Darryn C Watts Consultants Pty Ltd v LGB and Sons Pty Ltd [2011] QCAT 294
CITATION: Darryn C Watts Consultants Pty Ltd v LGB and
Sons Pty Ltd [2011] QCAT 294
PARTIES: Darryn C Watts Consultants Pty Ltd trading as
Watts Constructions
v
LGB and Sons Pty Ltd
APPLICATION NUMBER: BDL162-10
MATTER TYPE: Building matters
HEARING DATE: 8 April 2011
HEARD AT: Townsville
DECISION OF: Ms Joanne Browne, Presiding Member
Ms Keta Roseby, Member
DELIVERED ON: 20 May 2011
DELIVERED AT: Townsville
ORDERS MADE: The respondent pay the applicant the amount
of $31,334.28 by 4.00pm on 17 June 2011.
CATCHWORDS: Whether the subcontract was lawfully terminated
– repudiation of Contract – labour and material
costs to complete outstanding works under the
subcontract
Queensland Building Services Authority Act
1991, s 77
APPEARANCES and REPRESENTATION (if any):
APPLICANT: Self-represented
RESPONDENT: No appearance
REASONS FOR DECISION
[1] Darryn C Watts Consultants Pty Ltd trading as Watts Constructions1
engaged LGB and Sons Pty Ltd to paint the Combined Catholic Colleges
Student Accommodation Facility at James Cook University, Townsville (“the
site”). The painting works included rendering and painting internally and
externally of the student accommodation. Watts Constructions claim that
LGB and Sons Pty Ltd failed to complete the painting works as agreed.
1 Pursuant to section 63 of the Queensland Civil and Administrative Tribunal Act 2009.
-- 1 of 11 --
2
[2] Mr John Robert Atkinson an employee and representative of Watts
Constructions appeared at the hearing on 8 April 2011.2 There was no
appearance at the hearing for LGB and Sons Pty Ltd, in particular Mr
Lawrence Buttigieg, its representative.
[3] The Tribunal is satisfied for the purposes of section 93 of the Queensland
Civil and Administrative Tribunal Act 2009 that Mr Buttigieg received notice
of the hearing – the Tribunal called Mr Buttigieg on the telephone at the
commencement of the hearing. Mr Buttigieg advised the Tribunal that he
was aware the matter was listed for hearing on 8 April 2011; however he
thought the hearing was listed for a time later in the day. Mr Buttigieg
informed the Tribunal that he was working and it would take him
approximately two (2) hours to get to the hearing. Mr Buttigieg was
informed by the Tribunal that the hearing would proceed given that the
matter had previously been adjourned and Mr Atkinson was present at the
hearing and was ready to proceed. The Tribunal told Mr Buttigieg that he
should immediately travel to Townsville to attend the hearing. The Tribunal
made several attempts to telephone Mr Buttigieg throughout the hearing on
8 April 2011; however Mr Buttigieg did not answer his mobile telephone.3
[4] By way of background, this matter was listed for hearing on 23 November
20104 before member Joanne Browne. Mr Atkinson and Mr Buttigieg
appeared at the hearing on 23 November 2010. Mr Buttigieg requested that
the hearing be adjourned to another day on the basis that he did not bring
his material to be relied upon with him, having left his documents at home.
The hearing was adjourned to 9.30am on 7 December 2010 and further
directions were made by the Tribunal for the filing and exchange of
material.5
[5] Further directions were made by the Tribunal on 30 November 2010
vacating the hearing listed on 7 December 2010 and re-listing the matter for
hearing at 9.30am on 8 April 2011.6 The directions provided that “No further
extensions will be granted for filing of material and the Hearing will proceed
on the basis of material filed by 4.00pm on 14 December 2010.”
Background
[6] Watts Constructions entered into a contract with the James Cook University
(the head contract) to construct student accommodation, such works to
commence on 20 February 2009 and to be completed by 11 January 2010.
