Aimtek Pty Ltd v Brisbane Ship Constructions Pty Ltd [2010] QSC 160
SUPREME COURT OF QUEENSLAND
CITATION: Aimtek Pty Ltd v Brisbane Ship Constructions Pty Ltd [2010]
QSC 160
PARTIES: AIMTEK PTY LTD
ACN 009 679 207
(plaintiff)
v
BRISBANE SHIP CONSTRUCTIONS PTY LTD
ACN 010 621 275
(defendant)
FILE NO/S: BS 10771 of 2007
DIVISION: Trial Division
PROCEEDING: Application
ORIGINATING
COURT: Supreme Court of Queensland
DELIVERED ON: 18 May 2010
DELIVERED AT: Brisbane
HEARING DATE: 4 December 2009
JUDGE: Daubney J
ORDERS: 1. The plaintiff’s application to strike out paragraph
8 of the fifth amended defence is dismissed.
2. Within 21 days of today, the defendant shall
provide the plaintiff with further and better
particulars of:
(a) The allegation in paragraph 8(a)(iv)(B) of the
fifth amended defence that the defendant was
“totally reliant upon the plaintiff” as alleged in
that paragraph;
(b) The “build program” referred to in paragraph
8(a)(iv) of the fifth amended defence.
3. The costs of and incidental to the application will
be reserved.
CATCHWORDS: PROCEDURE – SUPREME COURT PROCEDURE –
QUEENSLAND – PROCEDURE UNDER RULES OF
COURT – PLEADING – DEFENCE AND
COUNTERCLAIM – where the plaintiff has sued the
defendant for monies alleged to be owing under a design
-- 1 of 12 --
2
contract – where the plaintiff claimed they provided technical
and support services outside the scope of supply under the
design contract at the request of the defendant – where the
defendant pleads in paragraph 8 of the defence that the
plaintiff made certain representations in relation to the
services provided which induced the defendant to assume the
plaintiff would provide the services to the defendant as part
of the scope of supply under the design contract – where the
plaintiff has applied for paragraph of the defence to be struck
out on the grounds that no reasonable defence is disclosed,
prejudice and delay, or that the pleadings are unnecessary or
embarrassing – whether paragraph 8 of the defence should be
struck out
PROCEDURE – SUPREME COURT PROCEDURE –
QUEENSLAND – PROCEDURE UNDER RULES OF
COURT – PLEADING – where the plaintiff seeks, in the
alternative, for the defendant to provide further and better
particulars of paragraph 8 of the defence – whether the
defendant should be required to provide further and better
particulars
Aon Risk Services Australia Limited v Australian National
University (2009) 239 CLR 175, applied
Development Assessment Commission v Macag Holdings Pty
Ltd (2001) 80 SASR 104, cited
Dey v Victorian Railway Commissioners (1949) 78 CLR 62,
cited
Trade Practices Commission v Pioneer Concrete (Qld) Pty
Ltd (1994) 52 FCR 164, cited
Walton v Gardiner (1993) 177 CLR 378, cited
COUNSEL: DR Cooper, SC for the plaintiff
M Johnston for the defendant
SOLICITORS: Morrow Petersen for the plaintiff
O’Reilly Lillicrap Solicitors for the defendant
[1] The plaintiff has sued the defendant for monies alleged to be owing under a design
contract dated 23 September 2006 in relation to the construction of six vessels by
the defendant for a third party.
[2] In that regard, the statement of claim pleads:
“2. By a written agreement styled Design Contract made between the
Plaintiff and the Defendant and dated 23 September 2006 (“the
Design Contract”) the parties agreed, subject to the signing of the
“build contract” for the vessels referred to in the said contract, that
the Plaintiff “shall provide the (Defendant) with design materials” for
the construction of the said vessels by the Defendant for Collins
River Enterprises Ltd (“CRE”) a company incorporated in the United
Kingdom.
-- 2 of 12 --
3
3. By clause 7 of the Design Contract it was agreed that the Plaintiff
“shall provide the design materials of a vessel as described in the
scope of supply to enable such vessel to be built by the (Defendant)”.
4. By clause 3 of the Design Contract it was agreed that:
“The design contract price for each two vessels ordered by (CRE)
shall be two hundred thousand Australian Dollars
(AUD$200,000.00) plus four per cent (4%) of the build contract
price per vessel excluding shipping costs.”
5. By clause 4(a) of the Design Contract it was agreed that:
“Payment of the design contract fee shall be made by the
(Defendant) to the (Plaintiff) in instalments within seven (7) days
of the milestone payments made by (CRE) to the (Defendant)
according to the build contract(s).”
