Duggan v Berry t/a Hotondo Homes Yeppoon [2010] QCAT 409
CITATION: Duggan v Berry t/a Hotondo Homes Yeppoon
[2010] QCAT 409
PARTIES: Ms Ellen Joyce Duggan
v
Mr Neville Berry t/a Hotondo Homes Yeppoon
APPLICATION NUMBER: BD418-08
MATTER TYPE: Building matters
HEARING DATE: 17 & 18 June 2010
HEARD AT: Rockhampton
DECISION OF: P McGrath – Presiding Member
DELIVERED ON: 18 August 2010
DELIVERED AT: Rockhampton
ORDERS MADE: 1. That the Respondent pay the Applicant the
sum of $3340.94 within 60 days.
2. That the Respondent complete the deck
staining as agreed by 30 September 2010.
CATCHWORDS : Domestic Building dispute
APPEARANCES and REPRESENTATION (if any):
APPLICANT : Ms Ellen Joyce Duggan appeared in person.
RESPONDENT: Mr Neville Berry t/a Hotondo Homes Yeppoon
appeared in person.
-- 1 of 8 --
BD418-08 / Page 2 of 8
REASONS FOR DECISION
1. This application was filed by Ellen Duggan in the Commercial and Consumer Tribunal on
20 November 2008 and a subsequent defence was filed by Neville Berry trading as
Hotondo Homes Yeppoon on 27 November 2008.
2. There are a number of claims by the Applicant Ms Duggan and her claims have been
amended as the proceedings have continued originally through the Commercial and
Consumer Tribunal and now through the Queensland Civil and Administrative Tribunal.
3. The application related to the erection of a house property by Hotondo Homes (here and
after called the builder) for Ms Duggan (here and after called the owner) at Lot 60 Miami
Crescent Pacific Heights, Yeppoon in the state of Queensland.
4. The matter was heard in Rockhampton on 17 June 2010 and both the owner and the
builder appeared. The owner called a witness, Mr Terry Bishdon and the builder called
one witness, Mr Brad Crook. I have taken into accoun the evidence of these witnesses
as well as the evidence of the parties themselves.
5. There are some 11 claims by the owner against the builder and there are some counter
claims in reply. I propose to deal with each of the items in the claim sequentially to
determine whether or not the claim and or the counter claim if appropriate should be
allowed.
Claim One
6. This relates to the rectification of retaining works from 0.5 of a metre to 1 metre of solid
ground as per the original plans before the council amendment for which no notification
was allegedly given by the builder to the owner and was made without a signed variation.
The owner states that there is an estimate of approximately $3263.00 to rectify the
retaining works.
7. The residential contract to build the property was signed on 7 September 2007. The
plans for the property were approved by the Livingstone Shire Council on or about the 19
September 2007. Apparently council regulations required an amendment to the plans
which required a concation of the retaining wall of the retaining wall on the western
boundary. The owner states that the amendment on the western boundary from 1.5 to 2
metres resulted in the distance between the house and the retainging works on the
eastern boundary being reduced from 1.5 of a metre which meant she was unable to get
round the corner of her house with any gardening equipment and there was
consequently a drop of 1.8 metres at this point on the property.
8. The builder states that there was discussion with respect of the truncation of the retaining
wall and that an engineer, Mr Mark Hull suggested the truncation. The builder admits he
did not notify the owner of the variation of the retaining wall as per the contract.
9. The builder states that the minor works contract was signed for a retaining wall with a
maximum height of 1.8 metres to be constructed as per the quotation but no application
was made to the Council by the builder to amend the western boundary from 1.5 metres
to 2 metres, this amendment was made by Council when approving plans on or about 19
September 2007. The builder states that the house could not have been moved closer to
-- 2 of 8 --
BD418-08 / Page 3 of 8
the road as it is located the minimum distance of 6 metres from the front boundary and
the developers covenant requirements provided that the building shall be 2 metres from
the side boundary for 2 storey dwellings. To move the wall further away from the house
would have meant increasing the height of the wall above the 1.8 metres allowed in the
contract.
10. Mr Bishdon provided an estimate to extend the retaining wall which did not include
drawing new plans, new engineering and new council approval. The builder states that
this would be required as it would be a new wall over 1.8metres high and would require a
new contract. The builder estimates the total cost of the new retaining wall including
revised plans, engineering and council approval would be $5,000 and again 160mm
would not warrant that expenditure. The owners accusation against the council was
referred to the BSA resulting in the BSA upholding the council decision and no loss had
been incurred, according to the builder.
