Chew v Queensland Building Services Authority [2010] QCAT 501
CITATION: Chew v Queensland Building Services Authority
[2010] QCAT 501
PARTIES: Ms Aida Chew
v
Queensland Building Services Authority
APPLICATION NUMBER: QR111-08
MATTER TYPE: Occupational regulation matters
HEARING DATE: 17 August 2010
HEARD AT: Brisbane
DECISION OF: Mr Barry Cotterell
DELIVERED ON: 13 October 2010
DELIVERED AT: Brisbane
ORDERS MADE: The Building Services Authority’s decision not to
direct rectification of building work is confirmed
CATCHWORDS : Review proceedings - whether work defective or
incomplete – whether BSA should issue a Notice
to Rectify to the building contractor - Queensland
Building Services Authority Act, sections 72 and
86(1); Queensland Civil and Administrative
Tribunal Act section 24
APPEARANCES and REPRESENTATION (if any):
APPLICANT : Ms Aida Chew was represented by Mr P
Maddugodda
RESPONDENT: Queensland Building Services Authority was
represented by Ms C Farthing
-- 1 of 11 --
QR111-08 / Page 2 of 11
REASONS FOR DECISION
1. This application seeks a review of the Authority’s decision of 22 April 2008 not
to direct rectification of building work which the Authority is empowered to do
by section 72 of the Queensland Building Services Authority Act (“QBSA Act”).
The Applicant did not attend the Tribunal hearing but was represented by Mr
Maddugodda and, to a lesser extent, by her expert Mr de Costa. Mr
Maddugodda represented the Applicant throughout much of the period that the
building work was carried out and afterwards. The BSA was represented by
Ms Farthing, a legal officer and it called evidence from Mr Vosper, a Building
Services Authority Inspector, Mr Robert Hughes, an Engineer and Mr Rod
Mehrtens, the contractor.
Background
2. The Applicant prior to purchasing this house obtained a building report from
Queensland Independent Building Inspectors Pty Ltd dated 21 March 2007. As
this report stated:-
“The concrete is out of level from north west to south east across the front
bedroom of approximately 35mm and is out of level from north to south
across the family room of approximately 65mm. This is considered to be
considerable and we recommend a further inspection to include a slab
survey by a structural engineer.”
3. The Applicant then obtained a report from Mr de Costa, an Engineer. Mr De
Costa subsequently prepared a pre and post underpinning structural
assessment dated September 2007 where, in relation to the pre underpinning,
he stated –
“Subsequent to a site inspection by the structural engineer (Mr de Costa)
the following recommendations were made –
It was unlikely that substantial further settlement would occur
considering the age of the house although it was possible to
determine the degree of consolidation taking place by taking a soil
sample it would be sufficient to monitor settlements for a period of 2
years before taking further action.
If any visible signs of further distress such as cracking brickwork or
interior walls would appear properly engineered remedial work needs
to be carried out to restore the house to a stable condition. This
work should be designed, supervised and certified by Registered
Professional Engineer Qld (RPEQ)…. “
4. No engineering report was prepared at this stage and these recommendations
were made verbally on 15 March 2007 at site to the owner’s representative,
presumably Mr Maddugodda. According to Mr Maddugodda, as part of the
negotiations for the Applicant to purchase the property, the seller agreed to pay
for some remedial work to be done on the house. This is apparently the
reason why the Applicant proceeded with obtaining a quote for work at this
time contrary to Mr de Costa’s recommendation to wait and observe if any
“substantial further settlement would occur”.
-- 2 of 11 --
QR111-08 / Page 3 of 11
5. According to Mr de Costa, Mr Maddugodda told him he obtained a cheap quote
to do “the work” but this was some time after the work had been done as Mr de
Costa was not further consulted until the work had been finished by the
contractor. Despite Mr de Costa’s recommendation he was not commissioned
by the Applicant to design, supervise or certify the work.
