Allen's Asphalt Pty Ltd v Kelleher [2010] QDC 444
DISTRICT COURT OF QUEENSLAND
CITATION: Allen’s Asphalt Pty Ltd v Kelleher [2010] QDC 444
PARTIES: Allen’s Asphalt Pty Ltd
(Plaintiff/Applicant)
v
Damien Francis Kelleher
(Defendant/Respondent)
FILE NO/S: BD 400 of 2010
DIVISION: Civil
PROCEEDING: Application
ORIGINATING
COURT: District Court
DELIVERED ON: 19 November 2010
DELIVERED AT: Brisbane
HEARING DATE: 23 June 2010
JUDGE: Devereaux SC
ORDER: 1. Application for judgment is dismissed
2. I will hear the parties as to further orders
CATCHWORDS: CONTRACTS: SPECIFIC – GUARANTEES – LIABILITY
OF GUARANTOR – where guarantor pleads set off of
principal debtor’s claim for damages against plaintiff’s claim
of debt for unpaid work - where principal debtor under
administration – whether the defendant has no reasonable
prospects of success.
COUNSEL: Mr G D Beacham for the applicant
Mr C A Wilkins for the applicant
SOLICITORS: James Conomos Lawyers for the applicant
Bennet and Philp Lawyers for the respondent
1. The plaintiff applies for judgment under UCPR rule 292. There is no contest,
on the pleadings, that the claim is made out. What is in issue is whether the
defendant has a valid set off sufficient to resist the application for judgment.
-- 1 of 6 --
2. The claim is brought against the defendant pursuant to a guarantee and
indemnity agreement. The defendant was the director of Kelleher Group Civil
Pty Ltd (KGC). On 27 August 2009, KGC entered into a credit agreement
with the plaintiff. On the same day, the defendant guaranteed payment to the
plaintiff of all moneys due to the plaintiff by KGC. The guarantee included the
following:
1. I will indemnify the Supplier against any losses, costs, charges and
expenses of any nature, which it might incur as a result of any default
by the Customer or arising under this Guarantee.
2. I will also be responsible to the Supplier for all outstanding monies
due now or at any time in the future for Goods supplied by the Supplier
to the Customer from time to time.1
3. The plaintiff supplied goods (a term defined to include services) and claims,
from the defendant, an amount for the goods plus other amounts payable under
the agreement between the plaintiff and KGC, namely $136,863.89.
4. The set-off is pleaded as follows. In or about April 2009, a company called
Queensland Civil Services Pty Ltd (QCS) contracted with another company,
Beech Constructions Pty Ltd (Beech) to reconstruct a car park at a shopping
centre. QCS engaged KGS to ‘enter into the necessary contracts with third
parties to complete the work required by’2 Beech. In August 2009, the plaintiff
supplied a quotation for certain works on the car park. KGC accepted the
plaintiff’s quote on the basis that the plaintiff would complete the first part of
the work by 17 September and the second part by 25 October. The plaintiff
completed phases 1 and 2 but not within those times. The plaintiff’s work in
those phases and phase 3 was of poor quality. Because of ‘the failure by the
plaintiff to complete [phases 1 and 2] by the early completion date …. and
because of the poor workmanship and quality of the [phase 1, 2A and 2b and
3]’ 3 work, Beech failed to pay QCS’s invoice of $328,880.72. QCS mitigated
its loss by negotiating a payment of ‘$170,000 in full and final payment for the
works completed by it.’4 QCS has ‘not been able to pay KGC $158,880.72
for’ 5 KGC’s work in engaging contractors to perform the works under the
agreement between QCS and Beech.
5. So, it is pleaded, KGC has a set-off against the plaintiff of $158,880.72, which
would extinguish its debt to the plaintiff. And the defendant guarantor is not,
therefore, liable to the plaintiff under the agreement to guarantee and
indemnify.
