Berry & Anor v Gold Coast City Council [2011] QLC 53 (2011) 32 QLCR 251
LAND COURT OF QUEENSLAND
CITATION: Berry & Anor v Gold Coast City Council [2011] QLC 53
PARTIES: Colleen Patricia Berry and Francis John Sheehan (as
Trustees)
(applicants/respondents)
v.
Gold Coast City Council
(respondent/applicant)
FILE NO: AQL036-11
DIVISION: General Division
PROCEEDING: Application
DELIVERED ON: 22 August 2011
DELIVERED AT: Brisbane
HEARD AT: Brisbane
PRESIDENT: CAC MacDonald
ORDER: The application for a partial joint hearing is refused.
CATCHWORDS: Practice and procedure – partial joint hearing – s.79 Uniform
Civil Procedure Rules 1999 – discretion to order joint
hearing – guidelines considered – application refused.
APPEARANCES: Mr E Morzone of Counsel for the applicants/respondents
Mr B Cronin of Counsel for the respondent/applicant
Mr D Gore QC, by leave, for Halcyon Waters Community
Pty Ltd
SOLICITORS: Collas Moro Ross for the applicants/respondents
Gall Standfield Smith for the respondent/applicant
Anderssens Lawyers Pty Ltd for Halcyon Waters
Community Pty Ltd
[1] The principal proceeding in this matter is a claim for compensation brought by Colleen
Patricia Berry and Francis John Sheehan (as Trustees) against the Gold Coast City
-- 1 of 8 --
2
Council (the Berry & Sheehan proceedings) in respect of the compulsory acquisition of
land under the provisions of the Acquisition of Land Act 1967 (the Act).
[2] In addition to the Berry & Sheehan proceedings a claim for compensation has been filed
in this Court by Halcyon Waters Community Pty Ltd against the Chief Executive, Gold
Coast City Council (AQL359-09, the Halcyon proceedings) in respect of the compulsory
acquisition of land adjoining the Berry & Sheehan land.
[3] This decision deals with a general application filed by the Gold Coast City Council (the
Council) on 25 March 2011 for an order that the Berry & Sheehan and Halcyon
proceedings be heard together.
The Berry & Sheehan proceedings
[4] The Berry & Sheehan land was taken by the Gold Coast City Council for park, recreation
ground and road purposes on 24 April 2008. The land taken was the whole of Lot 131 on
SP 192584 in the Parish of Coomera, County of Ward, containing an area of 1.713 ha.
[5] The claim for compensation was filed in this Court on 9 February 2011. The claimants
have asserted that, as at the date of resumption, the highest and best use of their land was
for residential development. As the land was subject to partial flooding, the claimant
identified the minimum developable area of the land as 5,900 m² and, on the basis that a
subdivision of that area of land would yield 28.6 unit dwelling sites which the claimant
valued at $87,000 per site, sought compensation for loss of land in the sum of
$2,490,000.00, together with compensation for disturbance, and interest.
[6] The Council has paid an advance of $800,000 to Berry & Sheehan. It appears that that
advance was calculated on the basis of a report prepared by Cardno Lawson Treloar
(CLT) for the Gold Coast City Council on the flooding characteristics of Lot 131.1 That
report determined that .16 ha of the site could have been filled in a site only filling
scenario, and that .05 ha could be filled in an equitable filling scenario.
[7] Prior to the resumption, Lot 131 was adjoined on its western boundary by Lot 11 on SP
204098 which was 19.11 ha in area. Lot 11 was owned by Halcyon Waters Community
Pty Ltd. The northern part of Lot 11, 4.35 ha, was resumed on 24 April 2008 in the same
taking of land notice and for the same purposes as Lot 131. The resumed land became
Lot 101 on SP 214275.
[8] At the time of the resumption of Lot 101, an approval existed for the development of
Stage Two of the Halcyon retirement development on that land, incorporating a
retirement community, a shop (chemist) and doctor's room. The approval allowed the
filling of 1.3 ha on Lot 101 but conditions 34 and 35 of the approval required
1 Exhibit DRS2 to the affidavit of DR Standfield filed 29 March 2011.
-- 2 of 8 --
3
certification from a qualified registered hydraulic engineer, prior to commencement of
works on site, to support an operational works (change to ground level) application.
