Fabcot Pty Ltd v Cairns Regional Council & Ors [2011] QPEC 148
1-1
[2011] QPEC 148
PLANNING AND ENVIRONMENT COURT
JUDGE R JONES
P & E Appeal No 2046 of 2011
FABCOT PTY LTD Appellant
and
CAIRNS REGIONAL COUNCIL Respondent
and
CHIEF EXECUTIVE OF First Co-Respondent
DEPARTMENT OF TRANSPORT AND MAIN ROADS
and
DEPARTMENT OF LOCAL GOVERNMENT Second Co-Respondent
AND PLANNING
and
MULGRAVE & DISTRICT CHAMBER OF Third Co-Respondent
COMMERCE INC
BRISBANE
..DATE 12/12/2011
ORDER
-- 1 of 13 --
1-2 ORDER
1
10
20
30
40
50
60
HIS HONOUR: In respect of the appellant's application, having
regard to the matters set out in the appellant's written
outline of argument and also the affidavit of Christopher
Schomburgk filed 15 November 2011, I am satisfied and make
orders in those terms as set out in orders 1, 2, 3 and 4 of
the appellant's draft orders handed to me this morning.
...
HIS HONOUR: The other proceeding is concerned with an
application by the respondent council for a change of venue of
the hearing of the appeal from Brisbane to Cairns.
The parties to this appeal are Fabcot Pty Ltd, the appellant;
Cairns Regional Council, the respondent; the Chief Executive,
Department of Transport and Main Roads, the first
co-respondent by election; the Chief Executive, Department of
Local Government and Planning, the second co-respondent by
election; and the Mulgrave & District Chamber of Commerce
Incorporated, the third co-respondent by election.
The second co-respondent by election has advised that it will
abide the orders of the Court in respect of the change of
venue application.
The first co-respondent by election opposes the change of
venue application.
-- 2 of 13 --
1-3 ORDER
1
10
20
30
40
50
60
The third co-respondent by election supports the change of
venue application, and the appellant opposes the application.
The appellant has appealed the decision of the respondent to
refuse its application for a preliminary approval for a
material change of use overriding the respondent's planning
scheme. Essentially, the proposed development involves a
supermarket, together with other commercial uses, including a
service station.
The reasons for the refusal are relatively extensive, as are
the grounds of appeal. If the appeal proceeds a number of
expert witnesses are likely to be required to address issues,
including town planning, need and traffic. Other issues may
also have to be addressed by expert witnesses. Most, but not
necessarily all, of the experts are located in Brisbane or in
south-east Queensland. And if the hearing of the appeal is
transferred to Cairns, then those witnesses will be required
to travel to and from Cairns and, in some cases, accommodation
would also be required.
That is also the case in respect of most of the barristers
involved in the appeal, and the solicitors acting for the
appellant, and first and second co-respondents by election.
However, the solicitors acting for the respondent, and the
third co-respondent by election, are located in Cairns.
-- 3 of 13 --
1-4 ORDER
1
10
20
30
40
50
60
The situation concerning the parties' lawyers and experts is
set out in paragraph 36 of the council's submission, and
relevantly is, in respect of the appellant. Its head offices
are Sydney and Brisbane. Solicitors located in Brisbane;
senior and junior counsel both located in Brisbane; three of
the experts, possibly four of its experts, will be located in
Brisbane or south-east Queensland.
In respect of the respondent council, it, of course, is
located in Cairns. Its solicitors are located in Cairns.
Junior counsel is located in Cairns, but Mr Hughes SC is, of
course, located in Brisbane.
Experts have not yet been appointed by the council, but they
are likely to include a mix of locally based experts and
Brisbane or south-east Queensland based experts.
It is also pointed out that most lay witnesses would be
located either in Cairns or the nearby Gordonvale area. The
first co-respondent by election's, head office is located in
Brisbane, solicitors located in Brisbane, counsel located in
Brisbane and its one possible expert is located in Brisbane.
I should note here that the extent of the first co-
respondent's involvement in this appeal is yet to be finalised
and it may in fact be the case that it does not, in fact, call
any witnesses.
In respect of the second co-respondent by election, its head
-- 4 of 13 --
1-5 ORDER
1
10
20
30
40
50
60
office located in Brisbane, solicitors based in Brisbane but
no counsel has been retained nor an expert. It is also quite
likely that the second co-respondent will not be further
involved in the appeal.
As to the third co-respondent, it's head office is located in
Gordonvale, solicitors based in Cairns, as yet, it has not
appointed either counsel or an expert, although, it's noted
here today Mr Favell of counsel is based in Brisbane. It may
be that the third co-respondent limits its involvement in the
proceedings to submissions, but at this stage it has not made
any final decision in that regard.
