Cavalier Homes Brisbane Pty Ltd v Findville Pty Ltd [2011] QCAT 397
CITATION: Cavalier Homes Brisbane Pty Ltd v Findville Pty
Ltd [2011] QCAT 397
PARTIES: Cavalier Homes Brisbane Pty Ltd
v
Findville Pty Ltd
APPLICATION NUMBER: BDL258-10
MATTER TYPE: Building matters
HEARING DATE: 28 February 2011
HEARD AT: Brisbane
DECISION OF: Mr Adrian Williams, Member
DELIVERED ON: 19 August 2011
DELIVERED AT: Brisbane
ORDERS MADE: The Respondent is required to pay the
Applicant within 30 days of the decision, the
sum of $10,166.11 comprised of:
Judgement Sum $9,447.78
Interest to 28.02.2011 $ 463.33
Filing fee $ 255.00
CATCHWORDS: Delays in Construction and extensions of time
allowed to builder – Assessment of damages for
late completion
APPEARANCES and REPRESENTATION (if any):
APPLICANT: Cavalier Homes Brisbane Pty Ltd represented by
Mr Peter James Gale
RESPONDENT: Findville Pty Ltd represented by Mr Adrian Stagg
REASONS FOR DECISION
[1] This is a decision of the Queensland Civil and Administration Tribunal
arising out of a hearing held in Brisbane on 28 February 2011 in the matter
of Cavalier Homes Pty Ltd (the Applicant) v Findville Pty Ltd (the
Respondent). The Presiding Member hearing the matter was Mr Adrian
Williams who now hands down the decision in the matter and provides an
outline, in written form, as to the reasons for that decision.
[2] This QCAT decision arose out of an Application made to that Tribunal
dated 1 September 2010 and filed on 2 September 2010. The
-- 1 of 20 --
2
Respondent filed a Response and Counter-Application on 27 September
2010.
[3] The facts of the matter are as follows.
[4] The Applicant in its Statement of Claim asserted the following.
[5] On 17 August 2006 the parties entered into a contract for the construction
of a residence at Lot 3 Bremer Parade Basin Pocket (a suburb of Ipswich).
The contract took the form of the then current HIA QC1 2000 New Home
Construction Contract.
[6] The contract specified a total contract price of $220,238.00 which was
payable as follows:
Stage Percentage Amount
i) Deposit 5% $11,015.00
ii) Base 10% $22,033.00
iii) Frame 20% $44,066.00
iv) Enclosed 35% $77,115.00
v) Fixing 20% $44,066.00
vi) Practical Completion Balance (10%) $22,033.00
[7] During the course of construction the Applicant made certain progress
claims in accordance with the provisions of the contract and these were all
paid by the Respondent other than the final payment upon practical
completion which was partly paid and the balance of $13,107.78 which
remains unpaid. The Applicant also sought orders for the payment of
interest and legal costs. The Applicant subsequently reassessed the
amount owing and reduced the amount of its claim to $12,927.78.
[8] It is a matter of agreement between the parties that the construction of the
dwelling took significantly longer than that anticipated under the contract.
The contract (in Schedule 1) specified the following time frames and
potential causes of delays:
Building Period – 230 days after commencement (Schedule 1 Item 10)
Calculable Delays – [Schedule 1 Item 10 (a)]
Inclement weather – 5 days
Weekends, public holidays, rostered days off etc – 65 days
Any other matter likely to delay – 5 days
-- 2 of 20 --
3
Incalculable Delays – [Schedule 1 Item 10 (b)]
1. Unavailability of suitable trades
2. Unavailability of suitable materials
3. Anything beyond the builder‟s control
[9] The section of Item 10(b) which specified the “general effect that the delay
is likely to have on the carrying out of the works” was not completed.
[10] Commencement under Clause 2.1 of the Contract was specified as being
the date specified in Item 6 of the Contract Schedule or within 20 working
days from the date in which a number of specified events have taken
place.
[11] What was the correct commencement date in accordance with the contract
was originally a matter in dispute between the parties however, prior to the
matter being heard they agreed that the commencement date was
21 December 2006.
[12] As events transpired the property did not reach practical completion until
2 July 2009 (according to the Applicant) or 25 February 2010 (according to
the Respondent). The difference between these two asserted completion
dates lies in the parties failing to agree that the property was completed
either without defects or with minor defects and was reasonably suitable
for habitation (see section 67 of the Domestic Building Contracts Act 2000
“DBCA”).
