Bunting v Jim's Fencing Springwood [2011] QCAT 411
CITATION: Bunting v Jim’s Fencing Springwood [2011]
QCAT 411
PARTIES: Mr James Robert Bunting
(Applicant/Appellant)
V
Jim’s Fencing Springwood
Darren Hitchon as representative
(Respondent)
APPLICATION NUMBER: MCDO808-10
MATTER TYPE: Other minor civil dispute matters
HEARING DATE: 23 June 2011
HEARD AT: Brisbane
DECISION OF: Kate Buxton, Adjudicator
DELIVERED ON: 29 July 2011
DELIVERED AT: Brisbane
ORDERS MADE: [1] The respondent pay to the
applicant the sum of $4,024.50 in
claim and fees by 15 August 2011.
CATCHWORDS: Damages for breach of contract – recovery
for unlicensed building work
Queensland Building Services Authority Act
1991, s 42
APPEARANCES and REPRESENTATION (if any):
APPLICANT: Mr Bunting in person
RESPONDENT: No appearance
REASONS FOR DECISION
[1] In this application, Mr Bunting seeks to recover a total of $6,781.29 from
the respondent, Mr Hitchon, for the following:
a) $1,859 for damages for breach of contract equal to the sum quoted to
repair gates installed by Mr Hitchon which are allegedly defective; and
-- 1 of 3 --
2
b) $4,922.29 by way of repayment of part of the amount paid to the
respondent for fencing works in circumstances where Mr Bunting
alleges that Mr Hitchon was unlicensed.
[2] The first of those claims is relatively straight forward. Mr Bunting asserts
that the motorised gate installed by Mr Hitchon is defective and has
produced evidence of the need for and cost of replacement. Despite
opportunities to attend and participate in this matter as it has progressed
through QCAT, Mr Hitchon has declined to participate or to produce any
evidence to the Tribunal in response to this claim. I am satisfied on the
basis of the evidence before me that the sum claimed is reasonable,
particularly when viewed in the context of the price for the original work.
[3] I therefore allow the claimed sum of $1,859.00 in respect of the defective
gate.
[4] The second element to this application, being the claimed $4,922.29, was
effectively amended during the hearing. Mr Bunting conceded that the
cost of a labourer, at the estimated daily rate of $250, should be added to
the costs claimable by the respondent under section 42(3) of the
Queensland Building Services Authority Act 1991 (QBSA Act) and that his
claim should reduce, accordingly, by $250.00. He has set out his
calculations in attachment c item 2 to his application (referred to in the
hearing as exhibit 2). In the alternative, he claims 20% of the total
invoiced amount as those are the profits disclosed by the respondent in its
promotional material (applicant’s submissions paragraph 47 to 51) and
seeks to recover the amount of $2,075.58 to represent the percentage of
the total amount which is unretainable profits.
[5] Mr Bunting submitted that, when Mr Hitchon undertook the work of
erecting the fencing and gates at his property, he was contracting building
work for which a license from the QBSA was required and, without such a
licence, ss 42(3) and (4) of the QBSA Act limit the way in which the
respondent is entitled to be paid for those works. Mr Bunting’s allegation
that Mr Hitchon was unlicensed is supported by the attachments to his
application and has not been contraverted in any way by Mr Hitchon,
despite the opportunity to do so. I therefore accept the submission that he
was unlicensed when the fencing work was undertaken.
[6] “Building work” is defined in schedule 2 to the QBSA Act to mean,
amongst other things, “(a) the erection or construction of a building …”. A
“building” is defined in schedule 2 to include “any fixed structure” and a
permanent fence is included in the schedule as an example of such affixed
structure.1
[7] I therefore accept Mr Bunting submission that ss 42(3) and (4) apply in this
case to limit the respondent’s entitlement to be paid for the works. In this
1 See also Wayne Thomas Brady Pty Ltd v QBSA & Raco [2005] QCCTB 150.
-- 2 of 3 --
3
case, as the respondent has already been paid for the works, those
provisions operate to limit the respondent’s entitlement to retain those
monies.
[8] The question which then arises is what, on the basis of the available
evidence, is the proper calculation of those amounts to which the
respondent who’s disentitled under ss 42(3) and (4). Subsection 42(3)
takes as its starting point a disentitlement to be paid for any unlicensed
building work. However, ss 42(4) goes on to provide that the respondent
is entitled no more than the cost of materials and labour; and is not entitled
to any allowance for the respondents:-
a. Own labour;
b. Profit; or
c. Any unreasonable costs.
[9] The applicant has made a valiant attempt at estimating the cost to the
respondent of the materials used and has provided some estimates as to
labour costs. However, there is no direct evidence of the actual amounts
incurred by the respondent. Whilst the applicant’s efforts are to be
appreciated in terms of the detail put in to the preparation of this claim and,
in particularly, exhibit 2, the calculations in this exhibit do not represent a
reliable estimate of the volume of materials, any wastage, an allowance for
transport, the accuracy of costing of tradesmen’s labour and the like.
[10] The alternative basis of the claim for 20% of the contract price (the sum of
$2,075.50) is less problematic. It does not require estimates to be made.
This methodology simply assumes an uncontroversial 10% builders margin
together with the stated 10% uplift from company’s in the “Jims Fencing”
franchise, as evidenced by the material referred to in the applicant’s
submission.
[11] I accept the proposition that 20% is a reasonable estimate of the
permissible retained profits pursuant to section 42(4) of the QBSA Act and
I allow the claim in the amount of $2,075.50.
[12] The allowed claims of $1,859.00 for the gate and $2,075.50 for the profits
total $3,934.50. I order that the respondent pay this amount in claim, plus
$90.00 filing fee, totalling $4,024.50 by 15 August 2011.
-- 3 of 3 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2011/411