Birch Carrol & Coyle Limited v Chief Executive, Office of Liquor and Gaming Regulation [2011] QCAT 244
CITATION: Birch Carrol & Coyle Limited v Chief
Executive, Office of Liquor and Gaming
Regulation [2011] QCAT 244
PARTIES: Birch Carrol & Coyle Limited trading as
Event Cinemas
v
Chief Executive, Office of Liquor and
Gaming Regulation
APPLICATION NUMBER: GAR414-10
MATTER TYPE: General administrative review matters
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Mrs Glenice Spender, Member
DELIVERED ON: 31 May 2011
DELIVERED AT: Brisbane
ORDERS MADE: 1. The time for filing the review
application is extended to
21 December 2010.
2. The strike out application is
dismissed.
CATCHWORDS: Strike out application – deemed refusal
Liquor Act 1992, s 31
APPEARANCES and REPRESENTATION (if any):
APPLICANT: Mullins Lawyers
RESPONDENT: Simon Grant, In-House Principal Lawyer
REASONS FOR DECISION
Introduction
[1] This is an application by the Chief Executive (“the Respondent”) of the
Office of Liquor and Gaming Regulation (“the OLGR”) seeking to have
struck out an application for review of a “deemed refusal” by the
-- 1 of 8 --
2
Respondent of an application for Change to Licensed Area lodged with
OLGR by Birch Carrol & Coyle trading as Event Cinemas (“the Applicant”).
[2] The Respondent seeks to strike out the review application on the ground
that there has been no decision or “deemed refusal” under section 31 of
the Liquor Act 1992 (“the Act”); that the time within which all steps required
or permitted under the Act must be taken has not ended; and that the
application for Change to Licensed Area continues to be considered under
the Act.
[3] The application for Change to Licensed Area under section 154 of the Act
was lodged on 23 June 2009 and the review application was filed on
14 December 2010. The Applicant submits that a “deemed refusal” has
occurred given the “unacceptable delay, inertia or inaction” by OGLR in
this case.
[4] The Respondent has filed relevant material on the departmental file and
the Applicant has filed copies of letters, reports, emails and telephone calls
relevant to the decision-making process. The parties have also filed
submissions on the strike out application and the jurisdictional issues
arising therefrom.
[5] The principal issue to be determined on the strike out application is
whether or not there has been a “deemed refusal”. If there has been no
“deemed refusal”, then the Tribunal has no jurisdiction to review because
there is no “decision”, and the review application must be struck out.
Factual background
[6] On 29 May 2009, the Applicant was granted a Commercial Other (On-
Premises) Licence for its Gold Class cinema, bar and connected lounge
area within its 11-cinema complex at Robina. The application had
included a request for licensing of the V-max cinema within the cinema
complex, but the Applicant agreed to excise the V-max cinema from the
application because the Respondent needed to give more consideration to
that aspect of the application.
[7] On 23 June 2009, the Applicant lodged a Form 24 Application to Change
the Licensed Area, noting in a covering letter that OLGR had agreed to
waive the application fee, the usual minimum requirements, and
advertising requirements for the new application. A notation on the OLGR
database as it stood at 2 June 2010 confirms that on 13 July 2009
advertising for the Change of Licensed Area application had been waived
(p 84 Appeal book). This was understandable, as licensing of the V-max
cinema had been advertised as recently as March 2009 as part of the
original application in respect of the 11-cinema complex.
[8] On 23 July 2009 the Respondent sent a letter to the Applicant setting out
four areas of concern in respect of the application, namely: lighting,
density, security and minors. In a letter dated 21 September 2009 Mullins
-- 2 of 8 --
3
Lawyers, on behalf of the Applicant, provided written submissions
addressing the four key areas of concern raised by the Respondent.
[9] In a letter dated 25 September 2009, the Respondent set out further and
better particulars in relation to the four mentioned key issues concerning
the application, and requested a further written response.
[10] In its response dated 24 February 2010, Mullins Lawyers, on behalf of the
Applicant, set out a detailed 25-page submission-in-reply and attached a
risk-assessed management plan (“RAMP”).
[11] On 19 April 2010 the Applicant and its lawyers met with OLGR officers
Smith and Russell at which time the Applicant was informed of an internal
dispute within OLGR as to whether or not the application should be
approved. The Applicant was informed that the Respondent may need to
develop a new Guideline for the handling of applications of this type and
that a review of how these matters were managed interstate may need to
be conducted.