There is evidence that modelling indicates that such fill would alter the existing water
flow patterns on Lot 131 by concentrating the flow entering Lot 131 from the west, to the
northern section of the lot, rather than it being more evenly distributed across the western
boundary.2
[9] Mr N Collins, the hydraulic expert commissioned to provide an expert report for Berry &
Sheehan has challenged the correctness of the hydraulic assessment undertaken by
Lawson and Treloar with respect to Lot 101 which was the basis of the development
approval for the material change of use approval. Mr Collins said that a review of the
CLT assessment revealed that the modelling had assumed that the 1.3 ha fill was in place
and that there was no main roads upgrade. This did not reflect Council's planning as
ultimately adopted. Based on Council's ultimate development outcome for the area and
the further modelling undertaken by his company, Mr Collins concluded that "it is our
opinion that our client was disadvantaged by the CLT July 2007 assessment and that a
more accurate assessment incorporating the removal of the 1.3 ha fill area and inclusion
of the proposed main roads and Halcyon Way upgrades to ARI 100 year immunity,
would have produced a more favourable outcome for our client in terms of
compensation".
[10] Both Mr Collins and Dr M Jempson, the expert commissioned by the Council, have said
in their joint report prepared for the Berry & Sheehan proceedings that the certification
required by conditions 34 and 35 of the Stage 2 approval of the Halcyon Waters
development would not have been achieved. They say that if the Halcyon land were not
filled in accordance with the development approval, Lot 131 would be advantaged in that
the land could be more extensively developed. Mr Collins says that 5,900 m² of the land
would be developable, Dr Jempson asserts a lesser area, in the vicinity of 4,100 m².
The Halcyon proceedings
[11] As noted above, Halcyon Waters Community Pty Ltd were the owners of Lot 101 prior
to its resumption by the respondent on 24 April 2008. Halcyon filed a claim for
compensation in this Court on 11 August 2009 in the sum of $16,060,000 plus
disturbance and interest. in respect of the resumption of Lot 101. This proceeding is well
advanced such that the parties will be in a position for the matter to be heard either before
the end of this year or early in 2012.
2 Joint hydraulic report form N Collins and M Jempson, Exhibit WJR2 to the affidavit of WJ Ross filed 15 July
2011.
-- 3 of 8 --
4
[12] In contrast to the Berry & Sheehan proceedings, the parties in the Halcyon proceedings
are not agreed that the certification contemplated by conditions 34 and 35 of the Halcyon
Waters Stage 2 approval of 16 February 2007, may not have been achieved. Halcyon's
expert (Dr Johnson) contends that he would have been able to provide the certification
required by conditions 34 and 35 whereas, consistently with his opinion in the Berry &
Sheehan proceeding, Dr Jempson for the Council expresses a contrary view. Further,
Halcyon says that there is another issue, namely, whether in view of the long history of
approvals relating to the Halcyon development, a competent hydraulic engineer would
have advised a hypothetical purchaser that it was not necessary to carry out any further
computer modelling.
The application
[13] The application for a joint hearing was filed in the Berry & Sheehan proceedings and
leave was given for Halcyon Waters Community Pty Ltd to appear and be heard in
respect of the application. It was made clear by Mr Cronin of counsel for the Gold Coast
City Council at the hearing of the application that the Council sought a partial joint
hearing only, to be limited to a hearing of the hydraulic evidence in both cases, on the
basis that the hydraulic evidence in each case be treated as the hydraulic evidence in the
other.
[14] The principal basis on which the order for a partial joint hearing was sought was that it
would be unfair for the Council to be faced with the possibility of different findings as to
whether Halcyon would have obtained the required certification under conditions 34 and
35 of the development approval and consequently have been in a position to fill 1.3 ha of
the site. If there were a finding in the Berry & Sheehan proceedings that the 1.3 ha of fill
on the Halcyon land could not progress, a larger area of the Berry & Sheehan land could
be developed and the result in those proceedings could be a higher valuation of
$1,690,000. On the other hand, if there were a different finding in the Halcyon
proceedings, namely that the 1.3 ha could be filled, the valuation of the Halcyon land
could be $5,500,000 higher.
[15] Mr Cronin said that the hydraulic evidence would be given by three experts if heard
together, that is a hydraulic expert for each claimant with Dr Jempson giving evidence
for the Council. Mr Cronin submitted that the time and cost difference between the two
hearings was not particularly significant. However different findings of fact could result
in very substantial differences in awards for compensation. It was undesirable that
inconsistent findings of fact should be made and the way that this could be avoided was
to hold a joint hearing in relation to the hydraulic evidence.
