necessary that there be a meeting on-site between the homeowner and
the builder. Upon reaching the practical completion stage the builder
must also give to the owner a final progress claim and a practical
completion stage notice stating the date at which the works reach
practical completion and providing for a final inspection.
[59] Mr Manion says that the final inspection took place on site at 1:30pm on
13 September 2010 and did not conclude until approximately 4:45pm. Mr
Manion says that both Mr Bell and Mrs Bell were present at that
inspection. Mr Manion says that at the final inspection he produced the
necessary defects document, as required by Clause 17.5, yet that Mr Bell
indicated that he would only sign the defects document if further words
were added referable to the agreed defects including those later identified
by Handovers.com. Mr Manion also says that he refused to agree to that.
[60] To the extent that there is any factual dispute as between the
homeowners and Fine Edge regarding the events of 13 September 2010,
I prefer the version of events given by Mr David Manion.
[61] I note that Clause 17.1(b)(ii) of the standard contract provides for a final
inspection of the works “with the owner or the owner‟s agent”. “Or” is a
disjunctive term, and I note that on both the version given by the
applicants and the version given by the respondent the homeowners
were available to participate (and did participate) in the final inspection
with Mr Manion, on 13 September 2010. I find therefore that it was
unnecessary for Handovers.com to attend as the owner‟s agent, and that
-- 14 of 27 --
15
Mr Manion was entitled to insist on conducting the final inspection with
the homeowners, only. The site remained under the formal control of the
builder until hand over, and Mr Manion then had sufficient contractual
authority to exclude a third party.
[62] On 16 September 2010, the homeowners provided correspondence to
the respondent indicating their view that the practical completion had not
been reached. Furthermore, the homeowners indicated that they were of
the view that failure to reach practical completion had the effect that the
liquidated damages provision in Clause 18 of the Residential Building
contract became operational from 15 September 2010, by reason that the
builder had not reached practical completion by the agreed date for
practical completion.
[63] As indicated previously, I do not accept that contention. The
homeowners‟ argument regarding the non-attainment of practical
completion suffers from a type of dogmatic circularity: if there are defects
or omissions there can be no practical completion. The logic in that
argument suffers because it is inconsistent with the standard terms of the
residential building contract, which comprehends that practical completion
may be attained notwithstanding the fact of either defects or omissions.
That much is clear from the definition of „Practical Completion Stage‟, and
is why the standard contract further contemplates, in Part 19, a „Defects
Liability Period‟, during which time the builder has make-good obligations,
which run for a further six months beyond practical completion.
[64] In my view, Fine Edge attained practical completion, by the required date
for same. The date for practical completion at the inception of the
contract was initially 3 September 2010 (being 382.6 days from the date
of commencement, being the date upon which the slab was done). Yet
this was later varied, by agreement, until 14 September 2010.
[65] Practical completion contemplates the works be certified by the builder as
completed in accordance with the contract and all relevant statutory
requirements for construction apart from minor omissions or minor
defects, and the works are then reasonably suitable for habitation.
[66] I find that as at 14 September 2010 the house at No 33 Leila Place,
Pullenvale was “practically complete” and “reasonably suitable for
habitation”. On the evidence before me the worst defect relates to the
condition of the tiled floor in the powder room and laundry, which were
constructed without proper fall-to-waste. However, that defect hardly
qualifies as a matter that renders No 33 Leila Place unfit for human
habitation.
[67] As part of their application the homeowners have requested that the
Tribunal adopt an independent inspection report produced by
Handovers.com as an agreed defects list. At no time has Fine Edge ever
agreed to the content of the document produced by Handovers.com Pty
Ltd. I decline therefore to adopt this as an “agreed” defects list. In all
events, I note that the document prepared by Handovers.com (that dated
22 September 2010) indicates that the builder had attained practical
-- 15 of 27 --
16
completion when Handovers.com inspected the property, relatively soon
after the final inspection conducted between Mr Manion and Mr and Mrs
Bell. It is disingenuous therefore for the homeowners to persist in
asserting that the builder has not reached practical completion (indeed,
as they have consistently, ever since their letter to Mr Manion dated 16
September 2010), in circumstances where their own expert‟s report
expresses the opinion that the project had attained practical completion.
