Anstead Constructions P/L v Stillwater Investments P/L [2010] QDC 37
DISTRICT COURT OF QUEENSLAND
CITATION: Anstead Constructions P/L v Stillwater Investments P/L
[2010] QDC 37
PARTIES: Anstead Constructions Pty Ltd ABN 55 097 667 411
(Plaintiff)
v
Stillwater Investments Pty Ltd ABN 53 082 165 151
(Defendant)
FILE NO/S: No: 2732 of 2006
DIVISION: Civil
PROCEEDING: Trial
ORIGINATING
COURT: District Court of Queensland
DELIVERED ON: 9 February 2010
DELIVERED AT: Brisbane
HEARING DATE: 2, 3,4 and 6 February and 11 March 2009
JUDGE: Andrews SC DCJ
ORDER: JUDGMENT RESERVED PENDING WRITTEN
SUBMISSIONS IN RESPECT OF INTEREST AND COSTS
CATCHWORDS: BUILDING CONTRACT – where cost plus contract – where
builder orally estimated cost at $80,000 but agreed to
insertion of estimated cost at $75,000 - whether builder’s
estimate not fair and reasonable – whether builder in breach
of Domestic Building Contracts Act s 55(2)
BUILDING CONTRACT – DAMAGES - where cost plus
contract – where breach of contract by builder – where
contact terminated by agreement – where owner entitled to
damages for cost to rectify works – whether owner entitled to
cost to complete works
BUILDING CONTRACT – DAMAGES – assessment of
damages
Domestic Building Contracts Act 2000 s55(2)
COUNSEL: G Coveney for the Plaintiff
L A Jurth for the Defendant
SOLICITORS: John Nagel & Co for the Plaintiff
-- 1 of 12 --
2
Mahoney Lawyers for the Defendant
Nature of the disputes
[1] The plaintiff is a builder which did renovation work on the defendant’s house. Their
disputes are over what works were the subject of the contract, whether work done
was in breach of contract, whether the contract was terminated by the owner for
breach, whether the owner’s damages for breach include the cost to complete
unfinished work. The builder claims $30,488.93 as the balance owing under a
standard form Master Builders “cost plus” building contract in writing. The owner
alleges that when the contract was signed the builder did not comply with a
statutory obligation 1 to include a fair and reasonable estimate of the total amount the
builder was likely to receive. The figure of $75,000.00 was inserted as the estimate.
The owner submits that figure was not a fair and reasonable estimate and that the
consequences are that the contract is void2 and unenforceable and that the builder’s
right to payment is reduced by statute3 to the cost of providing the contracted
services plus a reasonable profit, subject to that amount not being unfair to the
owner. The owner submits the proper result is that it is entitled to a refund for
overpayment of $5,930.00 and damages for breach of contract of $36,582.45. By
the end of oral submissions the builder conceded the owner’s entitlement to a set-off
for damages for the builder’s breaches of contract in the sum of $4,322.50.
[2] Some work was incomplete when the builder ceased work. The owner alleges that
work done in breach of contract requires rectification. More controversially, the
owner alleges that incomplete work requires completion at the builder’s expense.
The owner claims a declaration that the contract is void, voidable or unenforceable
pursuant to s 93(1)(a) Domestic Building Contracts Act 2000 ( the Act ) and seeks a
declaration that the builder is liable in restitution for overpayment made by the
owner to the builder.
[3] The owner has abandoned a claim for remedies pursuant to section 87 of the Trade
Practices Act 1974 (Cth). That claim was significant when made by the owner
because it could not be litigated in the Commercial and Consumer Tribunal where
litigation between the parties commenced. Because of that claim, the matter came to
this court. Costs are not awarded in the Tribunal for such a dispute as this.