6. It became clear to the Tribunal at the hearing that at least Mr Maddugodda’s
expectation of what was to be achieved by the work was significantly different
from what he assisted the Applicant to contract with the contractor to do in
accordance with the scope of work of the contract.
7. The Applicant entered into the contract with Merhtens Holdings Pty Ltd (“the
contractor”) to perform underpinning work at 41 Taralga Road, Guranava. The
contract consisted of quotation 100325 of 27 March 2007 and a minor works
contract schedule signed by Mr Merhtens on 30 April 2007 and the Applicant
on 15 May 2007.
8. The quotation set out the scope of works and provided as follows:
“I’ve inspected the property at the above address to assess the subsidence
and supply a quotation.
Arrange for engineering design and inspections
Remove and replace 1 concrete squares where (sic) under pinning is
required (please note the concrete may not be the same colour and
shape as the existing)
Construct (3) concrete piers and headstocks in the following areas:
to the south west subsided corner
Support the footing to the pier while the intermediate piers are being
constructed
After the concrete peering has taken place, we will jack the footings
and brickwork back to the appropriate level determined by Mehrtens
underpinning of construction
Cap the headstocks to the footing for permanent support
Remove and dispose of all waste material and leave the area clean
and tidy.
9. The amount quoted for this work was $10,062.25.
10. The Contract was subject to conditions and of relevance it stated under the
heading jacking,
“Jacking we require the house to be unoccupied and all valuables which
are in the area of the underpinning to be removed (we take no responsibility
for any damage caused during the jacking). Jacking the footings and
brickwork back to the appropriate level is based on the footing being strong
enough to be able to be jacked where when commencing jacking we
concentrate on closing up brickworks. Levelling of the internal slab can
only be assessed when we start jacking, in most cases the slab will follow
brickwork; however we cannot guarantee the underpinning will correct the
internal slab.”
-- 3 of 11 --
QR111-08 / Page 4 of 11
11. According to Mr Mehrtens upon commencement of the works the contractor
discovered that the area had been previously underpinned and a previous
underpinning had not been founded on suitable substrate material. The
previous underpinning consisted of a wall of concrete 2.4 metres long by 1.6
metres deep and 450mm wide sitting about 250mm above natural ground level.
With Mr Maddugodda’s consent the method of rectifying the area was then
varied to incorporate the previous underpinning works to be performed by the
contractor under the contract. The site was inspected on 16 May 2007 by the
contractor’s engineer Mr Graham Moulston of Graham Moulston & Associates,
who advised the contractor on the design of the underpinning and
subsequently certified the works as evidenced by the form 16 inspection
certificate.
12. The contractor completed the works on 23 May 2007. The Tribunal accepts
the above facts which were not disputed by Mr Maddugodda at the hearing.
13. Approximately 8 months later, on or about 31 January 2008, the BSA received
a complaint from the Applicant in relation to the works carried out by the
contractor. The complaint alleged:
a) The works had been illegally performed without appropriate planning
approval; and
b) Cracked brickwork to the chimney resulting from the works performed by
the contractor had caused a water leak to the internal facet of the fire place.
14. On 11 April 2008 Mr Vosper, a Building Inspector employed by the BSA,
carried out an inspection of the property and determined that;
a) Local authority planning approval was not warranted for the works
b) The contractor had acknowledged and rectified the brickwork by re-pointing
the brickwork
c) The works performed by the contractor were not defective or negligent and
d) The matter of achieving the appropriate level of jacking was a contractual
issue that the authority did not have jurisdiction to adjudicate.
15. Following the building inspection, by letter of 22 April 2008, the BSA notified
the Applicant of the outcome of the inspection (“the decision”).
