Balanced Securities Ltd v Thomas [2010] QDC 355
DISTRICT COURT OF QUEENSLAND
CITATION: Balanced Securities Ltd v Thomas [2010] QDC 355
PARTIES: BALANCED SECURITIES LIMTIED
(ACN 083 514 685)
(plaintiff)
v
DAVID LIONEL THOMAS
(defendant)
FILE NO/S: DC 1453 of 2010
DIVISION: Civil jurisdiction
PROCEEDING: Application for interest and costs
ORIGINATING
COURT: Brisbane
DELIVERED ON: 22 September 2010
DELIVERED AT: Brisbane
HEARING DATE: Written submissions
JUDGE: Dorney QC, DCJ
FURTHER
ORDERS:
1. The plaintiff is awarded interest in the sum
of $1,772.70 (at the rate of 10 per centum per
annum on the judgment sum of $113,115.37
from 8 July 2010 until 3 September 2010).
2. The defendant is to pay to the plaintiff the
plaintiff’s costs of the proceeding, including
costs of and incidental to its application for
summary judgment and the defendant’s
application for summary judgment, to be
assessed on the standard basis.
CATCHWORDS: INTEREST – COSTS – whether costs on standard or
indemnity basis for particular guarantee – whether
discretionary order should be exercised (even if indemnity
basis)
COUNSEL: P. Travis for the plaintiff
M. Lyons for the defendant
SOLICITORS: Elliott May Lawyers for the plaintiff
Piper Alderman Lawyers for the defendant
-- 1 of 4 --
2
Introduction
[2] On 3 September 2010, besides there being judgment that the defendant pay to the
plaintiff the amount of $113,515.37, I ordered that the plaintiff have liberty to apply
to seek interest on the judgment sum and the defendant have liberty to respond by
submissions filed by 10 September 2010. I also ordered that the defendant’s
application be dismissed and that the parties have liberty to file submissions with
respect to costs on both applications by 10 September 2010.
[3] The plaintiff has applied for interest on the judgment sum by application filed 7
September 2010, the defendant has filed written submissions on such interest and
both parties have filed written submissions on the costs in a timely manner.
Interest on judgment sum
[4] The relevant provision, section 47(1) of the Supreme Court Act 1995, states that the
court may order that there shall be included in the sum for which judgment is given
interest at such rate as it thinks fit. There is no reason why that discretion should not
be exercised in this case.
[5] Nevertheless, the provision does permit a further discretion as to the time for which
interest should run, being the whole or any part of the period between the date when
the cause of action rose and the date of the judgment.
[6] The defendant has submitted that in enforcing a liability against a surety there must
be a demand before the action is brought, relying upon MS Fashion Ltd & Ors v
Bank of Credit and Commerce International SA (in liquidation) & Ors [1993] Ch
425 per Dillon LJ at 447. The defendant further submits that the making of a
demand in this case was, at the least, an implied term of the guarantee contained in
the Facility Agreement and that, accordingly, the cause of action against the
defendant did not arise until the demand was made for payment by the defendant
pursuant to the guarantee, particularly in circumstances where a demand could not
have been made for any definite sum until the costs were assessed against the
borrower, and the actual extent of liability thus ascertained. The submission further
contended that, since there is no evidence before the District Court of a demand
being made on the defendant prior to the service of the claim and the statement of
claim in this proceeding, the claim in the proceeding for costs should be held to be
the relevant demand, with the result that the discretion to award interest should only
be exercised from the date when the claim and the statement of claim were likely
served.
[7] I accept that the arguments made by the defendant have traction in this particular
case. After all, what has been sought by the plaintiff here is simply an amount of a
costs judgment against the relevant “borrower”, whose liability for such the court
has found that the defendant guaranteed. It matters not for present purposes whether
the demand is a requirement of an implied term or a pre-condition to enforcing
liability. A proper demand could not have been made until 6 May 2010 in any
event.
-- 2 of 4 --
3
[8] Since there has been no evidence led before me by the plaintiff as to the date of
service of the originating documents in this proceeding, I take the date of the Notice
of Intention to Defend as the appropriate starting date. At least there is certainty
about it, and not speculation. That date is 8 July 2010. As to the rate to be applied,
in the absence of any evidence being led by either party as to any other appropriate
interest rate, I adopt the rate applicable to interest on default judgments set out in
Practice Direction No 6 of 2007, namely 10 per cent per annum. Thus, for the 57
days to 3 September 2010 at a daily interest rate of $31.10, the interest calculation
yields $1,772.70.
Costs
[9] Although the plaintiff’s written Outline of Argument on costs submits that the
plaintiff and defendant had agreed by way of the Facility Agreement that the
plaintiff was entitled to its costs on an indemnity basis under circumstances that
include this proceeding, I hold that that has not been established. To this end, I
accept, in general terms, the written submissions of the defendant in relation to the
issue of costs, at least insofar as they are concerned with the costs being on the
standard, rather than the indemnity, basis.
[10] By r 681(1) of the Uniform Civil Procedure Rules the costs of an application in a
proceeding are in the discretion of the court but follow the event unless the court
orders otherwise. There is absolutely no basis upon which the court should order
otherwise in this case where the relevant events are, first, the successful application
by the plaintiff for summary judgment and, secondly, the unsuccessful application
by the defendant for summary judgment.
[11] The real issue here is the basis for assessed costs. Clause 5.2(a)(ii) of the Facility
Agreement is relied upon by the plaintiff, as it must, if it wishes to recover legal
costs and expenses on a “full indemnity basis”. But, as pointed out by the
defendant, that particular provision depends upon a “demand” being made by the
plaintiff on the relevant borrower (Joelco Pty Ltd). In turn, because of the way this
proceeding has been conducted, there has been no evidence of a demand by the
plaintiff on Joelco for the costs incurred by the plaintiff in this proceeding. Joelco
was simply not a party to this proceeding. And the plaintiff has not sought any costs
against Joelco with respect to this proceeding. This has the consequence that there
is no liability pursuant to Clause 5.2(a)(ii), with the consequent effect that there are
no “Moneys Hereby Secured” within the meaning of Clause 1.1 from that source.
[12] The construction of the Facility Agreement does not, in my view, allow a claim to
be made on an indemnity basis by the plaintiff against the defendant in this
particular proceeding. If, nevertheless, I were to be wrong about that conclusion,
since any contractual right is simply one factor to be considered in the exercise of
the relevant discretion, I conclude that it is appropriate in these particular
circumstances that, were such a contractual right to exist, since the contractual right
would be derived by a very indirect process, it should not be exercised in this case:
cf Mid Australia Pty Ltd v Around Australia Pty Ltd [2004] QSC 091 at [22]-]23].
[13] Thus, the defendant should pay the plaintiff’s costs of and incidental to each
application, and of the proceeding, on the standard basis.
-- 3 of 4 --
4
Orders
[14] Pursuant to the conclusions reached:
1. The plaintiff is awarded interest in the sum of $1,772.70 (at the rate of 10
per centum per annum on the judgment sum of $113,115.37 from 8 July
2010 until 3 September 2010).
2. The defendant is to pay to the plaintiff the plaintiff’s costs of the proceeding,
including costs of and incidental to its application for summary judgment
and the defendant’s application for summary judgment, to be assessed on the
standard basis.
-- 4 of 4 --
Official source: https://www.sclqld.org.au/caselaw/QDC/2010/355