De Neefe Signs Pty Ltd v Build1 (Qld) Pty Ltd; Traffic Technologies Traffic Hire Pty Ltd v Build1 (Qld) Pty Ltd [2010] QSC 279
SUPREME COURT OF QUEENSLAND
CITATION: De Neefe Signs Pty Ltd v Build1 (Qld) Pty Ltd; Traffic
Technologies Traffic Hire Pty Ltd v Build1 (Qld) Pty Ltd
[2010] QSC 279
PARTIES: DE NEEFE SIGNS PTY LTD ACN 115 924 939
(applicant)
v
BUILD1 (QLD) PTY LTD ACN 110 000 130
(respondent)
TRAFFIC TECHNOLOGIES TRAFFIC HIRE PTY
LTD ACN 116 510 000
(applicant)
v
BUILD1 (QLD) PTY LTD ACN 110 000 130
(respondent)
FILE NO/S: BS 5714 of 2010
BS 5716 of 2010
DIVISION: Trial
PROCEEDING: Application
ORIGINATING
COURT:
Supreme Court at Brisbane
DELIVERED ON: 10 September 2010
DELIVERED AT: Brisbane
HEARING DATE: 23 June 2010
JUDGE: Fryberg J
ORDERS: In each matter:
1. Application dismissed.
2. Discharge the interlocutory injunction ordered by this
Court on 3 June 2010.
3. The applicant pay the respondent’s costs to be
assessed.
CATCHWORDS: Contracts – Building, engineering and related contracts –
Remuneration – Statutory regulation of entitlement to and
recovery of progress payments – Adjudication of payment
claims – Validity of adjudication application and decision –
Validity of payment claim
-- 1 of 18 --
2
Contracts – Building, engineering and related contracts –
Remuneration – Statutory regulation of entitlement to and
recovery of progress payments – Payment claims – What
constitutes valid payment claim – Building and Construction
Industry Payments Act 2004 (Qld), s 17
Procedure – Courts and judges generally – Courts – Attempt
to oust jurisdiction of court – By statute – Implied ouster –
Exclusivity of jurisdiction of statutory adjudicator
Statutes – Acts of Parliament – Interpretation – Particular
words and phrases – Generally – “structure” – Queensland
Building Services Authority Act 1991 (Qld) and Queensland
Building Services Authority Regulation 2003 (Qld), s 5
Building and Construction Industry Payments Act 2004
(Qld), s 12, s 15, s 16, s 17, s 21, s 25, s 26, sch 2
Judicial Review Act 1991 (Qld), pt 3, pt 5, s 18(2)(b), s 41(1),
sch 1 pt 2
Queensland Building Services Authority Act 1991 (Qld),
s 67AAA, s 67U, s 67W
Queensland Building Services Authority Regulation 2003
(Qld), s 5
Bezzina Developers Pty Ltd v Deemah Stone (Qld) Pty Ltd
[2008] 2 Qd R 495; [2008] QCA 213, cited
Bloomer Constructions (Qld) Pty Ltd v O’Sullivan [2009]
QSC 220, cited
Brodyn Pty Ltd t/as Time Cost and Quality v Davenport
(2004) 61 NSWLR 421; [2004] NSWCA 394, considered
Coordinated Construction Co Pty Ltd v Climatech
(Canberra) Pty Ltd [2005] NSWCA 229, cited
Coordinated Construction Co Pty Ltd v JM Hargreaves
(NSW) Pty Ltd (2005) 63 NSWLR 385; [2005] NSWCA 228,
cited
Downer Construction (Australia) Pty Ltd v Energy Australia
(2007) 69 NSWLR 72; [2007] NSWCA 49, cited
F K Gardner & Sons Pty Ltd v Dimin Pty Ltd [2007] 1 Qd R
10; [2006] QSC 243, cited
Gisley Investments Pty Ltd v Williams [2010] QSC 178, cited
Grocon Constructors v Planit Cocciardi Joint Venture
(No. 2) [2009] VSC 426, compared
Hansen Yuncken Pty Ltd v Ian James Ericson trading as
Flea’s Concreting [2010] QSC 156, compared
Hickory Developments Pty Ltd v Schiavello (Vic) Pty Ltd
[2009] VSC 156, cited
Intero Hospitality Projects Pty Ltd v Empire Interior
(Australia) Pty Ltd [2008] QCA 83, cited
Jemzone Pty Ltd v Trytan Pty Ltd (2002) 42 ACSR 42;
-- 2 of 18 --
3
[2002] NSWSC 395, cited
Kell & Rigby Pty Ltd v Guardian International Properties
Pty Ltd [2007] NSWSC 554, cited
Kirk v Industrial Court of New South Wales (2010) 239 CLR
531; [2010] HCA 1, cited
Liversidge v Anderson [1942] AC 206; [1941] 3 All ER 338,
cited
Nebmas Pty Ltd v Sub Divide Pty Ltd [2009] QSC 92, cited
Nepean Engineering Pty Ltd v Total Process Services Pty Ltd
(In Liq) (2005) 64 NSWLR 462; [2005] NSWCA 409, cited
Neumann Contractors Pty Ltd v Peet Beachton Syndicate Ltd
[2009] QSC 376, cited
Perform (NSW) Pty Ltd v MEV-AUS Pty Ltd [2009] NSWCA
157, cited
Walter Construction Group Ltd v CPL (Surry Hills) Pty Ltd
[2003] NSWSC 266, cited
Walton Construction (Qld) Pty Ltd v Salce [2008] QSC 235,
cited
COUNSEL: In each matter, P Dunning SC with D D Keane for the
applicant
In each matter, D Savage SC with I Erskine for the
respondent
SOLICITORS: In each matter, McCullough Robertson acting as Town Agent
for Middletons, for the applicant
In each matter, Carl Blumen Solicitors for the respondent
[1] FRYBERG J: Each of the applicants in the two originating applications before me
is a subsidiary of the same holding company, and is a manufacturer of signage
products. Each is a subcontractor engaged in relation to the construction of
roadworks. Each engaged the respondent, Build1, a builder, as a subcontractor, in
one case pursuant to two separate subcontracts and in the other pursuant to five
separate subcontracts. The terms of the subcontracts were not materially different.