Watts Constructions later engaged LGB and Sons Pty Ltd to conduct
2 See Statement of Darryn and Lynne Watts, directors of Darryn C Watts Consultants Pty
Ltd dated 26 November 2010 (filed 29 November 2010) confirming that Mr John Robert
Atkinson is an employee of Watts Constructions and is authorised to represent Watts
Constructions in these proceedings.
3 The hearing concluded at approximately 3.35pm on 8 April 2011.
4 As per directions made by Senior Member O’Callaghan dated 26 October 2010.
5 As per directions made by Member Joanne Browne dated 23 November 2010.
6 As per directions made by Senior Member O’Callaghan dated 30 November 2010 and
upon receipt by the Tribunal of a request for an adjournment of the hearing by Mr
Buttigieg. A Notice of Hearing dated 28 March 2011 was issued to the parties stating
that the hearing was listed for 9.30am on 8 April 2011.
-- 2 of 11 --
3
“painting and render works” and a Master Builders Commercial Subcontract
Agreement dated 14 April 2009 was signed by the parties prior to LGB and
Sons Pty Ltd commencing painting works in or about mid September 2009
(“the subcontract”). Attached to the subcontract were the Master Builders
standard Terms and Conditions.7 The original subcontract amount for the
completion of the paint works as quoted by LGB and Sons Pty Ltd was
$164,192.60.8 There was a variation in writing for the use of “Astec [sic]
paint externally” and LGB and Sons Pty Ltd issued a variation breakdown to
Watts Constructions dated 14 May 2009 representing materials, equipment
and labour.
[7] Mr Atkinson argues that the painting works were not completed by LGB and
Sons Pty Ltd and Watts Constructions engaged other painters, some of
whom were former employees of Mr Buttigieg, and purchased materials
such as paint, to complete the painting works at the site to ensure
completion of the works as required under the head contract.
[8] The application filed on 31 May 2010 seeks an order for payment of an
amount of $32,907.87, in particular the costs paid by Watts Constructions
for labour and materials, to complete the outstanding painting works under
the subcontract.9 The Tribunal gave leave at the hearing to Mr Atkinson on
behalf of Watts Constructions to amend the application filed 31 May 2010 to
show the name of the applicant as Darryn C Watts Consultants Pty Ltd
trading as Watts Constructions. Mr Atkinson filed and tendered statements
together with supporting documents and gave sworn evidence at the
hearing. Included in the material filed by Watts Constructions was a
recalculation of the amount claimed of $35,214.28 as set out in the
“reconciliation of subcontract payments”. Evidence was also given at the
hearing by Mr Andrew Von Pein (painting subcontractor) on behalf of Watts
Constructions.
[9] Mr Buttigieg filed a response in the Tribunal on 30 June 2010. No
supporting material or documents were filed by LGB and Sons Pty Ltd in
compliance with the several directions made by the Tribunal for the filing
and exchange of material to be relied upon at the hearing. Mr Buttigieg
states in the response:
“I would like the Tribunal to dismiss the application by Watts and order that Watt’s pay
the money owing to me. I feel the money owing to me is unreasonable and unfair. I will
not put my name to work I was unable to complete.
…
Watts broke the contract first by not paying in time as set out in the contract. Watts
denied me access to equipment and materials to enable me to complete the job. Watts
then used my equipment, paint and workers to complete the job”.
7 Exhibit 8.
8 See “Quote” dated 25 March 2009 from LGB and Sons Pty Ltd referring to Customer:
Watts Constructions, Exhibit 2 (Appendix A). See also “Purchase Order” dated 8 April
2009 issued by Watts Constructions to “Laurence Buttigieg Painting Service” referring to
“Total $164,192.60”.
9 The application is a minor commercial building dispute for the purposes of the
Queensland Building Services Authority Act 1991 and the Tribunal has the jurisdiction to
hear the dispute by virtue of section 77.