6. By clause 6 of the Design Contract it was agreed that the Plaintiff is
entitled to remuneration “for technical and support services outside
the scope of supply as requested by” the Defendant at the rates and in
the amounts more particularly specified in the clause.”
[3] Relevant for present purposes is the plaintiff’s claim pursuant to clause 6 for the
sum of $435,809.00. That claim is pleaded in paragraph 14 of the statement of
claim as follows:
“14. Further, the Plaintiff:
a) provided technical and support services outside the scope of
supply under the Design Contract at the request of the
Defendant;
b) thereby became entitled pursuant to clause 6 of the Design
Contract to invoice the Defendant for such services; and
c) consequently rendered invoice # 48436 dated 16 April 2007 to
the Defendant in the sum of $435,809.00.
Particulars
(i) The technical and support services provided consisted of
the preparation and delivery of 124 drawings to be used
by the Defendant as workshop drawings;
(ii) Workshop drawings were, by the terms of sub clauses 5(c)
and (d) of the Design Contract, outside the scope of
supply by the Plaintiff under such contract;
(iii) In accordance with the hourly rates set out in Schedule 6
to the Design Contract, the Plaintiff provided the services
of:
• Draftsmen for 1972 hours @ $145 per hour;
-- 3 of 12 --
4
• Naval architects/design engineers for 630 hours @
$175 per hour.”
[4] The current version of the defence (the fifth amended defence) defends that claim
for what have been described as “additional services”, inter alia, by the following
plea:
“8. In the further alternative, the Plaintiff is not entitled to the sum of
$435,809.00 billed in the Tax Invoice as claimed in paragraph 14 of the
statement of claim because:
(a) The Plaintiff, through its proper officers, represented to the
Defendant, on or about 22 and 23 September 2006, prior to
entering the Design Contract that (the Representations):
i. the vessels to be constructed were sister ships to the
‘Hurricane Clipper’, a vessel previously built by the
Plaintiff.
ii. the Plaintiff’s drawing package to be provided to the
Defendant under the Design Contract required little or no
modification prior to constructing the new vessels because
the vessels were to be classed as sister ships of the
‘Hurricane Clipper’;
iii. the Plaintiff had nearly completed work to update the
electrical drawings package to a stage ready for
subcontractor quoting;
iv. the Plaintiff would provide the Defendant, as part of the
scope of supply under the Design Contract, all required
drawings to meet a demanding and ambitious build
programme within the Plaintiff’s possession and within the
Plaintiff’s professional capacity to create and provide; and
Particulars
The build programme was demanding and ambitious
because, to the knowledge of Mr Hollis and the Plaintiff’s
Mr Don Fry at the time of the Representations (each of
these matters being raised and discussed during the
negotiations of 22 and 23 September 2006);
A. the Defendant had available to it approximately 50 to
75 staff and contractors, which was a small workforce
for the type of building programme being undertaken;
B. the building programme required an electrical design
capability which the Defendant did not have and was
totally reliant upon the Plaintiff to provide;
C. the Defendant was being required by the building
programme to construct and have ready for delivery
four vessels in seven (7) months and a further two
vessels within a further four (4) months and twenty one
(21) days;
-- 4 of 12 --
5
D. the usual time to construct one vessel of the size and
complexity of the Hurricane Clipper for a company the
size of the Defendant would be approximately 12 to 14
months;
E. to achieve the timeframes for construction, it would be
necessary for the construction works to be undertaken
in the most efficient and timely manner possible, with
significantly greater use of subcontractors than would
be usual, with high level daily project management
brought to bear to ensure no delay or disruption of any
kind, generally working seven days per week and
public holidays and without the normal Christmas
closure, and with extensive use of overtime, worker
bonus payment systems for achievement of scheduled
milestones, and night shiftwork where possible.
v. the Plaintiff would provide the Defendant an updated
electrical drawing package as part of the scope of supply
under the Design Contract.
Particulars
The Representations were made orally through the
Plaintiff’s Chairman, Mr Don Fry (‘Fry’), who was
authorised (or held himself out as authorised) to act on the
Plaintiff’s behalf for the purposes of negotiating the Design
Contract;
The Representations were made to the Defendant’s
Director, Mr Michael Hollis (‘Hollis’); and
The Representations were made at the Defendant’s
Toowong Office during the course of negotiations regarding
the Design Contract on or about 22 and 23 September 2006.
