Davidson v Jetta Express [2011] QCATA 294
CITATION: Davidson v Jetta Express [2011] QCATA 294
PARTIES: Aaron Davidson
(Applicant/Appellant)
v
Jetta Express
(Respondent)
APPLICATION NUMBER: APL144-11
MATTER TYPE: Appeals
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Richard Oliver, Senior Member
DELIVERED ON: 25 October 2011
DELIVERED AT: Brisbane
ORDERS MADE: Leave to appeal is refused.
CATCHWORDS: Minor Civil Dispute – whether the respondent
in breach of contract – where damages
claimed to remote – whether error of law
Queensland Civil and Administrative Tribunal
Act 2009, s 142(3)
QUYD Pty Ltd v Marvass Pty Ltd [2009] 1 Qd
R 41
Cachia v Grech [2009] NSWCA 232
Glenwood Properties Pty Ltd v Delmoss Pty
Ltd [1986] 2 Qd R 388
McIver Bulk Liquid Haulage Pty Ltd v
Fruehauf Australia Pty Ltd [1989] 2 Qd R 577
Hadley v Baxendale (1854) 156 ER 145
APPEARANCES and REPRESENTATION (if any):
This matter was heard and determined on the papers pursuant to s 32 of
Queensland Civil and Administrative Tribunal Act 2009 (QCAT Act).
-- 1 of 5 --
2
REASONS FOR DECISION
[1] On 7 September 2010 Mr Davidson entered into a contract with Jetta
express for it to deliver excess baggage to Guangzhau airport in China.
The shipper’s letter of instruction signed by Mr Davidson indicates that the
arrival time for the baggage was to be 13 September 2010.
[2] Associated with that document is a “yellow card” which has the estimated
arrival date 14 September 2010. Mr Davidson acknowledges receiving a
copy of this card. It provided:-
“All baggage is to arrival of destination airport (except door to door) and
does not include duty taxes, trust and clearances terminal fees, custom
fees and/or quarantine fees (if applicable) Jetta Express aim to get your
baggage to its destination at the requested time but sometimes delays
occur which are beyond our control due to airlines and current security
requirements.”
[3] The baggage was received by Singapore Airlines, the carrier, on
13 September 2010. The flight departed that night at 23.33, and arrived in
Guangzhau on 15 September 2010 at 13.30. On the face of it, there are no
unusual delays in the shipment from Australia to Guangzhau. Once the
baggage arrived at Guangzhau airport, it was then delivered to a bonded
warehouse for collection. Mr Davidson did not become aware of the
location of the baggage for another day after the 15th, presumably on the
16th.
[4] The “baggage” was in fact a miniature turbine which was to be displayed at
a trade fair in China which was conducted on 15 September. As it
happened he did not retrieve the baggage until approximately a month later
at a retrieval cost of $300.
[5] As he was not able to use the turbine at the trade fair, he contends that his
business trip to China was a failure and has sought to be reimbursed part of
the costs of the trip. He contends that Jetta Express’ breached the contract
in failing to have the baggage delivered on 14 September 2010 “at the
Guangzhau airport” so it could be immediately retrieved by him that day.
[6] He commenced a proceeding in the minor civil disputes jurisdiction of QCAT
on 7 October 2010. By way of a response, Jetta Express filed an
application in a miscellaneous matter to have the claim struck out and
dismissed on the basis that Jetta Express did not breach its contract with Mr
Davidson.
[7] The matter came on for hearing before a Tribunal Adjudicator on 11 April
2011. Reasons for the decision to dismiss Mr Davidson’s claim were
delivered.
[8] From that decision Mr Davidson has filed an application for leave to appeal
or appeal in the Tribunal. The grounds of appeal include the following:
-- 2 of 5 --
3
Jetta admitted the wrong doing;
Jetta did not deliver the excess baggage in 7 days as agreed;
Jetta did not deliver the baggage to the airport as agreed – it was
delivered to a bonded warehouse;
Jetta provided false and misleading information (of gouging on “all
the time” in China) prior to dispatch;
Jetta did not provide the number for Singapore Airlines on the
airwave bill;
Jetta introduced malicious and prejudicial evidence against the
applicant;
The applicant was denied an adjournment.
[9] As this is an appeal from a decision in the minor civil disputes jurisdiction,
leave to appeal is necessary.1
[10] The question whether or not leave to appeal should be granted is usually
addressed according to established principles: Is there a reasonably
arguable case of error in the primary decision?2 Is there a reasonable
prospect that the applicant will obtain substantive relief?3 Is leave
necessary to correct a substantial injustice to the applicant caused by some
error?4 Is there a question of general importance upon which further
argument, and a decision of the appellate court or tribunal, would be to the
public advantage?5
[11] The learned Adjudicator gave detailed reasons for the decision. She
correctly identified that the onus in proving the contract, its terms and any
breach was on the applicant. She correctly identified that it was Jetta
Express’s obligation to deliver the baggage to the arrival airport which
clearly occurred in this case. Subsequent to its arrival at Guangzhau airport
it was then placed into a bonded warehouse. This is obviously to comply
with Chinese import and security regulations.