[13] The Respondent for its part acknowledged that the final progress payment
had not been paid in full but denied it was payable on the basis that it had
suffered financial loss due to the Applicant:
a) Taking approximately 3 years and 2 months to complete construction
of the dwelling (calculated between 18 December 2006 and
25 February 2010).
b) Attempting to hand over possession of the dwelling at a time when it
had significant defects as identified in an independent report obtained
by the Respondent.
c) On numerous occasions allowing the construction of the dwelling to
remain at a stand-still for months at a time.
d) Omitting to complete various works required by the contract.
[14] In its Counter Application the respondent assessed its losses as being not
less than $29,000.00 comprising holding costs (including bank fees,
interest payment local government rates etc) and rectification works.
[15] The Respondent in accordance with Directions made by the Tribunal on
11 November 2010 subsequently quantified its alleged losses as being a
total of $35,069.49 comprising the following items:
-- 3 of 20 --
4
Bank Interest between September 2007
and February 2010: $21,508.59
Bank Fees (February 2009
To February 2010: $ 432.00
Council Rates (September 2007
to February 2010 $ 2,849.90
Lay carpet on stairs $ 857.00
Site Surveys $ 660.00
2nd Building inspection $ 330.00
Wrong skirting $ 400.00
Omit metal shelving $ 1,600.00
Total: $ 3,847.00
Advisory and legal fees $ 6,432.00
Total of counter-claim $35,069.49
[16] At the Directions hearing referred to above the parties agreed that the
matter would proceed to hearing on the basis that the following issues
remained in dispute:
a. Whether late completion damages should be calculated as provided
for under the contract (namely assessed as $15.00 per day);
b. Whether schedule 1 Item 10(b) of the contract is too broad to be
relied upon by the Applicant;
c. Whether the extensions of the contract claimed by the Applicant are
allowable under the contract;
d. Whether interest is payable on any amounts found to be owing by the
parties;
e. Whether clause 26 of the contract applies;
f. What was the date of practical completion;
g. whether monies are owed by the Applicant to the Respondent on
account of :
i losses claimed such losses to be specified by the respondent as
set out above; and
-- 4 of 20 --
5
ii claimed omissions to the contract – lack of carpet on the stairs,
incorrect wardrobe shelving, and incorrect skirting and architraves;
h. whether the applicant is responsible for the cost or reinstating
boundary pegs disturbed during construction.
[17] At the settlement conference it was agreed between the parties that the
commencement date under the contract was 21 December 2006.
[18] Much of the matters in dispute come down to issues of the correct
interpretation of the building contract entered into between them and, for
that reason, I will outline the essential terms of the agreement in so far as
they are relevant to the current dispute
[19] Item 11 of Schedule 1 specified that the late completion damages would
be the sum of $15.00 per day.
[20] For its part the Respondent contended that the Applicant had breached its
obligations under both section 44 of the DBCA and Clause 36.1(c) of the
Contract in that the delay in completing the dwelling within the time
required under the contract evidenced a failure to carry out the works in an
appropriate and skilful way and with reasonable care and skill. This
contention will be assessed later in these decisions.
[21] The Applicant in response asserted that it had complied with the relevant
provisions of the Contract in that once it became aware of incalculable
delay it had complied with Clause 17.3 by providing written notices to the
owner in the time frame specified in Clause 17.3(c) and further that the
Respondent had not in accordance with Clause 17.4 disputed the notices
as it was required to do if it objected to the builder‟s claim for an extension.
[22] It appears to me that Clause 17 of the Contract is central to the dispute
between the parties, for the reason that the delay in the completion of the
dwelling, the reasons provided by the Applicant for the delay, their
responses to it and the consequences for the Respondent of the delay, lay
at the heart of this case. For that reason I will record the relevant clauses
in full and refer to them in the course of this decision.
Clause 17 Delays and Extensions of Time
17.1 The builder is entitled to a reasonable extension of time to the
building period if commencement or the carrying out of the works
is delayed by a claimable delay.
17.2 A claimable delay means a delay caused by the builder
suspending the works under Clause 19 or from a cause beyond
the builder’s sole control that was not reasonably foreseeable at
the time the builder entered into the contract including:
(a)
(c) a calculable delay in excess of the allowance for that
cause of delay stated in item 10
-- 5 of 20 --
6
(d) an incalculable delay if the cause and general effect of the
delay is likely to have on the carrying out of the works as
stated in item 10;
17.3 To Claim an extension of time the builder must give the owner
written notice detailing both:
(a) the cause of the delay; and
(b) the extension of time claimed,
by the later of the day that is:
a. 20 working days on and after the builder is aware of both
the cause and the extent of the delay; or
b. 5 working days on or before the date of practical
completion.
