Burness v Halemead Investments Pty Ltd [2011] QCAT 405
CITATION: Burness v Halemead Investments Pty Ltd
[2011] QCAT 405
PARTIES: Mrs Hydie Dawn Burness
v
Halemead Investments Pty Ltd t/as Casino Pools
APPLICATION NUMBER: BDL060-11
MATTER TYPE: Building matters
HEARING DATE: 10 August 2011
HEARD AT: Southport/On the papers
DECISION OF: Mr Andrew McLean Williams, Member
DELIVERED ON: 29 August 2011
DELIVERED AT: Brisbane
ORDERS MADE: Application dismissed.
CATCHWORDS: Domestic building dispute – swimming pool –
unforeseen excavation costs invoiced to
customer together with contractor‟s margin – no
variation document presented to customer
beforehand – circumstances in which variation
document required/not required – contractual
entitlement to contractor‟s margin in
circumstances where site access difficulties
cause additional costs
APPEARANCES and REPRESENTATION (if any):
APPLICANT: Mrs Burness, in person
RESPONDENT: Mr Phillip Dufty (director), in person.
REASONS FOR DECISION
[1] This matter was originally listed for a compulsory conference before
me at Southport, at 9.30am on 10 August 2011. Owing to some
confusion regarding the location for the compulsory conference (a
matter that was not due to the fault of either of the parties), the
Applicant and the Respondent did not appear at the same time, such
that it was not physically possible to convene a compulsory
conference, at least not on the scheduled occasion.
-- 1 of 8 --
2
[2] In the circumstances, and rather than re-list the matter for a
compulsory conference on another occasion (and by consent), each
party agreed to make ex parte submissions to me, and to then have
the matter determined by me on the basis of those submissions,
together with any materials filed by them as part of this application.
I now proceed to give my reasons for decision on that basis.
Factual Background
[3] Mrs Hydie Dawn Burness commenced her application before QCAT on
18 March 2011. Mrs Burness seeks the recovery of $2,522.10,
together with her QCAT filing fee of $255 (a total claim of $2,771.10),
from the Respondent, who is Halemead Investments Pty Ltd, trading
as “Casino Pools” (hereafter referred to as “Casino Pools”).
[4] Mrs Burness entered into a contract with Casino Pools on a standard
Swimming Pool and Spa Association of Queensland („SPASA‟)
Domestic Contract – Swimming or Spa Pool. That contract (SPASA
Contract No. 10747) was signed by the contracting parties on
23 September 2010. The agreed price was $29,500 and the contract
required Casino Pools to construct an 8.5 metre by 4 metre in-ground
swimming pool (together with associated works) at an address at
Pacific Pines where Mrs Burness and her husband were also having a
new home constructed at about that time.
[5] The swimming pool has now been completed. Casino Pools handed
the pool over to Mrs Burness on 15 December 2010. Mrs Burness
reports no real difficulties with the quality of workmanship in the
construction of the swimming pool, and this dispute is confined to one
invoice (being Invoice No. 52174) as was sent to Mrs Burness on
26 November 2010, claiming $2,762.10 for additional pool fencing and
some extra excavation costs.
[6] The additional costs for approximately two metres of pool fencing
(totalling $240 inclusive of GST), which forms one part of invoice
52174, is not in dispute. Mrs Burness agrees that she was required to
pay this additional amount, due to some changes that were made
during construction to make further space available for the pool pump
and filter. Mrs Burness does however dispute her obligation to pay the
additional excavation costs, in the sum of $2,522.10 that makes up the
majority of the amount charged to her by invoice No. 52174.
[7] Invoice 52174 has already been paid by Mrs Burness, in full. Mrs
Burness seeks orders from QCAT that Casino Pools be required to
repay $2,522.10, together with her $255.00 QCAT filing fee.