11. Whilst the owner might have suffered some inconvenience in the relocation of the
retaining works they were done subject to council approval and in the circumstances her
claim in this respect is disallowed.
Claim 2
12. Claim 2 relates to the widening of a stair case inside the property. The owner states that
she made a verbal request that the internal stair case be widened from 900mm to
1100mm. 900mm is the internal measurement of the stair case as shown on the house
plan. On 15 April 2008 the owner signed a variation to widen the internal stair case and
she did not check the measurement until after she had moved into the house. The
internal measurement is 990mm, which is confirmed by Mr Bischdon in his evidence. In
reply the builder stated that the 900mm refers to the overall measurement of the
staircase including the springers and rails and this was widened as per the variation
sought by the owner.
13. In reply the builder stated that the rails are now 1100mm apart but that does not mean
that the distance down the stairs would be 1100mm. The measurement from the top of
the rails is 1100mm but it has to take into account a distance between the wall and the
steps going down to the ground floor and it was not possible to have the same width at
the top of the staircase as at the bottom. The owner claims a refund of $2500 in relation
to this claim. I am satisfied that the builder varied the width of the staircase at the top as
sought by the owner and therefore this claim must fail.
Claim 3
14. Claim 3 relates to the decking and the exterior wood finish to the decking. The owner
states that 3 coats of Sikkens exterior wood finish were included in the contract. After
approximately 4 months after moving into the house the wood finish was showing
significant signs of erosion. The owner states that this was placed on a 6 months
maintenance list which was due on 22 February 2009 and provided to the builder on 13
February 2009. The builder apparently, by letter of 30 March 2009 stated that –
“The coating was applied as directed, it is the owners responsibility to continue
maintenance as per the maintenance guide given on handover”.
-- 3 of 8 --
BD418-08 / Page 4 of 8
The owner states that she contacted the Sikkens representative who said that 3 coats of
Sikkens should not erode within 4 months and a query was forwarded to her to be
completed by both the painter who applied the finish and the builder to determine what
“had gone wrong”. The painter applied the wood finish with a pad adaptor as application
was not recommended by spray, roller or applicator pad.
15. The maintenance guide provided that all hard wood decks should be left uncoated for as
long as possible until all the extractives have leached from the timber fibres and the
timber is thoroughly dry. For very dense, slow drying timbers such as spotted gum
(which this was) it is recommended a minimum of 6 months or more.
16. The builder agreed that the decking needed to be recoated and had proposed to do so
although because of an unusual amount of rain in early 2010 the recommendation was
that the recoating be left until at least September. The issue was that the moisture
content should be under 18% before recoating should it take place. The builder stated
that the painting of the deck was applied appropriately after being sanded the builder
agreed to recoat the deck and the Tribunal is of the view that this should be done as
soon as the appropriate moisture level has been reached, in the circumstances this
should be done no later than 30 September 2010.
Claim 4
17. Claim 4 relates to the progress payments made by the owner to the builder apparently
there was a changed methodology with respect to the payments. The owner states that
when the contract was signed on 7 September 2007 the owners daughter, Miss Selina
Berry, went through the contract with her. The owner states that she believes an
inadequate explanation was given to her from the change from method A to method B.
She was not advised that method A contract built to all stages is the standard
“designated stages” and the stages listed in method B were significantly altered. Method
A would involve a percentage ratio of 30% up until the enclose stage and 70% for the
following stages whereas method B was changed up to the enclosed stage and 30% for
the following stages. The owner states that the consequences of the change in
percentage rates meant that in various stages of the contract the amount she owed the
builder was significantly less than the work that was still to be done and that the builder
benefited greatly by receiving 70% of the contract before the enclosed stage. The owner
states that she paid $4,210.57 in interest under method B as opposed to $1263.00 that
she would have paid under method A, being a difference of $2,947.00 which she is
claiming.
18. The builder states that the methodology of progress payments was explained to the
owner, she signed the methodology B as did the builder and it is clear on the face of it
the owner was aware of what she was up for by way of progress payments at each stage
of the construction. The builder stated that methodology B relates to a multi story house
as opposed to methodology house as opposed to methodology A which relates to a
single story premises. The Tribunal is satisfied that the owner was aware of the progress
payment methodology and accordingly in her claim for interest is disallowed.