-- 3 of 11 --
4
Issues for Determination
[10] The Tribunal must consider the following issues in determining whether to
make an order for the payment of money by LGB and Sons Pty Ltd to
complete the outstanding painting works, as claimed by Watts
Constructions:
1. Did LGB and Sons Pty Ltd breach the terms of the subcontract in
December 2009 by applying Dulux paint to the exterior of the
student accommodation building on the site as alleged by Watts
Constructions? Can Watts Constructions recover the costs paid to
approve the Dulux paint (the Sustainability House costs)?
2. Whether Watts Constructions lawfully terminated the subcontract on
2 February 2010.
3. In determining whether there was a lawful termination of the
subcontract by Watts Constructions, did LGB and Sons Pty Ltd
breach clause 2(a) of the Terms and Conditions by failing to attend
at the site on 2 February 2010; and did Mr Buttigieg’s actions
constitute a repudiation of the terms of the subcontract?
Evidence of Mr Atkinson
[11] Mr Atkinson states that there were continual problems with LGB and Sons
Pty Ltd submitting invoices for payment by Watts Constructions for the
painting works under the subcontract and he therefore relies on emails
exchanged between himself and Mr Buttigieg for “transparency”. Mr
Atkinson also states that there were several variations to the subcontract
and the variations were put in writing by Watts Constructions as set out in
the “purchase order” and various documents including emails and tax
invoices tendered at the hearing.10 Mr Atkinson also tendered documents
evidencing the various payments he states were made by Watts
Constructions to LGB and Sons Pty Ltd under the subcontract.11
[12] Mr Atkinson states that Mr Buttigieg was instructed to use certain paint for
the external surfaces, namely Astec paint, at the commencement of the
painting works. Mr Atkinson states that the Astec paint has “material
properties” resulting in a reflection of the sun’s rays.12 In particular, Mr
Atkinson states that the Astec paint complied with Section J of the Building
Code which enabled Watts Constructions to delete some items such as
internal linings and insulation from the scope of works under the head
contract and this was a saving of money to the client.13 Mr Atkinson states
that Mr Buttigieg used an alternative product, Dulux paint and this cost
Watts Constructions additional money to have the substitute paint (Dulux)
certified in accordance with Section J of the Building Code. Mr Atkinson
refers to various documents to support his submission that Mr Buttigieg was
directed and had agreed to use Astec paint to the exterior of the student
10 Exhibit 2 together with attachments.
11 Exhibits 3 and 4.
12 Statement of Mr Atkinson, para 5 (Exhibit 2).
13 Ibid, a variation in the amount of $17,678.00 (plus GST) was made as per VOR5RRR.
-- 4 of 11 --
5
accommodation building. In particular Mr Atkinson states that LGB and
Sons Pty Ltd had provided a written variation to Watts Constructions based
on the application of Astec paint and refers to emails exchanged and a
document prepared by LGB and Sons Pty Ltd: the Variation Breakdown
dated 14 May 2009, which refers to “Product is EC100 dirt guard elastic
(gloss or satin finish)…Complies with Section J of Builders Code”.14 Mr
Atkinson states that “EC100 dirt guard” is a reference to “Astec paints”.15
[13] Mr Atkinson stated that on or about 20 December 2009, Watts
Constructions became aware through their architect on the site that Mr
Buttigieg and his employees were applying Dulux paint to the exterior
surfaces of the student accommodation. Mr Atkinson states that the site
was busy and therefore the site foreman did not become aware of the issue;
that is the use of the Dulux paint, until some of the work had been
undertaken. Mr Atkinson argues that it was not the responsibility of Watts
Constructions to check that LGB and Sons Pty Ltd were complying with the
terms of the subcontract to use a specific product, Astec paint. Mr Atkinson
states that he made enquiries with a Dulux paint representative and was
advised that the existing Dulux paint applied did not comply with section J of
the Building Code. Mr Atkinson states that Mr Buttigieg was instructed by
Watts Constructions in December 2009 to stop painting the exterior of the