6. Mr Kelleher, the defendant, deposes that he is the director of KGC and also
was a director of QCS at the time QCS engaged in the contract with Beech
1 Statement of Claim paragraph 3
2 Defence paragraph 6
3 Defence paragraph 15(a)
4 Defence paragraph 15(b)
5 Defence paragraph 15(c)
-- 2 of 6 --
(and presumably when QCS engaged KGC). 6 He repeats, in precise terms, the
assertions pleaded in the defence, annexing some photos to show defects in the
work done. He then states that he is informed by his wife, who is now the
director of QCS, that QCS submitted invoices totalling $328,880.72 but that
Beech ‘failed to pay the invoices … as a result of the failure by the plaintiff to
complete… and because of the poor workmanship and quality....’ 7 He was
informed by his wife that QCS mitigated its loss as pleaded.
7. Given the closeness and commonality of the directors involved, Mr Kelleher
almost comically asserts:
‘KGC has requested QCS to pay the sum of $158,880.72 for the work
performed by KGC in engaging contractors to perform the works under the
[contract with Beech]. QCS has stated that it will not pay this amount due to
the poor workmanship and quality of the [works] performed by the plaintiff as
KGC’s subcontractor.’
8. There is no apparent relationship between the amount claimed by the plaintiff
from KGC and the amount invoiced by QCS to Beech. Indeed, on the
pleadings there is no apparent relationship between the work done by the
plaintiff which gave rise to the “Customer Statement” the subject of the claim
and the work referred to in the defence as untimely and poor in quality and
giving rise to the set off. How then, could KGC, let alone the
defendant/guarantor, rely on equitable set-off?
9. Two answers emerged at the hearing of the application. First, counsel for both
parties confirmed the work done which gave rise to the claim was part of the
work on the shopping centre car park complained about in the defence.
Second, the defendant/guarantor relies not only on the doctrine of equitable
set-off but also on s 553C of the Corporations Act 2001 (C’th), which
relevantly provides:
Insolvent companies—mutual credit and set-off
(1) Subject to subsection (2), where there have been mutual credits, mutual
debts or other mutual dealings between an insolvent company that is being
wound up and a person who wants to have a debt or claim admitted against
the company:
(a) an account is to be taken of what is due from the one party to the
other in respect of those mutual dealings; and
(b) the sum due from the one party is to be set off against any sum due
from the other party; and
(c) only the balance of the account is admissible to proof against the
company, or is payable to the company, as the case may be.
(2) …..
10. This provision comes into play because on 2 February 2010 the plaintiff
served a creditor’s statutory demand on KGC under s 459E(2) of the
6 Therefore, Mr Kelleher’s company QCS engaged Mr Kelleher’s company KGC to engage
contractors.
7 Affidavit of defendant paragraph 16
-- 3 of 6 --
Corporations Act. KGC did not seek to set it aside on the basis of an
offsetting claim within 21 days. But on 26 February 2010 KGC appointed an
administrator under s 436A of the Act. The deed of company arrangement
was executed on 19 April 2010.
11. The application was conducted on the basis that (1) if the plaintiff were to file
a proof of debt in the administration of KGC s 553C would require an
accounting of the unliquidated claim for damages the defendant pleads in
favour of KGC; and (2) that the defendant would be liable to guarantee only
the resultant debt, if any. That is, it was ultimately uncontested that
(a) a claim for damages could be set off against the plaintiff’s
claim;
(b) the claim for damages came within the terms ‘mutual dealings
between’ the plaintiff and KGC;
(c) the defendant guarantor could rely on any set-off established
by KGC, whether equitable or statutory.
12. Proceeding on that basis, the question becomes whether the defendant has a
real prospect – on the basis of the set-off – of successfully defending all or
part of the claim? Is there otherwise a need for a trial?8
13. The plaintiff argues the defence has no real prospect of success because the
evidence in support of the set-off is insufficient. There is little evidence of the
terms of the contract between Beech and QCS. There is no evidence (nor even
an assertion) that it was reasonable for Beech not to pay $328,880 to QCS.
There is no assertion or evidence that it was reasonable for QCS to settle its
claimed dispute with Beech by accepting $170,000 instead of $328,880. There
is no evidence of the contract between QCS and KGC, so no way to assess
whether KGG had breached its obligations to QCS. So there is no basis for
concluding that KGC was entitled to refuse to pay the plaintiff.