16. On 19 May 2008 the Applicant filed a review application in the former
Commercial and Consumer Tribunal, now the Queensland Civil and
Administrative Tribunal, seeking to review the decision. On 7 August 2008 the
BSA filed its statement of reasons for the decision. The statement of reasons
had been prepared on the basis that the decision constituted a decision not to
direct rectification to rectify to the contractor to rectify the revised works. On 15
September 2008 the Applicant filed material in the Tribunal and the Applicant’s
material included a document titled the Structural Engineer’s Statement of
Evidence, which is a report prepared by Mr de Costa. The BSA filed, as part of
its material, an affidavit sworn by Mr Mehrtens, Managing Director of the
contractor, dated 16 October 2008 and an affidavit by Mr Vosper dated 16
October 2008.
-- 4 of 11 --
QR111-08 / Page 5 of 11
17. On 20 January 2010 the Authority engaged structural and geotechnical
engineer, Mr Robert Hughes of Hughes Beal and Wright Consulting Engineers,
to attend the property and inspect the works. On 21 January 2010 Mr Hughes
and Mr de Costa attended an experts conclave at the Tribunal. At the experts
conclave Mr Hughes and Mr de Costa agreed and disagreed on a number of
facts which are outlined in the experts joint report.
18. On 21 June the Authority filed a statement from Mr Hughes which annexes his
report dated 1 February 2010. On or about 2 July the Applicant filed a
statement of Mr de Costa.
19. Of relevance from the joint report is the agreement that the two (2) engineers
expressed as follows:
“The installation and jacking from just 3 concrete blocks could never have
restored the substantial tilt on the house floor to its original constructed
level or even have lifted it significantly.”
The Law
20. This is an application for review commenced pursuant to section 102 of the
CCT Act in reliance on section 87 of the QBSA Act which provides as follows:
“A person affected by a reviewable decision of the authority may apply, as
provided under the QCAT Act, to the tribunal for a review of the decision.”
21. The Tribunal referred to in section 87 of the QBSA Act is now the Queensland
Civil and Administrative Tribunal. Section 86(1) of the QBSA Act relevantly
provides:
(1) The tribunal may review the following decisions of the authority—
…
(e) a decision to direct or not to direct rectification or completion of tribunal
work;
22. Pursuant to section 75 of the QBSA Act, “Tribunal work” “includes the
renovation, alteration, extension, improvement or repair of a building”. This
contemplates the underpinning work performed by the contractor at the
property. This proceeding involves the decision of the Authority not to direct
rectification of the works at the Applicant’s property. Relevantly the decision of
22 April 2008 states;
“It seems resolution of the dispute relates to contractual issues. The BSA
cannot be an adjudicator of the contractual issues in any dispute unfortunately
in this instance the BSA is not able to provide you with any further assistance.”
23. Pursuant to section 24 of the QCAT Act the Tribunal may in a proceeding or a
review of a reviewable decision:
a) Confirm or amend the decision under review
b) Set aside the decision under review and substitute his own decision or
-- 5 of 11 --
QR111-08 / Page 6 of 11
c) Set aside the decision under review and return the matter for
reconsideration to the decision maker for the decision with the directions
the Tribunal considers appropriate.
24. The Tribunal stands in the shoes of the Authority and makes the decision as at
the date of the hearing and has effect from when the reviewable decision takes
or took effect. Relevantly section 24(2) of the QCAT Act provides as follows:
(2) The tribunal’s decision under subsection (1)(a) or (b) for a reviewable
decision—
(a) is taken to be a decision of the decision-maker for the reviewable
decision except for the tribunal’s review jurisdiction or an appeal under
part 8; and
(b) subject to any contrary order of the tribunal, has effect from when the
reviewable decision takes or took effect.
25. The Authority’s power to require rectification work lies in section 72 of the
QBSA Act and provides how to require rectification of building work:
(1) If the authority is of the opinion that building work is defective or incomplete,
the authority may direct the person who carried out the building work to
rectify the building work within the period stated in the direction.
(2) In deciding whether to give a direction under subsection (1), the authority
may take into consideration all the circumstances it considers are
reasonably relevant, and in particular, is not limited to a consideration of the
terms of, including the terms of any warranties included in, the contract for
carrying out the building work.