building, however Mr Buttigieg continued to paint the interior of the student
accommodation. Mr Atkinson states that he had discussions in December
2009 with the site foreman and Mr Buttigieg about the Dulux paint that had
been applied – Mr Buttigieg admitted to him that he had used Dulux paint as
a substitute for Astec paint as he had been told by a Dulux paint
representative that the Dulux paint would “do the same job”. Mr Atkinson
states that although Mr Buttigieg may not have understood the importance
of using a paint which attracted certain “thermal qualities”, Mr Buttigieg
changed the type of paint (from Astec to Dulux) without the authority of
Watts Constructions and this was in breach of the subcontract. Mr Atkinson
states that in December 2009, Watts Constructions engaged Sustainability
House to test the product (Dulux paint) and the Dulux paint was later
approved by Sustainability House on 11 January 2010. Mr Atkinson states
that on 13 January 2010 he sent an email to Mr Buttigieg stating “Find
attached report and invoice [from Sustainability House]. We confirm our
instructions to proceed with the final coats of paint to the building exterior”.16
Mr Atkinson states that the cost of obtaining the approval from Sustainability
House as claimed by Watts Constructions is $4,070.00.17
14 Exhibit 6. The Variation No. V05RR representing scope of works refers to “supply and
application of Dirt Guard IR Elastic paint as recommended by Nev Ogden”. The email
from Watts Constructions to Lawrence Buttigieg dated 9 April 2009 (Exhibit 6) refers to
“Astec paints” and that Mr Buttigieg should “please coordinate with Astec paints…”.
15 There is also reference to “Astec Paints Three (3) coats EC 100 Energy Rated exterior
paint system…” in the email dated 20 March 2009 from the Architects to Watts
Constructions (Exhibit 6). The email from Watts Constructions dated 8 April 2009 to
Lawrence Buttigieg refers to the contract start date and retentions – “Also can you
please forward a variation price for the use of Aztec paint externally” (Exhibit 2,
Appendix B).
16 Exhibit 2, Appendix B.
17 Mr Atkinson in his statement, states that he is not claiming additional time spent
resolving the “technically complex issue” which equates to 45 hours per week for
-- 5 of 11 --
6
[14] Mr Atkinson gave evidence at the hearing that on 2 February 2010 he
received a phone call from the site foreman saying that Mr Buttigieg and his
workers had left the site. Mr Atkinson states that he went to the site on
2 February 2010 and the only painters present were Mr Andrew Von Pein,
Mr Jesse Von Pein and Mr Kevin Thompson. Mr Atkinson states that there
had been some earlier issues in relation to the internal painting works being
damaged by other workers on the site. Mr Atkinson states that Mr Buttigieg
was paid extra money to rectify the damage to the internal painting works
and this was paid as part of a variation to LGB and Sons Pty Ltd on
2 February 2010. Mr Atkinson states that after payment to Mr Buttigieg of
the additional internal painting works the amount outstanding by Watts
Constructions under the subcontract was $1,311.51 and that immediately
following the payment on 2 February 2010, “LGB and Sons left site and took
rendering product with them”.
[15] Mr Atkinson states that after he was advised by the site foreman that Mr
Buttigieg had failed to attend the site to complete the painting works, he
sent an email to Mr Buttigieg on 2 February 2010 stating that “…there is no
painting or rendering occurring [at the site]…I request your presence on site
100% until the works are complete”.18
[16] Mr Atkinson states that he attended the site on 3 February 2011 and saw Mr
Buttigieg on the site and that he was retrieving some of his materials. Mr
Atkinson states that he and Mr Buttigieg had a discussion about the
subcontract works and he “was extremely frustrated with damage caused by
other trades for which Watts had paid to have [remedied]”.19 Mr Atkinson
gave evidence at the hearing that during his conversation with Mr Buttigieg
on 3 February 2010, Mr Atkinson advised Mr Buttigieg that if he left the site
without finishing the painting works he would be in breach of the
subcontract. Mr Atkinson states that he was of the opinion that Mr Buttigieg
left the site without any intention of returning.