The works initially agreed
[4] The builder was a licensed building contractor at all material times. The builder and
the owner entered into a contract in writing on 22 August 2005 being in a standard
form styled “Queensland Master Builders – Cost Plus (Residential)”4 . At Item 3 of
the contract form it provided a space after a heading “DESCRIPTION OF
WORKS”. Into the space Mr Kuenstner for the owner inserted problematically
vague words: “Rennovations as directed by owner.” (sic) There is a dispute as to the
works which were the subject of the contract. Resolving that dispute is easier if the
discussions about the scope of works are set out chronologically.
1 Domestic Building Contracts Act 2000 (Qld) s 55 (2)
2 Domestic Building Contracts Act 2000 (Qld) s 93 (1)(a)
3 Domestic Building Contracts Act 2000 (Qld) s 55 (4)
4 Exhibit 5
-- 2 of 12 --
3
[5] Negotiations were done for the builder by Mr Smith and for the owner by Mr
Kuenstner. Each was a director of the corporate party he represented. Mr Smith had
a contractor’s license for as long as they have been required and a builder’s license
since 2000. Mr Kuenstner lived at the home with his wife and children. Mr Smith
met Mr Kuenstner at the site as a result of receiving a telephone call from Mr
Kuenstner in July 2005. That month, at the house, Mr Kuenstner showed Mr Smith
where he wanted some small renovations to be done. Those renovations included
relocating steps, changing a wall and fitting a door. Mr Smith estimated that the
builder would charge about $7,000.00 to $8,000.00 for such work. Following that
meeting Mr Kuenstner rang again to say he had an interior designer and that the
scope of work he wanted done had changed. In early August 2005, Mr Kuenstner
rang again to say that he had a lot more work in mind than had been discussed. Mr
Smith went to the house again to discuss with Mr Kuenstner prospective work. It
was prior to the 15th August. On 8 August 2005, Mr Kuenstner sent by facsimile a
detailed schedule of works for renovations. At that time the builder had not been
engaged.
[6] There is a dispute as to whether one page or two were sent by facsimile. Mr Smith
recalls receipt of one page, but not of the second page. It seems implausible that Mr
Kuenstner would have sent one page only. I accept his evidence that two pages were
sent. The content of the facsimile was essentially a draft prepared by Mr Kuenstner
of renovation works he wished to have done, identifying in most cases a contractor
to perform the task, the entity to manage performance, a starting date for various
jobs and an estimate of time to complete various jobs. It contained an estimate of
prices for about half of the items. It would have been an appropriate document to
refer to in any discussion of scope of works and estimates of prices. The document
which is exhibit 18 is a copy retained by Mr Kuenstner of the facsimile sent though
exhibit 18 bears handwriting added by Mr Kuenstner afterwards. I accept Mr
Kuenstner’s evidence that an identical document was produced by him at the time
of a discussion with Mr Smith and reject the contrary evidence of Mr Smith. I
accept Mr Kuenstner’s evidence that the discussion was on about 13 August 2005
and find that it was on that day that Mr Kuenstner wrote on the document a list of
costs as a result of advice from Mr Smith.
[7] Mr Kuenstner made handwritten notes on his copy of the document he had sent by
facsimile to Mr Smith. The notes appear on exhibit 18. In particular, notes on the
last page detail items under a notation “basis of estimate, Les Smith”. Those details
written in by Mr Kuenstner included certain prime cost items estimates of their cost,
an estimate of their total cost of $90,000.00 with a further $20,000.00 estimate for
the builder’s “cost plus” component. Those amounts written by Mr Kuenstner did
not repeat all of the typed items and were not all of the costs which would have
been incurred by the owner had the whole of the typed list of works been done.
Thus, for a component of the works Mr Kuenstner had been led by Mr Smith to
contemplate a cost of the order of $90,000.00 and about another $20,000.00 payable
to the builder. The parties did not then make an agreement that the builder would for
complete the works for the estimated prices.