17.4 If the owner wishes to dispute a claimed extension of time the
owner must within 5 working days of receiving the builder’s claim
give the builder a written notice:
(a) disputing the claim; and
(b) detailing the reasons why the claim is disputed.
17.5 The builder must allow a reasonable reduction to the building
period if by variation work is omitted from the works.
[23] The clause addresses both delays in the commencement of the work and
the subsequent carrying out of the works.
[24] Prior to outlining the written and oral evidence given by the parties I note
that there was significant time addressed in the hearing to testimony
concerning the reasons for the delay in the commencement of the works.
It will be not necessary for me to either record or assess this evidence as
the parties are in agreement as to the date of commencement. I will
address an alternative construction later in these reasons.
Evidence of the Parties
Written Evidence
[25] I will now address the written evidence submitted to the Tribunal before the
hearing.
[26] The Tribunal made Directions on 11 November 2010 which addressed the
question of written evidence to be filed with the Tribunal. These were as
follows:
For the Applicant:
To file and serve on or before 26 November 2010;
-- 6 of 20 --
7
a) An updated Extension of Time Calculation showing an amended
claim amount.
b) Copies of Extension of Time Notices for each of the extension of time
claims.
[27] The Applicant complied with this direction and also attached these
documents to the subsequently filed statement of evidence of Mr Peter
James Gale dated 17 January 2011 (“Mr Gale‟s Statement”);
For the Respondent:
[28] The Respondent was required on or before 23 December 2010 to file and
serve the document quantifying the basis and the quantum of its alleged
losses (Respondent‟s Statement of Loss”) and complied with this direction.
As specified above the Respondent files this document.
[29] The Tribunal allowed the Respondent to file and serve any statements it
wished to rely upon on or before 14 February 2010 (although this is clearly
intended to be 2011). The Respondent elected not to file a statement in
accordance with this Tribunal Direction. A Direction was made by the
Member hearing the matter permitting the Respondent to file and serve
any additional material upon which it sought to rely. As part of this the
Respondent did make formal submissions on the evidence and I propose
to refer to these submissions where they are relevant to matters I propose
to address.
Mr Gale‟s Statement
[30] Mr Gale is the Chief Financial Officer of the Applicant Company. In his
Statement he deposed as follows:
The Respondent was not entitled to seek the amounts claimed through his
Cross Claim and its Statement of Loss as it is only permitted to claim the
late completion damages specified in Clause 32 of the Contract and not
the amounts claimed for bank interest and fees and Council rates.
[31] He acknowledged that the house had not been completed by the date
specified under the contract for practical completion which should have
been 21 August 2007, but that clause 32 of the contract in accordance with
Item 11 of the Schedule provided the mechanism by which liquidated
damages in favour of the owner were to be assessed (taking into account
the claims for extension the Applicant had issued to the Respondent).
[32] In accordance with the Contract the Applicant had provided the
Respondent an updated Amendment to Contract dated 16 November 2010
and an updated File Progress date report under which the Applicant
agreed to pay the Respondent a sum of money calculated in accordance
with Clause 32 to compensate for the late completion of the house.
-- 7 of 20 --
8
[33] Mr Gale contended that the construction of the house reached “Practical
Completion” on 2 July 2009 which was the date a Form 21 Final Inspection
Certificate was completed and signed.
[34] Mr Gale asserted that at that time the property was at the “Practical
Completion” stage and reasonably habitable in accordance with the
contract. He alleged that the Applicant had attempted on numerous
occasions to hand over the house but the Respondent had claimed that
the scope of work included under deck linings, carpet to the stairs and not
included in the Contract, the plans or in Appendix “A” of the Contract.
[35] Mr Gale agreed that in accordance with the Amendment to the Contract
and related documents referred to in item 3 above the balance of the final
instalment due to be paid by the Respondent had been decreased to the
sum of $12,927.78. He attached a revised Debtor Statement in that sum.
[36] At the hearing a number of Documents were submitted by the parties as
Exhibits. These were submitted largely by the Respondent unless
indicated otherwise. These were as follows:
Exhibit 1: The Applicant‟s written quote to the Respondent dated 19 July
20106.
Exhibit 2: Bundle of Receipts for expenses incurred by the Respondent
as follows:
a. Invoice from Parson‟s Business Trust trading as Site Surveys
to identify boundaries of 8 Bremmer Parade ($660.00);
b. Invoice from Hoopers Carpet One Pty Ltd supply and lay
carpet to staircase ($857.00);
c. Invoice Pro Check Building Services Pty Ltd ($330.00);
d. Two invoices from Praeger Ellem Solicitors addressed to the
Respondent in the sum of $780.55 and $2,198.14;
e. Invoice from Building Matters Queensland $3,750.00.
