Aurisch v Millsons Pty Ltd and Others [2011] QCAT 245
CITATION: Aurisch v Millsons Pty Ltd and Others [2011]
QCAT 245
PARTIES: Barry Charles Aurisch and Sheila Denise Aurisch
v
Millsons Pty Ltd trading as Dixon Homes
Rockhampton
(First Respondent)
LA & SR Thorne Pty Ltd trading as Bowler
Geotechnical Capriciornia
(Second Respondent)
Tapsell Consulting Engineers Pty Ltd
(Third Respondent)
APPLICATION NUMBER: BD408-09
MATTER TYPE: Building matters
HEARING DATE: 4 May 2011
HEARD AT: Brisbane
DECISION OF: Ms Michelle Howard, Member
DELIVERED ON: 4 May 2011
DELIVERED AT: Brisbane
ORDERS MADE: 1. That the time limit fixed for the start of a
proceeding under section 51 of the
Domestic Building Contracts Act 2000, be
extended pursuant to section 61 of the
Queensland Civil and Administrative
Tribunal Act 2009 to allow the applicants’
until 9 December 2010 to file their claim
for breach of statutory warranties;
2. That the time for the filing of the
applicants amended statement of claim
contained in direction 1 of the directions
made on 29 November 2010 be extended
to 9 December 2010.
CATCHWORDS: BUILDING DISPUTE – Domestic Building
Contracts Act 2000 s 51 – whether time limit for
starting a proceeding for a breach of warranty
can be extended under Queensland Civil and
Administrative Tribunal Act 2009 s 61 – effect of
Limitation of Actions Act 1974 s 43A – relevant
factors in the exercise of discretion to extend
time
-- 1 of 10 --
2
Domestic Building Contracts Act 2000, ss 18, 42,
43, 44, 51, 55
Limitation of Actions Act 1974, ss 7, 43A
Queensland Building Services Authority Act
1991, s 77, Schedule 2
Queensland Civil and Administrative Tribunal Act
2009, ss 6(2), 6(7), 61
Australian Iron & Steel Ltd v Hoogland (1962)
108 CLR 471, applied
Brisbane South Regional Health Authority v
Taylor [1996] 186 CLR 541, considered
Reynolds v Aluma-Lite Products Pty Ltd (No 2)
[2010] FCA 914 (25 August 2010), applied
R v Roberts, ex parte Jacob [2002] QCA 87,
considered
Gallagher v QBSA [2010] QCAT 383, applied
Ryan v Cornwall [2010] QCAT 212, not followed
APPEARANCES and REPRESENTATION (if any):
This application was heard on the papers pursuant to section 32 of the
Queensland Civil and Administrative Appeal Tribunal Act 2009, with the benefit
of written submissions as follows.
APPLICANT: Mr P Travis of Counsel, instructed by Aden
Lawyers
RESPONDENT: CLS Lawyers
REASONS FOR DECISION
[1] Mr and Mr Aurisch (the applicants) have previously filed an application which
sought damages for negligence. The proceedings were commenced against
a builder (Millsons Pty Ltd trading as Dixon Homes Rockhampton). Later,
other parties were joined as respondents to the proceedings, namely a soil
tester (LA and SR Thorne Pty Ltd trading as Bowler Geotechnical
Capricornia); and engineers (Tapsell Consulting Engineers Pty Ltd). The
respondents were involved in the construction of a house property which the
Aurischs’ subsequently purchased, and in respect of which the claim in
negligence arises. They purchased the house on 5 April 2004 from the
original owner, Ravcorp Developments Pty Ltd which was a developer.
Construction was completed on 24 March 2004.
[2] The proceedings were commenced on 3 September 2009 in the since
abolished Consumer and Commercial Tribunal. QCAT now has
responsibility to deal with the proceeding.
