Anstead Constructions P/L v Stillwater Investments P/L [2010] QDC 38
DISTRICT COURT OF QUEENSLAND
CITATION: Anstead Constructions P/L v Stillwater Investments P/L
[2010] QDC 38
PARTIES: Anstead Constructions Pty Ltd ABN 55 097 667 411
(Plaintiff)
v
Stillwater Investments Pty Ltd ABN 53 082 165 151
(Defendant)
FILE NO/S: No: 2732 of 2006
DIVISION: Civil
PROCEEDING: Application for costs and interest
ORIGINATING
COURT: District Court of Queensland
DELIVERED ON: 24 February 2010
DELIVERED AT: Brisbane
HEARING DATE: Written submissions – 16 February 2010
JUDGE: Andrews SC DCJ
ORDER:
JUDGMENT FOR THE PLAINTIFF IN THE SUM OF
$36,620.35 INCLUSIVE OF INTEREST
ORDER THAT THE DEFENDANT PAY THE PLAINTIFF’S
COSTS OF THE PROCEEDING ON AN INDEMNITY BASIS
TO AND INCLUDING 9 FEBRUARY 2010 TO BE
ASSESSED
CATCHWORDS: Supreme Court Act 1995 (Qld) s 47
Uniform Civil Procedure Rules 360(1)
Codelfa Construction Pty Ltd v State Rail Authority of NSW
(1982) 149 CLR 337 applied
COUNSEL: G Coveney for the Plaintiff
L A Jurth for the Defendant
SOLICITORS: John Nagel & Co for the Plaintiff
Mahoney Lawyers for the Defendant
[1] On 9 February 2010 I gave reasons indicating an intention to give judgment for the
plaintiff in this proceeding in the sum of $26,102.73. The plaintiff was not then
ready to argue interest and costs. The issues of interest to be included in the
judgment and costs were reserved pending written submissions from the plaintiff
-- 1 of 4 --
2
and the defendant was given liberty to provide written submissions. Each party has
provided written submissions.
Interest
[2] The plaintiff applies for interest pursuant to s 47 of the Supreme Court Act 1995
(Qld) (“the Act”). It seeks simple interest at nine per cent per annum from 13
October 2005 to 30 June 2007 and at 10 per cent per annum from 1 July 2007 to the
date of judgment. The defendant makes no submissions as to the plaintiff’s method
of calculation or the rates of interest. Instead the defendant relies upon the terms of
the contract, submitting that no interest should be allowed.
[3] Clause 11.9 of the contract provided:
“11.9 Interest payable on outstanding payments
If the Owner fails to make any payment to the Builder
within the time for payment under this Contract the Builder
is entitled to interest on the outstanding amount at the rate
specified in Item 24 of the Schedule, payable from the time
for payment until the date of payment”.
At Item 24 of the Schedule to the contract the parties inserted the figure “0.0”. By
that, they indicated their intention to agree that no interest would be payable
pursuant to the contract if the defendant failed to make payment to the plaintiff
within the time for payment under the contract.
[4] The contract was terminated on 5 October 2005. The plaintiff claims interest from
13 October 2005. The plaintiff instituted proceedings in the Commercial and
Consumer Tribunal. The proceedings ended in that Tribunal after the defendant
brought a claim for relief under the Trade Practices Act 1974 (Cth). Because of that
claim proceedings were instituted in this court. The claim under the Trade
Practices Act was abandoned by the defendant during the trial. The plaintiff
instituted proceedings in this court on 20 September 2006.
[5] By the contract the parties did not expressly exclude the operation of s 47 of the
Act. Should a term be implied? In a case, like the present, where the parties have
attempted to reduce their agreement to a formal contract complete on its face, the
five conditions for the implication of a term are settled. 1 A term excluding the
operation of s 47 of the Act would fail to satisfy three of the five conditions for
implication of a term. It is not equitable to deprive parties of a statutory right to
interest where the court in exercising its discretion to award interest will necessarily
consider what is equitable. It is not necessary to give business efficacy to the
contract and the contract is effective without it. It is not so obvious that the parties
intended to exclude the operation of s 47 of the Act that “it goes without saying”. I
find that it was not the intention of the parties to exclude the operation of s 47 of the
Act. If the parties in this case had made it clear that their intention was that neither
party should be liable to the other party for interest pursuant to s 47 of the Act, that
intention would be a relevant matter for the court to consider. The parties did not.
1 Codelfa Construction Pty Ltd v State Rail Authority of NSW (1982) 149 CLR 337 at 347 per Mason
J with Stephen and Wilson JJ concurring
-- 2 of 4 --
3
The wording of the contract suggests that the parties intended that no interest would
accrue if payment under the contract was made within a reasonable time. I take that
into account in considering how to exercise the discretion.
[6] I propose to allow interest from about two months after the contract was terminated
and to apply the interest rates submitted for by the plaintiff and to allow interest
until 9 February 2010 as submitted for by the plaintiff for that is the date when the
plaintiff would ideally have been ready to argue the point. Interest is payable for
573 days to 30 June 2007 in the sum of $3,688. Interest is payable for the period
from 1 July 2007 to 9 February 2010, in the sum of $6,829.62. Interest ordered
under the Act is included in the judgment sum. Interest which should be included in
the judgment sum for the plaintiff is $10,517.62. Accordingly there should be
judgment for the plaintiff in the sum of $36,620.35 inclusive of that interest.
Costs
[7] The plaintiff’s solicitors wrote on 23 January 2008:
“We confirm our client is prepared to resolve the issues on the basis
that each discontinues proceedings and meets his own costs.”
The plaintiff’s solicitors wrote on 7 February 2008:
“Our client has instructed us that he is prepared to resolve the issues
on the basis that each party abandons its claim and each party meets
its own costs. The offer made is open for acceptance for a period of
five (5) working days from the date of this letter.”
[8] The defendant’s counsel does not dispute the submission that each of those letters
was a genuine offer of compromise which allowed sufficient opportunity to the
defendant to consider the offers and to respond.
[9] On 1 September 2008 the plaintiff’s solicitors made an offer pursuant to Chapter 9
Part 5 of the Uniform Civil Procedure Rules that each party release the other from
all claims arising out of and incidental to the proceedings; that each party
discontinue the claim against the other and that each meet its own costs. That offer
was left open for 14 days.
[10] No offer was accepted. The plaintiff’s offer to settle pursuant to the Uniform Civil
Procedure Rules was an offer which was no less favourable to the defendant than
the judgment. The ordinary rule would see the plaintiff awarded indemnity costs
from September 2008, in accordance with the Rules unless the defendant shows
another order for costs is appropriate. It did not make submissions as to why another
order was appropriate. Instead, it made submissions to the effect that the ordinary
rule of costs on a standard basis should apply though without explaining why that
should be or why UCPR 360(1) should not apply. The plaintiff also submitted that
the genuine offers of compromise contained in the earlier letters justify an award of
indemnity costs implying that this would be of advantage to the plaintiff by
permitting an order for costs to be made from as early as 23 January 2008. The
effect of UCPR 360(1), where its conditions are met, is to provide for indemnity
costs to be ordered from the commencement of the proceeding and not simply from
the date of the offer. The conditions are met in this case. The defendant should not
-- 3 of 4 --
4
be liable for the costs since 9 February 2010 as the plaintiff should have been in a
position to argue costs and interest on that day.
[11] I order that the defendant pay the plaintiff’s costs of the proceeding to and including
9 February 2010 on an indemnity basis to be assessed.
-- 4 of 4 --
Official source: https://www.sclqld.org.au/caselaw/QDC/2010/038