-- 4 of 8 --
5
[16] The application has been strenuously resisted by Berry & Sheehan and Halcyon.
Consideration of the issues
[17] This application was brought under s.79 of the Uniform Civil Procedure Rules 1999
which, by virtue of s.4(1) of the Land Court Rules 2000 applies to proceedings in this
Court. Section 79 provides -
"79 Sequence of hearings
The court may order that 2 or more proceedings be heard together or in a
particular sequence."
[18] As s.79 does not say anything about the matters which the Court is to take into account in
deciding whether to make an order under the section, it appears that the Court has an
unfettered discretion as to whether to make such an order.
[19] The authorities indicate that a number of factors have been considered relevant in
exercising such a discretion. There are no inflexible rules.3 In Cameron v McBain4
Herring CJ said that -
"The question would seem to be whether in all the circumstances it is
convenient that the actions be consolidated, and in deciding whether it is
convenient, regard may be had to such matters as the desirability of
avoiding multiplicity of actions, and the saving of time and expense. At
the same time the interests of the parties should not be prejudiced by the
making of an order."5
[20] In Bishop v Bridgeland Securities6, Wilcox J set out the principles which he considered
should guide the exercise of such a discretion. He said that the basic principle to be
applied is that the Court should take whatever course seems to be most conducive to a
just resolution of the dispute between the parties, having regard to the desirability of
limiting, as far as practicable, the cost and delay of litigation.
[21] In Ghose v CX Reinsurance Co Ltd7 Austin J said that the task of the Court is to "work
out pragmatically whether the most efficient course consistent with the requirements of
fairness would be consolidation, a joint hearing, sequential hearing, entirely separate
hearings or something else (such as determination of separate questions prior to or after
the hearing of the remainder of the proceedings)".
[22] In Humphries v Newport Quays Stage 2A Pty Ltd8 Besanko J stated that the relevant
factors in deciding whether actions should be tried together are -
3 See Cousins v Cousins (1948) 51 WALR 57 at 60.
4 [1948] VLR 245 at 247.
5 Although Herring CJ was discussing consolidation, it appears that the same principles apply when the application
is for a joint hearing (Ghose v CX Reinsurance Co Ltd [2010] NSWSC 110 at [27]).
6 Bishop v Bridgeland Securities (1990) 25 FCR 311 at 314.
7 [2010] NSWSC 110 at [27].
8 (2009) FCA 699 at [11].
-- 5 of 8 --
6
"1. Are the proceedings broadly of a similar nature?
2. Are there issues of fact and law common to each proceeding?
3. Will witnesses (lay and expert) in one proceeding be witnesses in one or
more of the other proceedings?
4. Has there been an alternative proposal put forward that there be a test case
and have the parties agreed to abide the outcome, or, at least, the
determination of common issues of fact and law?
5. Is there a prospect of multiple appeals with substantial delays if the
proceedings are not tried at the same time?
6. Will there be a substantial saving of time if the proceedings are tried at the
same time compared with each proceeding being tried separately?
7. Will an order that the proceedings be tried at the same time create
difficulties in terms of trial management, complexity of procedural issues
and difficulties of determining cross-admissibility of evidence?
8. Is one proceeding further advanced in terms of preparation for trial than the
others?
9. Are there parties to one or some only of the proceedings who will be
inconvenienced if all of the proceedings are tried at the same time?"
[23] It can be seen from the extracts from the authorities set out above, that it is necessary to
balance all the relevant factors in deciding whether to order a joint hearing. The Council
has asserted that it would be fundamentally unjust if there were different findings of fact
in relation to the hydraulic issues in each of the cases. Strictly speaking, it is not the
function of this Court to determine whether in fact the 1.3 ha of Halcyon land could be
filled. In both proceedings the Court has to decide the market value of the resumed land
as at the date of resumption by deciding what the hypothetical prudent purchaser would
pay for the land, on the basis that such a purchaser was aware of all the facts that would
affect its value.9 As is common in cases of this nature, the claimants have commissioned
experts to provide their opinions as to various issues relevant to the determination of
value and have submitted that that information would have been available to the
hypothetical prudent purchaser on the date of resumption.