The subject land is located on the corner of Draper Road and
the Bruce Highway at Gordonvale, which is a relatively small
town located approximately 22 kilometres to the south of the
Cairns CBD. The land is located within the local government
boundary of the respondent and within the jurisdictional
limits of the Cairns Planning and Environment Court.
The application has created considerable local interest. Some
137 properly made submissions and 15 not properly made
submissions have been received in response to the public
notification of the proposal.
A petition was also signed, as I understand it, by some 300
persons who oppose the development. I do not know how many,
if any, of the submitters were also signatories to that
petition.
-- 5 of 13 --
1-6 ORDER
1
10
20
30
40
50
60
The proposal has also been the subject of coverage in the
local press. The public reaction, as I understand it, to the
proposal is both positive and negative. I should mention here
that the third co-respondent who also opposes this application
represents the local business and community interest in the
Gordonvale area.
The Cairns Registry of this Court has two resident Judges with
Planning and Environment Court Commissions. By reference to
the affidavit of Ms Danielle Sibenaler filed 11 November 2011,
the 2012 calendar for the Planning and Environment Court at
Cairns, at least at 11 November 2011, had the following
sitting dates available; two weeks commencing 6 February 2012,
one week commencing 18 June, one week commencing 6 August and
one week commencing 19 November 2012. It is common ground that
this appeal would not be ready to be dealt with in the
February of 2012 sittings.
Ms Meurling, solicitor for the appellant, has given evidence
to the effect that, given the number of parties and the issues
involved, the hearing of the appeal is likely to exceed one
week including an inspection.
While it is difficult to predict accurately at this stage,
that estimate does not seem unreasonable. Mr Hughes, senior
counsel for the Council, considers that the appeal may be able
to be completed in five days but, not surprisingly, cannot be
precise at this stage.
-- 6 of 13 --
1-7 ORDER
1
10
20
30
40
50
60
Mr Trotter, junior counsel for the appellant, is also
reluctant to give a precise prediction, but considers that the
hearing is more likely to run into six or seven days. On the
material before me, I consider that there is a real risk that
the matter may extend beyond one week, which makes a hearing
in Cairns problematic, given the availability of hearing dates
in that jurisdiction.
The respondent counsel contends that the appropriate venue is
Cairns because, in circumstances where there is such
significant public interest, it would be inappropriate to
allow the appeal to proceed in Brisbane, as that would be
likely to prevent or seriously limit the extend of public
interest considerations, including the attendance at Court of
not only members of the public but also interested Council
officers.
Also, having the matter heard in Brisbane would also obviously
impact on the availability of lay witnesses to give evidence
and it may, in fact, act as a deterrent to such witnesses
being prepared to give evidence.
And it is also pointed out that to have the appeal dealt with
in Brisbane would involve the counsel and the third co-
respondent by election in considerable expense. The third -
as I said, the third co-respondent by election supports the
Council's application but it is difficult to have, in my view,
too much regard to the situation of the third co-respondent
because, at this stage, it is not able to give any meaningful
-- 7 of 13 --
1-8 ORDER
1
10
20
30
40
50
60
indication as to what level of involvement it might have in
the hearing of the appeal.
As Mr Hughes correctly pointed out, the real debate is between
the position of the Council and the appellant. Rule 17 of the
Planning and Environment Court Rules effectively provides
that, prima facie, the appeal should be heard in the place
where the originating process is filed. In this appeal, that
is Brisbane.
Rule 17 therefore places an onus on the counsel to convince
the Court that for reasons including convenience and fairness,
there are good reasons to change the venue. Reference was
made by all parties in this respect decision of Focus
Development and Construction Pty Ltd and Maroochydore Shire
Council [2008] QPELR 554.
Reference was also made to rule 45 of the Uniform Civil
Procedure Rules 1999. Everyone is familiar with the content
of that rule and I do not intend to address it in full.
Mr Hughes pointed to the following matters in support his
application. First, that the land and the local Council
representing the community is located in Cairns and in
circumstances where a developer wants to carry out major
development within a district, it should be prepared to
litigate in that district.
Second, that to have the hearing in Brisbane will involve the
-- 8 of 13 --
1-9 ORDER
1
10
20
30
40
50
60
counsel incurring considerable expenditure and, as I have
said, make it more difficult for Council officers to attend.
Third, that the Planning and Environment Court in Cairns has
two Judges with Planning and Environment Commissions and last,
and this is probably the major point made by Mr Hughes, which
is connected with the first to which I have already referred,
that the level of community interest that has been shown in
this case warrants a hearing in Cairns.