[8] I do not find dishonesty against Mr Smith arising out of the rejection of his evidence
that the facsimile was of one page and his evidence that it was not the subject of
discussion. There are plausible explanations for Mr Smith’s failure to recall receipt
of the second page. He gave evidence that the list of works set out in the facsimile
did not become the subject of an agreement between him and Mr Kuenstner and was
-- 3 of 12 --
4
not produced to him when the two men were negotiating orally about the scope of
the works on the day when the contract was later signed. Instead, he gave evidence
of several discussions with Mr Kuenstner during which the scope of the works Mr
Kuenstner proposed varied and of agreement being reached on 22 August 2005
before signing the contract that the builder do works Mr Kuenstner identified
without reference to the list in the facsimile. If this evidence is accepted, the second
page of the facsimile would not have been of much significance to a builder in Mr
Smith’s position and the list of works and prices contained in the facsimile would
have been superseded by subsequent discussion about particular work and prices.
[9] On 15 August 2005 Mr Smith went to the site with some of his workers to discuss
with them the work which they should do. On 16 August work started on the site.
The work done then over three days was the demolition of an existing patio and
demolition of a bar-be-que and some bricks. It would not have been necessary to
conclude agreement about the scope of prospective works before undertaking the
demolition. The parties had not concluded agreement as to the scope of the works
when demolition commenced.
[10] On 22 August the contract was signed. Mr Kuenstner’s evidence was that the words
he inserted into the contract at item 3 “Description of Works” being the words
“Rennovations as directed by owner” were sufficient to identify the works. His
evidence was they were sufficient because he and Mr Smith had previously agreed
that the builder would do all the works set out in the schedule he had sent by
facsimile being the typed words appearing in exhibit 18. It is the owner’s case that
the works set out in exhibit 18 became the scope of works which the builder was
obliged to perform. The owner relies upon more than the oral testimony of Mr
Kuenstner.
[11] In addition, the owner refers to the builder’s pleading in the reply at paragraph
3(l)(ii) which alleged that “on about 22 August 2005 and prior to the defendant’s
entering into the contract, at the site, the plaintiff (by Mr Smith) and the defendant
(by Mr Kuenstner) prepared a list (the list of items of work that the defendant
wanted done at the site)”. The owner submits that no written list was produced and
that Mr Smith agreed that the facsimile5 was the only document capable of being a
detailed description of works under the contract. The owner’s submissions imply
that the “list” referred to in the builder’s reply must be a fantasy because the builder
did not produce it in court. The reply did not give particulars of whether the list was
written or of its author.
[12] Mr Smith gave evidence about his meeting with Mr Kuenstner on 22 August 2005.
According to Mr Smith, Mr Kuenstner nominated certain of the works which he
wanted to be done and Mr Smith gave him prices for those works. Mr Kuenstner
wrote the various prices down on a piece of paper. Mr Smith did not receive Mr
Kuenstner’s notes or a copy of them. The total came to $80,000.00. The
uncertainties created by the builder’s ambiguous pleading about a “list” and the
confusion shown by Mr Smith under cross examination about the pleading did not
cause me to reject his evidence that Mr Kuenstner nominated only certain works
which led to Mr Smith’s estimate.
5 Exhibit 18.
-- 4 of 12 --
5
[13] Mr Smith gave evidence which I accept that Mr Kuenstner, on 22 August 2005
nominated the following works to be done:
• Sheet exposed bricks inside the house;
• Extend kitchen walls;
• Fill a doorway;
• Remove a kitchen window;
• Remove a big lounge room window, brick up the lower
portion of the space created and install a smaller window
above the bricks;
• Rebuild the patio;
• Downstairs, remove three sets of louver windows and replace
two of them with aluminium sliding windows and brick up
the space created by the removal of the third set;
• Downstairs, demolish the existing cellar and build an office
area.