[17] Mr Atkinson states that Watts Constructions engaged three (3) painters –
Mr Andrew Von Pein, Mr Jesse Von Pein and Mr Kevin Thompson, who
were left on the site on 2 February 2010; and another painter, Mr Mark
Gibson at a later date, to complete the painting works on the basis that
“there were significant liquidated damages applicable if the facility was not
able to be occupied by the client at the start of the University academic
year”.20
[18] In relation to securing the materials left on site by Mr Buttigieg, Mr Atkinson
states that “Watts immediately secured all the painting materials on site”.21
During the hearing Mr Atkinson gave evidence that Mr Buttigieg made no
attempt to contact him to retrieve his materials left on the site and denied
3 weeks at $130.00 per hour (Exhibit 2). The invoice from Sustainability House is dated
22/01/10 and is in the amount of $4,070.00 (inc GST), Exhibit 2, Appendix B.
18 Appendix D to statement of Mr Atkinson (Exhibit 2).
19 Ibid.
20 Statement, para 11 (Exhibit 2).
21 Statement, para 12 (Exhibit 2).
-- 6 of 11 --
7
that he never allowed Mr Buttigieg access to his materials to complete the
painting.
[19] Mr Atkinson states that Watts Constructions wrote to LGB and Sons Pty Ltd
by letter dated 22 March 2010 stating that “the departure from [the site] on
2nd February 2010 and your non-compliance with our final request for your
attendance on site to complete works at 12.07pm on 2nd February 2010 [by
email] constitutes a breach of clauses 2a and 8c”.22 Mr Atkinson states that
in or about March 2010 Watts Constructions received an invoice for
outstanding money from LGB and Sons Pty Ltd in the amount of $28,000.00
including GST – Watts Constructions responded in writing on 16 April 2010
to Mr Buttigieg’s invoice. Mr Atkinson states that the invoice was a
“dummy” as there was no money owing by Watts Constructions to LGB and
Sons Pty Ltd in March 2010 under the subcontract. Mr Atkinson states that
there was an adjustment made in the amount of $2,469.50 in the
“reconciliation of subcontract payments” prepared by Watts Constructions,
in favour of LGB and Sons Pty Ltd representing the balance of money owing
on invoice dated 22 January 2010. Mr Atkinson gave evidence at the
hearing that Watts Constructions made several requests in writing to Mr
Buttigieg requesting he submit an invoice showing the correct amount
payable inclusive of GST as the original invoice for payment was calculated
on an amount exclusive of GST. Mr Atkinson states that Watts
Constructions made a “safe payment” of $10,000 to LGB and Sons Pty Ltd
on 22 January 2010 and requested that Mr Buttigieg contact him to discuss
– Mr Atkinson refers to an email dated 22 January 2010 sent to Mr
Buttigieg.23
Evidence of Mr Andrew Von Pein
[20] Mr Von Pein signed a statement and gave sworn evidence on behalf of
Watts Constructions at the hearing. Mr Von Pein was engaged by Mr
Buttigieg together with his son to complete painting works at the site. Mr
Von Pein states that he supervised the painting performed by the other
painters on the site and worked five (5), sometimes six (6) days per week.
Mr Von Pein stated that payment of his wages by Mr Buttigieg was
unreliable – Mr Buttigieg would pay his wages by cheque and sometimes it
would take a week for the funds to clear. Mr Von Pein states that Mr
Buttigieg still owes himself and other painting contractors money for work
performed: approximately $500.00 is owing to Mr Von Pein, $200.00 is
owing to Mr Kevin Thompson and $100.00 is owing to Mr Jesse Von Pein.