[3] The tribunal made directions on 26 October 2010 at the conclusion of a
compulsory conference, which included directions for some disclosure of
documents by the builder to the applicants within 14 days; and for the
-- 2 of 10 --
3
applicants to file and serve an amended application which had been
foreshadowed at a compulsory conference by 23 November 2010. The time
for filing of the amended application was subsequently varied by directions
made on 29 November 2010, to 7 December 2010.
[4] In November 2010, Dixon Homes disclosed to the Aurischs’ a copy of the
contract between them and the developer for the construction of the home.
The contract was dated 29 August 2003.
[5] On 9 December 2010, the applicants’ filed a second amended statement of
claim to include a claim for breach of statutory warranties against the builder
under the Domestic Building Contracts Act 2000 (the DBC Act). In
response, the builder asserted that the claim is statute barred under section
51(1) of the DBC Act.
[6] Mr and Mrs Aurisch now seek an order, pursuant to section 61 of the
Queensland Civil and Administrative Tribunal Act 2009 (the QCAT Act),
extending the time limit fixed by section 51 of the DBC Act to commence a
proceeding for breach of warranties. The applicants and the builder have
provided written submissions to the tribunal about the application for
extension of time.
[7] It is common ground that the limitation period under section 51 of the DBC
Act expired in September 2010.
[8] There are two issues for consideration. Firstly, whether the time limit under
section 51 DBC Act can be extended pursuant to section 61 of the QCAT
Act; and if so, whether the tribunal should exercise its discretion to extend
the time limit.
The Legislative Framework
[9] Section 61 of the QCAT Act provides that the tribunal may extend procedural
time limits as follows:
61 Relief from procedural requirements
(1) The tribunal may, by order--
(a) extend a time limit fixed for the start of a proceeding by this Act or an
enabling Act; or
(b) extend or shorten a time limit fixed by this Act, an enabling Act or the
rules; or
(c) waive compliance with another procedural requirement under this Act,
an enabling Act or the rules.
(2) An extension or waiver may be given under subsection (1) even if the
time for complying with the relevant requirement has passed.
(3) The tribunal can not extend or shorten a time limit or waive
compliance with another procedural requirement if to do so would cause
prejudice or detriment, not able to be remedied by an appropriate order
for costs or damages, to a party or potential party to a proceeding.
(4) The tribunal may act under subsection (1) on the application of a
party or potential party to the proceeding or on its own initiative.
-- 3 of 10 --
4
(5) The tribunal's power to act under subsection (1) is exercisable only
by--
(a) the tribunal as constituted for the proceeding; or
(b) if the tribunal has not been constituted for the proceeding--a legally
qualified member, an adjudicator or the principal registrar.
[10] An enabling Act is defined in section 6(2) as an Act, other than the QCAT
Act, which confers jurisdiction on the tribunal. An enabling Act which confers
original jurisdiction, may add to, otherwise vary, or exclude functions stated
under the QCAT Act,1 including, under section 6(7), the period within which
an application must be made.2 If an enabling Act modifies the tribunal’s
functions in a jurisdiction conferred by it, or a matter mentioned in section
6(7), then the modifying provision in the enabling Act prevails to the extent of
any inconsistency.3
[11] Part 7 of the Queensland Building Services Authority Act 1991 (the QBSA
Act) confers original jurisdiction on the tribunal to decide building disputes.4
Definitions of ‘building dispute,’ ‘domestic building dispute’ and ‘reviewable
domestic work’ are provided in Schedule 2 of the QBSA Act. By virtue of
these provisions, the tribunal may decide a building dispute relating to
breach of the statutory warranties under the DBC Act subject to some
exceptions which are not relevant.
[12] The DBC Act does not give jurisdiction to the tribunal to determine the
dispute which is the subject of this application. However, it is an enabling
Act for conferring jurisdiction on QCAT for other applications.5
[13] Section 51 of the DBC Act specifies that:
51 Proceedings for breach of warranties
(1) A proceeding for a breach of a warranty under this part for a regulated
contract must be started within 6 years and 6 months after--
(a) the subject work is finished; or
(b) if the subject work is not finished--the stated completion date or
period.