[14] I accept this evidence because of the figure which appears in the contract at item 6
for “Estimated Total Cost Of The Works”. That figure entered into the contract on
22 August 2005 was $75,000.00. The figure is substantially less than the
$110,000.00 which Mr Kuenstner wrote as Mr Smith’s estimate for works discussed
on about 13 August 2005 by reference to the facsimile. There was no evidence or
submission to the effect that the estimate was reduced from $110,000.00 to
$80,000.00 on account of some demolition work already performed. The most
obvious rational explanation is one consistent with Mr Smith’s evidence that the
works nominated that day by Mr Kuenstner were less than the works for which a
higher estimate had been given. The figure of $75,000.00 was written in by Mr
Kuenstner. It leads me to reject Mr Kuenstner’s argument that he and Mr Smith
agreed that the works to be done were all of the works set out in Exhibit 18 and it
leads me to reject the owner’s argument that “Rennovations as directed by owner”
should be interpreted as referring to the typed items in Exhibit 18.
[15] Mr Kuenstner asked if Mr Smith could reduce the figure for “Estimated Total Cost
of the Works” to $75,000.00. Mr Smith agreed. At trial Mr Smith explained that he
agreed because the contract was a cost plus contract and the owner was going to pay
for all the costs and would pay the builder an agreed margin.
[16] It is not obvious why Mr Kuenstner would ask for the estimate of $80,000.00 to be
reduced to $75,000.00 if Mr Kuenstner was contemplating a cost plus contract. The
estimate was not guaranteed by the builder to be the total cost. Whatever figure was
inserted as the estimate, the contract required the owner to pay the builder all actual
costs and expenses paid by the builder in the construction of the works and to pay
the builder 20 per cent of all the actual costs and expenses paid by the owner and the
builder in the construction of the works. The amount to be paid was not limited by
the estimate inserted. There was no obvious financial benefit to the owner and no
obvious financial detriment to the builder caused by reducing the estimate inserted
in the contract. Mr Smith expressed the opinion that Mr Kuenstner was trying to
save the owner some fees which the owner may have been obliged to pay to the
Building Services Authority. I accept that this was Mr Smith’s opinion. I make no
finding as to Mr Kuenstner’s motive for the request. I accept that the figure of
$75,000.00 was written into the contract by Mr Kuenstner after Mr Smith had
-- 5 of 12 --
6
estimated $80,000.00 as an appropriate figure to insert in the contract. I accept that
the estimate made by Mr Smith was for works which were less than the scope of
works set out in exhibit 18 and was for the works Mr Kuenstner orally nominated
on 22 August 2005 before the contract was signed.
Is the contract void?
[17] When the contract was signed there was a statutory obligation6 upon the builder to
include a fair and reasonable estimate of the total amount the builder was likely to
receive under the terms of the contract. The figure of $75,000.00 was inserted as the
estimate. The owner submits that figure was not a fair and reasonable estimate and
that the consequences are that the contract is void 7 and unenforceable and that the
builder’s right to payment is reduced by statute8 to the cost of providing the
contracted services plus a reasonable profit, subject to that amount not being unfair
to the owner.
[18] If the builder estimated about $110,000 on 13 August and then estimated $75,000
for the same works on 22 August, the owner submitted that, prima facie, the lower
estimate was not fair and reasonable. The submission is attractive but its premise is
unsound. The owner’s submission was premised upon my finding a fact which I
have not found, namely that the agreed works for which an estimate of about
$110,000.00 was made on about 13 August were the same as those for which an
estimate was made on 22 August.
[19] The builder does not dispute that the contract is a “regulated contract” to which
Domestic Building Contracts Act 2000 s 55 applies. It provides:
“55 Cost plus contracts
(1) A building contractor must not enter into a cost plus contract
that would be a regulated contract unless—
(a) the contract is included in a class of contracts prescribed
under a regulation; or
(b) the cost of a substantial part of the subject work can not
reasonably be calculated without some of the work
being carried out.
Maximum penalty—100 penalty units.
(2) A building contractor must not enter into a cost plus contract
that would be a regulated contract unless the contract contains
a fair and reasonable estimate by the building contractor of the
total amount the building contractor is likely to receive under
the contract.
Maximum penalty—100 penalty units.
(3) If a building contractor enters into a cost plus contract in
contravention of this section, the building contractor can not
enforce the contract against the building owner.