(ab) The Plaintiff’s Representations induced the Defendant (by Hollis)
to assume that:
i. the drawings to be provided by the Plaintiff under the
Design Contract would require little modification;
ii. the Plaintiff would supply to the Defendant as part of the
scope of supply under the Design Contract all required
drawings (including electrical drawings) to enable the
Defendant to construct the vessels (‘the Assumptions’);
(b) The Defendant relied on the Plaintiff’s Representations and the
Assumptions to the Plaintiff’s knowledge by:
i. Entering into the Design Contract on the terms contained in
the Design Contract;
-- 5 of 12 --
6
ii. Failing to negotiate for the amount agreed as payable under
the Design Contract to expressly include the services now
claimed as the subject of the Tax Invoice.
Particulars
Hollis advised Fry during the course of negotiations
regarding the Design Contract on or about 22 or 23
September 2006 that:
A. the Defendant did not have an in-house electrical
design capability and that the Defendant would require
the updated electrical drawing package as part of the
scope of supply under the Design Contract.
B. to meet a demanding and ambitious build programme,
it was important that the Plaintiff’s drawing package to
be provided to the Defendant required little
modification (particulars of the demanding and
ambitious build programme are at 8(a)(iv) above).
(ba) The Plaintiff’s Representations have proven to be untrue in that
the Plaintiff’s drawing package as provided to the Defendant
under the Design Contract did not enable the Defendant to
construct the vessels because, for the reasons pleaded in paragraph
9 of the counterclaim the Drawing Package (in the respects
pleaded in paragraph 9 of the counterclaim) were not reasonably
fit for the purpose of facilitating construction of the vessels under
the Construction Contract (as that term is defined in paragraph
4(a) of the counterclaim) and were not free from defect and error
in design. provide all of the information required to construct the
vessels and required extensive modifications and further
information.
Particulars
i. The Defendant repeats and relies upon paragraphs 9 and 10
of the counterclaim;
ii. The 124 drawings referred to in paragraph 14(c)(i) of the
statement of claim were essentially comprised of electrical
drawings which were necessary to enable the Defendant to
construct the vessels. Further particulars will be provided
after disclosure;
(c) The Defendant will suffer detriment if the Plaintiff were to be now
found entitled to claim the amount of the Tax Invoice for the
Purported Services because but for the Plaintiff’s Representations
the Defendant would not have entered into the Design Contract on
the terms on which it did and would have insisted in its
negotiation of the Design Contract that the Design Contract price
include any remuneration payable to the Plaintiff in respect of the
technical and support services alleged at paragraph 14(c) of the
statement of claim.
-- 6 of 12 --
7
(d) Further, the Defendant would have insisted in its negotiation of
the Design Contract that the Design Contract price include any
remuneration payable to the Plaintiff in respect of the technical
and support services alleged at paragraph 14(c) of the statement of
claim, in circumstances where the opportunity to conduct such a
negotiation carried with it a real chance that the Defendant would
have been successful in that negotiation.
Particulars
That there was a real chance of success is to be inferred from the
following matters:
i. the Plaintiff had made the Representations;
ii. the Plaintiff had the capability in-house to provide the
technical and support services;
iii. the Plaintiff had experience with building the Hurricane
Clipper and the professional capacity to provide the
technical and support services;
iv. the Plaintiff had failed to secure an agreement with another
ship builder;
v. the Plaintiff was desirous of entering the Construction
Management Agreement with CRE which hinged on the
Plaintiff finding and securing a suitable ship builder in a
timely way;
vi. the Plaintiff desired to have one ship builder to construct
and deliver all vessels proposed under the build programme,
rather than multiple builders, for ease of management and
economies of scale;
vii. the Plaintiff wished to quickly enter an agreement with the
Defendant.
(e) In the premises, the Plaintiff is estopped from asserting that the
Purported Services were provided as services outside the scope of
supply under the Design Contract and from claiming the amount
stated in the Tax Invoice.”
[5] The plaintiff has applied for this paragraph of the defence to be struck out in its
entirety, or at least for paragraphs 8(a)(i) – (iii), 8(ab) and 8(e) and 8(ba) to be
struck out, on the grounds that:
(a) no reasonable defence is disclosed;
(b) the pleadings have the tendency to prejudice or delay the fair trial of the
proceeding; or
(c) the pleadings are unnecessary or embarrassing.