Build1 made claims against each applicant for its work. The issues which arise on
those claims are identical in each application. The parties agreed that I hear the
applications together and that the outcome on one contract would determine the
outcome on the others.
Facts giving rise to the applications
[2] I shall take the facts from the first subcontract included in application 5714/10, the
application of De Neefe Signs Pty Ltd. This, like the other De Neefe subcontract
and two of the Traffic Technologies Traffic Hire Pty Ltd subcontracts, related to the
North-South Bypass Tunnel.
-- 3 of 18 --
4
[3] The various subcontracts required Build1 to install permanent directional signs
including gantries in various zones of the project and elsewhere.1 Payment terms
set out in cl 4 of the contract for zone three, made on 5 June 2009, are typical:
“4. Payment Terms
4.1 Payment will be made to the Sub Contractor within 45
days of the end of the month in which the Tax Invoice is
submitted and approved.
4.2 Tax invoices are to be submitted by 22nd of each month.
Tax Invoices received after this date will be processed in
the following month.”
[4] On 22 March 2010 Build1 delivered a document entitled “Payment Claim” to De
Neefe. It covered the period up to 19 March 2010. At the bottom it was endorsed,
“This Payment Claim is made under the Building and Construction Industry
Payments Act 2004 Qld”. De Neefe did not issue a payment schedule in response.
On 12 April Build1 delivered a document entitled “Notice under section 21(2) of
the Building and Construction Industry Payments Act 2004 (Queensland)”. That
notice asserted that De Neefe had failed to provide a payment schedule within the
time allowed and had therefore become liable to pay the whole amount of the claim
on the due date. It asserted that the whole amount had not been paid. It advised that
Build1 had elected to apply for adjudication of the claim; that De Neefe had five
business days in which to serve a payment schedule or pay the claim in full; and that
if it failed to pay the whole amount Build1 would proceed to adjudication.
[5] De Neefe responded to that document in a letter from its solicitors to the solicitor
for Build1. It asserted that the document was not a valid notice under s 21(2) of the
Building and Construction Industry Payments Act 2004 (Qld) (“the Act”) because it
was premature: the Act required a notice to be given within 20 business days
immediately following the due date for payment, and under cl 4.1 of the contract,
that date was after 12 April 2010. In the alternative it asserted that the notice was
invalid because it referred to the amended payment claim, not that dated 22 March.
[6] Build1 applied for adjudication under the Act on 30 April 2010. An adjudicator,
Mr Pettersson, was duly nominated and on 12 May De Neefe gave him a document
purporting to be an adjudication response under the Act. Both parties subsequently
delivered unsolicited submissions to the adjudicator. He decided the application on
26 May. He held (among other things) that the payment claim was issued in
accordance with the requirements of the contract and that Build1’s notice under
s 21(2) was valid; and he allowed the full sum claimed.
De Neefe’s submissions
[7] De Neefe now seeks declarations that the payment claim was not valid and that the
adjudication based on it was void (ie a nullity) and an injunction preventing Build1
from relying on the adjudication for any purpose. It submitted that there were two
foundations for this relief: the claim was delivered before the due date for payment;
1 The North-South Bypass Tunnel (four subcontracts), the Mudgeeraba Interchange Exit 79, the Hale
Street Link and the Bribie Island Interchange.
-- 4 of 18 --
5
and the alleged s 21(2) notice of 12 April was not given within the period specified
for it under that section.2
[8] The submission was somewhat elliptical. Expressed sequentially, the argument as I
understand it was this. The power conferred on an adjudicator under ss 25 and 26
of the Act is to decide an adjudication application. If an adjudication application is
not a valid adjudication application, the statutory power to decide under those
sections is not engaged and the decision is a nullity. The adjudication application in
the present case was not valid for two reasons.
[9] The first reason was this. Under s 21 an adjudication application must seek
adjudication of a payment claim within the meaning of the Act. The adjudication
application in this case did not do that because an essential precondition to the
existence of a valid application was the existence of a valid payment claim; or,
putting it another way, the application was not an adjudication application within
the meaning of the Act because there was no valid payment claim giving rise to it.