[8] Mrs Burness states that the first that she became aware that she was
being asked to pay these extra excavation costs by Casino Pools was
when she received Invoice No. 52174, which was sent to her as an e-
mail attachment, on 26 November 2010. Mrs Burness also informs
QCAT that she did not receive any variation document pursuant to the
contract before she received Invoice No. 52174. Her own inquiries
-- 2 of 8 --
3
with the Swimming Pool Association („SPASA‟) lead her to believe that
Casino Pools were required to issue her with a variation document
before she was invoiced for any extra amounts.
[9] In his evidence, Mr Dufty (who is the principal of Casino Pools)
confirmed that he did not send a variation notice to Mrs Burness. It
seems therefore that the central issue in this dispute becomes whether
Casino Pools are entitled to claim payment for the additional
excavation costs, notwithstanding that no variation document was
raised by Casino Pools before the invoice was sent. The answer to
that question is to be discerned from an analysis of the terms and
conditions of the standard SPASA contract.
[10] Before analysing the terms and conditions of the SPASA contract,
some further understanding of the reasons why Casino Pools invoiced
Mrs Burness for additional excavation costs is also important, as it may
have some bearing on any contractual entitlement to payment.
[11] In both the written material filed by Casino Pools before QCAT, and in
his brief oral submissions on 10 August 2011, Mr Dufty explained that
there had been a number of initial delays in constructing the pool by
reason that the builder, (who was also constructing a new home for
Mrs Burness on the same site), was unable to provide Casino Pools
with unfettered site access, for a variety of practical reasons. This
meant that the pool dig had to be rescheduled a couple of times, in
circumstances in which Mrs Burness was also anxious to see the pool
construction completed quickly. Finally, the pool dig was scheduled for
1 November 2010. However, in the days leading up to 1 November
2010, there had been a lot of rain, such that site became very boggy.
Mr Dufty informed me – and I now accept – that his excavator arrived
at approximately 10am to commence the dig on 1 November 2010,
together with trucks to remove the spoil. However, the first truck that
day became very heavily bogged, and it became clear to Mr Dufty that
it would be all but impossible to remove the spoil from site, at least not
until the ground had first been allowed to dry out enough to enable his
trucks to run over it. Mr Dufty says that he had a conversation with the
builder, Keith, and a decision was made on the morning of
1 November 2010 that it would be better to cancel the trucks and
stockpile the soil excavated from the pool site into a spoil heap, with
the trucks to return on a later date to collect the spoil, once conditions
had become drier. Mr Dufty says this was his decision, but that Keith
had agreed that this was a sensible strategy, given the circumstances.
Mr Dufty also informed me – and I accept – that he tried to telephone
Mrs Burness to tell her about the problem, yet he was unable to
contact her. Mr Dufty says that the extra excavation costs were
thereby incurred by reason that he had to have trucks and an
excavator return on another date, to remove the stockpile of spoil.
[12] Having developed a factual appreciation of the circumstances in which
the extra costs came about, examination must now turn to the terms
and conditions in the standard SPASA contract, which govern the
-- 3 of 8 --
4
relationship between the parties. A copy of the contract was provided
to me for these purposes by Mrs Burness.
[13] Clause 7 of the Standard Form SPASA contract provides:
“Clause 7 Site Access
1. The customer gives the contractor a licence to enter and
occupy the site for the purpose of performing the works
and exercising the contractor‟s rights under the contract,
and must, at its own cost, ensure that the contractor has
sufficient access to the site to carry out the works,
including sufficient access for vehicles and other
equipment, during the contract and the defects and
liability period.
2. The contractor may exclude persons from the site other
than the customer or the customer‟s authorised
representative and any officer of the BSA or other
authority.
3. The contractor is not liable to the customer for any
damage to any driveway, footpaths, curb, gutter, paving,
underground service, drain, structure or other property
on or near the site, which arises as a result of the
reasonable carrying out of the works by the contractor
and the contractor‟s employees and sub-contractors.
