Cornpig Pty Ltd v Queensland Building Services Authority [2011] QCAT 255
CITATION: Cornpig Pty Ltd v Queensland Building
Services Authority [2011] QCAT 255
PARTIES: Cornpig Pty Ltd
v
Queensland Building Services Authority
APPLICATION NUMBER: GAR029-11
MATTER TYPE: General administrative review matters
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Peta Stilgoe, Member
DELIVERED ON: 3 June 2011
DELIVERED AT: Brisbane
ORDERS MADE: 1. Application to extend time dismissed.
2. Application to review a decision
dismissed.
CATCHWORDS: BUILDING MATTERS – where Authority
issued scope of works and decision that
homeowner validly terminated contract –
where builder filed application for review
2 months later – where application to extend
time – whether discretion should be
exercised
Queensland Civil and Administrative
Tribunal Act 2009, ss 61(1), 61(3)
Queensland Building Services Authority Act
1991, s 86(2)(c)
Smith v Queensland Building Services
Authority [2010] QCAT 448
APPEARANCES and REPRESENTATION (if any):
This matter was heard on the papers in accordance with section 32 of the
Queensland Civil and Administrative Tribunal Act 2009.
-- 1 of 3 --
2
REASONS FOR DECISION
[1] On 7 February 2011, Cornpig filed an application to review the Authority’s
decision of 22 October 2010. The Authority issued a scope of works and
determined that that the homeowner properly terminated a contract for
residential construction work. On 27 April 2011, Cornpig filed an
application to extend time for the filing of its application.
[2] To the extent that the application to extend time relates to the scope of
works, it must fail. Section 86(2)(c) of the Queensland Building Services
Authority Act 1991 provides that the tribunal cannot review a decision in
relation not a scope of works if 28 days have elapsed since the decision
was served on the building contractor and the contractor has not, within
that time, fined an application for review. As the tribunal has pointed out1:
Section 86(2) is a provision relevant to the substantive issue of whether
jurisdiction exists to review a decision of the QBSA. Failure by a prospective
applicant to file an application within the statutorily prescribed period of 28
days cannot be "cured" or "waived" by the operation of s.61(1) of the QCAT
Act.
[3] Cornpig did not file an application to review the scope of works within
28 days of receiving the decision.
[4] The tribunal does have a discretion to extend time for filing the application
for review of the decision about termination: s 61(1) Queensland Civil and
Administrative Tribunal Act 2009. That relief is not available to a party if to
do so would cause prejudice or detriment not able to be remedied by an
appropriate order for costs or damages: s 61(3) QCAT Act.
[5] In determining any application for an extension of time, the reasons for the
party’s failure to comply are a relevant consideration. Cornpig says there
are many reasons for not filing the application within time all of which only
became evident in late January 2011:
a) It believed the work had been taken out of its hands.
b) It believed that the Authority’s estimate to complete the work was
inflated and the Authority has not considered the scope of works in
the original contract.
c) The lack of quotes for the work is unfair.
d) There is an allegation of a conflict of interest.
e) Cornpig does not agree with the Authority’s assessment of the
rectification works required on the deck; or the concreting of the
posts.
[6] The Authority’s chronology notes that Cornpig did not file an application to
review a direction to rectify dated 6 August 2010. Although this application
is couched as an application to review the decision of 22 October 2010, it
is apparent that it is really a belated attempt to review the direction to
rectify and/or the decision to engage another contractor. In the application
itself, Cornpig refers to matters such as:
1 Smith v QBSA [2010] QCAT 448 at [30].
-- 2 of 3 --
3
a) The lack of access to the site and the extreme weather conditions.
b) The cost of completing the works.
c) The terms of the contract.
d) That it would like the “failure to rectify” notation removed from its
licence.
[7] There is no cogent reason for Cornpig’s delay in filing the application.
Since the decision was issued, the Authority has approved the
homeowner’s claim under the statutory insurance scheme and the
homeowner has entered into a contract for the completion of the works.
These are not matters that can be altered or remedied by an order of the
tribunal, given that neither the homeowner nor the new contractor is a
party to this application.
[8] Cornpig has left its decision to challenge the Authority’s decision far too
late. It has not adequately explained its delay and the events that have
occurred in the interim cannot be undone by an order of the tribunal.
Cornpig’s application to extend time must fail and the substantive
application should be dismissed.
-- 3 of 3 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2011/255