(2) In a proceeding for a breach of a warranty mentioned in this part, it is
a defence for the defendant to prove that the deficiencies of which the
plaintiff complains arise from instructions given by the building owner
contrary to the defendant's written advice.
[14] In Ryan v Cornwall,6 a differently constituted QCAT tribunal found that the
limitation period in section 51 of the DBC Act was unable to be extended
under section 61 of the QCAT Act. The tribunal reached this view, having
regard to section 43A of the Limitation of Actions Act 1974 (LA Act). Section
43A provides as follows:
1 QCAT Act section 6(4).
2 QCAT Act section 6(7); Acts Interpretation Act 1954 section 14(3).
3 QCAT Act section 7.
4 QBSA Act section 77.
5 For example, see sections 18(6), 55(4).
6 [2010] QCAT 212 (Member Fitzpatrick).
-- 4 of 10 --
5
43A Characterisation of limitation laws
(1) In this section--
limitation law means a law (including, but not limited to, this Act) that
provides for the limitation or exclusion of any liability or the barring of a
right of action for a claim by reference to the time when a proceeding on,
or the arbitration of, the claim is started.
(2) A limitation law of the State is to be regarded as part of the
substantive law of the State.
(3) This section applies to a cause of action that arose before the
commencement of this section but does not apply to a proceeding started
before the commencement.
[15] The tribunal concluded that section 43A of the LA Act makes section 51 of
the DBC Act a substantive provision and that as a result, the right was
extinguished at the expiration of the limitation period prescribed.7 Further, it
considered that express statutory authority was necessary if the right was to
be revived.8 It did not consider that section 61 of the QCAT Act was
sufficient or intended for this purpose.9
The threshold question -- whether time may be extended for commencing
the proceedings for breach of statutory warranty
[16] The Aurischs’ argue that section 43A of the LA Act does not operate to
extinguish underlying rights. They rely upon a recent decision of the Federal
Court of Australia in Reynolds v Aluma-Lite Products Pty Ltd (No 2).10 In this
decision, Justice Logan considered the operation of section 43A of the LA
Act.11
[17] The applicants argue that, as Justice Logan identified, section 43A(2) did not
operate to bar rights at the end of a limitation period. He drew this
conclusion having regard to conventional statutory construction approach
which bars remedies not rights;12 that when Parliament intended a limitation
period to have substantive effect, the statutory provision would expressly
state this;13 having regard to the Explanatory Notes, section 43A was
intended to characterise a limitation provision for purposes of choice of law
determination;14 and finally, provision in the LA for extension of limitation
periods was inconsistent with an interpretation that section 43A had wide
substantive effect.15
[18] In essence then, the applicants argue that the tribunal erred in the Ryan
decision by merging the concept of the limitation period being part of
7 [2010] QCAT 212 (Member Fitzpatrick) [27-29].
8 [2010] QCAT 212 (Member Fitzpatrick) [29].
9 [2010] QCAT 212 (Member Fitzpatrick) [30-31].
10 [2010] FCA 914 (25 August 2010).
11 [2010] FCA 914 (25 August 2010), [36-45].
12 [2010] FCA 914 (25 August 2010) [41].
13 [2010] FCA 914 (25 August 2010) [42].
14 [2010] FCA 914 (25 August 2010), [43].
15 [2010] FCA 914 (25 August 2010) [44].
-- 5 of 10 --
6
substantive law for a choice of law analysis as provided for in section 43A of
the LA, with the separate concept of substantive rights being extinguished.
[19] The builder argues that Ryan was correctly decided and urges the tribunal to
adopt a similar approach, although it does not make submissions about how
the decision of Justice Logan in Reynolds v Aluma-Lite Products Pty Ltd (No
2) should be reconciled with it. Alternatively, it argues that if the Aurischs’
correctly assert that s 43A does not operate as Ryan suggests, then the LA
Act cannot be used to determine the character of the limitation provided in
s 51 of the DBC Act. In this regard, reliance is placed on section 7 of the LA
Act, which provides among other things, that subject to sections 11(2) and
43A, the LA Act does not apply to an action for which a time limitation is
fixed by another Act.