The purported payment claim here was not valid because an essential precondition
to the existence of a valid payment claim was unsatisfied; or, putting it another way,
the claim was not one within the meaning of the Act. Under sch 2 of the Act,
“payment claim” means a claim referred to in s 17. The purported claim in the
present case was not one referred to in s 17 for two reasons:
a. Section 17(2)(b) requires a claim to state the amount of the progress
payment that the claimant claims to be “payable” (which it calls “the
claimed amount”). “Payable” in this context means due and payable.
Section 15 prescribes the due date for payment and in this case the due date
had not arrived; so nothing could lawfully be claimed to be payable under
s 17(2)(b).
b. Section 17(4) requires a claim to be served within the later of two stated
periods, and this was not done.
Alternatively expressed, by reason of those matters an essential precondition for the
existence of a valid claim was unfulfilled.
[10] The second reason was this. The only right to make an adjudication application is
in accordance with s 21 of the Act. It is conceded in these proceedings that
s 21(1)(a) does not apply because no payment schedule was ever served. The case
falls under s 21(1)(b), which means that an adjudication application is prohibited
under s 21(2) unless the terms of that subsection are complied with. Paragraph (a)
of that subsection obliges the claimant to give the statutory notice within 20
business days immediately following the due date for payment. The due date for
payment is determined by s 15. Section 15(1)(a) applied to the case because the
contract contained a provision, cl 4.1, that was not void under s 16 nor under the
Queensland Building Services Authority Act 1991 (Qld) (“QBSAA”), ss 67U or
67W; and it made the amount payable on the day on which it became payable under
that clause. That day was 45 days after 31 March 2010, so the adjudication
application was made before the statutory period of 20 business days commenced to
run. Consequently it was prohibited by s 21(2). An adjudication decision founded
upon it was therefore void.
2 In the interests of readability I have set out the relevant sections in an annexure to these reasons for
judgment instead of in the body of the text.
-- 5 of 18 --
6
[11] Build1 raised a preliminary argument that this Court had no jurisdiction to
determine the validity of a payment claim, arguing that the scheme of the legislation
is to commit that issue to the determination of the adjudicator. I ruled against that
submission on the basis that the jurisdiction of this Court to supervise statutory
offices and tribunals has not been ousted by the Act. It is most unlikely that the
legislature would have intended that adjudicators should be able conclusively to
define the scope of their own jurisdiction. Indeed any attempt by the legislature to
oust the supervisory jurisdiction of this Court might encounter constitutional
difficulties.3
[12] Build1 also submitted that the Court lacked jurisdiction because decisions by
adjudicators had been excluded from the scope of the Judicial Review Act 1991
(Qld).4 It relied on a number of New South Wales cases in support of the
submission that, even if the exclusion was limited to pt 3 of that Act, relief in the
nature of a prerogative writ under pt 5 was not available. De Neefe avoided that
argument by disclaiming reliance on any part of the Judicial Review Act. Its
application is simply for declarations and an injunction. It is entitled to proceed in
this manner:
“52 However, it is plain in my opinion that for a document
purporting to be an adjudicator’s determination to have the
strong legal effect provided by the Act, it must satisfy
whatever are the conditions laid down by the Act as essential
for there to be such a determination. If it does not, the
purported determination will not in truth be an adjudicator’s
determination within the meaning of the Act: it will be void
and not merely voidable. A court of competent jurisdiction
could in those circumstances grant relief by way of
declaration or injunction, without the need to quash the
determination by means of an order the nature of certiorari.”5
I ruled that the Court had jurisdiction and heard the application.
[13] It is unnecessary to consider in any detail the competing dicta expressed in the
Court of Appeal by Chesterman J6 and Fraser JA7 respectively on the question of
whether adjudications are reviewable under pt 5 of the Judicial Review Act.8 I note
however that if the latter view is correct, it follows that s 41(1) of the Judicial
3 Kirk v Industrial Court of New South Wales (2010) 239 CLR 531; and cf Grocon Constructors v
Planit Cocciardi Joint Venture (No. 2) [2009] VSC 426; Hansen Yuncken Pty Ltd v Ian James Ericson
trading as Flea’s Concreting [2010] QSC 156.
4 Section 18(2)(b) and sch 1 pt 2.
5 Brodyn Pty Ltd t/as Time Cost and Quality v Davenport (2004) 61 NSWLR 421 at p 441; see also
Walton Construction (Qld) Pty Ltd v Salce [2008] QSC 235. Neither party challenged the
correctness of Brodyn in this case, although I acknowledge that it has been the subject of a good deal
of discussion in other states: Coordinated Construction Co Pty Ltd v JM Hargreaves (NSW) Pty Ltd
(2005) 63 NSWLR 385; Nepean Engineering Pty Ltd v Total Process Services Pty Ltd (In Liq)
(2005) 64 NSWLR 462; Downer Construction (Australia) Pty Ltd v Energy Australia (2007) 69
NSWLR 72 at pp 97-8; Perform (NSW) Pty Ltd v MEV-AUS Pty Ltd [2009] NSWCA 157; Hickory
Developments Pty Ltd v Schiavello (Vic) Pty Ltd [2009] VSC 156.
6 Intero Hospitality Projects Pty Ltd v Empire Interior (Australia) Pty Ltd [2008] QCA 83.
7 Bezzina Developers Pty Ltd v Deemah Stone (Qld) Pty Ltd [2008] 2 Qd R 495.
8 See also Bloomer Constructions (Qld) Pty Ltd v O’Sullivan [2009] QSC 220 and the cases there
cited.