-- 7 of 12 --
8
[6] This is not the first occasion on which the plaintiff has applied to strike out parts of
the defence. Specifically, on 27 May 2009 the plaintiff made an application to
strike out paragraph 8 of the then defence (the fourth amended defence). That
application was heard by me on 17 June 2009. As argument evolved on that day,
the defendant accepted that it would be necessary for it to amend paragraph 8 of the
defence, and it was given leave to re-plead that paragraph.
[7] On the hearing of the present application, the defendant mounted a vigorous
argument to the effect that, because the bases relied on by the plaintiff in the present
application were the same or similar as those it had advanced in the previous
application to seek to strike out paragraph 8, the present application ought be
dismissed as an abuse of process. The defendant relied in that regard on the
fundamental proposition that an attempt to relitigate a case which has been disposed
of by earlier proceedings may constitute an abuse of process, citing Walton v
Gardiner (1993) 177 CLR 378 per Mason CJ, Deane & Dawson JJ at 393 and
Brennan J (Toohey J agreeing) at 414, Development Assessment Commission v
Macag Holdings Pty Ltd (2001) 80 SASR 104, per Doyle CJ at [61], and Aon Risk
Services Australia Limited v Australian National University (2009) 239 CLR 175,
per French CJ at [33] – [34].
[8] It is quite correct that there is significant overlap between the submissions
previously made and those now advanced by the plaintiff in relation to paragraph 8
of the defence, and that the plaintiff raises the same or materially similar issues to
those on which it relied in the previous application. I do not, however, think it can
properly or fairly be said that these issues were determined or disposed of by the
earlier application. Rather, as I have said, what occurred in the course of the earlier
hearing was, as commonly happens in the course of such applications in the face of
criticism of a pleading and with the benefit of engaging in argument on the matter,
counsel for the defendant accepted, at least, that it would be desirable for the
defence to be repleaded. In view of the acceptance of that outcome as a pragmatic
resolution of the application then before the Court, it can hardly be said either that
there was an express judicial determination of the issues which the plaintiff had
sought to raise at that time or, as would now be said by the defendant, some sort of
implied judicial decision to the effect that if amendments were made then the
criticisms of paragraph 8 would be finally answered.
[9] The defendant sought to bolster its abuse of process argument by alleging that the
plaintiff had been guilty of undue delay in progressing the proceeding. True it is
that prior to the hearing in June 2009, significant delays and non-compliance with
procedural timetables had been occasioned by the plaintiff. That was dealt with at
the time of those delays and events of non-compliance. I do not, however, consider
that the plaintiff engaged in any further significant delay after June 2009. There
was some slippage in the procedural timetable due to the defendant’s late delivery
of its amended defence, and directions for the hearing of the present application had
to be recalibrated by four weeks on account of delay by the plaintiff. But all in all, I
do not consider the plaintiff’s more recent approach to the conduct of this litigation
to have been so tardy as to amount to an abuse of process.
-- 8 of 12 --
9
[10] I would therefore reject the defendant’s submission that this application by the
plaintiff ought to be dismissed as an abuse of process.
[11] Turning to the strikeout application, the central assertions made by the plaintiff
were:
(a) The allegations in paragraphs 8(a)(i), (ii) and (iii) are now otiose; they may
have been relevant to a previous version of the defence, but are not relevant to
the defendant’s current case;
(b) Paragraph 8, by its terms, seeks to set up a promissory estoppel in relation to
the entire cost of all of the drawings which the plaintiff contends were
“additional services” falling under clause 6. But the assumption pleaded in
paragraph 8(ab)(ii), which is said to have been induced by the pleaded
representations, was an assumption that the plaintiff would supply “as part of
the scope of supply under the Design Contract all required drawings
(including electrical drawings) to enable the defendant to construct the
vessels”. The plaintiff contends that:
(i) This pleaded assumption is ambiguous, because the phrase “scope of
supply” contemplates both the work performed for the Design Contract
price (under clause 3) and the “additional services provided for under
clause 6”;
(ii) There is no assumption that the cost of the drawings would be
subsumed into the lump sum payable as the “Design Contract price”.
The plaintiff submitted, in short, that “the representations and assumptions related to
the nature of the documents to be provided which would achieve a specific result,
and not to the Defendant’s liability to pay for them under that Contract as “extras””.
(Underlining as per written submissions).