…
26. Relevantly the term “building work” is defined in schedule of the QBSA Act and
underpinning is building work because it involves repair or rectification works to
a building. The term “defective” is also defined in schedule 2 of the QBSA Act
and provides as follows:
“Defective in relation to building work includes faulty or unsatisfactory.”
27. The power of the Authority to require rectification of building work must be
exercised in accordance with the objects of the QBSA Act which are set out in
section 2 of the QBSA Act.
28. The relevant principles to be applied by the Tribunal in an application to review
a decision to issue or not to issue a direction are well settled and are:
a) The Tribunal in exercising its discretion pursuant to section 72 of the QBSA
Act stands in the position of the Authority.
b) The Tribunal must consider the competing interests of the parties involved
in fact as such as blame worthiness of the owners and the cause of the
defective building work irrelevant.
c) In exercising its discretion the Tribunal must give consideration to the
circumstances mentioned in the defects policy.
-- 6 of 11 --
QR111-08 / Page 7 of 11
d) The Tribunal must take into account all of the evidence including the
circumstances raised at the Tribunal hearing.
29. In proceeding such as this the Tribunal must consider 3 issues:
a) Is the building work defective and or incomplete?
b) Is the contractor responsible for the defective building work?
c) Is the decision not to direct rectification reasonable in the circumstances?
The alleged defects identified by the Applicant appear in the Applicant’s
complaint, by way of summary the complaint identified the following:
a) The works were performed by the contractor in a defective manner
b) The works were not completed by the contractor
c) Cracked brickwork to the chimney resulted from the revised works
performed by the contractor had caused a water leak to the internal face of
the fireplace. However this item of complaint has been previously rectified
by the contractor and is not an issue in these proceedings.
Was the building work defective?
30. According to the opinion of Mr Hughes with regard to defective building work,
he gave evidence that the written contract between the owner and the
contractor had been adhered, three (3) underpins were installed and some
jacking took place. There is no defect as the result of the construction of the
underpins or the jacking and, if there is no defect, there is nothing to rectify.
31. The Tribunal accepts the contractor’s evidence that it constructed piers below
the existing underpinning of 700mm by 450mm containing y16 bars and sitting
on the natural ground as referred to in the diagram by its engineer Mr Moulston
and certified by him.
32. The scope of the contract provided that the contractor would lift the dwelling to
a level determined appropriate by the contractor. The contract did not require
the contractor to jack the footings to any particular level but rather required the
contractor to determine the appropriate level.
33. The Tribunal accepts the evidence from the BSA witnesses that the contract
has been adhered to because three (3) underpins were installed and some
jacking took place. Neither the construction of the underpins nor the jacking is
defective.
34. The Applicant, through Mr Maddugodda, alleges that the original defect was
the inclination of the main slab of the entire dwelling and the contractor was
engaged to remedy this defect in its entirety. This statement contemplates that
the Applicant envisaged that the works undertaken by the contractor (that is
three (3) underpins) would restore the dwelling back to its original level. Both
Mr de Costa and Mr Hughes agreed that, “the installation and jacking from just
three (3) concrete blocks could never have restored the substantial tilt in the
house floor to its original constructed level or even have lifted it significantly”.
-- 7 of 11 --
QR111-08 / Page 8 of 11
35. The Tribunal accepts that:
a) Upon completion of the contract the slab was not restored to a level position
and
b) The work undertaken by the contractor does not satisfy the Applicant’s
expectations.
36. The Tribunal accepts that the work which the Applicant contracted with the
contractor to perform was of a much more limited nature and related to the
installation of three (3) piers in the south west corner of the house. The
Tribunal rejects the Applicant’s allegation that the works undertaken by the
contractor pursuant to the contract are defective because the house was not
restored to a level position. The Tribunal accepts the BSA’s submission that
the question of achieving the appropriate level of jacking is a contractual issue
and the Tribunal also accepts that the BSA does not have jurisdiction to
intervene in contractual disputes.