-- 6 of 18 --
7
Review Act has no application to adjudication decisions. Consequently there would
be no obstacle to an application for a writ of mandamus, prohibition or certiorari.
Perhaps a trial judge confronted with an application for an order nisi for certiorari
should follow the old practice and give directions for it to be returnable before the
court en banc, ie the Court of Appeal.
[14] De Neefe submitted that the statutory regime demanded strict compliance with the
requirements of the Act.9 I proceed on the assumption that this submission is
correct.
Validity of the payment claim: the claimed amount
[15] A number of questions arise in relation to this aspect of De Neefe’s submissions. It
is unnecessary to answer all of them.
The meaning of “payable”
[16] I am not persuaded that “payable” in s 17 means “due and payable”. Such a
construction would make little sense. It would mean that a claim could not be
lodged, at least in ordinary cases, until after the date for payment of the amount in
the claim had passed. I note that Parliament used “payable” in place of “due”, the
term used in the New South Wales analogue. On the alternative construction it
would be immaterial that the due date for payment had not arrived when the
payment claim was made; the claim would set out the amount payable. However I
note that this construction would not apply to “payable” in s 15.10 It is unnecessary
to reach a final decision on this point.
“Claims to be payable”
[17] Build1 submitted that the requirement under s 17(2)(b) for a valid payment claim
was that it state the amount which Build1 claimed to be payable; it was not
necessary to show the correctness of the claim as a jurisdictional fact/precondition
to validity/essential element of a claim. It argued that it was for the adjudicator to
determine the correctness of the amount of the claim if the amount remained
unpaid.11
[18] In my judgment that construction of s 17(2)(b) is correct. It is not a requirement of
s 17 that the payment claim correctly state the amount payable. It is sufficient to
state the amount which the claimant claims to be payable. That is consistent with
the obligation of an adjudicator under the Act: he is to decide the amount to be paid
to the claimant, considering the provisions of the QBSAA.12 I find that the payment
claim complied with the requirements of s 17(2).
9 F K Gardner & Sons Pty Ltd v Dimin Pty Ltd [2007] 1 Qd R 10; Walter Construction Group Ltd v
CPL (Surry Hills) Pty Ltd [2003] NSWSC 266; Jemzone Pty Ltd v Trytan Pty Ltd [2002] NSWSC
395.
10 And contrast the language of s 12: “From each reference date … a person is entitled to a progress
payment …” (emphasis added).
11 Section 26(1)(a).
12 Section 26(2)(a).
-- 7 of 18 --
8
Other issue
[19] Build1 also submitted that even if “payable” meant “due and payable”, the amount
in the payment claim was due and payable on the date of the claim. It argued that
the payment became due 10 business days after the payment claim was made under
s 15(1)(b) of the Act. De Neefe submitted that this argument was wrong, relying on
cl 4.1 of the contract. It submitted that this was a provision about when a progress
payment becomes payable and that the case fell under s 15(1)(a) of the Act. Build1
submitted that cl 4.1 was void under s 67W of the QBSAA, with the consequence
that the case fell under s 15(1)(b). On the facts, 10 business days had elapsed, so
payment was due.
[20] Having regard to my earlier finding, it is unnecessary to determine the validity of
cl 4.1 at this point.13
Validity of the payment claim: service of the claim
[21] De Neefe submitted (perhaps somewhat faintly) that the payment claim was not
valid because it had not been served within the period specified in s 17(4)(a) of the
Act. That argument raises (among other things) the question of whether cl 4.2
provides for the working out of a period for service of a payment claim. At first
glance the terms of the clause are not apt to achieve that result. The requirements
for a valid tax invoice are set out in ss 29-70 and 48-57 of the A New Tax System
(Goods and Services Tax) Act 1999 (Cth). They are quite different from those for a
payment claim under the Act. A subcontractor might choose to satisfy the
requirements of both Acts in the one document, but is under no obligation to do so.
It also raises the question why the time for service should be calculated under para
(a) of s 17(4) rather than under para (b). The subsection provides that the claim may
be served only within the later of the two periods specified. In the circumstances of
the present case, the period under para (b) would finish after that under para (a). It
would be necessary to consider whether “later” is to be measured by the end of the
period rather than by the commencement of it and if the latter, to examine the facts
to ascertain when each period commenced. These issues were not addressed in
argument.
[22] It is unnecessary to decide those questions because in my judgment, even if the
claim was not served in accordance with s 17(4), it did not cease to be one “referred
to in section 17” merely because of that non-compliance. On the contrary, that
subsection presupposes the existence of a payment claim and provides for its
service. That is not to say that a claimant may ignore the subsection. The
consequences of doing so are not presently material. What matters is that
compliance is not a condition precedent to the existence of, nor an essential element
of a valid payment claim.14
[23] It follows that the payment claim was valid and the first declaration sought should
be refused. Also, the adjudication decision cannot be impugned on the basis of
invalidity of the payment claim.15
13 It is considered in a different context below, paras [27] ff.
14 Compare the decision of Douglas J in relation to the validity of a payment schedule not served in
accordance with the Act in Gisley Investments Pty Ltd v Williams [2010] QSC 178.