Claim 5
19. This relates to the timber decking and other flooring in the premises, the Applicant states
that the contract which was signed on 7 September 2007 included black butt select grade
-- 4 of 8 --
BD418-08 / Page 5 of 8
timber flooring and spotted gum decking. It was the responsibility of the builder to supply
and lay this flooring. The decking was to be supplied and installed by Northern Rivers
Timbers. The owner states that she advised Miss Selina Berry during the signing of the
contract on 7 September 2007 that Northern Rivers Timbers would require 3 months
notice to ensure the availability of the timber and that she advised the builder on at least
1 other occasion that 3 months notice was required.
20. The owner states that at a later date which is unknown she was verbally advised by the
builder that Northern Rivers Timbers would no longer be supplying and installing the
timber as per the contract as the timber was unavailable and that the cost for transporting
the timber to Yeppoon were far higher than originally quoted. The owner states on 3 May
2008 she discovered that the partially laid decking timber was not 140 x 25mm as
specified but was 130 x 19mm. She complained to the builder about the change in
contract in variation credit of $1500 was signed by her. This amount was for the different
size that he partially laid.
21. The owner states that she requested on several occasions a copy of the invoice in
respect to the timber but this was refused and she wasn’t able to establish the grade of
the timber. By email of 11 June 2008 the builder stated –
“Our contract price is to build your house is a fixed price contract this means that I do
not charge you extra if items cost more than I have allowed which they have.
Likewise if they cost less you cannot claim a refund.”
22. The owner subsequently received tax invoices following a directions hearing in the
Tribunal and the owner subsequently requested a price from Northern Rivers Timbers
which price was more than the timber purchased by the builder. The difference was
$4.49 per linear metre between 140 x 25mm select grade and 130 x 19mm standard (?)
grade. The owner claims an amount of $2,226.70 being the price difference of
$20,726.70 less $1,500 already paid by the builder. The owner received a letter from
the builder dated 26 May 2009 claiming an amount of $19,085.52 which letter stated
“clients are responsible for any costs over and above the allowance”. The builder claims
the difference in cost of timber as he had to purchase timber from a different supplier and
arranged for it to be laid. The Tribunal accepts that there was a difference in the cost of
the timber for the decking but refers to the email dated 11 June 2008 from the builder to
the owner which states – “I do not charge you extra if items cost more than I have
allowed which they have”. In the circumstances both the owners claim and the builders
counter claim in respect of this item is disallowed.
Claim 6
23. This claim relates to the eastern boundary retaining wall, the owner states that she wrote
to the builder regarding this issue on 13 February 2009 as part of the 6 month
maintenance list. She stated that part of the retaining wall was considerably lower than
the house site level. When she signed the contract the retaining wall and the site
levelling quotation she had thought that the retaining wall would be the same height or
near to the height of the house level site. The owner states that she was not on any
occasion warned the retaining wall on the boundary would be considerably lower than
the height of the house site.
24. The builder replied on 19 February 2009 stating that on commencing construction of the
house there was an agreement to raise the house to the same level as the garage and
-- 5 of 8 --
BD418-08 / Page 6 of 8
avoid having to step down from the garage. A credit was given for this as there was less
work involved. The owner states that the difference in height between the retaining
works and the house site is significantly more than 300mm. The owner states that she
has obtained the quote from Terry Bishdon to raise the height of the existing eastern
retaining wall and this quote is for $1734.00. The builder states that the wall which was
erected was designed by Mark Hull the engineer, as per the quote, and the height was
1.8 metres at which it was constructed. The owner states that she paid the final claim
even though she thought the works had not been completed. The builder states that the
owner inspected the retaining wall works before construction of the dwelling commenced
and made payment of final claim accordingly. In the circumstances the claim by the
owner is disallowed.
Claim 7
25. Claim 7 relates to the commencement of the building. The owner is claiming liquidated
damages of $10 per day from 7 September 2007 when the builder commenced on the
work site until 31 October 2007 which is when the builder claims the contract
commenced being a total of 54 days at $10 per day.
26. The owner states that materials were delivered to the site on approximately 7 September
2007 but work was not commenced until 1 November 2007. On 21 August 2008 in
answer to a query by the owner the builder replied, “Your contract date commences on
the preparation of the footing slab when the piers are poured our invoice is for concrete
confirm that this was done on 31 October 2007 your contract start date is therefore 31
October 2007”. The residential building contract item 9 states the date for
commencement is “on preparation of footings/slab”. The date of practical completion is
273 days. The builder states that the preparation for the slab i.e. site levelling, profiling,
plumbing trenches commenced approximately the 27-28 October, practical completion
occurred on 22 August 2008 which is approximately 290 days extension of time given
because of implement weather. In the circumstances the Tribunal finds that there may
be approximately 7 days that the owner could claim liquidated damages and orders that
the builder pay the owner the sum of $70.00 in relation to this claim.