[12] On 20 May 2010, Mullins Lawyers filed a further detailed 10-page
submission, on behalf of the Applicant, including advice and information as
to how applications of this nature are managed in other state jurisdictions.
[13] On 4 June 2010 Mullins Lawyers made a telephone enquiry of Officer
Smith who had been assigned to investigate the application. During that
phone call Officer Smith advised that no one at OLGR was in favour of the
Applicant’s application but there appeared to be no apparent lawful reason
to refuse the application. Neither Officer Smith nor any other officer
advised the Applicant that a further community impact statement (C.I.S.) in
addition to the one provided with the original application, or further
advertising, were required.
[14] On 2 July 2010 Officer Smith submitted to Officer Leotta, Manager
Licensing, a decision memorandum of advice which set out three optional
decisions and recommended that as there was presently insufficient
evidence to refuse the application, a heavily-conditioned approval would
be satisfactory.
[15] On 5 July 2010, 10 August 2010, 30 August 2010 and 6 September 2010,
Mullins Lawyers, on behalf of the Applicant, requested advice of the
Respondent as to whether or not a decision had been made.
[16] On 14 July 2010 Officer Smith advised Mullins Lawyers that he had
completed his decision memorandum and on 25 August 2010 he further
advised that he had reported to OGLR management, following his
enquiries with interstate jurisdictions, that there had been no issue with
licensing of V-max cinemas there. Officer Smith did not advise the
Applicant that it was necessary to lodge a further C.I.S. or to undertake
further advertising.
-- 3 of 8 --
4
[17] On 19 October 2010 and 29 October 2010, Mullins Lawyers sent emails to
OLGR requesting that a decision be made and warning that the Applicant
was considering a s 31 “deemed refusal” application. There was no reply
to these emails.
[18] On 16 November 2010 the Executive Director of OLGR, Officer Moynihan
telephoned Mullins Lawyers and advised that the Respondent was not in a
position to make a decision and was considering requiring a full C.I.S. and
advertising, but said that she would confirm these requirements in writing if
it was decided to insist on such requirements.
[19] On 14 December 2010 the Applicant filed a review application in the
Tribunal registry. The application was stamped as “received” on that date.
There is a further stamp dated 21 December 2010 on the face of the
application bearing the words “filed at the insistence of the applicant”. The
application was not served on the Respondent until 22 December 2010.
The delay in serving the Respondent was the result of uncertainty on the
part of registry staff as to the validity of a review application which was not
accompanied by a copy of the relevant decision.
[20] The Tribunal is satisfied that the effective date of filing of the application for
review of a “deemed refusal” under s 31 was 14 December 2010. The
Applicant was not to blame for the delay caused by registry staff making
necessary investigations with respect to an unfamiliar type of review
application.
[21] On 21 December 2010, the Chief Executive gave written notice to the
Applicant requiring provision of a further C.I.S. and further advertising of
the application for Change of Licensed Area.
The Law
[22] The application for Change of Licensed Area was made under s 154 which
provides:
“154 Alteration etc. and maintenance of licensed premises
(1) The owner, licensee or other person in control of licensed premises must
not, without the chief executive’s approval, alter, rebuild, change or increase
the area of the licensed premises.
Examples for subsection (1)—
1 The licensee of a detached bottle shop in a shopping centre
changes the relevant leasing arrangements by reducing the overall
area the shop is to occupy. Therefore the licensee must apply for the
chief executive’s approval to alter the licensed premises permanently.
2 An RSL club is the licensee of a licensed club and wishes to erect a
tent next to its licensed premises to provide liquor on Anzac Day.
Therefore the licensee must apply for the chief executive’s approval to
increase the area of the licensed premises for that occasion.
-- 4 of 8 --
5
Maximum penalty—25 penalty units.
(2) For subsection (1)—
(a) in giving an approval, the chief executive must have regard to the
business that is the principal activity conducted under the licence; and
(b) a change in the area includes not using a part of the licensed
premises as if the part were not licensed premises.
(3) Before giving an approval, the chief executive may ask the applicant to
give the chief executive a management plan relating to the proposed
alteration, rebuilding, change or increase.