(4) However, the tribunal may, on an application made to the
tribunal by the building contractor, award the building
contractor the cost of providing the contracted services plus a
6 Domestic Building Contracts Act 2000 (Qld) s 55 (2)
7 Domestic Building Contracts Act 2000 (Qld) s 93 (1)(a)
8 Domestic Building Contracts Act 2000 (Qld) s 55 (4)
-- 6 of 12 --
7
reasonable profit if the tribunal considers it would not be
unfair to the building owner to make the award.”
[20] I accept the owner’s submissions that the section required the builder to ensure that
the contract contained an estimate, that Mr Kuenstner’s selection of the figure of
$75,000.00 and his writing of the estimate did not absolve the builder of its statutory
obligation, that the estimate must be the builder’s estimate, that the estimate must be
fair and reasonable at the time of contracting and that the estimate was to include
the builder’s cost plus fee of 20%.
[21] The owner pleaded that the builder breached its statutory obligation and accepted in
oral submissions that it bears the onus of proof of this factual matter. The owner
also submitted that there was a shifting onus because Mr Smith orally estimated
$80,000.00. The owner submitted that it must follow that the builder’s acceptance
of $75,000.00 could have no reasonable basis. I do not accept that submission. If
$80,000.00 was a fair and reasonable estimate it is plausible that a 6.25% reduction
below $80,000.00 was also a fair and reasonable as falling within a reasonable
margin to allow for uncertainties. There was no evidence that it was not plausible.
The issue of whether $75,000.00 could not be reasonable if $80,000.00 was
reasonable was not alleged the owner’s pleadings and was not explored by either
counsel with Mr Smith. There was no sufficient evidence to satisfy me that
$80,000.00 and $75,000.00 were not fair and reasonable estimates when made for
the scope of works discussed on 22 August 2005.
[22] The owner has not satisfied me that the contract contravened the Domestic Building
Contracts Act s 55(2). It is not void. In that circumstance the builder’s claim for
payment for work done for $30,488.93 which was the subject of unpaid invoice 171
is not disputed by the owner and it becomes unnecessary to calculate the builder’s
claim on the hypothesis of a void contract being the amount to which the builder
would have been entitled under s 55(4) for that work and other work for which he
was paid. The owner’s claim for a declaration that the contract is void, voidable or
unenforceable pursuant to s 93(1)(a) Domestic Building Contracts Act 2000 fails.
Termination of the contract
[23] Much time was devoted during the trial to the issue of whether the contract was
terminated by mutual agreement or by the owner for breach by the builder. Each
accepts that the contract was terminated on 5 October 2005. The owner submitted
that the manner in which the contract came to an end is only relevant in the event
that the contract was not declared unenforceable. The reason that the owner
requires that this issue be determined appears to be based upon a concern by the
owner that there is doubt as to whether the owner would be entitled to claim
damages for breach of contract if the contract was terminated by mutual agreement.
[24] I find that the contract was terminated by mutual agreement. That is the effect of
the evidence given by Mr Smith. It is consistent with the evidence given by
Mr Kuenstner at trial. It is consistent with the owner’s solicitors’ letters of 19
October and 2 November 2005 which purport to set out the owner’s instructions
about termination.
[25] The finding of termination by mutual agreement rather than termination by the
owner for breach by the builder does not prejudice the owner. The consequence of
-- 7 of 12 --
8
the termination was that each party was discharged from any future obligations
pursuant to the contract whilst preserving existing rights. The existing rights
preserved include the owner’s right to damages for losses suffered by the owner
from the builder’s breaches of contract occurring before termination. The issue of
whether there was termination for breach can be significant in a case where the
builder has agreed to perform the works for a fixed price. In such a case the owner’s
damages for the builder’s breach of contract would include the amount by which the
cost of the works exceeds the contract price for the works. In such a case the cost to
complete unfinished work has relevance to damages. It does not have the same
significance where, as here, the builder has not agreed to a fixed price. The owner
has not sought to prove that the works were completed by others at a cost which is
higher than the builder would have been entitled to charge pursuant to the terms of
the contract.