Claim 8
27. This claim relates to the supply of 79 lineal metres of retaining wall in respect of the
erection of the retaining wall. The retaining wall and site levelling quotation states,
“supply 79 lineal metres of retaining wall – hardwood”. The retaining wall measures 71.4
lineal metres. The owner wrote to the builder on 18 May 2009 about this. She stated –
“I can only assume that when the suggestion was made to truncate a section of the
retaining wall to save money and a 3 metre height corner post the saving was not
passed on.”
The wall is 7.6 lineal metres short of the quotation this amounts to an amount $2,423.94.
The Tribunal notes that the builder did not dispute that the retaining wall is shorter than
the original length quoted and accordingly the amount claimed by the owner is allowed in
the amount of $2,423.94.
-- 6 of 8 --
BD418-08 / Page 7 of 8
Claim 9 - Window
28. This relates to a window in the family room. The house plans show a 1200mm window in
the family room, the owner states that on the original plan the family room was to be on
the western side of the house and the kitchen on the eastern side. This was changed
and the kitchen window had to be 1200m high to allow for kitchen cupboards underneath
and the family room was to have a full length window. During the construction 2 1200m
high windows were fitted, 1 to the kitchen and 1 to the family room instead of a full length
window in the family room. The owner asked for the correct sized window to be installed
as per her request when the rooms were changed. She had not noticed that the plans
still showed a 1200m high window in the family room. She states that she was originally
charged $60.50 for the replacement but after discussions with the builder this was $500
being half the cost of the actual window. The builder states that he could not presume as
to what the owner wanted in respect of the window and a variation was made and the
owner was given credit for the sum of $1160.50. In he circumstances the error was not
the builders but the owners and accordingly the claim is disallowed.
Claim 10 – Solar Power Variation
29. The initial power in relation to the hot water system in the contract was to be a standard
gas T26 tank but there was a variation completed prior to the contract being executed
which provided for a solar hot water system tank on ground of 315 litres. This was
subsequently changed to a 400 litre tank by variation and agreement. The owner states
that she was charged a difference between a standard gas tank of $1,229.70 and
$4,057.99 which was the 315 litre solar tank. The 400 litre solar tank was valued at
$4,378.64. The builder stated that there was always going to be a solar hot water
system, not a gas one, a credit was given on 20 May 2008 by the builder when the owner
decided not to proceed with the solar hot water system, that credit was $3678.64 and the
owner admits to receiving the credit in the circumstances as the owner was aware of the
variation to the contract in respect of the size of the tank and that subsequently she did
not proceed with the solar powered hot water system, the fact that she has received a
credit in the amount that she has leaves the Tribunal to disallow this particular claim.
Claim 11
30. Items needed to complete your home included an estimate price. This relates to the
installation of stainless steel fans, there was to be 8 stainless steel fans supplied by the
electrician for the PC allowance of $1576.00. The owner states that she cancelled the
installation of these fans as she had purchased alternate fans. She was credited with
$1576.00 but an amount of $847 was deducted from this and is clear the PC allowance is
for the supply of the fans and not the installation. The installation was to be included in
the contract price, the owner states that there were actually 10 fans installed as provided
by the owner not 8, in the circumstances the $847 was deducted from the amount
originally credited of $1576 should be credited to the owner. The Tribunal orders
accordingly.
31. There was also an issue in claim 11 related to the installation of standard rural security
screens to all doors and windows. The owner stated that she did not require security
screens to the upstairs windows apart from to the doors. The builder states that there
was only insect screens provided upstairs not security screens, he stated that the owner
got what she paid for by way of security screens and insect screens and that no credit
-- 7 of 8 --
BD418-08 / Page 8 of 8
was applicable to this item. The owner has not claimed a specific amount in respect of
this and no claim will be allowed by the Tribunal in this regard.
32. In submissions the owner stated that the builder did not meet his contractual obligations
with respect to the retaining wall and no variation notice was given to her in respect of
certain items. The builder stated that the owner removed some $40,000 work from the
contract and she wasn’t charged variation fees for this.
Conclusion
33. I conclude that the owner is entitled to recover from the builder sums relating to claim 7 in
the amount of $70.00, claim 8 in the amount of $2,423.94 and claim 11 in the amount of
$847.00.
Therefore the order of the Tribunal is as follows –
1. That the Respondent pay to the Applicant the sum of $3340.94 within 60 days
2. That the Respondent complete the deck staining as agreed by 30 September 2010.
-- 8 of 8 --