[21] Mr Von Pein states that on 2 February 2010 he was advised by another
worker on the site that Mr Buttigieg “had taken off”. Mr Von Pein states that
he telephoned Mr Atkinson and was advised that Watts Constructions would
pay him and his workers to complete the painting works. Mr Von Pein
stated that Mr Buttigieg had taken his paint and equipment with him
however there were two (2) full drums of paint and approximately six (6) to
eight (8) half drums of paint left behind at the site although the two (2) full
22 Appendix D to the Statement of Mr Atkinson, Exhibit 2. A further letter was sent by Mr
Atkinson to Mr Buttigieg dated 29 March 2010 noting that there had been no response
by LGB and Sons Pty Ltd to their earlier letter.
23 Exhibit 2, Appendix B.
-- 7 of 11 --
8
drums of paint were the wrong colour. Mr Von Pein stated that the drums of
paint left behind had been paid for by Mr Buttigieg and the approximate total
cost of the paint would be $600.00.24 Mr Von Pein states that the drums of
paint were placed into a storage unit as he had been told by Mr Atkinson to
finish off the job and clean up the job site – “there were bits and pieces
everywhere”. Mr Von Pein stated that he worked for approximately two (2)
hours on 2 February 2010 being the balance of the afternoon after Mr
Buttigieg “took off”. Mr Von Pein states that he claimed on an hourly basis
for the painting works performed by him and the other painters and they
were paid by Watts Constructions.25 Mr Von Pein verified that the hours
claimed by himself and the other contractors were for labour to complete the
outstanding painting works at the site. Mr Von Pein states that he did
attempt to contact Mr Buttigieg on 2 February 2010; and that he would have
returned the paint drums to Mr Buttigieg had he requested the paint be
returned. Mr Von Pein states that the tins of paint are still in Watts
Constructions’ storage facility and he may have used approximately one
half (1/2) drum of paint to complete some internal painting after Mr Buttigieg
left the site on 2 February 2010.
[22] Mr Von Pein also gave evidence about the application of Dulux paint to the
exterior of the student accommodation building – he was directed by Mr
Buttigieg to use Dulux paint so when Mr Buttigieg left the site on 2 February
2010, Watts Constructions had to purchase new paint so that Mr Von Pein
and the other painters could finish the painting works.26
Findings
[23] The Tribunal accepts the evidence of Mr Atkinson in relation to the various
payments made by Watts Constructions to LGB and Sons Pty Ltd under the
subcontract and finds that the payments made are supported by the various
documents tendered at the hearing. The Tribunal also accepts the
evidence of Mr Atkinson, supported by relevant documents, that the amount
of “retention held on contract” as at 2 February 2010 was $1,311.51 and
that Mr Buttigieg did not, despite Watts Constructions’ several requests in
writing, submit further information to “validate” the calculation of the amount
purportedly owing to LGB and Sons Pty Ltd as at 22 January 2010.
[24] The Tribunal accepts the evidence of Mr Atkinson that Mr Buttigieg applied
Dulux paint to the exterior of the student accommodation building and that
LGB and Sons Pty Ltd had prior to painting the exterior of the building
issued a written variation dated 14 May 2009 to use the paint product
“EC100 dirt guard elastic” (Astec paint) to the exterior surfaces of the
building. The Tribunal also accepts the evidence of Mr Atkinson that Mr
Buttigieg was instructed by Watts Constructions in or about December 2009
24 This is based on an estimate of $120.00 per drum of paint as stated by Mr Von Pein at
the hearing.
25 Mr Von Pein states that he was paid a rate of $25 per hour for 207 hours, Mr Kevin
Thompson was paid at a rate of $28 per hour for 18.8 hours, Mr Jessie Von Pein was
paid at a rate of $22 per hour for 192 hours and Mr Mark Gibson was paid at a rate of
$30 per hour for 219.4 hours.
26 Watts Constructions claim that the cost of the new paint purchased to complete the
external surfaces is $5,301.32.