(4) The management plan must include information the chief executive
considers appropriate having regard to—
(a) the business that is the principal activity conducted under the
licence; and
(b) the nature of the alteration, rebuilding, change or increase.
(5) If the chief executive asks the applicant for a management plan under
subsection (3), the chief executive must not give the approval unless the
applicant complies with the request.
(6) The licensee of licensed premises must keep the premises clean and in
good repair.
Maximum penalty—25 penalty”
[23] There is relevantly no requirement for advertising included in s 154.
[24] Section 31 provides:
“31 Failure to notify about decision
(1) This section applies if the chief executive fails to notify an applicant
of the grant or refusal of an application within 30 days after the end of
the time within which all steps required or permitted by this Act to be
taken relating to the application must be taken.
(2) For the purposes of a review by the tribunal, the chief executive is
taken to have given to the applicant notice of a decision to refuse the
application at the end of the period of 30 days Pursuant to section 31”.
Discussion
[25] The Respondent submits that the application to vary the licensed area
involved in effect an application to vary the licence conditions of the
existing licence to allow minors to be present on the premises and this
amounted to a variation of licence which is required to be advertised under
section 118 of the Act.
[26] The Tribunal does not accept this argument. It was not, in the Tribunal’s
view, appropriate for the Applicant to apply for a variation of licence
conditions to allow non-exempt minors to be present on the proposed
increased licensed area, because it was within the discretion of the Chief
Executive in approving the variation of licensed area application to impose
whatever conditions it deemed fit in respect of the operation of the V-max
cinema.
-- 5 of 8 --
6
[27] It was neither appropriate nor necessary for the Applicant to nominate
what conditions should be imposed, by way of an application for variation
of the licence conditions which had been imposed on the existing licence,
from which the V-max cinema had been excised. The Applicant at no
stage prior to 14 December 2010 made an application to vary the existing
licence conditions. The advertising requirement under section 118 does
not apply to the application under s 154 which the Applicant submitted.
The Chief Executive in the Chief Executive’s discretion can order
advertising of such an application but the Chief Executive did not do so
until 21 December 2010.
[28] The Tribunal in reviewing the “deemed refusal” and standing in the shoes
of the Chief Executive would have the power to order advertising of the
s 154 application, but, in the Tribunal’s view, the Chief Executive was
prohibited by the principles of procedural fairness, which will be discussed
later, from ordering advertising on 21 December 2010.
[29] The Chief Executive also submits that the Applicant has failed to meet the
requirement to lodge a fresh RAMP, in addition to the RAMP which was
approved in respect of the original application in respect of the cinema
complex. The Tribunal is satisfied that the requirement under s 154 to
lodge a RAMP was complied with on 24 February 2010 when the Applicant
resubmitted the RAMP which had been approved under the original
application before the V-max cinema was excised. At no stage did the
Respondent inform the Applicant that the RAMP submitted on 24 February
2010 was not approved or was otherwise deficient.
[30] The Tribunal further finds that the lodging of the RAMP on 24 February
2010 was the last and final mandatory requirement on the part of the
Applicant under the Act. However the Applicant was permitted at any
stage before a decision was made to take a further step by making a
further submission, which it did on 20 May 2010.
[31] The last step required on the part of the Respondent was the submission,
in the normal course of the decision-making process, of a decision
memorandum of advice to the decision-maker, setting out
recommendations as to the decision to be made. This memorandum took
the form of the Community Interest Analysis and recommendations
submitted by Officer Smith to Officer Leotta on 2 July 2010.
[32] Pursuant to s 31, the Respondent’s delegate was required to make a
decision by 1 August 2010, which was the date 30 days after the last step
required or permitted to be made by either party.
[33] The Tribunal finds that a “deemed refusal” under s 31 occurred on
1 August 2010, as no decision had been made within 30 days of the final
step in the decision-making process under the Act.
[34] The purpose of s 31 in the Tribunal’s view is to provide a statutory remedy
to an applicant where there is procedural unfairness as a result of
-- 6 of 8 --
7
unreasonable delay in making a decision or failure on the part of the
decision-maker to make a decision: see Kioa v West (1985) 159 CLR 550.