[24] In the Berry & Sheehan proceedings, the expert hydraulic engineers have agreed that
Halcyon would not be able to fill the 1.3 ha because no hydraulic engineer would provide
the certification required by conditions 34 and 35. There is therefore no live issue
between the parties in that proceeding as to whether the 1.3 ha could be filled. If the
hydraulic evidence in both proceedings were heard together as proposed by the Council,
Halcyon's evidence as to its capacity to comply with conditions 34 and 35 would become
9 Spencer v The Commonwealth (1907) 5 CLR 418 at 440, 441 (Isaacs J).
-- 6 of 8 --
7
evidence in the Berry & Sheehan proceedings and thus create an issue in those
proceedings that would not otherwise arise. The consequence may be that the
compensation payable to Berry & Sheehan may be $1,690,000 lower than if that issue
had not been raised.
[25] It is also the case that Berry & Sheehan and Halcyon have the right to bring two separate
claims. Each claim arises out of a separate event, namely the acquisition of two separate
parcels of land. The claimants in each proceeding have a substantive right to recover
compensation for the value of the land taken. The respondent has a substantive
correlative contingent liability in the same amount. In those circumstances, to make a
procedural order which would lessen the potential value of the Barry & Sheehan
claimants' substantive rights and lessen the respondent's correlative substantive
contingent liabilities would work a radical reordering of the parties' substantive rights
and obligations, with the risk of substantial prejudice to those claimants.10
[26] Further, I consider that it is relevant to take into account the fact that compulsory
acquisition proceedings differ from ordinary litigation in that the claimants in
compulsory acquisition proceedings have no choice whether to make a claim or not.11 In
those circumstances it would seem unfair to force claimants such as Berry & Sheehan
into a joint hearing where they would face, potentially, a substantially lower
compensation determination.
[27] Berry & Sheehan would also become involved, unwillingly, in proceedings which are
significantly more complex than if their claim were heard separately. The applicant in
the Halcyon proceedings claims compensation of some $16,000,000 for the loss of land.
Those proceedings are complex and it is estimated will involve a two week trial with as
many as eleven expert witnesses giving evidence. By contrast, the claim in the Berry &
Sheehan proceedings is for approximately $2,500,000; the central issue is the maximum
developable area of the land as at the date of acquisition and it is estimated the trial will
be a two day trial. While the order sought by the Council is limited to a joint hearing of
the hydraulic evidence, the claimants in the Berry & Sheehan proceedings will be
involved in additional expense as their legal advisers and hydraulic engineer will be
required to undertake significant additional work in order to meet the evidence in the
Halcyon proceedings as to the ability to fill the 1.3 ha of land.
10 See Buckley v The Herald and Weekly Times Pty Ltd [2009] VSCA 118 at [12].
11 See Yalgan Investments Pty Ltd v Council of the Shire of Albert (1997) 17 QLCR 401 at 407; Minister for the
Environment v Florence (1980-81) 45 LGERA 127 at 149; Banno v Commonwealth of Australia (1993) 81
LGERA34 at 35.
-- 7 of 8 --
8
[28] It is also relevant that the claimants in each proceeding have a right of appeal from any
determination of compensation following the hearings. If a determination were made in
respect of the jointly heard hydraulic evidence that the Halcyon land could not be filled,
the claimants in the Berry & Sheehan proceedings would possibly be faced with an
adverse finding in an appeal in the Halcyon proceedings in respect of a matter which
would not have been an issue if the Berry & Sheehan claim had been heard separately.
[29] It is acknowledged that it is undesirable that there should be inconsistent findings of fact
in separate proceedings. However, while that is a factor to be taken into account in
exercising the discretion given under s.79, it is not a determinative factor.12 In my
opinion, the factors pointing to a refusal of a joint hearing as set out above significantly
outweigh those in favour of such a hearing. I consider that the material prejudice that
would be suffered by Berry & Sheehan if a partial joint hearing were ordered is such that
the application should be refused.
ORDER
The application for a partial joint hearing is refused.
CAC MacDONALD
PRESIDENT OF THE LAND COURT
12 Ghose v CX Reinsurance Co Ltd [2010] NSWSC 110 at [95].
-- 8 of 8 --
Official source: https://www.sclqld.org.au/caselaw/QLC/2011/053