15 Neumann Contractors Pty Ltd v Peet Beachton Syndicate Ltd [2009] QSC 376.
-- 8 of 18 --
9
Validity of the adjudication claim
[24] De Neefe’s submission is summarised above.16
“The day on which the payment becomes payable”
[25] The first difficulty with that submission is that cl 4.1 does not make provision for a
day on which payment is to be made, as s 15(1)(a) envisages the contractual
provision to do. It simply provides that payment will be made “within” 45 days of
the end of the month in which the tax invoice is submitted and approved. Under
cl 4.2 tax invoices are to be submitted by the 22nd of each month but there is no
express provision covering who is to approve them or what period is allowed for
that process. It may be that one would imply that a decision must be made by De
Neefe before the end of the month of submission. Even so, payment is to be made
within 45 days from the end of the month, which must mean that it may be made on
any of those 45 days.
[26] Whether this is sufficient to take cl 4.1 outside the description “a provision about
the matter” was not the subject of submissions by counsel, so I shall not pursue the
question. On the strict construction approach urged by De Neefe, it probably would
suffice for that purpose. However I shall assume, in accordance with De Neefe’s
submission on the present point, that the earliest date for payment under the clause
was 14 May 2010.
Time for giving the s 21(2) notice: validity of cl 4.1
[27] As noted above,17 Build1 submitted that cl 4.1 was void under s 67W of the
QBSAA. If that submission is correct, the case falls under s 15(1)(b) of the Act,
with the consequence that the progress payment was (due and) payable from 5
April. The s 21(2) notice was given on 12 April, within the statutory period.
[28] Section 67W provides:
“67W Void payment provision in commercial building contract
A provision in a commercial building contract is void to the
extent it provides for payment of a progress payment by a
contracting party to a contracted party later than 15 business
days after submission of a payment claim.”
The contract between the parties was a “commercial building contract” as defined
in QBSAA if (and only if), among other requirements, it was a building contract as
therein defined. Relevantly, it was such a building contract if it was a contract for
carrying out building work as defined. By a combination of definitions, building
work means (among other things) the construction of a fixed structure (which the
work the subject of the subcontract was), but the term does not include work of a
kind excluded by regulation from the definition. De Neefe submitted that the work
was of such a kind.
16 Paragraph [10].
17 Paragraph [19].
-- 9 of 18 --
10
[29] Regulation 5 of the Queensland Building Services Authority Regulation 2003
provides (as far as is relevant18):
“5 Work that is not building work
(1) For the Act, schedule 2, definition building work, the following
work is not building work—
…
(l) construction, maintenance or repair of—
(i) a busway or road; or
(ii) a tunnel for a busway or road;
…
(u) construction, maintenance or repair of a sign that does not
have a supporting structure;
Example—
a sign that consists of only a flat sheet of acrylic resin, fabric, metal
or wood
(v) construction, maintenance or repair of a supporting
structure for a sign if—
(i) the value of building work for the supporting structure
is less than $5000; or
(ii) the top of the sign or supporting structure, whichever
is higher, is less than 3m above the surface
immediately below the sign or structure, including, for
example, the ground, or a road or path on which an
individual may travel, whether in a vehicle, while
walking, or in any other way;
…
(3) A supporting structure for a sign is a structure the main purpose
of which is to display the sign.
(4) Without limiting subsection (3), a supporting structure for a
sign includes any structure that is attached to or suspended from
a building to allow the sign to be displayed, including, for
example, a sign case or other box-type structure, but does not
include the building.
(5) In this section—
…
road—
(a) means an area of land, whether surveyed or unsurveyed—
(i) dedicated, notified or declared to be a road for public
use; or
(ii) taken under an Act, for the purpose of a road for public
use; and
(b) includes—
(i) a street, esplanade, highway, pathway, thoroughfare,
toll road, track or stock route; and
(ii) a causeway or culvert in, on, or under a road that is
associated with the road; and
18 De Neefe expressly abandoned reliance on s 5(1)(v), but the paragraph is relevant to the construction
of para (u).
-- 10 of 18 --
11
(iii) a structure in, on, or under a road that is associated
with the road.”
[30] I shall assume that the work under all of the subcontracts related to signs that did
have supporting structures, with the consequence that none of it was excluded from
the definition of building work by s 5(1)(u). Mr Savage SC so stated in his
supplementary written submissions, with references to the evidence,19 and this was
not challenged by Mr Dunning SC in reply.
[31] De Neefe submitted that the work was not building work because of s 5(1)(l), on the
ground that it satisfied the exclusionary requirements of a tunnel for a road. In my
judgment that submission fails. A sign in a tunnel is not itself a tunnel. The
regulation clearly uses words with some precision. It deals separately with sirens
and it has considered separately the position of structures associated with the road.
There is no reason to assume that “tunnel” is intended to include structures
associated with the tunnel.
[32] De Neefe further submitted, relying on s 5(5)(b)(iii)
“that the signs were structures on or associated with the road
pursuant to the Regulations. In particular the signs are traffic signs
for the road and the tunnel.”
[33] When a person refers to a sign in ordinary usage, “sign” is understood to include not
only the face which imparts information but also the whole of the structure of the
sign, including the supporting structure. It seems to be otherwise in the regulation.