-- 8 of 11 --
9
to stop painting the exterior of the building and that Mr Buttigieg continued
to paint the interior of the student accommodation building as required
under the subcontract. The Tribunal finds that the work performed by Watts
Constructions, that is engaging the services of Sustainability House to
approve the application of Dulux paint, was extra work outside the scope of
the subcontract and that this was a purported variation. The Tribunal also
finds that Watts Constructions have failed to comply with clause 5
(variations) of the terms and conditions of the subcontract – Watts
Constructions do not authorise the works (engaging Sustainability House) in
writing as required under clause 5(f); nor was there any agreement in
writing between the parties as to payment of the costs of the purported
variation (the costs payable to Sustainability House). The Tribunal cannot
be satisfied on the evidence given by Mr Atkinson alone that LGB and Sons
Pty Ltd agreed to the work being performed by Watts Constructions that is
engaging the services of Sustainability House and that LGB and Sons Pty
Ltd had agreed to pay the Sustainability House costs. Furthermore, Watts
Constructions directed Mr Buttigieg to continue with the painting works to
the exterior of the building on 13 January 2010 by stating “[we] confirm our
instruction to proceed with the final coats of paint to the building”,
notwithstanding the alleged breach of the subcontract by LGB and Sons Pty
Ltd, as argued by Mr Atkinson. The Tribunal finds that Watts Constructions
has therefore waived any entitlement to claim the Sustainability House costs
from LGB and Sons Pty Ltd for breach of the subcontract as alleged by
Watts Constructions.
[25] The Tribunal accepts the evidence of Mr Atkinson supported by the
evidence of Mr Von Pein that on 2 February 2010 Mr Buttigieg failed to
attend the site on 2 February 2010 and that Mr Buttigieg attended the site
on 3 February 2010 to collect his materials. The Tribunal also accepts the
evidence given by Mr Von Pein that as at 2 February 2010, Mr Von Pein
and other painting contractors were owed money by Mr Buttigieg for
painting work performed under the subcontract. The Tribunal finds that Mr
Buttigieg’s actions such as: failing to pay painting contractors for work
performed under his direction as required under clause 9 of the terms and
conditions, failing to attend the site to complete the painting works as
required under clause 2 of the terms and conditions; and attending the site
on 3 February 2010 to remove material and equipment, was a clear
intention not to be bound by the subcontract constituting repudiation which
entitled Watts Constructions to terminate the subcontract.27
[26] The Tribunal accepts the evidence of Mr Atkinson supported by the
evidence of Mr Von Pein, that Watts Constructions engaged the services of
other painting contractors after Mr Buttigieg failed to attend the site on
2 February 2010; and that this was an acceptance by Watts Constructions
of Mr Buttigieg’s breach of the terms of the subcontract.28 Watts
Constructions later confirmed the termination of the subcontract in writing to
27 See Shevill v Builders Licensing Board [1982] 149 CLR 620 referred to in Ingles Homes
[QLD] Pty Ltd v Mr & R Hudson Plumbing Pty Ltd [2010] QCAT 556 at [54].
28 See Holland v Wiltshire (1954) 90 CLR 409 referred to in Wenn v Café San Paul P/L
[2008] QCA 108 at [43] and see Ryder v Frohlich [2004] NSWCA 472 at [117]-[118] and
Ingles Homes [QLD] Pty Ltd v Mr & R Hudson Plumbing Pty Ltd [2010] QCAT 556 at
[57].
-- 9 of 11 --
10
LGB and Sons Pty Ltd by letter dated 22 March 2010. The Tribunal accepts
the evidence of Mr Atkinson supported by Mr Von Pein, that he only
directed Mr Von Pein to pack up the leftover paint drums and complete the
outstanding painting works after Mr Buttigieg failed to attend the site on
2 February 2010 and that Mr Atkinson would have returned the paint drums
to Mr Buttigieg had he attended the site to complete the painting works on
2 February 2010. Furthermore, the Tribunal accepts the evidence of Mr
Von Pein that he only used one half (1/2) drum of Mr Buttigieg’s paint and
the remainder of the paint is still in storage and available for Mr Buttigieg to
collect from Watts Constructions.