Owner’s damages
[26] When the builder left the site after the termination of the contract the works which
the builder had contracted to perform were incomplete. If the builder had continued
with the work after 5 October 2005 until completion of the works it would have
been entitled to seek payment for the further works in accordance with the terms of
the contract. By establishing that certain works were incomplete when the contract
was terminated the owner does not establish that it suffered damages for breach of
contract. The contract in issue in this trial was not a contract to complete works for
a fixed price but rather to perform them for costs and expenses and a percentage of
costs and expenses. By establishing that the owner paid or needs to engage other
contractors to complete work left unfinished by the builder, the owner does not
establish loss. The owner is entitled to the cost to rectify work where the need was
caused by the builder’s breach of statutory and contractual warranties.
[27] The evidence of the costs incurred by the owner to rectify work was not always
separated from evidence of the costs incurred to complete work left unfinished
when the contract was terminated. As a result, there are instances where it is not
possible to determine from the evidence what portion of a cost can be attributable to
the need to rectify defective work caused by breach of contract and for which the
owner is entitled to damages and what portion is attributable to the cost of
completion of work for which the owner has no entitlement to damages.
[28] The owner’s claim for damages for the cost of rectifying defects was reduced to
$36,582.45 by the time of oral submissions.
Apron flashing
[29] The owner claims $11,998.80 for defective apron flashing on the roof and for the
cost of tie downs for patio posts and patio rafters. The builder does not contest the
owner’s entitlement to damages for the apron flashing but contests the quantum.
The owner based the claim in submissions upon exhibit 22, an invoice for labour to
do 148½ hours work and for some materials. Ten and a half hours of the labour are
identified in the invoice as relating to work including work related to flashings. It is
unclear how much of the ten and a half hours was attributable to flashings
rectification. $96.20 of the cost of materials can be seen to relate to flashings. I am
unable to determine from exhibit 22 what part of the cost is attributable to the apron
flashing defect. The builder concedes that it is appropriate to allow $250.00 for this
-- 8 of 12 --
9
item in accordance with the evidence of Mr Dickson who regarded that as
appropriate for labour but did not regard it as necessary to purchase materials. The
owner bears the onus of proof. The owner has satisfied that onus to the extent of an
allowance of $250.00 for labour and the material cost of flashing shown in the
invoice of $96.20.
Patio post tie down and patio rafter tie down
[30] The builder contests the owner’s entitlement to damages for tie downs. The owner
relies upon exhibit 22 for the quantum. It is not possible by referring to exhibit 22
to determine what portion of the labour cost or of the cost of materials is attributable
to the relevant tie downs. The builder contests this claim on another basis too. I
accept the builder’s submission that the tie downs installed after the builder left the
site were not the cost of rectifying defective work but were more properly the cost
of completing work. However, if the builder had installed the appropriate tie downs
at an earlier time before various building elements were fixed into place the owner
would have saved the cost of removal of various building elements required to
access the areas of concern. I accept the evidence of Mr Dixon that it is appropriate
to allow 16 hours labour for this. The labour charges in exhibit 22 were a minimum
of $40.00 per hour. The builder does not contest the damages to the extent of
$640.00. The owner has satisfied its onus of proof of this issue to the extent of
$640.00.
Soffit Sheeting
[31] The owner claims $2,340.00 for the cost of removal and replacement of soffits.
Contemporary building practices with respect to soffits are different from those of
50 years ago. The builder placed new soffit sheeting and timber moulding on to the
original soffit frame. I am not satisfied that there was a breach of contract by the
builders’ selection of this method rather than a more contemporary method
preferred by Mr Fritz. The evidence of Mr Dixon is that the proper remedial cost
for defective workmanship by the builder is an amount of $800.00. The builder
concedes for this item an amount of $1,000.00. I assess damages for this item at
$1,000.00.