Paragraphs (u) and (v) draw a distinction between a sign and the supporting
structure for a sign. At least in theory this could produce peculiar results: low or
cheap supporting structures could be excluded from the definition while the signs on
them were not. It is reasonable to suppose that the amounts at stake would mean
that this would not be a problem in practice.
[34] De Neefe’s submission just quoted does not use “signs” in the statutory sense.
Consequently it fails to address the question relevant to the applicability of the
regulation. The signs (in the statutory sense) had supporting structures and are not
excluded from the definition by para (u). The correct question is whether the
supporting structures for the signs were structures within the meaning of “structure”
in s 5(5)(b)(iii).
[35] Regulation 5 deals with supporting structures in para (1)(v). That paragraph
envisages a situation where a supporting structure may be immediately above a
road. “Road“ includes the whole of the declared road area. In other words, the
paragraph envisages a situation where supporting structures are on roads and
excludes them from the definition of building work only in certain circumstances.
For that reason it is unlikely that the much wider word “structure” in s 5(5)(b)(iii)
was intended to include a supporting structure for a sign. There remains work for
that word to do notwithstanding the exclusion from its ambit of supporting
structures for signs. I conclude that the work done by Build1 was not excluded
from the definition of “building work” in QBSAA.
19 Footnote 43 and sch A.
-- 11 of 18 --
12
[36] It is therefore not necessary to decide whether a contract to carry out work part of
which is excluded and part of which (the signs themselves) is not excluded from the
definition is a building contract within the meaning of s 67AAA of QBSAA.
[37] It follows that to the extent that it provides for payment of a payment claim later
than 15 days after its submission, cl 4.1 of the subcontract is void.
[38] The case therefore falls under para (b) and not under para (a) of s 15(1). The
progress payment was payable 10 business days after the payment claim was made,
ie on 5 April 2010. The notice under s 21(2) given on 12 April was within the
period of 20 business days immediately following the due date for payment
prescribed by s 21(2)(a). The adjudication application was not prohibited by that
provision.
Non-compliance with s 21(2)
[39] Build1 submitted that in any event, the adjudication was not invalidated because the
notice under s 21(2) was given out of time. It supported that submission with the
decision in Nebmas Pty Lty v Sub Divide Pty Ltd.20
[40] I have already held that failure to serve a payment claim within the period
prescribed by s 17(4) does not mean that the claim is not one answering the
description “payment claim” in s 17(1). However s 17 contains no provision
equivalent to s 21(2).21 The latter does not simply mandate a time for service of an
adjudication application; it provides that no such application can legally be made in
specified circumstances. The task of an adjudicator is to decide an adjudication
application.22 How can it be that a decision by an adjudicator based on an
application which cannot legally be made could have any legal validity?
[41] In Nebmas McMurdo J reached his decision after referring to the decisions of the
New South Wales Court of Appeal in Brodyn and Coordinated Construction Co Pty
Ltd v Climatech (Canberra) Pty Ltd.23 His Honour cited the well-known passage
from the judgment of Hodgson JA in the former case;24 but he recognised that the
requirement for compliance with s 21(2) was not referred to in that passage as being
in either the category of “basic and essential requirements” for a valid determination
or in the category of “more detailed requirements” compliance with which was not
essential to a valid adjudication decision. I respectfully agree. For that reason,
Brodyn does not determine the point now under consideration.
[42] His Honour based his decision on a passage in the reasons for judgment of
Basten JA in the latter case. I shall not repeat it, nor shall I undertake an analysis,
necessarily obiter, of it.25 The Act and its interstate equivalents have generated
20 [2009] QSC 92.
21 Section 21(3)(c) is the analogue of s 17(4) in relation to an adjudication application. I respectfully
agree with the conclusion reached by Douglas J in Gisley Investments Pty Ltd v Williams [2010]
QSC 178 that non-compliance with that provision does not invalidate an adjudication decision based
on an improperly served adjudication application.
22 Sections 25(3), (4) and 26(2).
23 [2005] NSWCA 229.
24 (2004) 61 NSWLR 421 at p 441.
25 Note that the wording of s 13(2) of the New South Wales Act differs materially from that of s 17(2).
-- 12 of 18 --
13
much discussion in judgments. Many of the statements made need to be considered
in the light of the precise facts of the case. For example, statements and decisions
about the reviewability of the identification of construction work in a payment
claim26 should not be generalised to apply to all elements of s 17(2), any more than
should statements and decisions about any one element of s 21(3) be generalised to
apply to all elements of that subsection. In construing this Act great care is needed
when applying dicta from previous decisions in different circumstances.
[43] The passage from Climatech cited in Nebmas has subsequently been held to be
authority for this proposition: “Whether a payment claim identifies the construction
work or related goods and services to which the payment relates, as required by
s 13(2) [s 17(2) in Queensland] of the Act, is generally a matter for the adjudicator
to determine”.27 So interpreted, it provides no support for a conclusion that a
decision by an adjudicator based on an application which cannot legally be made
under s 21(2) cannot be challenged in this Court. It should be noted that
Basten JA’s dicta were directed toward a different section, one which set out what
some judges have viewed as procedural or non-essential requirements for a payment
claim, not toward a section which declared the happening of a nominated event
impossible (or at least prohibited) unless certain conditions were fulfilled. Wording
in this form is much more difficult to assimilate into his Honour’s reasoning.