Cracking of the concrete slab
37. There are a number of minor cracks in the concrete slab on the verandah. The
Applicant asserts that these cracks are “very likely due to attempted jacking”
and this amounts to defective work.
38. The Tribunal accepts the BSA’s submission based on the evidence of Mr
Hughes that these minor cracks are probably the result of concrete shrinking
and that there is no evidence that the cracks were caused by the works
undertaken by the contractor.
Was the building work incomplete?
39. The term completed must be read in the context of the phrase in which
appears the words should be given its ordinary meaning of finished. The
QBSA Act and the defects policy fix a point in time by reference to which the
building work was either finished or left in an incomplete state. Mr Hughes
gave the opinion that it is his view that the work is complete as the written
contract dated 15 May 2007 has been complied with and there is no mention in
the contract that the intention was to jack the building back to its original
constructed level. It is further stated by Mr Hughes that if the contract had
required the building to be jacked back to its original constructed level the work
would be incomplete but that it was never remotely possible for this to be done
from just three (3) underpins. Both experts accept that this was never possible
as stated above. Mr de Costa’s opinion on the incomplete building work was
as follows:
“The work is incomplete because of the fact that the slab did not lift at all and
as it is clear from the report by the contractor dated 1 August 2007 which
states:
“Our piers went under this concrete and jacking was carried out raising the
brickwork to the original level.”
-- 8 of 11 --
QR111-08 / Page 9 of 11
That the contractor very well understood the owner’s expectation (as he was
telling the owner that he had completed the expected work) disproves that the
agreed primary intention of the two (2) parties was to lift the slab.”
40. This “report” dated 1 August 2007, according to Mr Mehrtens, was an internal
document generated by one of his workers and he was puzzled as to how the
Applicant came to be in possession of it. It is clearly not addressed to anyone
and is not signed by anyone. The Tribunal’s interpretation of this report
differed from that of the Applicant’s.
41. Based on the evidence of what occurred, the Tribunal finds that the piers went
under the concrete piers previously placed there by others in the void down to
natural ground level. The slab and brickwork was maintained in the original
level prior to the contractor commencing. The original level of the time the
house was constructed is unknown and was not part of this work.
42. Continuing with Mr de Costa’s opinion:
“The first item of the contract “engineering design” which was a vital part of
the contract was not carried out. If this was commissioned to an engineer
he would have ordered necessary investigation, performed proper
calculations and the lifting must have been successful. In this regard the
party to conduct engineering design led to all the subsequent problems and
failures. As the main item was not completed the work is incomplete. If the
engineering design was properly commissioned and slab did not lift, it is a
negligent act of the engineer.”
43. Mr de Costa’s opinion in this quote is based on Mr de Costa’s lack of
knowledge of what was done by the contractor in compliance with the
directions of his engineer, Mr Graham Moulston. The Tribunal is satisfied on
the basis of the evidence that the contractor did commission an engineer and
act on the engineer’s design. This design was only committed to writing on 27
April 2008 and perhaps if this had occurred earlier, and been provided to the
Applicant, some of the misunderstandings that have occurred could have been
avoided.
44. Mr De Costa went on to say:
“The second item of the contract “remove and replace concrete squares”
was never performed thus work is incomplete. This statement implies
provision of an internal pin which was replaced by the ineffective pin on the
extreme corner which was easier to do.”
45. Mr Mehrtens gave evidence that removing and replacing the concrete squares
were not necessary because the verandah footings and the house footings
were joined. However the pin at the extreme corner was installed.
46. Mr de Costa’s last criticism is that:
“The owner or the owner’s representative did not have any clue as to
whether the building could have been lifted using just three (3) pins
-- 9 of 11 --
QR111-08 / Page 10 of 11
(because they are not engineers). They relied entirely on the contract and
to provide expertise in that regard.”