[68] I find therefore that the builder‟s entitlement to the final progress payment
had crystallised at the time when Fine Edge provided the practical
completion certificate and that payment ought to have been made by the
homeowners in accordance with the usual time frames contemplated in
the standard terms and conditions of the Residential Building Contract.
Fine Edge ought to have been paid their final progress claim by
18 September 2010.
[69] Although Fine Edge says that the defects and omissions identified by Mr
David Manion on 13 September 2010 constitute the entirety of the defects
and omissions, it is now the case that this contention has been overtaken
by my own findings, as the umpire in this dispute. I have found there are
some further defects and omissions that were not part of the original
defects and omissions list prepared by Mr Manion on 13 September
2011. These matters have been the subject of orders by me for contract
variations in favour of the applicants. For the complete avoidance of
doubt, I declare that the additional minor defects and omissions identified
by me in these reasons do not detract from my having found that the
builder attained practical completion, on 13 September 2010.
[70] In their correspondence dated 16 September 2010, the homeowners also
contend that the builder is in breach of Clauses 9, 10 and 11 of the
general conditions by reason that the builder has failed to carry out the
works in accordance with the plans and specifications by the
incorporation into the works of non-compliant materials. I infer this to be
a reference to the H-3 timber issue (in circumstances where no
particulars have ever been provided by the homeowners), and in
circumstances in which ultimately, it has been demonstrated that the
builder did, in fact, use timber that had been treated to the H-3 standard.
[71] Further, the homeowners contend that the builder is in breach of contract
for having failed to carry out the works with reasonable care and skill by
his covering up non-compliant material (again an apparent reference to
the H-3 timber issue) and, contrary to Clause 10.1(c) failing to calculate
prime cost items and provisional sums with reasonable care and skill, by
the builder having stated amounts in the contract that are less than the
reasonable costs of providing the item or service. Having made the
allegation of a breach of contract by the builder, there is an onus on the
homeowners to point to some evidence to establish that breach. Yet
there is no satisfactory evidence before me in support of the assertion
that the builder has failed to calculate either prime cost items or
provisional sum items with reasonable care and skill. I therefore dismiss
the alleged breach of clause 10.1(c) of the contract. The alleged further
breaches of Clauses 9, 10 and 11 of the contract by the builder are also
-- 16 of 27 --
17
matters that have insufficient particularity and such inadequate evidential
foundation that these also cannot be established. I will however have
something more to say about provisional sum and prime cost items, later
in these reasons, in the context of a an application by the homeowners
for a statutory remedy under s 60 of the Domestic Building Contracts Act
2000.
The Liquidated Damages Claim
[72] The Homeowners contend that the project has not attained practical
completion, such that they are entitled to lay claim to liquidated damages
at the contractually agreed rate of $75.00 per day. The Homeowners
now claim the sum of $15,630.00, being their calculation of $75.00 per
day from 14 September 2010 (the date set by the contract for practical
completion) until 11 April 2011, being the first day of the hearing of this
matter before QCAT.
[73] Not by any stretch could a claim for liquidated damages in this sum be
available to the homeowners. Any entitlement to liquidated damages
must first accord with what is permissible under Clause 18.1 of the
standard Master Builders‟ Residential Building Contract.
[74] Clause 18.1 provides that liquidated damages are only payable from the
date of practical completion until the sooner of either the day on which the
project attains practical completion; or the date on which owner takes
possession. It is a matter of record that the homeowners took
possession of No 33 Leila Place from the builder around 16 September
2010, thus terminating any entitlement they may have had to liquidated
damages just two days after the date that had been agreed for practical
completion. Even that entitlement is no more than academic, as I have
found that Fine Edge did attain practical completion one day before the
agreed completion date. I find that the homeowners therefore have no
entitlement to liquidated damages.