Soffit Venting
[32] The owner claims $940.00 being the amount of an estimate by Mr Fritz for
scaffolding and for labour to install vents in soffits. Mr Fritz reported that it had
become more expensive to install the soffits at the end of the job because of the
need to erect and dismantle scaffolding. I accept the evidence of Mr Smith to the
effect that it was appropriate practice for the builder not to fit the vents because they
would be removed by the painting contractor and instead to allow the painting
contractor to fit vents. As a result, I do not find a breach of contract arising out of
the builder’s failure to fit vents at the time that the builder installed the soffits. I
disallow the claim for scaffolding as an extra cost because the cost of scaffolding
does not arise from a breach of contract. I disallow the claim for the other labour
costs of installing the vents because it is an expense which would have been payable
by the owner to the painting contractor or to the builder.
Patio Ceiling
-- 9 of 12 --
10
[33] Ceiling sheeting was fixed as part of the scope of work done within a new roof over
the patio at the site. The rafters to which the sheeting was attached were at spaces
greater than 600 mm centres which was contrary to the recommendations of the
manufacturer of the plasterboard ceiling sheets. As a consequence, there was
undulation showing in the sheets. At the time the builder left the site the patio
ceiling had been fixed to the rafters but had not been set, sanded or painted. The
builder accepts that it is appropriate for the owner to have as damages the costs of
removal of the sheeting. The builder contends that it should not be liable for the
cost of sanding and painting and installation of rafters because that is not a loss
caused by its breach of contract because they are costs of completing the work
rather than of repairing it. I accept that this distinction must be drawn. The owner’s
evidence does not distinguish what part of expenses met by the owner with respect
to the patio ceiling were the costs of remedying the defects. The builder allows a
sum of $1,600.00 in its submission. I accept that concession and assess damages
under this head at $1,600.00.
Chimney Flashing
[34] The owner claims $660.00 in respect of this item by reference to an invoice exhibit
24 for that amount. The claim is inconsistent with the evidence of the plaintiff’s
expert witness that the defect “has been addressed by the roofer at his cost”. I am
not satisfied that a defect in chimney flashing has arisen as a result of a breach of
contract by the builder. I am not satisfied that the owner has suffered a loss in the
amount claimed.
Guttering
[35] The owner claims $602.00 for this heading. Mr Fritz in his report exhibit 3 refers to
the incorrect shape of guttering used as a replacement to a section of roofing above
and forward of the front entry stairs and said that it was a defect which had been
rectified. The allegedly defective guttering was removed and replaced for $602.80.
The owner has not by its pleading alleged that the defect was caused by breach of
contract. I accept the builder’s submission that, in these circumstances, no amount
should be allowed for the item.
Office Wall
[36] The builder constructed an office wall under the house. The area was already tiled
with floor tiles. The partition wall which was constructed was made parallel by the
builder to the external perimeter wall. That is normal practice. By constructing it
parallel with the external perimeter wall an aesthetic problem arises in that the wall
constructed does not follow the lines created by the floor tiles. I accept that this
result is not ideal. I am not satisfied that the method of construction has arisen as a
result of a breach by the builder of contract. Rectification would cost $1,500.00.
Because I find no breach, I do not allow this sum.
Lounge Ceiling
[37] The owner claims $9,822.00 as the estimated cost to remove and replace the ceiling
in the lounge room. The original fibrous plaster ceiling in the lounge room was
cracked and undulating when the builder was engaged. Two choices available to
the owner were to have the builder remove and replace the ceiling or to fix a
-- 10 of 12 --
11
replacement ceiling below and onto the existing ceiling. Removal and replacement
would have been more expensive than fixing a replacement ceiling onto the existing
ceiling. After consulting with Mr Kuenstner, the builder used the cheaper method.
[38] Mr Kuenstner gave evidence that he saw undulations in the finished ceiling. I
accept his evidence, though I am unable to say whether those undulations were
sufficient to amount to evidence of breach of contract. Despite the undulations seen
by Mr Kuenstner, after the builder left the site the owner had the lighting and air-
conditioning ducts installed in it and had it painted.