[44] I wrote above that the task of an adjudicator is to decide an adjudication
application.28 Absent an application a decision by an adjudicator has no legal force.
The statutory dictionary provides for “adjudication application”, “see section
21(1)”. Prima facie there is an adjudication application if a claimant has applied for
adjudication of the payment claim in the circumstances set out in s 21(1). I need not
decide whether any of the elements of s 21(3) is essential to the existence of such an
application. The question is, in cases to which it applies, does non-fulfilment of the
conditions specified in s 21(2) have the consequence that no application has been
made.
[45] That question must be answered by construing the opening words of the subsection.
I acknowledge that they must be construed in the light of the two conditions,
particularly the nature and content of those conditions. I acknowledge the force of
the view that those conditions seem on their face purely procedural matters aimed at
ensuring the provision of natural justice and perhaps reducing the chance that the
case will actually go to adjudication. There is however no reason why Parliament
should not if it so chooses make fulfilment of conditions of that nature essential to
the making of an application. In my judgment, the words “an adjudication
application … cannot be made” produce that result. They should be given their
natural meaning. If by statute an application cannot be made, then anything
purporting to be one cannot be an application. The existence of an application is a
basic and essential requirement of an adjudicator’s determination.29
26 Difficulties arising from “identify” in s 17 may be better solved by an appropriate interpretation of
that word.
27 Perform at para [64] (citations omitted).
28 Para [40].
29 Brodyn at p 441.
-- 13 of 18 --
14
[46] That is the same conclusion as was reached in Kell & Rigby Pty Ltd v Guardian
International Properties Pty Ltd.30
[47] The effect of the contrary conclusion is the re-wording of s 21(2) to read “unless the
adjudicator thinks” in place of “unless” (and it consequentially requires a change of
tense in the two conditions). While the subject matter of BCIPA can hardly be
compared with the liberty of the subject, there is powerful (albeit dissenting)
authority against adopting that technique of statutory interpretation.31
[48] It follows that if I were wrong in my conclusion that the notice was given within the
time described in s 21(2)(a), the purported adjudication application made on
30 April 2010 would be a nullity, as would the decision of that application. But I
must determine this case on the basis of that conclusion.
Orders
[49] The applicants are not entitled to either of the declarations sought by them and there
is no basis for granting an injunction. In each matter the orders should be:
1. Application dismissed.
2. Discharge the interlocutory injunction ordered by this Court on 3 June 2010.
I shall hear the parties on costs.
30 [2007] NSWSC 554.
31 Liversidge v Anderson [1942] AC 206 at p 244 per Lord Atkin.
-- 14 of 18 --
15
Annexure A
Building and Construction Industry Payments Act 2004 (Qld)
12 Rights to progress payments
From each reference date under a construction contract, a person is entitled to a progress
payment if the person has undertaken to carry out construction work, or supply related
goods and services, under the contract.
15 Due date for payment
(1) A progress payment under a construction contract becomes payable—
(a) if the contract contains a provision about the matter that is not void under
section 16 or under the Queensland Building Services Authority Act 1991, section
67U or 67W—on the day on which the payment becomes payable under the
provision; or
(b) if the contract does not contain a provision about the matter or contains a
provision that is void under section 16 or under the Queensland Building Services
Authority Act 1991, section 67U or 67W—10 business days after a payment claim
for the progress payment is made under part 3.
(2) Subject to subsection (3), interest for a construction contract is payable on the unpaid
amount of a progress payment that has become payable at the greater of the following
rates—
(a) the rate prescribed under the Supreme Court Act 1995, section 48(1) for debts
under a judgement or order;
(b) the rate specified under the contract.
(3) For a construction contract to which Queensland Building Services Authority Act 1991,
section 67P applies because it is a building contract, interest is payable at the penalty rate
under that section.
16 Effect of pay when paid provisions
(1) A pay when paid provision of a construction contract has no effect in relation to any
payment for construction work carried out or undertaken to be carried out, or related
goods and services supplied or undertaken to be supplied, under the construction contract.
(2) In this section—
an amount owing, in relation to a construction contract, means an amount owing for
construction work carried out or undertaken to be carried out, or related goods and
services supplied or undertaken to be supplied, under the construction contract.
pay when paid provision, of a construction contract, means a provision of the contract—
(a) that makes the liability of one party (the first party) to pay an amount owing to
another party (the second party) contingent on payment to the first party by a
further party (the third party) of the whole or any part of that amount; or
(b) that makes the due date for payment of an amount owing by the first party to
the second party dependent on the date on which payment of the whole or any part
of that amount is made to the first party by the third party; or
(c) that otherwise makes the liability to pay an amount owing, or the due date for
payment of an amount owing, contingent or dependent on the operation of another
contract.
17 Payment claims
(1) A person mentioned in section 12 who is or who claims to be entitled to a progress
payment (the claimant) may serve a payment claim on the person who, under the
-- 15 of 18 --
16
construction contract concerned, is or may be liable to make the payment (the
respondent).
(2) A payment claim—
(a) must identify the construction work or related goods and services to which the
progress payment relates; and
(b) must state the amount of the progress payment that the claimant claims to be
payable (the claimed amount); and
(c) must state that it is made under this Act.
(3) The claimed amount may include any amount—
(a) that the respondent is liable to pay the claimant under section 33(3); or
(b) that is held under the construction contract by the respondent and that the
claimant claims is due for release.