The Trust Monies Entitlement
[75] The sum of $28,000 – representing the quantum of the builder‟s final
progress claim made under Fine Edge invoice No. 265 (as was issued by
the builder to the homeowners by hand on 13 September 2010) is
presently held in trust by the Queensland Master Builders Association,
whom have produced a trust account receipt for same dated
16 September 2010.
[76] It follows from my earlier line of reasoning that I am of the view that
practical completion was reached by Fine Edge on 13 September 2010.
I order therefore that the responsible officer at Master Builders‟
Queensland now release the sum of $28,000 (QMBA File Reference T-
10-024) to Sambuc Pty Ltd (Trading as Fine Edge Homes).
The Commercial Issues
-- 17 of 27 --
18
[77] As the term has been used in these proceedings the so-called
“commercial issues” really relate to the builder‟s contractual entitlement to
be paid interest on late payments by the homeowners in relation to
progress claims, as well as the builder‟s entitlement to payment for
various provisional and prime cost items under the contract, particularly in
light that the homeowners have now made application to QCAT to have
some of these determined pursuant to sections 59 and 60 of the
Domestic Building Contracts Act 2000.
The Interest Claims
[78] The dispute in this domain relates to late payments of builder‟s progress
claims numbered: 2 („Slab down‟); 5 („Frames and Trusses installed‟);
6 („Roof installed‟); 7 („Decking‟); 9 („Internal fit off‟); and 11 („Final‟).
[79] Progress claim 2 (“Slab down”) was submitted to the Homeowners on
18 August 2009 by means of invoice 115. Pursuant to item 20 („payment
period‟) of the contract, payment was required within 5 days, or by
24 August 2009. The homeowners did not make payment until
3 September 2009. The payment was late, by 9 days.
[80] Progress claim 5 (“Frame and trusses installed”) was submitted to the
Homeowners on 15 February 2010 by means of invoice 161. Pursuant to
the contract payment was required by 20 February 2010. The
homeowners did not make payment until 22 March 2010, some 30 days
late.
[81] Progress claim 6 (“Roof on”) was submitted to the Homeowners on
24 February 2010 by means of invoice 167. Pursuant to the contract
payment was required by 1 March 2010. The homeowners did not make
payment until 22 March 2010, some 21 days late.
[82] Progress claim 7 (“Decking”) was submitted to the Homeowners on
5 March 2010 by means of invoice 171. Payment was required by
10 March 2010. Payment was not made by the homeowners until
22 March 2010, some 20 days late.
[83] Progress claim 9 (“Internal fit off”) was submitted to the Homeowners on
7 June 2010 by means of invoice 228. Payment was required by 12 June
2010. Payment was not made by the homeowners until 16 June 2010,
some 4 days late.
[84] Progress claim 10 (“Landscaping”) was submitted to the Homeowners on
22 July 2010 by means of invoice 243. Payment was required by 27 July
2010. The homeowners did not make payment until 19 August 2010,
some 23 days late.
[85] Progress claim 11 (“Final”) was submitted to the Homeowners on
13 September 2010 by means of invoice 265. Payment was required by
18 September 2010. Payment was not made by the homeowners and
instead this sum was placed into the QMBA trust, after the Homeowners
-- 18 of 27 --
19
had notified Fine Edge of a dispute regarding practical completion. Fine
Edge now seeks interest on that sum, as well.
[86] In their materials filed on 9 February 2011 the homeowners seek, in part,
that this tribunal determine the entitlement of the builder to payment of
interest in relation to these late payments of the builder‟s progress claims.
In their written response submissions to the cross-application filed by
Fine Edge, which was filed by the homeowners on 5 May 2011 (by leave
given by me at the conclusion of the hearing), the homeowners raise, for
the first time, the point that the progress claims presented to them by the
builder did not contain any certification from the builder that the works
had been completed to the relevant stage, as required by clause 11.6.