4. If sufficient access to the site is not available when
required by the contractor, the cost incurred by the
contractor in obtaining access, plus the contractor‟s
margin is to be added to the contract price and included
in a progress claim.
5. The customer, and any person authorised by the
customer to attend the site, must not interfere with the
performance of the works.
6. If the customer fails to comply with this Clause, the
customer is liable to the contractor for any delay and any
additional cost incurred by the contractor if the
contractor gives the customer a written notice advising
of the delay or the additional cost within five working
days of the contractor becoming aware of the
interference.
[the emphasis is not in the original, and has been
included here, by me]
[14] Relevant provisions in the contract going to variations and provisional
sums are clauses 11 and 13, which provide:
-- 4 of 8 --
5
“Clause 11 Variations
1. The work to be done, or materials used, under the
contract may be varied:
a. by agreement between the parties;
b. where there is a latent condition, in order to
overcome the latent condition; or
c. where due to the requirement of a private certifier,
statute, local authority or other body having
jurisdiction over the carrying out of the works, in
order to comply with the requirement.
…/
Procedure for Variations
13. Before commencing any work comprising of variation,
the contractor must ensure that the details of the
variation are put in writing in a variation document
signed by both the parties and initialled as necessary
by the customer.
…/
Clause 13 Provisional Sums
1. The contract price includes the items of work shown in
the provisional sums schedule, which sets out the
contractor‟s estimate allowance of the cost of carrying
out each item of work for which the contractor cannot
give a definite price.
2. The contractor may at its discretion allow the customer
a reasonable opportunity, upon the giving of adequate
notice, to be present of the site during the performance
of any work included as a provisional sum in order to
verify the actual cost of the work.
3. If the actual cost for a provisional sum is greater than
the amount allowed, the excess amount together with
the contractor‟s margin on the excess amount is to be
added to the contract price.
4. If the actual cost for a provisional sum is less than the
amount allowed, the difference between the amount
allowed and the actual cost is to be deducted from the
contract price.
-- 5 of 8 --
6
5. Unless otherwise agreed in advance in writing by the
parties, any adjustments to the contract price in
accordance with this Clause, are claimed by:
(a) the contractor making a claim for any adjustment
within five working days from the contractor
becoming aware of the actual cost/s, and
(b) the customer must pay each adjustment claim
within five working days of receiving the
contractor‟s claim.
6. Where the actual cost for a provisional sum is greater
than the provisional amount, the contractor must
provide a copy of any relevant invoice; receipt or other
document evidencing the actual cost of the work at the
time payment is requested.”
[15] In essence, Mrs Burness contends that Casino Pools has no
entitlement to the cost of the additional excavation works occasioned
by the pool builder having to send away the trucks because of wet
weather and then return on a later date, because she did not receive a
variation document from Casino Pools, in accordance with the
procedure specified in clause 11.13.
[16] Variations (thus requiring a “variation document”) are those matters
identified in clause 11.1, being:
(a) variations agreed between the contracting parties;
(b) those arising as a result of “latent conditions”; or
(c) those caused by the need to conform with some directive given
by an inspector, or certifier.
[17] At least arguably, the practical problems that confronted Casino Pools
on 1 November 2010 fall within the rubric of a latent condition, as that
term is used in clause 11.1(b), which would then require the giving of a
variation document beforehand. Latent conditions are referred to in
clause 11.5 and 11.6 of the SPASA contract in the following terms:
“Variation for Latent Condition
5. If, in carrying out the works or attempting to gain access to
the site for materials or equipment, the contractor becomes
aware of any latent condition which affects the
performance of the works, the contractor must give the
customer a written notice describing the latent condition and
the contractor‟s estimate of the work and cost required to
overcome the latent condition.
-- 6 of 8 --
7
6. Subject to this Clause, the contractor may, with the written
consent of the customer, vary the works to overcome the
latent condition.