(4) A payment claim may be served only within the later of—
(a) the period worked out under the construction contract; or
(b) the period of 12 months after the construction work to which the claim relates
was last carried out or the related goods and services to which the claim relates
were last supplied.
(5) A claimant can not serve more than 1 payment claim in relation to each reference date
under the construction contract.
(6) However, subsection (5) does not prevent the claimant from including in a payment
claim an amount that has been the subject of a previous claim.
21 Adjudication application
(1) A claimant may apply for adjudication of a payment claim (an adjudication
application) if—
(a) the respondent serves a payment schedule under division 1 but—
(i) the scheduled amount stated in the payment schedule is less than the
claimed amount stated in the payment claim; or
(ii) the respondent fails to pay the whole or any part of the scheduled
amount to the claimant by the due date for payment of the amount; or
(b) the respondent fails to serve a payment schedule on the claimant under division
1 and fails to pay the whole or any part of the claimed amount by the due date for
payment of the amount.
(2) An adjudication application to which subsection (1)(b) applies can not be made
unless—
(a) the claimant gives the respondent notice, within 20 business days immediately
following the due date for payment, of the claimant’s intention to apply for
adjudication of the payment claim; and
(b) the notice states that the respondent may serve a payment schedule on the
claimant within 5 business days after receiving the claimant’s notice.
(3) An adjudication application—
(a) must be in writing; and
(b) must be made to an authorised nominating authority chosen by the claimant;
and
(c) must be made within the following times—
(i) for an application under subsection (1)(a)(i)—within 10 business days
after the claimant receives the payment schedule;
(ii) for an application under subsection (1)(a)(ii)—within 20 business days
after the due date for payment;
(iii) for an application under subsection (1)(b)—within 10 business days
after the end of the 5 day period referred to in subsection (2)(b); and
-- 16 of 18 --
17
(d) must identify the payment claim and the payment schedule, if any, to which it
relates; and
(e) must be accompanied by the application fee, if any, decided by the authorised
nominating authority; and
(f) may contain the submissions relevant to the application the claimant chooses to
include.
(4) The amount of an application fee must not exceed the amount, if any, prescribed under
a regulation.
(5) A copy of an adjudication application must be served on the respondent.
(6) The authorised nominating authority to which an adjudication application is made
must refer the application, as soon as practicable, to a person eligible to be an adjudicator
under section 22.
22 When person may be an adjudicator
(1) A person may be an adjudicator in relation to a construction contract if registered as an
adjudicator under this Act.
(2) A person is not eligible to be an adjudicator in relation to a particular construction
contract—
(a) if the person is a party to the contract; or
(b) in circumstances prescribed under a regulation for this section.
(3) A regulation may be made under subsection (2)(b) only to prescribe circumstances in
which the appointment of an adjudicator might create a conflict of interest
25 Adjudication procedures
(1) An adjudicator must not decide an adjudication application until after the end of the
period within which the respondent may give an adjudication response to the adjudicator.
(2) An adjudicator must not consider an adjudication response unless it was made before
the end of the period within which the respondent may give a response to the adjudicator.
(3) Subject to subsections (1) and (2), an adjudicator must decide an adjudication
application as quickly as possible and, in any case—
(a) within 10 business days after the earlier of—
(i) the date on which the adjudicator receives the adjudication response; or
(ii) the date on which the adjudicator should have received the adjudication
response; or
(b) within the further time the claimant and the respondent may agree, whether
before or after the end of the 10 business days.
(4) For a proceeding conducted to decide an adjudication application, an adjudicator—
(a) may ask for further written submissions from either party and must give the
other party an opportunity to comment on the submissions; and
(b) may set deadlines for further submissions and comments by the parties; and
(c) may call a conference of the parties; and
(d) may carry out an inspection of any matter to which the claim relates.
(5) If a conference is called, it must be conducted informally and the parties are not
entitled to any legal representation.
(6) The adjudicator’s power to decide an adjudication application is not affected by the
failure of either or both of the parties to make a submission or comment within time or to
comply with the adjudicator’s call for a conference of the parties.
26 Adjudicator’s decision
(1) An adjudicator is to decide—
-- 17 of 18 --
18
(a) the amount of the progress payment, if any, to be paid by the respondent to the
claimant (the adjudicated amount); and
(b) the date on which any amount became or becomes payable; and
(c) the rate of interest payable on any amount.
(2) In deciding an adjudication application, the adjudicator is to consider the following
matters only—
(a) the provisions of this Act and, to the extent they are relevant, the provisions of
the Queensland Building Services Authority Act 1991, part 4A;
(b) the provisions of the construction contract from which the application arose;
(c) the payment claim to which the application relates, together with all
submissions, including relevant documentation, that have been properly made by
the claimant in support of the claim;
(d) the payment schedule, if any, to which the application relates, together with all
submissions, including relevant documentation, that have been properly made by
the respondent in support of the schedule;
(e) the results of any inspection carried out by the adjudicator of any matter to
which the claim relates.
(3) The adjudicator’s decision must—
(a) be in writing; and
(b) include the reasons for the decision, unless the claimant and the respondent
have both asked the adjudicator not to include the reasons in the decision.
-- 18 of 18 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2010/279