This is not a matter that has been raised by the homeowners at any time
prior to 5 May 2011, such that I find that the homeowners have waived
the benefit of clause 11.6.
[87] I determine that the homeowners did receive progress claims in sufficient
conformity with clause 11.6, such that their obligations under clause 11.7
to pay the builder on each of those progress payments did arise, and, to
the extent that these were not paid within the time allowed by item 20 of
the contract, Fine Edge became entitled to interest pursuant to clause
11.9 of the contract at the rate specified in item 19 of the contract, being
15%, calculated daily. Accordingly I find that in relation to the late
progress payments the homeowners should pay Fine Edge interest in
accordance with the following:
Stage & Amount Days
overdue
Interest
Calculation
Interest
Amount
2 („Slab down‟)
$84,000
9 9/365.25 x .15 =
0.003696
$310.46
5 („Frames and
Trusses installed‟)
$28,000
30 30/365.25 x .15 =
0.0123203
$344.97
6 („Roof installed‟)
$28,000.01
21 21/365.25 x .15 =
0.0086242
$241.48
7 („Decking‟)
$56,000.00
20 20/365.25 x .15 =
0.0082135
459.96
9 („Internal fit off‟)
$112,000.00
4 4/365.25 x .15 =
0.0016427
$183.98
11 („Final‟)
$28,000.01
204 204/365.25 x .15
= .0837782
$2,345.79
Total Interest: -- -- $3,886.64
Provisional sum and prime cost items
[88] On 22 July 2010 Fine Edge sent the Homeowners “the first and not the
final”1 invoice for provisional sum and prime cost items („ps/pc‟) in the
form of Tax Invoice No. 244, in the sum of $36,300.97.
1 See the e-mail from Mr David Manion to Mr Jon Bell dated 22 July 2010.
-- 19 of 27 --
20
[89] By an e-mail dated 9 August 2010 Mr Manion then sent an updated
invoice for ps/pc items, which says that it included all the various invoices
that Fine Edge had received from various subcontractors and suppliers
for ps/pc items. I accept that to be the case. On or about 24 August
2010 Invoice 244 was reduced to $24,189.99 after taking into account
some payments and credits, totalling $12,110.98.
[90] The homeowners have, again by their filed material, specifically
contested the costs that have been passed on to them for the following
ps/pc items: air-conditioning; floor sanding and polishing; and the external
(veranda) balustrade.
[91] Earlier in these reasons I have indicated that the state of the evidence
does not allow me to make a finding that Fine Edge are in breach of a
contractual warranty raised by clause 10.1(c) of the standard Residential
Building Contract, by reason of any (alleged) failure to calculate prime
cost items and/or provisional sum items with reasonable care and skill.
That however is not the end of the matter, as there are also parallel
statutory remedies that are available to the homeowners, pursuant to s 60
of the Domestic Building Contracts Act 2000 („DBCA‟). The homeowners
now rely upon s 60 of the DBCA, and ask that QCAT use s 60 of the
DBCA to reduce their liability with respect these particular provisional
sum items, down to the amount originally stated in Part B of the contract,
to the extent that QCAT considers appropriate.
[92] To understand the potential remedy for homeowners to be found in s 60
of the DBCA, one must first have recourse to s 59. The relevant portions
of s 59 provide that, with respect to prime cost or provisional sum items:
59 Stating amounts
(1) A building contractor must not enter into a regulated contract
stating-
(a) an amount for a prime cost item that is less than the
reasonable cost of supplying and delivering the item; or
(b) a provisional sum that is less than the reasonable cost of
providing the contracted services to which the sum relates.
Maximum penalty - 50 penalty units.
…
(3) In deciding, for subsection (1), what is a reasonable cost, regard
must be had to—
(a) the information the building contractor had, or reasonably
should have had, when the contract was entered into; and
(b) the nature and location of the building site.
[93] Section 60 of the DBCA then provides:
60 Effect of improper statements
-- 20 of 27 --
21
(1) This section applies if a building contractor enters into a regulated
contract in contravention of section 59(1).