[20] The builder argues that the limitation provision in section 51(1) of the DBC
Act is ‘the essence of the right to bring proceedings,’ and that the applicants’
rights terminated with its expiry. The builder submits that there is a
distinction between limitation statutes and limitation provisions, as discussed
in Australian Iron & Steel Ltd v Hoogland.16 Reliance is placed on the
judgment of Justice Windeyer, who said:
It may be that there is a distinction between Statutes of Limitation,
properly so called, which operate to prevent the enforcement of rights of
action independently existing, and limitation provisions annexed by a
statute to a right newly created by it. In the latter case the limitation does
not bar an existing cause of action. It imposes a condition which is of the
essence of a new right.17
[21] The builder also refers to a decision of Supreme Court of Queensland which
considered that a limitation provision in a statute which both creates a right
and a time limit, may annexe the limitation to the right, and accordingly be ‘of
the essence of the right:’ R v Roberts, ex parte Jacob.’18 The builder
submits that the time limit in section 51 of the DBC Act is annexed to the
right to bring proceedings.
[22] In response to these arguments, the Aurischs’ submit that further comments
of Justice Windeyer in the Australian Iron and Steel case are relevant as
follows:
……And, even when a time limit is imposed by the statute that creates a
new cause of action or right, it may be so expressed that it is regarded as
having a purely procedural character, as a condition of the remedy rather
than an element in the right ; and in such cases it can, it seems, be
waived, either expressly or in some cases by estoppel … 19
[23] In this case, the DBC Act creates statutory warranties,20 such as having a
builder carry out the work with reasonable care and skill,21 which an owner
16 (1962) 108 CLR 471.
17 (1962) 108 CLR 471 at [488-489] (Windeyer J).
18 [2002] QCA 87 (Davies J), [13].
19 (1962) 108 CLR 471 at [488-489] (Windeyer J).
20 DBC Act sections 42-44.
21 DBC Act section 44.
-- 6 of 10 --
7
may enforce. The applicants submit that the time limit is merely a condition
of the remedy, namely enforcing those rights by starting a proceeding. The
argument is that the limitation period is therefore a ‘condition of the remedy’
rather than an element of the right. They argue that section 61 of the QCAT
Act gives the tribunal power to extend the time limit fixed for starting the
proceeding.
[24] The DBC Act does not confer jurisdiction on the tribunal for deciding
proceedings for breach of the statutory warranties which it contains. That
jurisdiction is conferred by the QBSA Act. However, the DBC is an enabling
Act, as it confers jurisdiction for other types of applications. Unless the
enabling Act has modified the QCAT Act in some relevant way, then
pursuant to section 61 of the QCAT Act, the tribunal may extend the time
limit for the start of the proceeding, provided that the time limit fixed is a
procedural requirement.
[25] The decision of Justice Logan in Reynolds v Aluma-Lite Products about the
effect of s 43A in characterisation of a limitation provision for a choice of law
analysis is directly relevant and applicable. Having regard to the
Explanatory Notes regarding the insertion of section 43A into the LA, it is
clear that it was inserted for the purposes of determining choice of law
issues, so that when applied in another jurisdiction as the law governing
proceedings, Queensland limitation laws will be applied. It was inserted to
discourage forum shopping. Accordingly, I do not construe section 43A to
make the time limit in section 51 of the DBC Act a substantive provision.
[26] However, in that decision, Justice Logan was considering limitation periods
contained in the LA Act. His broader comments must be understood in that
context. Specifically, section 7 of the LA Act provides that subject to s 43A
and 11(2), which is not relevant in this case, the LA Act does not apply to an
action for which a limitation period is fixed in another Act. In this instance,
the relevant time limit is set in the DBC Act.