47. This lack of clarity by Mr Maddugodda as to what he wanted or expected from
the work arose at least partly from the fact that the Applicant did not follow Mr
de Costa’s advice to have the work designed and supervised by a registered
engineer. Instead the Applicant purchased the property and sought through Mr
Maddugodda a low priced contract to do work without clearly setting out what
the Applicant wanted to achieve from that work. The contract price in the
Applicant’s mind may well have been limited by what the seller was prepared to
pay towards the work but this was not in evidence and is not relevant to the
Tribunal’s decision.
48. On about 29 may 2007 the contractor issued a certificate of warranty which
signed the completion of the works. Mr Graham Moulston, the contractor’s
engineer, signed a form 16 certifying the works on completion on 24 May 2007
and on 27 April 2008 he issued a plan showing the piers as constructed.
49. The Tribunal finds that the building work was completed and therefore finished
when the works subject to the contract were performed by the contractor and
certified as such by Mr Moulston on 24 May 2007. Further the Tribunal finds
that for the purposes of section 72 of the QBSA Act the building work is not
incomplete.
Is the builder responsible?
50. The contractor is responsible for the building work the subject of the contract.
The scope of the work is determined by the contract although it is apparent the
Applicant contemplated that the underpinning works would cure the subsidence
in its entirety, the Tribunal finds this position is misconceived.
51. The contract never provided for such an extensive scope of work, it merely
provided for the construction of three (3) piers to the south west subsiding
corner of the dwelling. It would be unreasonable for the BSA to direct
rectification of the subsidence in its entirety when this is clearly beyond the
scope of the contract.
52. The Tribunal has found that the works are neither defective nor incomplete.
Subsequently the Tribunal accepts that the BSA cannot direct the contract to
rectify the work.
53. In the joint report Mr de Costa made remarks which the Tribunal needs to
address as his comments are as follows:
“De Costa’s opinion on irregularity of the contract is work procedure
and QBSA’s subsequent enquiry which he thinks important
The work was carried out in an illegal manner, a manner not expected from
a license builder because his work involved modification of the foundation
not merely the foundation of minor structural element. The contractor was
aware of the fact that he should carry out engineering design but did not do
it. He did not conduct credited soil investigations and submission for
council approval. The QBSA (the Authority) should have appointed a
-- 10 of 11 --
QR111-08 / Page 11 of 11
qualified person to the initial investigation, someone who understands
engineering. Their obligation to the community as well as their own interest
to investigate the matter so that the legality of the work could have been
properly understood. Before even attempting to find defects legality of the
work would have been checked more thoroughly by the Authority. As the
foundation of the house is one of the most important structural elements
there is no way that this work can be considered as covered by section 8 of
the Building Regulation 2006 which applies to only minor structural
components.
The contract is designed to let the contractor avoid rectification of defective
work because there are conditions written in fine letters stating that the
contractor does not take responsibility for damages done during the
underpinning process in one case strictly according to the contract
whatever the defects found would become a “contractual issue” and
therefore QBSA easily can avoid giving directions to the contractor to rectify
interpreting the issue as contractual. However under section 72(2) of the
QBSA Act the Authority’s empowered to consider all relevant circumstances
not only the terms stated in the contract.”
54. These comments by Mr de Costa are more those expected from an advocate
than from an expert bound by the experts obligations to the Tribunal. It came
out in the hearing that Mr de Costa had also reported Mr Moulston and Mr
Mehrtens to the Board of Professional Engineers for what Mr de Costa wrongly
thought happened in relation of the job. The Board cleared both Mr Moulston
and Mr Mehrtens according to letters provided to the Tribunal. Mr de Costa’s
comments are based on an inaccurate knowledge of what transpired and lack
of understanding of the role of the BSA. Mr de Costa’s campaign against the
BSA may have been responsible for the Applicant pursuing this application
which has now been unsuccessful.
55. The Tribunal accepts the BSA’s submission that the decision of 22 April 2008
not to direct rectification of building work should be confirmed. The
consequence of the Tribunal confirming the decision of 22 April 2008 is that no
direction to rectify will issue to the contractor.
-- 11 of 11 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2010/501