Exhibit 3. List of Architraves made by Carter Holt Harvey under the
ULTRAprime brand name.
Exhibit 4: Photograph‟s of steel and melamine shelving.
Exhibit 5. Copy of sections 33 and 34 of the DBCA.
Exhibit 6: Copy of Section 18 of the DBCA.
Exhibit 7: Copy of Purchase Order dated 28 March 2008 (for the
Applicant).
-- 8 of 20 --
9
Exhibit 8: Copy of the Applicant‟s updated progress dates with
annotations made by Mr Adrian Stagg on behalf of the
Respondent.
[37] Before turning to the evidence given by the parties at hearing it is
instructive to refer to a number of time lines during the course of the
dwelling‟s construction, namely the dates on which various stages were
certified as being completed as well as the dates progress claims were
then issued and the dates the Respondent provided payment on those
progress claims.
Stage Inspection & Certificate dates
Stage Inspection Date Certificate date
Foundation & Excavation 23.02.2007
Slab Stage 06.03.2007
Frame Stage 07.04.2008
Final Stage 24.06.2009 02.07.2009
Other stage (set out) 16.02.2007
Progress Claim & Payment Dates
Date & Stage Issue date Date of Payment
Deposit 16.08.2006 17.08.2006
Deposit 21.09.2006 21.09.2006
Slab 07.03.2007 19.03.2007
Frame* 01.04.2008 02.05.2008
Enclosed 20.08.2008 11.09.2008
Fixing 15.01.2009 05.02.2009
Final** 18.09.2009 25.02.2010
*A number of separate claims and subsequent reversals for this stage are
recorded in the Applicant‟s ledger on 24 October 2007, 19 November
2007 and 29 January 2008. I have only therefore recorded the last date.
**Again the Applicant issued an earlier claim for this stage on 5 June 2009
which was recorded as reversed on the same date. I have therefore
recorded the last date.
Oral Evidence
-- 9 of 20 --
10
Applicant
[38] Mr Gale provided evidence on behalf of the Applicant.
[39] He said that the Applicant had entered into a contract with the Respondent
to build another dwelling on the next door lot and the history of relations
between the Applicant‟s supervisors and contractors and the Respondent‟s
Director had then had a negative effect upon the construction of the
building the subject of this dispute.
[40] Over the period of time in which the property was under construction there
had been significant difficulties in locating appropriate tradespersons in the
Ipswich area. He partly put this down to the preference of many
contractors to work in a number of large subdivisions under development
at that time. He identified these as being at Mango Hill, Springfield and
Ormeau. At that time there was very little building activity in the Ipswich
area.
[41] When questioned about the initial delay between the agreed date of
commencement and the creation of the first progress claim for laying the
concrete slab but did cite that some frequent causes of delay were the
need for soil and plumbing inspections performed by a private certifier. He
said that given the date when the slab was inspected in early March he
would have anticipated work began in late January or early February 2007.
He also cited that he recalled that in January 2007 it was difficult to source
appropriate trades people.
[42] With respect to the company‟s procedure with respect to issuing claims for
extension Mr Gale said that these would usually be issued on the advice of
the supervisor appointed by the company for the site. The company‟s
customer relations officer would then issue the notice in accordance with
Clause 17 of the Contract. He deposed that the company had not been in
receipt of any notices disputing the extension claims from the Respondent
over the period the building was under construction. When asked to
examine the individual notices he confirmed they would all appear to have
been issued on the dates specified on them. With respect to the claims for
extensions for the industry shut down period these would as a matter of
practice be issued in advance as these dates were generally well known.
[43] Mr Gale indicated that the amount specified under Item 11 of the Schedule
for late completion damages in the sum of $15.00 was the minimum
amount specified by the Housing Industry Association and was, in his
experience, the amount specified in about 95% of all residential building
contracts. He said that it was rarely reduced or increased and would not
have been increased on a job such as this one, as it had a small profit
margin and was very price sensitive.