[27] The observations of Justice Windeyer in Australian Iron and Steel about
limitation provisions, and the distinction between a condition which is the
essence of a right, as opposed to a time limit which is a condition of a
remedy, are relevant in determining the nature and effect of the time limit
specified in section 51 of the DBC Act. The issue in this case is whether the
time limit in s 51 of the DBC Act is annexed to the right as submitted by the
builder, or whether, as the applicants argue, it is a condition of the remedy.
[28] The DBC Act provides for statutory warranties. It separately provides in s 51
for a proceeding for a breach of a warranty to be commenced within the
6 years and 6 months time limit. The statutory warranties provided for in the
DBC Act are not extinguished upon the expiration of the time prescribed for
commencing proceedings: the warranties themselves remain in place under
the legislation. Since the warranties are unaffected by the expiration of the
time limit, I am satisfied that the effect of section 51 is to bar resort to a
remedy through proceedings, rather than extinguish the right to the
warranties. Therefore, the time limit is a condition of the remedy.
[29] However, proceedings can not be commenced after that time, unless there
is a mechanism for extending the time for the commencement of the
-- 7 of 10 --
8
proceeding. I accept, as Justice Logan said, statutory construction rules
suggest that if Parliament intended the time limitation to have substantive
effect it would expressly state this. It has not done so. Further, enabling
Acts may modify the provisions of the QCAT Act in which case the modifying
provision would prevail. There is no modifying provision in the DBC Act
which prohibits extension of the time limit fixed by section 51 pursuant to
section 61 of the QCAT Act.
[30] Accordingly, I am satisfied that I may, if I consider it appropriate to exercise
my discretion to do so, extend time for the start of a proceeding for a breach
of warranty under the DBC Act.
Should the discretion to extend the time limit be exercised?
[31] Gallagher v QBSA22 identifies the matters relevant to an application for
extension of time. In that case, Member Oliver identified these as whether
there is reasonable explanation for the delay; whether there has been any
prejudice suffered as a result of the delay in filing the application; whether
the proposed claim has some merit; and whether it would be fair and
equitable in all of the circumstances.
[32] Section 61(6) of the QCAT Act provides that a time limit can not be extended
if this would cause prejudice or detriment not able to be remedied by an
order for costs or damages. Prejudice must be considered in the context of
the circumstances at the time of the application.23
Delay
[33] The applicants noticed defects in the home, in about March 2005. In April
2005, they made a claim against the statutory insurance fund under the
QBSA Act. The works that were the subject of that claim were completed in
February 2009. In September 2009, the Aurischs’ filed their original
application in these proceedings. Later, amendments were made due to the
inclusion of the soil tester and the engineers as parties.
[34] In October 2010, when Counsel was briefed to appear for the applicants at a
compulsory conference, he formed the view that they may have a claim for
breach of statutory warranty, but that disclosure was required to determine
whether that claim should proceed. Directions were made at the conclusion
of the compulsory conference on 26 October 2010 for the builder to ‘provide
to the applicants a copy of any contract between Ravcorp Developments Pty
Ltd and the’ builder ‘in relation to the subdivision which included’ the
Aurischs’ house property within 14 days.
[35] On 8 November, the builders provided a copy of the contract. On
9 December 2010, the amended statement of claim including the claim for
breach of statutory warranties was filed.
[36] The applicants submit that they filed the amended claim including the breach
of statutory warranty ten weeks from the expiration of the time limit, and that
22 [2010] QCAT 383, [43].
23 Brisbane South Regional Health Authority v Taylor [1996] 186 CLR 541.
-- 8 of 10 --
9
the chronology shows that they have not sat on their rights, rather that they
have actively and diligently pursued them.
[37] The builder submits that despite defects having been observed in April 2005,
it was not until 2009 that proceedings were commenced. Further, at the time
of the compulsory conference, when the possibility of bringing a contractual
claim was first raised, the time limit for starting a proceeding for breach of
statutory warranty had already expired. Further the builder argues that the
applicants had been aware of the existence of the contract since the builder
filed its defence in September 2009.