(2) The contravention does not make any provision of the contract
illegal or void.
(3) However, the tribunal may, on an application made, as provided
under the QCAT Act, to the tribunal by the building owner, reduce
the building owner's liability, for the item or contracted services to
which the stated amount or sum relates, to the extent the tribunal
considers appropriate.
[94] Disputes regarding escalations in the costs of provisional sum allowances
and/or prime cost items in domestic building disputes are all too common
before QCAT. This was also the case before QCAT‟s predecessor, the
Commercial and Consumer Tribunal („CCT‟).
[95] In T & T Corporation Pty Ltd t/a Townsend Building Services v Boyaci,
B. [2008] QCCTB 135 (“T & T”), CCT Member Butler AM SC (as he then
was), expressed the view that dramatic provisional sum increases really
warrant the preparation of a written variation, by the builder, for
presentation to the homeowner. Here, the thinking was that this would
then provide the party who is ultimately responsible for payment with a
proper opportunity to consider their position, about the costs of the
proposed works, before instructing the builder to proceed with it. Member
Butler put the matter in these terms:
The builder is entitled to receive the provisional sum increase
where there has been a legitimate increase in cost of the specified
work ordered by the proprietor over the amount estimated by the
builder at the time of contracting. Ordinarily this would arise
because the price charged by a sub-contractor varied from the
builder’s original estimate. The magnitude of the increase claimed
here indicates it is not such a [sic] increase. In the absence of any
specific evidence, one can only assume that an increase of such a
magnitude reflects the introduction of work not contemplated at
the time the provisional sum estimate was made. If that be so, the
cost of additional work should have given rise to an application for
a variation of the contract sum so that the respondent could
consider his position as to the nature and extent of the proposed
works.
[96] In T & T, Member Butler found that an increase in joinery costs for the
project did not constitute a legitimate provisional sum, but should have
been the subject of a variation, raised by the builder. The proprietor of
the premises where the work was performed in T & T had not been given
an opportunity to consider his position, which would have occurred had
the works been the subject of a written variation. This is for the reason
that a written variation, to be valid, needs to be signed before the works
are performed. Accordingly, Member Butler fixed the costs for the joinery
work performed at the level of the provisional sum estimate reflected in
the contract.
-- 21 of 27 --
22
[97] The authority afforded by T & T is not absolutely determinative of the
approach that must be taken in an effort to resolve these types of
disputes. For reasons that I will shortly elaborate, the circumstances of
this case are different, at least in my view, to those that arose in T & T.
[98] On the facts before me, I consider the approach taken by CCT Member
Oliver (as he then was) in Sparkes v Bali Pools Pty Ltd [2009] QCCTB
95 (“Sparkes”) affords a more apposite approach, in this case. In
Sparkes, Member Oliver (I think correctly), identified that the effect of s 59
of the DBCA, by virtue of s 60, “does not vitiate the contract, but provides
for a penalty to the contactor and permits a financial adjustment to ensure
fairness”. This is expressed in s 60(3) as a discretion that inures in
QCAT, by reason of the expression used in the provision: “to the extent
the tribunal considers appropriate”. In other words the adjustment need
not be all the way down to the estimate originally allowed by the builder
for the provisional sum or prime cost item, in the contract.
[99] I find that the facts before me are distinguishable from those that were
before Member Butler in T & T. In contrast to matters in T & T, where the
evidence did show that the homeowner‟s joinery requirements had
remained unchanged, here, I find that the state of the evidence does not
allow me to draw that conclusion. In deciding whether to reduce the
homeowners‟ liability for the quantum of the air-conditioning, floor
polishing and balustrade, I must have regard to the information that Fine
Edge had, or reasonably should have had, at the time the contract was
entered into, as well as any extrinsic evidence regarding the escalation in
price for each of these items. I must, of necessity, do that on a piecemeal
basis.
[100] With respect each these disputed costs, the homeowners have not
produced any actual evidence (beyond their own assertion) that might
tend to show that these works could have been undertaken for less than
the costs that were eventually passed on to them, with the builder‟s
margin.