Assessment of Applicant’s Claims for Extension
[44] The Applicant made the following claims for extensions and provided the
following reasons:
-- 10 of 20 --
11
Number Process date Reason for Claim Days Claimed
1 17.05.07 Public Holidays 4
2 21.05.07 Shortage of trades 14
(framing carpenter)
3 02.08.07 Shortage of Trades 7
4 21.09.07 Inclement weather &
shortage of trades 2
17.12.07 Industry Shutdown 21
5 07.02.08 Inclement weather 3
6 26.02.08 Inclement weather 2
7 25.03.08 Inclement weather 2
8 11.04.08 Shortage of trades 5
Easter holidays 2
Shortage of trades 3
Shortage of trades 5
Changes of materials 5
9 Not Known
10
11 Document not provided 24
reason(s) not provided
10 03.07.08 Client to finalise variation 4
Inclement weather 2
Shortage of trades 4
Inclement weather 1
Shortage of trades 5
11 14.07.08 shortage of trades 5
Inclement weather 3
12 21.07.07 Inclement weather 1
13 29.07.08 Shortage of trades 5
14 18.08.08 Inclement weather 2
shortage of trades 3
15 29.08.08 Shortage of trades 2
Delays of materials 5
Delays of materials 2
16 04.09.08 Delays of materials 4
-- 11 of 20 --
12
17 15.09.08 Inclement weather 2
18 30.10.08 Shortage of trades
(plasterer) 20 total over 4
weeks
19 30.10.08 Shortage of trades 5
(plasterer)
20 Xmas Break industry shutdown 21
Total 189 days
[45] It is impossible to determine this matter without assessing the validity or
otherwise of the Applicant‟s numerous claims for extensions issued in
accordance with Clause 17 of the contract.
[46] Firstly I note that there was no evidence before me that they were issued
fraudulently, that the Respondent was unaware they had been sent to it
and it is a matter of evidence that the Respondent did not issue any written
notice of objecting to the claims in accordance with Clause 17(4) of the
contract.
[47] The evidence provided by Mr Gale as to the systemic industry and site
specific reasons for the difficulty in sourcing appropriate tradespeople were
cogent and not contradicted by any other material put before the Tribunal.
[48] Against this the respondent argued that:
a. The overall delays claimed were not reasonable as required by
sections 33 and 34 of the DBCA;
b. The relevant clause of the contract placed a positive obligation for the
“builder to get on with contractual obligations and is not in the contract
as a „cover all’ to both hide their ineptitude and to save them from the
monetary consequences of such ineptitude”;.
c. That the matters raised in the extension claims were not matters
really outside the builder‟s control;
d. Unavailability of trades means a total lack of trades and material not
‘a shortage at a particular price’ or because they did not have a
supervisor in place to organise it;
e. Item 10b of the Particulars did not specify the general effect of the
delay and failed to comply with section 34(2) of the DBCA.
f. The Builder had failed to comply with sections 18(5) and (6) of the
DBCA in that
i) Section 18(5) provides for the building period to be extended for
incalculable delays (s34) „where the builder has complied with the
variation provisions‟ (sections 79-83 DBCA); and
ii) The builder had not complied with section 18(6) of the DBCA in
that it failed to comply with the requirement to apply to the Tribunal
for an adjustment to take into account any additional days to carry
out the subject work and that therefore no extension is allowable.
-- 12 of 20 --
13
[49] The primary response to the Respondent‟s objections is that the contract
provided it with the means to object to the claims for extension at the time
they were issued and it failed to do so. Whilst it remains open for the
Respondent to subsequently claim that the claims were not reasonable I
have, for the reasons provided above determined in all the circumstances
that they were not unreasonable.
[50] With regards to the references in item (f) above, to sections 18.5 and 18.6
of the DBCA these submissions are a misreading of the effect of those
provisions of the Act. These provisions address circumstances in which
the contract contains a specified completion date (which this contract does
not) and which are subject to a claim for variation (which again this
contract is not).
[51] I will however reduce the Applicant‟s total extension period by 24 days to
reflect that the Applicant did not provide documentary evidence for
Extension Claim number 9.
Delay in Connecting Water
[52] The single largest factor in delaying completion of the contract and
allowing the Applicant the ability to take possession of the dwelling was the
discovery very late in the construction period that the dwelling was not
connected to the Council‟s water supply. On the basis of the evidence it
would appear that in the period prior to this water was being accessed
from taps on Lot 2 but close to the boundary and it therefore was not
appreciated that Lot 3 was not connected. From the evidence of Mr Gale it
would seem that this became apparent in May or June of 2009.
[53] The question then to be determined was whose responsibility it was to
ensure the property was connected to the water mains and for the ensuing
delay.
[54] The Applicant submitted that this responsibility under the contract clearly
lay with the owner referring to Item 1(e) of the Contract Specification. The
Applicant submitted that this took 80 days and this additional period of time
was added to the total number of days in requested extensions. In their
view this took between May or June and August or September.
[55] The Respondent‟s Mr Stagg in his evidence said that the water connection
took between 27 May and 6 July as he had made the application to the
Council and was advised by Council that the connection was completed on
6 July 2009. In his submission the delay was only 41 days not 80 days as
claimed by the Applicant.