The expression “latent condition” as used in the SPASA contract is
defined in clause 28 of the Standard SPASA contract, such that “latent
condition” means:
“Any physical condition on or around the site, including
surface, access and sub-surface conditions, which differ
materially from the physical conditions reasonably expected by
the contractor at the time the contract was entered into.”
[18] It seems tolerably clear that, when confronted with abnormally wet and
boggy conditions on 1 November 2010 this was something that
constituted a “latent condition” (as defined), by reason that those
boggy conditions were matters within the notion of “any physical
condition” going to “access conditions”, which differed materially from
the physical conditions reasonably expected by the contractor, from
the time when the contract was entered into. It would seem therefore
that Casino Pools would ordinarily be required, because of clause
11.13, to ensure that the details of the latent condition variation were
put in writing in the form of a variation document for presentation to
Mrs Burness, for her signature, before works proceeded any further.
Although that conclusion is open, I have used the word “ordinarily”
because it is to be noted that clause 11.13 also needs to be read in
conjunction with clause 11.18, which provides that the requirement for
a signed variation document prior to the carrying out of any works does
not apply if, in the contractor‟s opinion, the variation was required to be
carried out urgently and/or it was not reasonably practicable to
produce and have signed a variation document, prior to carrying out
those works.
[19] I accept for present purposes that Mr Dufty had to make a practical
decision “on the spot” on the morning of 1 November and call off the
trucks, as there was really no point in having the trucks continue to
become bogged; thereby still incurring an hourly cost, yet not
achieving any practical purpose. I further accept that reasonable
attempts were made by Mr Dufty to contact Mrs Burness by telephone,
albeit unsuccessfully. I find that, by reason of clause 11.18, Mr Dufty
was not required in these circumstances to issue a variation document
to Mrs Burness before making this pragmatic decision. The inevitable
result of the decision to call off the trucks was that it meant that the
trucks had to return on another occasion, and that further costs were
thereby incurred. This was largely unavoidable, and certainly not due
to any fault by Casino Pools.
[20] Any entitlement to have the disputed invoice paid must also be
considered in the context of the specific site access provisions
contained in clause 7 of the Standard SPASA contract. I have already
set out the words of clause 7, earlier in these reasons for my decision.
-- 7 of 8 --
8
[21] Clause 7.4 (which I have emphasised by means of underlining, further
above) provides that, should insufficient access be available (for
whatever reason) when required by the contractor, then any additional
cost incurred by the contractor in obtaining access, plus the
contractor‟s margin is to be added to the contract price.
[22] Clauses 7 and 11 must be construed and read in a manner such that
the two clauses can sit together as part of the same contract. In my
view that reconciliation is to be found by means of clause 11.18 which
provides that the process for a signed variation document prior to the
carrying out of any works does not apply if in the contractor‟s opinion
the variation is required to be undertaken in circumstances where it is
“not reasonably practicable” to produce and have signed the variation
document prior to carrying out those works. Casino Pools has
thereafter sufficiently complied with clause 13.6 (also set out by me,
above), by reason that it has subsequently provided Mrs Burness with
a copy of the relevant invoice given to it by the earthworks excavation
company, in order that Mrs Burness has been kept informed of the
actual provisional sum cost which was greater than that originally
allowed under the contract on a provisional basis.
[23] I am of the view therefore that the additional claim made by Casino
Pools pursuant to No. Invoice 52174 is a legitimate claim, and it should
have been paid to the pool builder, by Mrs Burness. Casino Pools are
entitled to claim their contractor‟s margin in addition to the actual
amount of the extra excavation costs, because of clause 7.4. The
emergent conditions on the day the trucks were cancelled is a matter
governed by clause 11.18, such that Casino Pools are excused from
their not having provided a variation document, at least in the specific
circumstances of this case.
[24] For the foregoing reasons I find that Mrs Burness‟ claim should be
dismissed. Casino Pools legitimately raised invoice 52174 and the
respondent remains entitled to retain the disputed sum.
-- 8 of 8 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2011/405