[39] I accept the evidence of Mr Dixon that when he inspected the ceiling from the
lounge room floor and was directed by Mr Kuenstner to an area he nominated as
being of concern, Mr Dixon was unable to detect any undulation though he looked
at the area from different angles and different light conditions. I find that at the time
of Mr Dixon’s inspection, such undulation as may have existed was not so great as
to lead to a finding of a breach of contract by the builder.
[40] A concern arises from the method used by the builder of attaching new sheeting to
the old. The possibility arises that the old sheeting can be expected to sag
progressively over time because of the extra weight from the fresh sheeting.
[41] There has been some sagging of the ceiling since the time of Mr Dixon’s first
inspection. It is difficult to say that it was caused by the builder because it is highly
likely that the areas of concern have since been subjected to the weight of workmen
in the roof space and it is difficult to determine the cause of any subsequent sagging.
I accept this evidence of Mr Dixon. He estimated that it would be appropriate to
reduce the undulation by screwing, patching and painting at a remedial cost of
$500.00 and that it would be inappropriate to upgrade the finish in the way
recommended by Mr Fritz as the result would achieve a quality finish exceeding the
original construction undertaken 50 years before. I accept the evidence of Mr
Dixon in that regard.
[42] Despite Mr Dixon’s evidence that remedial work of $500.00 is required, the builder
admits that $800.00 is appropriate. I allow that item.
Council Approval
[43] The owner claims $3,437.50 being an amount due or paid to a consulting engineer.
Particulars of the work done by the consulting engineer are set out in exhibit 26
being an invoice. The builder was obliged by clause 10.1(a)(iv) of the contract to
carry out the works in accordance with all relevant laws and legal requirements.
[44] Local authority approval was required. To obtain it, it was necessary to obtain
suitable plans prepared by a licensed drafts-person or designer so that those plans
could be submitted with the application for approval.
[45] The cost of obtaining such plans and an approval are not a proper subject for
damages for breach of contract if the owner would have been obliged to meet those
costs had the builder complied with the obligation at clause 10.1(a)(iv) of the
contract.
[46] Mr Kuenstner gave evidence that the owner could have obtained for no charge the
services of a drafts-person to prepare the necessary drawings to submit with an
-- 11 of 12 --
12
application for local authority approval and that that drafts-person would not have
charged the owner for that work. There was no evidence called from the drafts-
person to that effect. The builder objects to the evidence of Mr Kuenstner being
received as evidence of the truth of the opinion of Mr Kuenstner. On the hypothesis
that the builder’s failure to obtain at the owner’s expense or advise the owner that
plans were required was a breach of contract, in the absence of evidence from the
drafts-person I am not satisfied that the owner has suffered damages in the sum
claimed. I am not persuaded on the admissible evidence that the owner has been put
to a greater cost of submitting drawings with an application to the local authority
than it would have paid if the builder had properly advised it to obtain plans.
Special Damages
[47] The owner claims $450.00 as special damages being inspection fees paid to the
Master Plumber’s Association of Queensland. The claim was first raised in
submissions. It is supported by exhibit 27 and referred to by Mr Fritz as an
inspection fee incurred to identify defects in the roof. It has not been established
that the defects were due to a breach of contract by the builder. It is not a matter
which was the subject of a pleaded claim. I reject the submission that it should be
allowed as special damages.
SAI Global Invoice
[48] The builder claims $73.15 being an amount paid to SAI Global related to metal
cladding. It has not been the subject of a pleaded claim and it has not been
established to have been an expense incurred as a result of a breach of contract by
the builder.
Conclusion on Counterclaim
[49] As a result of those findings, the owner is entitled on its counterclaim to damages in
the sum of $4,386.20. The owner seeks to set that amount off against the amount of
the builder’s claim.
Conclusion
[50] There should be judgment for the builder in the proceeding in the sum of
$26,102.73. I will hear the parties as to the matters of interest and costs about
which they have made no submissions.
-- 12 of 12 --
Official source: https://www.sclqld.org.au/caselaw/QDC/2010/037