[56] He submitted that the fault for the delay lay with the Applicant arising out of
their removal of the survey pegs which, if they had remained in place
would have alerted it to the fact that they were taking water from the
neighbouring lot. In any event the Applicant was not entirely prevented
from continuing other work on the dwelling.
-- 13 of 20 --
14
[57] I do not accept the Respondent‟s submissions with respect to the
responsibility for the oversight being with the Applicant due to the removal
of the survey pegs. I will address this item under my responses to the
Respondent‟s Cross Claim but, put simply there is insufficient evidence to
lay this at the feet of the Applicant.
[58] However I do accept the Respondent‟s evidence as to the date of the
connection and will reduce the Applicants period of extension by 39 days
being the difference between the two periods of 80 versus 41 days.
What was the Date of Practical Completion
[59] The Applicant for its part submitted that the relevant date for Practical
Completion was at the time it issued its Certificate of Compliance on 2 July
2009.
[60] The Respondent submitted that the proper date for the Tribunal to
determine as the date for Practical Completion was the date it took
possession of the dwelling on 28 January 2010 when he was handed the
keys to the dwelling by a representative of the Applicant named Gary.
[61] Both parties sought reliance upon the terms of the Contract and section 67
of the Domestic Buildings Contracts Act 2000. I set out below the section
in full as this provision assists in determining whether the parties have
complied with it
67 Completion payments
(1) This section only applies to a regulated contract for which the subject
work consists of--
(a) the erection or construction of a detached dwelling to a stage
suitable for occupation; or
(b) the renovation, alteration, extension, improvement or repair of a
home to a stage suitable for occupation.
(2) The building contractor under a regulated contract must not demand
all or part of the completion payment unless the practical completion
stage has been reached.
Maximum penalty--100 penalty units.
(3) The building contractor under a regulated contract must not receive
all or part of the completion payment unless--
(a) the practical completion stage has been reached; and
(b) if the building owner claims the stage has been reached with
minor defects or minor omissions--the first and second
requirements stated in subsections (4) and (5) have been
complied with.
Maximum penalty--100 penalty units.
(4) The first requirement is that the building contractor must have given
the building owner a document (the defects document) that--
(a) lists the minor defects and minor omissions that both the building
contractor and building owner agree exist; and
(b) states by when the building contractor is to correct the listed
defects and omissions; and
-- 14 of 20 --
15
(c) lists the minor defects and omissions the building owner claims
exist, but that are not agreed by the building contractor to exist;
and
(d) is signed by the building contractor.
(5) The second requirement is that the building contractor must have
made all reasonable efforts to have the building owner sign the
defects document to acknowledge its contents.
(6) In this section--
completion payment, for a regulated contract, means a payment
required to be made under the contract by the building owner to the
building contractor for the practical completion stage. practical
completion stage, for a regulated contract, means the stage when--
(a) the subject work has been completed in accordance with the
contract and all relevant statutory requirements, either--
(i) without any omissions or defects; or
(ii) apart from minor omissions or minor defects; and
(b) the detached dwelling or home is reasonably suitable for
habitation.
[62] The Applicant‟s submission made through the evidence of Mr Gale was
that the dwelling was reasonably suitable for habitation and was so from
anywhere between March and June 2009. His evidence was that the
Applicant would have sent a letter to the Respondent in June 2009
advising that the property was almost ready for hand-over. He
subsequently confirmed this was sent on 15 June 2009. He said, in
response to the Respondent‟s independent building report, that whilst the
report did identify some defects these did not result in the house being not
reasonably suitable for habitation.
[63] What is clear is that there is no evidence that the Applicant complied with
section 67(4) of the DBCA. No defects list would appear to have been
prepared and offered to the Respondent to sign. It may be that the
Applicant took the view that as the Respondent had engaged its own
independent consultant that that report effectively operated as a de facto
defects list which the Applicant over time remedied. I am satisfied though
that the report revealed significant defects and omissions some of which
were major in character. I would not agree with the Applicant‟s contention
that these were minor matters that could be addressed in the six month
maintenance period.
[64] The reality was that the Applicant had not complied with its obligations
under section 67 of the DBCA and sought to both pass the property to the
Respondent and seek to be paid for the final stage under the contract
when it was not entitled to do so. I acknowledge that by this stage the
parties had reached an impasse in their professional relationship, however
this does not permit the Applicant to seek to circumvent its obligations
under the contract.
[65] Given all of these circumstances I take the view that practical completion
was the date at which the Respondent took possession of the premises on
28 January 2010.
-- 15 of 20 --
16
The Respondent’s Damages Claim
[66] This aspect of the Respondent‟s Cross Claim can be addressed in fairly
simple terms.