[101] Unfortunately Fine Edge also did not address these issues with any great
particularity, such that it now falls to me, largely by an examination of the
available sub-contractor invoices for each of the disputed items, in order
to make some determination as to what seems just and reasonable, in all
the circumstances.
The Air-conditioning
[102] As regards the air-conditioning, the homeowners say that the provisional
sum amount allowed by the builder was $11,925.45. Despite the scope
of air-conditioning works having been allegedly reduced by them to
exclude air-conditioning from the rumpus room and bedroom 4, the
amount eventually claimed by Fine Edge for air-conditioning works was
$16,702.20; or an increase of about 40% over the sum provided on a
provisional basis in the contract.
-- 22 of 27 --
23
[103] There is limited evidence from either of the parties going to the
circumstances of the air-conditioning selection and installation. I do note
an e-mail from Mr Manion to Mr Bell on 31 July 2009 enclosing a quote
for air-conditioning works. That e-mail also advises that the system
would require an upgrade to three-phase power and the installation of a
separate metre box (themselves matters the subject of an agreed
variation). The air-conditioning invoices provided by the builder (dated
2 July 2010) from Elliott Air Conditioning indicate the system, was an
18Kw ducted system, quoted at $13,753, which was just for the air-
conditioning unit, alone. Other associated works (ducting, insulation, and
so on), were also performed by Elliott Air Conditioning.
[104] The price of ducted air conditioning is notoriously variable, depending on
what type of system is ultimately selected. I am not prepared to find that
the provisional sum allowance amount of $11,925.45 was manifestly
inadequate or in any way a provisional sum that might be regarded as
less than the reasonable estimated cost of providing the contracted
services to which the sum relates, as contemplated by s 59 of the DBCA.
I decline therefore to find any breach of s 59 of the DBCA, and hence do
not have the power to exercise a discretion and reduce the amount of
Fine Edge‟s claim for this particular item, pursuant to s 60 of the DBCA.
Floor Sanding and Polishing
[105] The homeowners say that Fine Edge allowed a provisional sum amount
of $4,727.27 under the contract, yet they were eventually charged
$9,920.51 for the finishing of their hard wood floors (an increase of about
110%), despite the homeowners claiming that there had been no change
in the scope of works for this item.
[106] The evidence as to why the cost of this provisional sum item blew out by
so much is scant, indeed. Floor sanding and polishing is a far more
predictable undertaking than is that of air conditioning installation. Given
the state of the evidence my sense of the matter is that Fine Edge made
insufficient allowance for this particular provisional sum item, in breach of
s 59(1)(b) of the DBCA. In light of this I am prepared to make an
adjustment under this head pursuant to s 60(3) of the DBCA. I do so
solely on the basis of the statutory discretion. As indicated previously I
am not prepared to go further and find that Fine Edge are in breach of
clause 10.1(c) of the contract, given the state of the evidence.
[107] In my view, a reasonable escalation in the cost of floor sanding and
polishing would be no more than about 20% of the sum provisionally
allowed. I will therefore allow a payment for this provisional sum item on
the basis of:
Contract allowance: $4,727.27
Reasonable additional cost ($4727.27 x 0.2): $ 945.45
Builder‟s margin on excess ($945.45 @ 20%): $ 189.09
Allowable Claim: $5,861.81
The Veranda Balustrade
-- 23 of 27 --
24
[108] In respect of the veranda balustrade, the homeowners say that the
provisional sum allowed for this item was $12,000 on an assumption that
the balustrade would be 43.1 lineal metres. Yet, the homeowners also
say the scope of works was reduced by them during construction by
6.617 lineal metres (making for a total balustrade length of approximately
36.5 lineal metres). Ultimately, Fine Edge has charged them $18,223.81,
or about 52% more, for this item. I have seen photographs of the
selected balustrade. It is an architectural feature of the home (in other
words a non-standard item), wherein steel and timber are combined. In
all the circumstances I am not inclined to the view that the sum claimed
by the builder on a provisional basis is unreasonable, or that the amount
allowed on a provisional basis is in breach of s 59(1) of the DBCA. I find
therefore that the homeowners should pay the amount claimed by Fine
Edge for this item.