[12] The fact that the baggage arrived a day late was certainly within the
contemplation of the terms of the contract because the date of arrival was
estimated only. The fact that it was kept in Brisbane for seven days seems
to result from some security requirements for baggage leaving Australia,
although there is some uncertainty on this point.
[13] There is no reason why the learned Adjudicator could not rely on the
disclaimer clause referred to in the terms and conditions of the contract.
[14] Mr Davidson contends that Jetta Express engaged in misleading and
deceptive conduct and breached section 52 of the Trade Practices Act
1 QCAT Act section 142(3).
2 QUYD Pty Ltd v Marvass Pty Ltd [2009] 1 Qd R 41.
3 Cachia v Grech [2009] NSWCA 232 at 2.
4 QUYD Pty Ltd v Marvass Pty Ltd [2009] 1 Qd R 41.
5 Glenwood Properties Pty Ltd v Delmoss Pty Ltd [1986] 2 Qd R 388 at 389; McIver Bulk
Liquid Haulage Pty Ltd v Fruehauf Australia Pty Ltd [1989] 2 Qd R 577 at 578, 580.
-- 3 of 5 --
4
1974. There are two things to be said about this. Firstly, the Trade
Practices Act 1974 was not relied upon during the course of the hearing.
Secondly there is no evidence that Jetta Express is a corporation, although I
assume it probably is, so that jurisdiction under the Trade Practices Act
1974 is enlivened.
[15] If I am wrong about this contention, then the question becomes whether the
representation by the Jetta Express staff that they had no knowledge of
price gouging in China actually induced Mr Davidson to enter into the
contract. The learned Adjudicator did not have to consider this question
because the misleading and deceptive conduct claim has only been raised
on this appeal. Further there was no evidence that he was so induced nor
is there evidence of actual price gouging. The cost of holding the turbine in
bonded storage for a month seemed reasonable.
[16] Even if the applicant could identify some error to justify a finding that Jetta
Express did breach its contract, a difficulty still arises with the damages
claimed. At the time of the hearing the claim was for $4,775 which included
cost of half the trip plus, it seems some costs of preparing the affidavit of Mr
Ansell. Damages can only be recovered from a breach of contract if they
fairly and reasonably arise naturally, according to the usual course of things
from the breach itself. Damages might also be recovered if it could be
reasonably supposed to have been in the contemplation of both parties at
the time the contract was made and they were a probable result of the
breach6.
[17] With respect to the first limb, the only direct loss from the breach is the cost
of the goods being held in the bonded warehouse for a period of about a
month. This loss is limited to about $300. Even so, in terms of mitigation,
there does not appear to be any apparent reason why the goods could not
have been recovered at an earlier time.
[18] With respect to the second limb, that is the loss that might have been in the
reasonable contemplation of the parties, on any view, a the time the
contract was made, Jetta Express could not have reasonably contemplated
that if the baggage arrived one day late Mr Davidson’s whole mission to
China would result in failure. There is no evidence of any discussion
between Mr Davidson and any Jetta Express representative where he made
known the purpose of his trip to China and the importance of the turbine
arriving on time. This consequential loss is not recoverable. In addition to
that, the learned Adjudicator made specific findings that the trip was not a
complete loss because, according to the newspaper7 Mr Davidson claimed it
as a success. This evidence is certainly not conclusive but it does purport
to report Mr Davidson’s views about the trip.
[19] Even if a breach of contract was proved, the damages claimed are not
recoverable.
6 Hadley v Baxendale (1854) 156 ER 145 at 151.
7 Although I have reservations about the lack of this evidence.
-- 4 of 5 --
5
[20] The detailed reasons of the learned Adjudicator are not indicative of any
denial of procedural fairness. Mr Davidson was able to adduce all relevant
evidence during the hearing, including the documentary evidence, and it is
difficult to see how he could have presented his case any better than he did
on the day of the hearing.
[21] Mr Davidson has been unable to satisfy the Appeal Tribunal that the learned
Adjudicator has fallen into error nor is there any prospect he would obtain
substantive relief if leave was granted. Here, there is no substantial
injustice to remedy. The conclusions reached by the learned Adjudicator
were clearly open on the evidence available to her. As no error of law has
been identified, nor is any apparent, leave to appeal must be refused.
-- 5 of 5 --
Official source: https://www.sclqld.org.au/caselaw/QCATA/2011/294