[67] The Respondent‟s Director in his evidence claimed that he was under a
significant amount of pressure to sign the contract as he was due to leave
overseas for an extended trip. He said that if he had not been in this
position he would have sought to increase the amount payable by way of
liquidated damages under Clause 32 of the Contract.
[68] Also it is clear from the Respondent‟s evidence that he did receive the
claims for extension made by the Applicant, and that he did not object in
writing as required in accordance with Clause 17.4 of the Contract. In his
evidence he said that he had objected “passively” to the Applicant‟s
notices which would appear to have been oral in nature. He agreed that
he was not aware of the terms of the contract dealing with claims for
extensions and his obligations to object in writing. His position was that
because the Applicant was in breach of the agreement it was therefore not
entitled to seek the benefit of this Clause.
[69] None of the above entitles the Respondent to seek, through the Tribunal,
some other basis to calculate the compensation payable to it. The
Contract specifies the basis upon which the owner can be reimbursed if
the builder fails to complete construction in accordance with the time
frames laid down by the Contract. The fact that the Respondent in
hindsight believes it would have, in other circumstances renegotiated the
daily amount payable for late completion, that it objected “passively” to the
claims for extension, its Director‟s asserted ignorance of these contractual
provisions, or the assertion that the Applicant‟s own breach now disentitles
it from seeking the benefit of these provisions, changes the unalterable
fact that the contract specifies the manner in which such damages are
calculated.
[70] Even if this were not the case, it is also clear that many of the amounts
claimed by way of bank interest and bank fees and council rates are
amounts it would have been liable to pay in any event, at least until such
time as the property had been sold to a third party. It is impossible for a
Tribunal to reach a view as to when the Respondent‟s property would have
sold if the construction had been completed in the timeframe anticipated
by the contract.
[71] As far as the other items claimed I make the following observations under
their separate headings:
Carpet on Internal Stairs
[72] The basis for this claim by the Respondent was largely based on the fact
that this had been an explicit inclusion in the contract for the other dwelling
constructed by the Applicant on the neighbouring Lot 2. The Respondent
submitted that this had been specifically referred to in the scope of works
for that lot but had not been included in the Contract for Lot 3. He
-- 16 of 20 --
17
submitted this was an “oversight” and probably stemmed from the fact that
at that time the Applicant was building mostly low set homes. In the
alternative the Respondent submitted that it should be implied that carpet
was to be included as the stairs were referred to in Item 24 of the Building
Specification as being “standard timber, carpet grade” and that other
surfaces within the dwelling were required to be tiled or carpeted.
[73] The Respondent is effectively seeking the Tribunal to imply this
specification in the Annexure to the contract on the basis that it was
specified in the prior contract for Lot 2 or from other items specifically
referred to in the Annexure.
[74] I am not prepared to accept this argument. The Respondent was in the
business of property development and was not, nor should have been,
unaware of the contract‟s terms and the need to ensure that the scope of
works as outlined in the Schedule was exhaustive and contained all of the
items it had agreed with the Builder were to be included.
[75] Similar considerations apply to the contention that the linings should have
been added to the under-deck areas, however, there was no specific claim
for compensation made for this item in the respondent‟s claim or in its
other later submissions.
Metal Shelving and Skirting and Architraves
[76] The Respondent‟s contention was that what was supplied and installed by
the Applicant under these headings was not in compliance with the
Contract‟s Building Specification.
[77] Item 21 of the Specification specified as follows:
(i) Robe shelving to be Double Coated Epoxy Ventilated Wire shelving, 4
– with top shelf at 1800 height (Unless Notified Otherwise)
(j) Linen shelving to be Double Coated Epoxy Ventilated Wire shelving, 4
– with top shelf at 1800 height (Unless Notified Otherwise)
Item 25 of Appendix A to the Specifications specifies as follows:
Internal Finish
25 Provide splayed skirting and architraves as standard
[78] The evidence of the Applicant was that what was supplied still fitted the
description of these items in the Specifications and in both cases were
products from a different supplier but still largely met the description given
in the Specifications. In the case of the shelving the replacement product
was more expensive that their usual wire shelving.
[79] I accept the Applicant‟s evidence on these two items. As far as the
Architraves I accept that there is little difference between the item
described in the Specifications and that supplied.
-- 17 of 20 --
18
[80] In any event the Respondent‟s estimates as to the replacement costs for
the shelving are just that, estimates and it has not provided any
independent basis on which to assess their costing of this item.