[12] In relation to the first of these submissions, the defendant’s case, as previously
pleaded, had asserted an assumption by it, induced by the representations pleaded in
paragraph 8(a), that “the drawings to be provided by the plaintiff under the Design
Contract would require little modification”. That allegation (previously paragraph
8(ab)(i) was deleted in the current version of the defence. One can see, particularly
by reference to the representation pleaded in paragraph 8(a)(ii), that the
representations pleaded in paragraphs 8(a)(i), (ii) and (iii) on their face appeared to
have more direct logical connection with the assumption previously pleaded in
paragraph 8(ab)(i) than the sole assumption now relied on, being that pleaded in
paragraph 8(ab)(ii). The defendant says, however, that the plaintiff’s approach of
dissecting the pleading in this way is erroneous, and contends that when one reads
paragraph 8 as a whole it is clear that the defendant is seeking to plead a series of
representations concerned with the character of the drawings to be provided which
cumulatively induced the assumption now pleaded in paragraph 8(ab)(ii).
-- 9 of 12 --
10
[13] Mindful as I am of the longstanding proposition that a case must be very clear
indeed to justify the summary intervention of the Court, 1 and also acknowledging
that it is appropriate for a court, when asked to strike out all or part of a pleading, to
err on the side of caution lest it deprive a party of a case which, upon analysis of the
facts and law at trial, it is entitled to bring.2 I would be disinclined to accede to the
plaintiff’s submission that these paragraphs ought to be struck out at this stage. It is
clear that the trial of this proceeding will require some factual investigation into the
dealings between the parties prior to the execution of the Design Contract. It would
be quite inappropriate for me, on a summary basis, to hold that these particular
representations manifestly had nothing to do with the remaining pleaded
assumption. In any event, the factual enquiry arising out of the pleading of these
representations is clearly limited in scope, and would add little to the length of, or
cost associated with, the trial. It may be that, having heard all the evidence, the trial
judge concludes, as is presently contended by the plaintiff, that these particular
representations did not contribute to the formation of the remaining sole pleaded
assumption. But that is not a matter on which I would be prepared to make a
determination at this stage.
[14] The plaintiff’s complaints about ambiguity in the assumption pleaded in paragraph
8(ab)(ii) are, it seems to me, quite untenable. It was submitted that this pleaded
assumption “is necessarily and inherently ambiguous because the phrase ‘scope of
supply’ contemplates both work performed for the ‘Design Contract price’, and/or
‘additional services’ rendered under that contract at an hourly rate”. That, however,
is clearly not what was provided for under the contract. Indeed, paragraph 6 of the
statement of claim (which I have set out above) quotes clause 6 of the Design
Contract, which comprised the agreement that the plaintiff was entitled to
remuneration “for technical and support services outside the scope of supply as
requested by” the defendant (underlining added). Paragraph 8 of the defence is
responsive, as I have already noted, to paragraph 14 of the statement of claim,
which expressly averred that the plaintiff “provided technical and support services
outside the scope of supply under the Design Contract at the request of the
defendant” (underlining added). It is therefore quite obvious that the case pleaded
by the plaintiff is that works within the “scope of supply” were to be paid for at the
Design Contract price specified in clause 3 and work outside the scope of supply
was to be remunerated by reference to clause 6.
[15] When one understands that the defendant is using the term “scope of supply” in
paragraph 8(ab)(ii) in precisely the same sense and context as that ascribed to the
term in the plaintiff’s pleaded case, there is no ambiguity at all about this paragraph
in the defence.
[16] Similarly, I think the plaintiff’s attack on these paragraphs on the basis that there
was no assumption pleaded that the drawings would be subsumed into the “Design
Contract price” completely ignores the contractual construct which the plaintiff
itself seeks to advance. The stated assumption that the plaintiff would supply the
drawings “as part of the scope of supply under the Design Contract” necessarily
1 Dey v Victorian Railway Commissioners (1949) 78 CLR 62 per Dixon J at 91.
2 Trade Practices Commission v Pioneer Concrete (Qld) Pty Ltd (1994) 52 FCR 164; (1994) 80 PR
41-345 at 42,515.
-- 10 of 12 --
11
means that the defendant asserts thereby that the cost of the drawings was included
in the remuneration payable for works which fell within the scope of supply under
the Design Contract, i.e. the remuneration payable in accordance with clause 3 of
the Design Contract.
[17] Accordingly, when one reads paragraph 8 not merely in its own context but also in
context of the plaintiff’s case to which it is responsive, it seems to me that there is
no ambiguity in respect of the case which the defendant would seek to make out in
this regard.
[18] The plaintiff also sought to make some point, as a matter of law, that the pleading
failed to disclose a causal connection between the pleaded assumption and the
detriment which the defendant asserted it would suffer from abandonment of that
assumption. This argument was, however, premised on what I have found to be an
incorrect reading of the assumption pleaded in paragraph 8(ab)(ii), and there is the
clear potential for the defendant to establish the necessary nexus in accordance with
the case that it has pleaded in this paragraph.