The Builder’s Counter-Application.
[109] Fine Edge filed a Response and/or Counter-Application before QCAT on
17 August 2010, originally seeking that the homeowners‟ application be
dismissed, together with payment of $66,721.20 then claimed to be owing
to it in accordance with various unpaid progress claims. For reasons that
should by now be clear from the foregoing parts of these Reasons for
Decision, I have not dismissed the homeowner‟s application, which I have
upheld, in part.
[110] Examination must now turn to the builder‟s counter-application, which
was revised downwards on 21 April 2011 to the outstanding tax invoices,2
which total $74,974.47. Fine Edge also however acknowledge that there
are a number of credit notes,3 totalling $12,583.58, thereby making for a
claimed outstanding balance of $62,390.89. The homeowners contend4
that they have paid Fine Edge in full, and that no amounts remain
outstanding.
[111] Invoice 110 relates to a variation for steel portals as arose per a variation
contract by signed e-mail on 5 August 2009. The amount is $2,839.00.
In my view, that is a legitimate claim and the homeowners should now
pay it.
[112] Tax invoice 109 was raised on 10 August 2009 and relates to a variation
to the contract for three-phase power connection and upgrade to the
meter box, as per an e-mail of 4 August 2009. The amount claimed by
invoice 109 is $1,900.94. Again, in my view this is a legitimate claim by
the builder, and the homeowners should now pay it.
[113] Fine Edge raised invoice number 119 on 25 August 2009. It is a claim in
the sum of $2,474.34 referable to additional costs for rock anchors (and
builder‟s margin), referable to the construction of some retaining walls.
I am of the view that this sum should also now be paid to Fine Edge, by
the homeowners.
2 Invoice Nos. 110, 109, 117, 242, 244, 261, 260, 265 and 264.
3 Credit Notes Nos. 263, 258, 259, 195, 121 and 282.
4 See the homeowner‟s response to cross application, filed before QCAT on 5 May 2011.
-- 24 of 27 --
25
[114] Invoice number 242, in the sum of $2,420.22, relates to additional
excavation costs incurred by the builder referable to the rectification of
cave-ins to footings caused by rain; unforeseen rock excavation of
footings, and additional excavator hire time, for the construction of a
sewerage line at the rear of the house. The homeowners have refused to
pay this invoice. The homeowners contend that the builder has no
entitlement to payment for these sums because the builder failed to notify
them in relation to his discovery of a “latent condition” as required by
Clause 14.1 of the Standard Contract.
[115] It is to be noted that not all of invoice 242 relates to any latent condition,
as some of these costs (for example, additional machine time and
additional costs occasioned by the cave-in of footings) is not referable to
any latent condition, as defined. On balance, I am not prepared to find
that the builder has failed to comply with Clause 14.1 of the contract
insofar as it requires the builder to notify the owner of latent conditions.
This is because I note e-mail correspondence from Mr John Bell to Mr
David Manion on 31 October 2009 in which Mr Bell approves variations
referable to a redesign of footings for the construction of the house at 33
Leila Place. Although Mr Bell also purports by that e-mail that his
approval is conditioned upon “no extra costs for this variation”. It is
sufficiently clear that the homeowners have approved additional works
referable to the preparation of footings, and it is unreasonable for them to
take the benefit of these variations yet unilaterally declare that they will
not pay for the costs of additional works occasioned by them. In my
further view, the additional costs occasioned by the need for 7 ½ hours of
unforseen excavator hire time in order to undertake rock excavation for
the preparation of these footings is not a matter that was reasonably
foreseeable by the builder, notwithstanding that the builder had a geo-
technical report beforehand. Oftentimes these types of things cannot be
estimated in advance with any precision. Clause 14.5 of the contract
does not, in my view, preclude Fine Edge from an entitlement to these
additional costs. The full amount outstanding on invoice 242 should now
be paid to the builder.