14. The defendant argues the set-off should be regarded as occurring
automatically at the time of the execution of the deed of company
arrangement, by analogy with the position in a winding-up.9 The question
which follows – whether at 26 February 2010 KGC was indebted to the
plaintiff taking into account its claim for damages for breach of contract or
negligence - should be decided at trial, this not being a clear case of a defence
with no real prospect of succeeding.10
15. Proof of the facts supporting the set-off is largely if not wholly within the
power of the defendant. The plaintiff was not privy to the agreements between
Beech and QCS and between QCS and KGC, nor to the dealings among those
entities which led to the asserted short-payment by Beech to QCS. The claim,
a simple one pursuant to a guarantee upon the failure of KGC to pay for goods
8 UCPR Rule 292
9 Barton v Atlantic 3 Financial (Australia) Pty Ltd (2004) 212 ALR 348 at [40-49].
10 Counsel referred to Queensland University of Technology v Project Constructions (Aust) Pty Ltd (in
liq) [2003] 1 Qd R 259; Deputy Commissioner of Taxation v Salcedo [2005] 2 Qd R 233 and other
cases.
-- 4 of 6 --
supplied (as defined), is prima facie made out. But the defendant claims to
have suffered loss as a result of the failure of the plaintiff to complete work
within expressly agreed time frames and as a result of the quality of the work,
that is, in breach of express and implied terms of the agreement between the
plaintiff and the principal debtor.
16. On the materials available, it is difficult to assess the reliability of the
defendant’s claim that KGC suffered a loss of $158,880 because of the timing
and quality of the plaintiff’s work. As the plaintiff submits, there is no
evidence that QCS reasonably settled its dispute with Beech11 and no clear
explanation for the passing on of that loss through KGC to the plaintiff. On
balance, however, I am not satisfied the deficiencies in the defence and the
materials reveal a case with no real prospects of succeeding. Rather, the
paucity of materials reveals the potential difficulties in assessing the value of
any loss KGC may have suffered as a result of the claimed breaches by the
plaintiff. Difficulty in assessing damages for breach of contract should not
prevent a party having a trial anymore than it does not deter a court from
making an assessment.12
17. In the circumstances, the application for judgment must be refused.
18. Although the principal debtor is under administration, the better view seems to
be that it should be joined as a defendant.13 The defendant argued that the
plaintiff should be ordered to join the principal debtor, because it is said such
joinder is for the benefit of the plaintiff. I favour the plaintiff’s argument that
the defendant, having asserted and sought to rely on the debtor’s set-off,
should meet the procedural laws of having that point properly determined.14
19. Mr Wilkins, counsel for the defendant, conceded the defence would need to be
wholly repleaded. Mr Beacham, for the plaintiff, sought the retention of
paragraph 1 of the defence, and Mr Wilkins did not seek to resist such an
order.
20. The plaintiff submitted that, should the application for judgment fail, the
defendant should be required to make a payment into court to secure the claim
because any defence that is permitted to continue would be “thin and
shadowy”. It may be that the strength of the claimed set-off is yet to be seen
and will not be clear until the defence is re-pleaded. I am not prepared to call
the defence thin and shadowy15 although the defendant has much to reveal.
21. Because the defence is yet to be made clear I think the costs of this application
should be reserved for the consideration of the trial judge.
11 BNP Paribas v Pacific Carriers Ltd [2005] NSWCA 72
12 See for example, HTW Valuers (Central Qld) Pty Ltd v Astonland Pty Ltd (2004) 217 CLR 640
13 O’Donovan and Phillips, Modern Contract of Guarentee (Thomson Reuters subscription service)
14 Counsel referred to the orders made in Doherty v Murphy [1996] 2 VR 553
15 Or tricky or suspicious: Duhs v Pettett [2009] QCA 347
-- 5 of 6 --
22. As to the precise form of orders, I invite written submissions from Counsel
within 7 days of this judgment, absent which, the orders will be:
1. The application for judgment is dismissed;
2. Paragraphs 2 to 16 inclusive of the Defence are struck out;
3. The defendant is given leave to file an amended defence on condition
that the defendant with due expedition take the necessary steps to apply
to join Kelleher Group Civil Pty Ltd as a defendant to the proceeding;
4. The costs of and incidental to this application be reserved.
-- 6 of 6 --
Official source: https://www.sclqld.org.au/caselaw/QDC/2010/444