Site Survey Fees
[81] There was no compelling evidence submitted by the Respondent that
could persuade me that the removal of the surveyor‟s pegs from the lot on
which the dwelling was constructed could be laid at the feet of the
Applicant. The Respondent submitted that the Applicant had possession
of the site and was therefore responsible for its upkeep, including
maintenance of the integrity of the survey pegs during that time. The
Respondent did not proffer any contractual or other basis for this alleged
obligation and therefore I will not allow this aspect of the Respondent‟s
claim.
Independent Building Inspection Fees
[82] On this aspect of the claim and on the basis of my findings with respect to
the validity of the Applicant‟s final progress claim, I find that that the
Respondent is entitled to recover this item and will allow the sum of
$330.00.
Legal and Advisory Fees
[83] These items properly come under a separate heading of costs as they
both relate to legal advice with respect to the dispute between the
Respondent and the Applicant.
[84] Pursuant to the provisions of section 100 of the Queensland Civil and
Administrative Tribunal Act each party must bear their own costs unless
(pursuant to section 102) it considers the interest of justice require
otherwise. Section 101(3) specifies those matters the Tribunal may take
into consideration in reaching a view on the interests of justice. These are:
(a) whether a party to a proceeding is acting in a way that unnecessarily
disadvantages another party to the proceeding, including as
mentioned in section 48(1)(a) to (g);
(b) the nature and complexity of the dispute the subject of the
proceeding;
(c) the relative strengths of the claims made by each of the parties to the
proceeding;
(e) the financial circumstances of the parties to the proceeding;
(f) anything else the tribunal considers relevant.
[85] In my view there is no material of any weight before me that persuades me
to overturn the requirements of section 100 of the Act. There is no
-- 18 of 20 --
19
evidence that the Applicant has acted in a way that has disadvantaged the
Respondent, the dispute was not in its nature anything other than a
straight forward dispute between owner and builder, there was no great
strength in the Respondent‟s claim and the Respondent‟s financial
circumstances also do not warrant a costs order.
Findings of Fact and Law
[86] Earlier in these reasons I identified what matters the parties at the
Directions Hearing of 11 November 2010 agreed would proceed to hearing
on the basis that they remained in dispute. Based on the outline of the
evidence and my findings of fact and law I find as follows (specified in bold
type):
a. Whether late completion damages should be calculated as provided
for under the contract (namely assessed as $15.00 per day); Yes.
b. Whether schedule 1 Item 10 (b) of the contract is too broad to be
relied upon by the Applicant; No.
c. Whether the extensions of the contract claimed by the Applicant are
allowable under the contract; Yes subject to qualifications set forth
below.
d. Whether interest is payable on any amounts found to be owing by the
parties; No.
e. Whether clause 26 of the contract applies; Yes.
f. What was the date of practical completion; For the reasons I have
specified above I find that this date was 28 January 2010.
g. whether monies are owed by the Applicant to the Respondent on
account of :
i losses claimed such losses to be specified by the Respondent as
set out above; and
ii claimed omissions to the contract – lack of carpet on the stairs,
incorrect wardrobe shelving, and incorrect skirting and architraves;
No to items i and ii.
h. whether the applicant is responsible for the cost or reinstating
boundary pegs disturbed during construction; No.
Conclusions
[87] As outlined above I have come to the view that some of the extensions
claimed by the Applicant are not permissible either on the grounds of:
1. Lack of evidence (i.e. Claim Number 9 - 24 days);
-- 19 of 20 --
20
2. The claimed period was excessive (claim for 80 days to connect
water reduced to 41 days).
[88] I also find that the Date of Practical Completion was the date the
Respondent took possession of the property on 28 January 2010. The
Applicant had calculated in its document entitled Updated File Progress
Dates (Annexure 1 to Mr Gale‟s Affidavit) that the date of practical
completion was 3 September 2009.
[89] I therefore will allow the intervening period of 147 days between these two
dates to be added to the calculation of the Late Completion Damages in
addition to the 24 days (claim # 9) and the 39 days difference between the
Applicant‟s claim for the additional delay in the connection of the water
supply and the Respondent‟s evidence of the date of connection.
[90] This amounts to a total of 210 additional days.
[91] When calculated against the daily late completion rate of $15.00 these
three items amount to $3,150.00 to which I will add the cost of the building
inspection ($330.00) which I have allowed for providing a total deductable
amount of $3,480.00.
[92] Deducting the total of these items from the amount sought by the Applicant
this is now reduced to the sum of $9,447.78.
[93] I will allow interest to be claimed on that amount from the date of the
Applicant‟s filing of his application on 2 September 2010 to the date of this
hearing (28 February 2011) which I assess as being the sum of $463.33
and continuing thereafter.
-- 20 of 20 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2011/397