[38] I am satisfied that the Aurischs’ have been pursing their rights since April
2005, through the QBSA and since 2009, through these proceedings. There
has been some delay in identifying and pursuing the claim for breach of
statutory warranties against the builder. But once it was identified it has
been promptly pursued. The builder has been aware since 2005 of the claim
through the QBSA, and in any event, has been aware of these proceedings
against it for damages for negligence since September 2009. The claim for
breach of the statutory warranties arises out of the same circumstances and
the amended claim including the statutory warranties was filed some ten
weeks after the expiry of the time limit.
[39] In my view, a reasonable explanation has been given for the delay.
Prejudice
[40] The applicants submit that prejudice can not mean mere delay, costs of
delay, or the possibility of an adverse finding by the tribunal on determination
of the application, relying upon Chesterton v Smith.24 In this instance, they
submit that there can be no prejudice since the claim arises from the same
facts alleged against the builder since the commencement of the
proceeding.
[41] The builder argues that if the time limit is extended, it will suffer prejudice.
Reliance is placed on the judgment of Justice McHugh in Brisbane South
Regional Health Authority v Taylor,25 who said that a limitation provision sets
out the general rule while an extension of it represents an exception to it.26
Further, he stated that it will often be unfair to make current shareholders
liable for a wrong in the distant past and that it is Parliament’s judgment that
society is best served by causes of action being litigated within the
prescribed period.27 The builder argues that it will suffer inherent prejudice
as a result of the applicants’ delay, in the sense described by Justice
McHugh.
[42] Further, the builder submits that the character of the claim to be met by it
would substantially change if an extension was granted, resulting in undue
delay and a lengthy hearing, as it will be necessary to consider whether the
contract falls within the DBC Act.
24 [2009] QCCTB 106.
25 [1996] 186 CLR 541.
26 [1996] 186 CLR 541, 533.
27 [1996] 186 CLR 541, 533.
-- 9 of 10 --
10
[43] I do not consider that there is material prejudice to the builder if the
discretion to extend time is exercised. The builder is well aware of the
circumstances giving rise to the claim and will be required to meet the
Aurischs’ application arising essentially out of the same set of facts for
negligence irrespective of whether the claim for breach of statutory
warranties also proceeds.
Merits of the Claim
[44] The applicants submit that the new claim has merit. Further, they submit
that the builders subsequent assertions that there are other contracts with
Ravcorp which could be a single contract for construction of two or more
dwellings are unsubstantiated as the contracts relied upon have not been
disclosed although the direction of the tribunal of 26 October 2010, required
it.
[45] They argue that the tribunal’s directions of 26 October 2010, were for the
builder to provide a copy of any contract between the original owner and the
builder in relation to the subdivision. The builder advised the applicants
when providing only one contract relating to the property owned by the
applicants, that this was the only contract used for properties constructed by
the builder in the development.
[46] The builder argues that the contract is not a domestic building contract under
the DBC Act because it entered into two or more separate contracts with
Ravcorp which could be the subject of a single contract for the construction
of 2 or more detached dwellings.
[47] The builder’s arguments that the claim does not have merit turn on the
content of documents of which it has not provided in evidence or disclosed in
accordance with the direction made by the tribunal. On the basis of the
available evidence, I am satisfied that the claim has some merit.
Is it just and equitable
[48] In all of the circumstances, I am satisfied that justice would be served by
exercising my discretion to make orders under section 61 of the QCAT Act,
extending time for the starting of a proceeding for breach of warranty under
section 51 of the DBC Act. As the applicants already had proceedings on
foot, the claim for breach of statutory warranties was filed as part of the
applicants’ second amended statement of claim on 9 December 2010.
Accordingly, I will order that time be extended for the filing of the claim to the
date on which the applicants filed their second amended statement of claim
which included the claim for breach of statutory warranties.
[49] To further give effect to these orders to extend the time limit, I will also
formally direct that the time for the filing of the applicants’ amended
application in accordance with the direction made on 29 November 2010, be
extended to 9 December 2010.
-- 10 of 10 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2011/245