[27] The Tribunal accepts the evidence given by Mr Von Pein in relation to the
labour costs paid by Watts Constructions to Mr Andrew Von Pein, Mr Jessie
Von Pein, Mr Kevin Thomson and Mr Mark Gibson; and the evidence given
by Mr Atkinson together with supporting documents in relation to the total
costs incurred by Watts Constructions including materials, to complete the
outstanding painting works under the subcontract referred to as item
reference numbers 19 to 29 in the “reconciliation” and totalling $39,126.44.
The Tribunal accepts the evidence of Mr Atkinson that there was no money
owing by Watts Constructions to LGB and Sons Pty Ltd as at February 2010
under the subcontract, however there was an amount of $2,469.50 owing to
LGB and Sons Pty Ltd in respect of an invoice dated 22 January 2010. The
Tribunal having accepted the evidence of Mr Atkinson and Mr Von Pein that
Mr Buttigieg was never denied access to the paint drums left at the site on
2 February 2010 and that the paint is still in storage available for Mr
Buttigieg to collect from Watts Constructions, finds that the one half (1/2)
paint drum used by Mr Von Pein after 2 February 2010 to complete some of
the outstanding painting works at the site was paint belonging to Mr
Buttigieg and the cost of the paint used should therefore be deducted from
the total costs claimed by Watts Constructions to complete the painting
works under the subcontract. The Tribunal finds that having accepted the
evidence given by Mr Atkinson and Mr Von Pein in relation to the cost of the
paint belonging to Mr Buttigieg, the amount of $60.0029 should be deducted
from the total costs claimed by Watts Constructions to complete the painting
works.
[28] The Tribunal, having been satisfied that the subcontract was properly
terminated by Watts Constructions, has determined that the following
amount is owing by LGB and Sons Pty Ltd to Watts Constructions:
Amount claimed (to complete outstanding works) $ 39,126.44
Less retention held on contract $ 1,442.66
Less money owing on invoice (22 January 2010) $ 2,469.50
Less deduction (Sustainability House costs) $ 4,070.00
Less deduction (paint belonging to Mr Buttigieg) $ 60.00
TOTAL $ 31,084.28
Costs
29 Based on an estimate given by Mr Von Pein of $120.00 per paint drum.
-- 10 of 11 --
11
[29] The starting point concerning costs in QCAT is that each party must bear its
own.30 This presumption may, however, be displaced if the Tribunal
considers it in the interests of justice to order a party to pay all or part of the
costs of another party.31 The phrase “in the interests of justice” is not
defined in the Act but is to be construed according to its ordinary and plain
meaning, which obviously confers a broad discretionary power on the
decision-maker. In determining whether it is in the interests of justice to
award costs against another party the Tribunal may have regard to the
nature and complexity of the dispute; the relative strengths of the claims
made by each of the parties; and, whether a party has acted in a way that
unnecessarily disadvantages another party.32
[30] Watts Constructions claim the amount of $250.00 being the “costs for
lodgement with QCAT”. Mr Buttigieg as representative of LGB and Sons
Pty Ltd failed to attend the hearing on 8 April 2011 and did not comply with
the former directions of the Tribunal for the filing and exchange of material
to be relied upon at the hearing. The Tribunal is satisfied having regard to
the discretionary power to award costs under section 100 and the issues to
be determined in this matter that it is appropriate to make an order for costs
in the amount of $250.00 as claimed.
[31] The Tribunal orders that LGB and Sons Pty Ltd pay the amount of
$31,334.28 to Watts Constructions by 4.00pm on 17 June 2011.
30 Queensland Civil and Administrative Tribunal Act 2009 (“the Act”), s 100.
31 Ibid, s 102(1).
32 Ibid, s 102(3).
-- 11 of 11 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2011/294