[116] Invoice number 244 is for provisional sum and prime cost items. Fine
Edge raised it on 24 August 2010 in the sum of $33,000.88. The
homeowners take issue with same saying that many of the items covered
in invoice 244 are replicated in invoices 264 and 265. They also say that
invoice 244 was met by them when they paid the progress claim for
landscaping. On balance I prefer the evidence of the builder. In my view
the homeowners are required to pay tax invoice 244.
[117] Invoice number 261 was raised by the builder for a variation signed on
17 July 2009 for a rear deck extension beyond that which had been
originally envisaged in the plans that accompanied the building contract
for the house at 33 Leila Place. It is in the sum of $2,200.00. The
homeowners should also now pay that sum.
[118] Similarly, invoice 260 also relates to a signed variation (signed on
8 March 2010) for an adjustment made to the timber frame and door to
-- 25 of 27 --
26
the powder room. The amount of the invoice is $1,220.00. In my view
that sum should now be paid by the homeowners.
[119] Invoice 265 relates to the final progress claim. Earlier in these Reasons
for Decision I have indicated that the amount of the final progress claim
which has been placed by the homeowners in trust with the Queensland
Master Builders Association should be paid to Fine Edge, on the basis of
my determination that the builder had attained practical completion on
13 September 2010.
[120] The final invoice that Fine Edge claims remains outstanding is invoice
264. This invoice is also for provisional sum and prime cost items and is
in the amount of $12,204.32. The homeowners contend that the items
covered by this invoice are a duplication of items previously included in
invoice 244. I have not been provided with any examples of any alleged
duplication. I do not accept the homeowners‟ contention in that regard,
and note that the builder is in a better position to determine which items
have now been paid, and which have not. The homeowners should also
pay invoice 264.
Credit Adjustments
[121] As indicated earlier in these reasons, the builder has identified certain
items for which credit notes and adjustments should be given to the
homeowners. The builder has included these credit notes as part of its
final submissions filed before QCAT on 21 April 2011. I am satisfied that
on a full settling of accounts, the builder is correct in identifying that
$12,593.58 should now be credited against any outstanding balance
owed by the homeowners to the builder. I conclude therefore that Fine
Edge has a legitimate claim for $62,390.89.
Final Accounting
[122] In light of my foregoing reasons, there should be contract adjustments in
favour of Mr and Mrs Bell in accordance with the following:
SHS Posts $1,200.00
Internal Painting $2,000.00
Rainheads $500.00
Floor Wastes $3,063.50
S 60 DBCA adjustment: Floor polishing $4,058.70
TOTAL: $10,822.20
[123] Fine Edge has established an entitlement to $62,390.89 and I have found
a further entitlement to interest on late payment of progress claims of
$3,886.64, thus making for a total entitlement by the builder from the
homeowners of $66,277.53. The sum still owing to Fine Edge should
then be reduced by $10,822.20 on the basis of the contract variations that
I have found, such that I find that the Applicants now owe to the
Respondent the sum of $55,455.33. This figure includes the sum of
$28,000 currently held in the Queensland Master Builders‟ Trust Account,
pending the resolution of this dispute.
-- 26 of 27 --
27
Conclusions & Order
[124] In conclusion, I order as follows:
(a) By consent, all issues relating to H3 treatment of timber are
dismissed.
(b) The responsible officer at Master Builders‟ Queensland is to
release from trust the sum of $28,000 (QMBA File Reference T-
10-024) to Sambuc Pty Ltd (Trading as Fine Edge Homes).
(c) The Applicants are to pay to the Respondent the further sum of
$27,455.33 within 28 days of the date of these orders in final
satisfaction of the respondent‟s claims for payment for the costs of
constructing the house at 33 Leila Place, at Pullenvale.
-- 27 of 27 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2011/378