[19] Accordingly, I would refuse the plaintiff’s strike out application.
[20] The plaintiff has sought, by way of alternative relief, for the defendant to provide
certain further and better particulars of paragraph 8 of the defence. I will deal with
each of those requests in turn.
[21] In relation to paragraph 8(a)(iv)(B), the plaintiff seeks further and better particulars
of the allegation that the defendant was “totally reliant upon the plaintiff to provide”
the electrical design capability referred to. In response, the defendant says that it
has already pleaded in that paragraph that the defendant “did not have” such
capability, and moreover that in paragraph 8(b)(ii)(A) it pleaded that one of its
officers advised the plaintiff that the defendant did not have such an in-house
capability. These answers by the defendant, however, do not address the allegation
which is made, in terms, that the defendant was “totally reliant” upon the plaintiff to
provide the defendant with such a capability. To assert, as the defendant does, that
it was “totally reliant” is something more than merely saying that it did not have the
requisite capability or it informed the plaintiff that it did not have the requisite
capability. Accordingly, I would be inclined to order that these further and better
particulars be provided.
[22] The plaintiff’s next complaint related to paragraph 8(b). Specifically, it is said that
the particulars pleaded under the matters of reliance alleged in paragraphs 8(b)(i)
and (ii) do not appear to relate to the matters of reliance and serve no function in
respect of those matters of reliance. The plaintiff submits that the defendant ought
to amend its pleading to either delete those particulars or relocate them to a place in
the pleading in which they would make more sense. Properly read, however, it
seems to me that these particulars are really a statement of the matters which the
defendant will seek to prove at trial from which the judge will be asked to infer the
matters of reliance pleaded in paragraph 8(b). On that basis, then, I would be
disinclined to accede to the plaintiff’s application on this point.
-- 11 of 12 --
12
[23] The plaintiff then seeks further and better particulars of the “build program”
referred to in paragraph 8(a)(iv). The plaintiff contends that the term “build
program” does not appear anywhere in the Design Contract, and that if there is
some document which records its concept, then the defendant ought identify it. The
defendant’s response was, however, a little elliptical. The defendant baldly asserted
that there could be no confusion as to the build program, because it was “at the very
heart of the proceedings”, and that it was referred to in paragraph 8(a)(iv)(C) and,
further, that it was discussed in the course of negotiations which are pleaded
elsewhere in the defence. Interesting though that information might be, it does not
actually identify precisely what the “build program” was, as referred to in paragraph
8(a)(iv). There seems to be an assumption that everyone knows which “build
program” the defendant speaks of in that paragraph. I think, however, that for the
benefit not least of the judge who is to hear this matter, let alone for the proper
purpose of particularizing the case the defendant is advancing, that it would be of
use if the particulars of that build program were properly articulated.
[24] Finally, the plaintiff seeks particulars of paragraph 8(a)(iv)(D), and specifically for
the defendant to provide the facts and matters relied on to assert that the “usual
time” for construction of a vessel as referred to therein would be approximately 12
to 14 months. The defendant says that this is a request for evidence. I agree. There
is nothing about the allegation which is ambiguous or which would leave the
plaintiff in doubt as to the case which is sought to be advanced.
Conclusion
[25] The plaintiff’s application to strike out paragraph 8 of the fifth amended defence
will be dismissed. As will be apparent from the reasons above, much of the
argument in respect of that part of the application was, in fact, directed to the
defendant’s assertion that the application was an abuse of process, and in respect of
that part of the argument I have found against the defendant. The plaintiff has been
partially successful in relation to its application for the defendant to provide further
and better particulars, while the defendant has successfully resisted several of the
matters which were the subject of the application. In all the circumstances, it seems
to me that the appropriate order for costs is that they be reserved.
[26] There will therefore be the following orders:
1. The plaintiff’s application to strike out paragraph 8 of the fifth
amended defence is dismissed.
2. Within 21 days of today, the defendant shall provide the plaintiff with
further and better particulars of:
(a) The allegation in paragraph 8(a)(iv)(B) of the fifth amended
defence that the defendant was “totally reliant upon the plaintiff”
as alleged in that paragraph;
(b) The “build program” referred to in paragraph 8(a)(iv) of the fifth
amended defence.
3. The costs of and incidental to the application will be reserved.
-- 12 of 12 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2010/160