[35] Procedural fairness in the particular circumstances of this case required
the making of a decision by 1 August 2010 and, in the Tribunal’s view, the
Respondent was not lawfully permitted to act inconsistently with
procedural fairness by requiring any further step to be taken by the
Applicant after 1 August, unless the Applicant before filing a s 31 review
application waived its entitlement to lodge such an application by
consenting to the imposition upon it of further requirements by the
Respondent.
[36] The “deemed refusal” could be reviewed by the Respondent and could be
confirmed or another decision could be substituted for it during the period
while the Respondent was still seized of the s 154 application between
1 August 2010 and 14 December 2010, and it was not procedurally unfair
to do so. However pursuant to s 31 it was procedurally unfair to require
the Applicant to take any further steps if it did not agree to do so.
[37] The Applicant had clearly not waived its entitlement to bring a review
application when it sent warning letters to the Respondent on 19 October
and 29 October 2010. The Tribunal is not satisfied on the basis of Mr
Schatz of Mullins Lawyers’ and Officer Moynihan’s respective file notes of
their conversation of 16 November 2010, which are extremely brief, that Mr
Schatz, on behalf of the Applicant, waived the Applicant’s entitlement to
bring the review application. The Tribunal is not satisfied that Mr Schatz
agreed that the imposition of onerous and time-consuming requirements
for a further full C.I.S. and further advertising was “reasonable”, when
Officer Moynihan expressed her “preliminary view” in that regard in the
conversation.
[38] Pursuant to the combined operation of s 33 of the Queensland Civil and
Administrative Tribunal Act 2001 (“the QCAT Act”) and s 31(2) of the Act,
the Applicant was required to file the review application within 28 days of
the “deemed refusal”. The Applicant was thus required to file the review
application within 28 days of 1 August 2010. However under s 61 of the
QCAT Act the Tribunal may extended the period within which a person
must make an application.
[39] The difficulty for the Applicant in meeting the 28-day time limit was that it
had no right to be informed of the internal decision-making process of the
OLGR or when the last step in that process, namely a decision
memorandum of advice, was submitted to the Respondent for decision.
The Applicant could never know when the period for filing a review
application for a “deemed refusal” expired. The delay in lodging the review
application was caused because of those circumstances and because of
the Applicant’s reasonable conduct in giving warnings to the Respondent
of its intention to file such an application, thus giving the Respondent the
opportunity to make a decision.
-- 7 of 8 --
8
[40] The Tribunal is not satisfied that in the circumstances there is any
prejudice to the Respondent if an extension of time in which to file the
review application is granted. The Tribunal considers that it is appropriate
that the time for lodging of the review application be extended to
14 December 2010, but to meet any argument that, contrary to the
Tribunal’s finding, the application was not formally filed until 21 December
2010, the Tribunal will order that the time for filing the review application
be extended to 21 December.
[41] Upon the filing of the review application on 14 December 2010 the Tribunal
became seized of the application for Change of Licensed Area and the
Respondent was then functus officio. The Respondent thus had no power
to require in its written notice of 21 December 2010 that the Applicant take
further steps in respect of the application by way of advertising and the
provision of a further full C.I.S. The Respondent was also, as the Tribunal
has found, prohibited from taking such steps on the basis of procedural
fairness. Even if the Respondent did not become functus officio until it
was served with the review application on 22 December, the notice of
21 December was of no legal effect because the imposition of further
requirements on the Applicant after 1 August 2010 constituted a breach of
the principles of procedural fairness.
[42] While it is acknowledged that the application under s 154 raises important
concerns and is likely to have implications for future licensing of cinemas
throughout the State, there was, in the Tribunal’s view, no reasonable
excuse for the Respondent’s failure to make a decision over the 18-month
period between the lodging of the Change of Licensed Area application
and the filing of the review application. The Applicant alleges and the
Tribunal accepts that the Respondent’s protracted failure to make a
decision has adversely impacted on the Applicant’s cinema premises and
business plan. The inordinate delay which has occurred here is the very
sort of delay which in the Tribunal’s view s 31 of the Act is meant to
address.
Conclusion
[43] The Tribunal finds that the application for review has been lawfully
instituted pursuant to s 31 of the Act, and the Tribunal has jurisdiction to
hear and determine the application. The Tribunal will order that the strike
out application be dismissed.
-- 8 of 8 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2011/244