Mr Favell, counsel for the third co-respondent largely relies
on the submissions made by Mr Hughes. Mr Trotter, for the
appellant, while acknowledging it is a relevant consideration,
submits that the public interest point should not be
overstated and is not determinative. I agree with that
observation. Mr Trotter also submitted that the cost argument
favours his client's position, given the likely location of
counsel and most witnesses.
Of particular concern to Mr Trotter was that if the matter was
listed in Cairns and did not finish within five days, which he
considered it probably would not, then the parties and the
Court would be involved in a part heard case and having to
make new arrangements for the Court's calendar or otherwise
wait until the next Planning and Environment sittings in
Cairns, which is August 2012.
This would create an undesirable situation, in my view. It
would be preferable to list the appeal for hearing at a venue
-- 9 of 13 --
1-10 ORDER
1
10
20
30
40
50
60
where if the matter does run over, it can be more readily
accommodated. That venue is Brisbane.
In this application the costs and convenience considerations,
would suggest the appropriate venue is Brisbane. However, the
hearing of the appeal in Brisbane has its own costs
ramifications for the respondent and the third co-respondent
by election. And, as I have already mentioned, the public
interest considerations favour a hearing of the appeal in
Cairns.
The proposition that lay witnesses could give evidence from
Cairns by telephone does not adequately address the public
interest considerations in my view.
These competing interests or considerations, as counsel
observed, are quite finely balanced. It is well recognised
that this Court is not only concerned with commercial
interests as between parties, matters of this have wider
community ramifications and generate legitimate local concern
and interest.
In my view, considerable weight has to be given to those
matters.
On balance, I have reached the conclusion that to accommodate
the public interest issues involved but while also recognising
the more practical issues associated with this appeal the
appropriate course of action would be to have the matter heard
-- 10 of 13 --
1-11 ORDER
1
10
20
30
40
50
60
partly in Cairns but the majority of it heard in Brisbane.
If this matter is listed to commence on 4 June 2012 before me
it will be completed in the existing allocated Planning and
Environment 2012 sittings for this Court.
However, as an inspection is likely, the Court, and at least
some of the parties' legal representatives will be required in
Cairns. The estimate given by Mr Hughes for the inspection
was about half a day.
If some two days were set aside for Cairns - probably the 4th
and the 5th of June 2012 the case could be opened including
any preliminary statements other parties might want to make in
Cairns before the inspection took place the following day, any
lay witnesses and any other witnesses as agreed between the
parties could be dealt with on those days.
Accordingly, in respect of the Council's application I order
as follows;
1) The application is successful in part.
2) The appeal is to be listed before me for seven days
commencing 4 June 2012.
3) The opening of the appeal and any, preliminary statements
that any other party might want to make on the opening day
will take place in Cairns before the inspection of the
-- 11 of 13 --
1-12 ORDER
1
10
20
30
40
50
60
site.
4) The evidence of any lay witnesses or other witnesses as
agreed between the parties will be dealt with on the 4 and
5 June 2012 in Cairns or as otherwise ordered by the Court.
5) The balance of the appeal is to be heard in Brisbane.
6) The matter is to be listed for review before me at 9.30, 22
February 2012 at Brisbane.
Just finally, I should mention that a suite of other orders
were contended for by Council and the appellant. Many of
those orders are not contentious, save as to dates. However,
the orders contended for by the appellant are more extensive
including providing for the exchange of expert reports.
The orders proposed by Mr Trotter effectively took the matter
up to hearing. I think all counsel really acknowledge at this
stage that this appeal is still at a very early stage and as
yet the first and third co-respondents by election do not know
what level of involvement, if any, they might have in the
future conduct of the appeal.
On balance I do not consider it appropriate to make orders
going beyond the completion of the disclosure process which is
effectively at or about - takes it up to order 16 of the
appellant's draft or order. Just beyond order 15 I think of
your draft, Mr Hughes. Whether there is still some debate
-- 12 of 13 --
1-13 ORDER
1
10
20
30
40
50
60
about the date I will not make any final directions at this
stage but indicate that the orders that I intend to make are
in the form of the respective drafts up to and including
completion of the disclosure process.
And as I mentioned the matter will be otherwise mentioned
before on 22 February 2012.
Hopefully the parties will be able to agree about dates and if
that is the case an email setting out the orders as agreed, as
long as it is made clear that all the parties are in agreement
there will be no need for any further attendance at the Court.
I will simply make the orders as per the draft.
If the matter needs to be agitated further I will be available
on short notice.
...
-----
-- 13 of 13 --